Abc General Contractor: Takeoff Sheet
Abc General Contractor: Takeoff Sheet
Abc General Contractor: Takeoff Sheet
TAKEOFF SHEET
project: G+1 residential building
client: Mr X
contractor: ABC general contractor
consultant: XYZ design and construction
34.91
13.84
483.1544
2 5.32
5.73
0.6
36.58032
2 4.34
4.3
0.6
22.3944
2 5.35
4.3
0.6
27.606
1 3.33
4.3
0.6
8.5914
2 5.32
4.93
0.6
31.47312
2 4.34
4.93
0.6
25.67544
2 5.35
4.93
0.6
31.6506
1 3.33
4.93
0.6
15.8253
199.7966
8 3.1
3.1
2.5
192.2
14 2.8
5.1
2.5
499.8
2 2.3
2.3
2.5
26.45
718.45
1 14.55
0.6
0.6
5.238
1 13.35
0.6
0.6
4.806
1 15.65
0.6
0.6
5.634
1 3.58
0.6
0.6
1.2888
1 3.58
0.6
0.6
1.2888
4 3.73
0.6
0.6
5.3712
1 3.58
0.6
0.6
1.2888
1 4.28
0.6
0.6
1.5408
26.4564
718.45
8 2.6
2.6
0.65
35.152
14 2.3
4.6
0.55
81.466
2 1.8
1.8
0.45
2.916
119.534
8 0.4
0.25
2.5 2
6 0.4
0.25
2.5 1.5
4 0.5
0.25
2.5 1.25
6 0.4
0.25
2.5 1.5
6.25
592.666
26.4564
14.55
0.2
0.6
1.746
13.35
0.2
0.6
1.602
15.65
0.2
0.6
1.878
4.28
0.2
0.6
0.5136
3.58
0.2
0.6
0.4296
4 3.73
0.2
0.6
1.7904
3.58
0.2
0.6
0.4296
4.28
0.2
0.6
0.5136
8.9028
17.5536
610.2196
817.6378
2 5.32
5.73
0.25
15.2418
2 4.34
4.3
0.25
9.331
2 5.35
4.3
0.25
11.5025
1 3.33
4.3
0.25
3.57975
2 5.32
4.93
0.25
13.1138
2 4.34
4.93
0.25
10.6981
2 5.35
4.93
0.25
13.18775
1 3.33
4.93
0.25
6.593875
83.24858
14.55
0.2
0.6
1.746
13.35
0.2
0.6
1.602
15.65
0.2
0.6
1.878
4.28
0.2
0.6
0.5136
3.58
0.2
0.6
0.4296
4 3.73
0.2
0.6
1.7904
3.58
0.2
0.6
0.4296
4.28
0.2
0.6
0.5136
8.9028
8 2.6
2.6
54.08
14 2.3
4.6
148.12
2 1.8
1.8
6.48
208.68
14.55
0.2
2.91
13.35
0.2
2.67
15.65
0.2
3.13
4.28
0.2
0.856
3.58
0.2
0.716
4 3.73
0.2
2.984
3.58
0.2
0.716
4.28
0.2
0.856
14.838
223.518
8 2.6
2.6
0.65
35.152
14 2.3
4.6
0.55
81.466
2 1.8
1.8
0.45
2.916
119.534
6 0.4
0.2
2.5
1.2
6 0.4
0.2
2.5
1.2
4 0.4
0.2
2.5
0.8
6 0.4
0.2
2.5
1.2
2 0.4
0.2
2.5
0.4
4.8
21.21
0.2
0.48
2.03616
31.51
0.2
0.48
3.02496
31.51
0.2
0.48
3.02496
10.36
0.2
0.48
0.99456
10.36
0.2
0.48
0.99456
4 8.63
0.2
0.48
3.31392
10.36
0.2
0.48
0.99456
10.36
0.2
0.48
0.99456
15.37824
139.7122
8 1.3
2.5
26
6 1.3
2.5
19.5
4 1.3
2.5
13
6 1.3
2.5
19.5
65
8 10.4
0.65
54.08
14 13.8
0.55
106.26
2 7.2
0.45
6.48
166.82
1 21.21
0.4
8.484
1 31.51
0.4
12.604
1 31.51
0.4
12.604
1 10.36
0.4
4.144
1 10.36
0.4
4.144
4 8.63
0.4
13.808
1 10.36
0.4
4.144
1 10.36
0.4
4.144
64.076
295.896
ERAL CONTRACTOR
ntial building
neral contractor
ign and construction
description
A. SUB STRUCTURE
1. EXCAVATION AND EARTH WORK
1.1 SITE CLEARING(to the depth of 20cm)
1m working space each side
m3 on footing pad F1
footing pad 2
m3 on footing pad F2
footing pad 3
m3 on footing pad F3
m3 total pit excavation
1.4 TRENCH EXCAVATION(60cm thickness)
0.2m working space both side
m3 excavation on axis A
m3 excavation on axis B
m3 excavation on axis C
m3 excavation on axis 1
m3 excavation on axis 2
