2 EOQ Calculation
2 EOQ Calculation
2 EOQ Calculation
Concept
Inventory Management
Inventory Management
Cycle time
95% 5%
Input Wait for Wait to Move Wait in queue Setup Run Output
inspection be moved time for operator time time
Managing Inventory
quantity = Q on hand
(maximum
Q
inventory
level) 2
Minimum
inventory
0
Time
Minimizing Costs
Objective is to minimize total costs
Total cost of
holding and
setup (order)
Minimum
total cost
Annual cost
Holding cost
D
= (S)
Q
The EOQ Model
Annual setup cost =
D
Q
S
Q
Q = Number of pieces per order Annual holding cost = H
2
Q* = Optimal number of pieces per order (EOQ)
D = Annual demand in units for the inventory item
S = Setup or ordering cost for each order
H = Holding or carrying cost per unit per year
Order quantity
= (Holding cost per unit per year)
2
Q
= (H)
2
The EOQ Model
Annual setup cost =
D
Q
S
Q
Q = Number of pieces per order Annual holding cost = H
2
Q* = Optimal number of pieces per order (EOQ)
D = Annual demand in units for the inventory item
S = Setup or ordering cost for each order
H = Holding or carrying cost per unit per year
D Q
S = H
Q 2
Solving for Q*
2DS = Q2H
Q2 = 2DS/H
Q* = 2DS/H
An EOQ Example
Determine optimal number of needles to order
D = 1,000 units
S = $10 per order
H = $.50 per unit per year
2DS
Q* =
H
2(1,000)(10)
Q* = = 40,000 = 200 units
0.50
An EOQ Example
Determine optimal number of needles to order
D = 1,000 units Q* = 200 units
S = $10 per order
H = $.50 per unit per year
Expected Demand D
number of = N = =
orders Order quantity Q*
1,000
N= = 5 orders per year
200
An EOQ Example
Determine optimal number of needles to order
D = 1,000 units Q* = 200 units
S = $10 per order N = 5 orders per year
H = $.50 per unit per year
Number of working
Expected days per year
time between = T =
orders N
250
T= = 50 days between orders
5
An EOQ Example
Determine optimal number of needles to order
D = 1,000 units Q* = 200 units
S = $10 per order N = 5 orders per year
H = $.50 per unit per year T = 50 days
D Q
TC = S + H
Q 2
1,500 200
TC = ($10) + ($.50) = $75 + $50 = $125
200 2
D Q
TC = S + H
Q 2 Only 2% less
1,500 244.9 than the total
TC = ($10) + ($.50) cost of $125
244.9 2
when the
TC = $61.24 + $61.24 = $122.48 order quantity
was 200
Reorder Points
EOQ answers the “how much” question
The reorder point (ROP) tells “when” to
order
Demand Lead time for a
ROP = per day new order in days
=dxL
D
d = Number of working days in a year
Reorder Point Curve
Q*
Inventory level (units)
Slope = units/day = d
ROP
(units)
Time (days)
Lead time = L
Reorder Point Example
Demand = 8,000 iPods per year
250 working day year
Lead time for orders is 3 working days
D
d=
Number of working days in a year
= 8,000/250 = 32 units
ROP = d x L
= 32 units per day x 3 days = 96 units
Production Order Quantity
Model
Used when inventory builds up
over a period of time after an
order is placed
Used when units are produced
and sold simultaneously
Production Order Quantity
Model
Part of inventory cycle during
which production (and usage)
is taking place
Inventory level
t Time
Production Order Quantity
Model
Q = Number of pieces per order p = Daily production rate
H = Holding cost per unit per year d = Daily demand/usage rate
t = Length of the production run in days
Annual inventory
= (Maximum inventory level)/2
level
= pt – dt
Production Order Quantity
Model
Q = Number of pieces per order p = Daily production rate
H = Holding cost per unit per year d = Daily demand/usage rate
t = Length of the production run in days
Maximum Q Q d
inventory level = p –d =Q 1–
p p p
2
2DS
Q =
H[1 - (d/p)]
2DS
Q*p =
H[1 - (d/p)]
Production Order Quantity
Example
D = 1,000 units p = 8 units per day
S = $10 d = 4 units per day
H = $0.50 per unit per year
2DS
Q* =
H[1 - (d/p)]
2(1,000)(10)
Q* = = 80,000
0.50[1 - (4/8)]
2DS
Q* =
annual demand rate
H 1–
annual production rate
Quantity Discount Models
Reduced prices are often available when
larger quantities are purchased
Trade-off is between reduced product cost
and increased holding cost
D Q
TC = S+ H + PD
Q 2
Quantity Discount Models
A typical quantity discount schedule
Discount Discount
Number Discount Quantity Discount (%) Price (P)
1 0 to 999 no discount $5.00
2 1,000 to 1,999 4 $4.80
0 1,000 2,000
Order quantity
Quantity Discount Example
Calculate Q* for every discount 2DS
Q* =
IP
2(5,000)(49)
Q1* = = 700 cars/order
(.2)(5.00)
2(5,000)(49)
Q2* = = 714 cars/order
(.2)(4.80)
2(5,000)(49)
Q3* = = 718 cars/order
(.2)(4.75)
Quantity Discount Example
Calculate Q* for every discount 2DS
Q* =
IP
2(5,000)(49)
Q1* = = 700 cars/order
(.2)(5.00)
2(5,000)(49)
Q2* = = 714 cars/order
(.2)(4.80) 1,000 — adjusted
2(5,000)(49)
Q3* = = 718 cars/order
(.2)(4.75) 2,000 — adjusted
Quantity Discount Example
Annual Annual Annual
Discount Unit Order Product Ordering Holding
Number Price Quantity Cost Cost Cost Total
1 $5.00 700 $25,000 $350 $350 $25,700
Q4
Q2
On-hand inventory
Q1 P
Q3
Time
Probabilistic Demand
ROP
Normal distribution probability of
demand during lead time
Expected demand during lead time (350 kits)
0 Lead
time Time
Place Receive
order order