m3 excavation on axis 3,4,5&6
m3 excavation on axis 7
m3 excavation on axis 8
m3 total trench excavation
1.5 BACK FILL
1.5.1back fill around pit excavation
V backfill= V pit - V footing pad - V fon column
m3 total V pit excavated
deduction
V footing pad
m3 volume of C1&C5
m3 volume of C2
m3 volume of C3
m3 volume of C4
m3 total volume of foundation column
V backfill= V pit - V footing pad-V fon column
m3 total volume of backfill around pit
1.5.2 back fill around trench(masonery)
V backfill= V trench - V masonery wall below NGL
m3 total trench excavated
deduction
m2 formwork for C2
C3
perimeter, P=2*.4+2*.25=1.3m
m2 formwork for C3
C4
perimeter, P=2*.4+2*.25=1.3m
m2 formwork for C4
m2 total formwork for foundation column
4.2 formwork for footing pad
F1
perimeter, P=4*2.6=10.4m
m2 formwork for F1
F2
perimeter, P=2*2.3+2*4.6=13.8m
m2 formwork for F2
F3
perimeter, P=4*1.8=7.2m
m2 formwork for F3
m2 total formwork for footing pad
4.3 formwork for grade beam
on axis A
m2 formwork on axis A
on axis B
m2 formwork on axis B
on axis C
m2 formwork on axis C
on axis 1
m2 formwork on axis 1
on axis 2
m2 formwork on axis 2
on axis 3,4,5&6
m2 formwork on axis 7
on axis 8
m2 formwork on axis 8
m2 total formwork for grade beam
m2 total formwork needed
No. of bar total no of
structure location Diam (mm) shape No.of bars member length bar 6
footing pad F1 14 38 8 3.6 304
F2 12 40 14 3 560
F3 12 24 2 2.4 48
foudation column column 1 16 8 6 4.14 48
column 2 20 8 6 4.14 48
column 3 20 12 4 4.14 48
column 4 14 8 6 4.14 48
column 5 16 8 2 4.14 16
grade beam 14 2 1 7.31 2
14 2 1 8.68 2
14 2 1 7.32 2
axis A
12 2 1 9.59 2
12 2 1 8.68 2
12 2 1 4.54 2
14 2 2 7.8 4
14 2 2 5.14 4
14 2 2 8.68 4
14 2 2 5.15 4
axiis B&C 14 2 2 7.79 4
12 2 2 5.52 4
12 2 2 9.69 4
12 2 2 8.68 4
12 2 2 9.57 4
14 2 4 11.01 8
axis
1,2,7&8 12 2 4 10.31 8
20 2 4 3.195 8
axis 14 2 4 9.68 8
3,4,5&6 12 2 4 9.18 8
14 2 1 5.9 2
axis A'
12 2 1 5.4 2
14 2 1 9.97 2
axis A'
12 2 1 9.47 2
foun column stirrup for C 1 8 15 6 1.2 90
for C 2 8 14 6 1.2 84
for C 3 8 14 4 1.2 56
for C 4 8 17 6 1.2 102
for C 5 8 15 2 1.2 30
grade beam stirrup axis A 6 134 1 1.1 134 147.4
axis B&C 6 198 1 1.1 198 217.8
axis1,2,7,8 6 66 1 1.1 66 72.6
axis3,4,5,6 6 55 1 1.1 55 60.5
axisA' 6 33 1 1.1 33 36.3
axisA' 6 33 1 1.1 33 36.3
total length(m) 570.9
unit weight(kg/m) 0.222222
weight(kg) 126.8667
total length
8 10 12 14 16 18 20
1094.4
1680
115.2
198.72
198.72
198.72
198.72
66.24
14.62
17.36
14.64
19.18
17.36
9.08
31.2
20.56
34.72
20.6
31.16
22.08
38.76
34.72
38.28
88.08
82.48
25.56
77.44
73.44
11.8
10.8
19.94
18.94
108
100.8
67.2
122.4
36
434.4 0 2160.32 1675.24 264.96 0 423
0.395062 0.617284 0.888889 1.209877 1.580247 2 2.469136
171.6148 0 1920.284 2026.834 418.7022 0 1044.444
SUPER STRUCTURE
1. CONCRETE WORK
TIMING DIM square Discription
1.1 In elevation column,C-25 concrete
6 0.4 for Ground floor elevation column concrete work H=2.88m
0.25
2.88 1.728 m3 concrete for C1
6 0.4
0.25
2.88 1.728 m3 concrete for C2
4 0.4
0.25
2.88 1.152 m3 concrete for C3
6 0.4
0.25
2.88 1.728 m3 concrete for C4
2 0.4
0.25
2.88 0.576 m3 concrete for C5
for frist floor elevation column concrete work H=2.88
6 0.4
0.25
2.88 1.728 m3 concrete for C1
6 0.4
0.25
2.88 1.728 m3 concrete for C2
4 0.4
0.25
2.88 1.152 m3 concrete for C3
6 0.4
0.25
2.88 1.728 m3 concrete for C4
2 0.4
0.25
2.88 0.576 m3 concrete for C5
13.82 1.2
M3 In floor
total beam
concret work for elevation columns
8. FINISHING
8.1. plastering
7.1 Apply 2 coat of plastering in cement mortar (1:3) ratio
GROUND FLOOR PLASTERING
A. External wall plastering
multiply by 2 considering back side and fore side
2 250.6304
501.2608 m2 area of external wall plastering
B. Internal wall Plastering Work
multiply by 2 considering back side and fore side
2 55.4344
110.8688 m2 area of internal wall plastering
First Floor plastering
A. external wall plastering
multiply by 2 consider back side and fore side
2 276.3994
552.7988 m2 area of wall plastering for first Floor
B. for internal wall plastering
2 131.4572
262.9144 m2 area of internal wall plastering for first Floor
soffit plastering
2 4.825
5.23
50.4695 m2 plastering on axis 12-A'B&78A'B
2 3.84
3.8
29.184 m2 plastering on axis 23-AB & 67-AB
2 4.85
3.8
36.86 m2 plastering on axis 34-AB & 56-AB
1 2.83
3.8
10.754 m2 plastering on axis 45-AB
2 4.82
4.43
42.7052 m2 plastering on axis 12-BC & 78-BC
2 3.84
4.43
34.0224 m2 plastering on axis 23-BC & 67-BC
2 4.85
4.43
42.971 m2 plastering on axis 34-BC& 56-BC
1 2.83
4.43
12.5369 m2 plastering on axis 45and BC
259.503 m2 total plastering for slab
8.2. Sckirting work
1 19.81 ground floor scarting
19.81 m sckirting on axis A
1 24.43
24.43 m sckirting on axis B
1 8.8
8.8 m sckirting on axis 1&8
12 8.8
105.6 m sckirting on axis 2,3,4,5,6&7
158.64 m total ground floor sckerting
first floor sckerting
1 273.9994 by using parameter , 10cm width of sckerting
273.9994 m for sckerting on axis A-B& 2-3
43467.265 m total sckirting
8.3. PAINTING
GROUND FLOOR PAINTING
A. External wall painting
2 248.2304 multiply by 2 considering back side and fore side
496.4608 m2 area of wall for Ground Floor
B. Internal wall painting Work
2 167.6332
335.2664 m2 total area of internal painting wall for ground floor
831.7272 m2 total painting for ground floor
First Floor painting
A. external wall painting
2 273.9994 consider back side and fore side
547.9988 m2 area of wall for first Floor
B. for internal wall painting
2 131.4572
262.9144 m2 area of internal wall painting for first Floor
SOFFIT PAINTING
first floor celling chipwood painting
1 259.503
259.503 m2 area of soffit painting
CHIPWOOD PAINTING
1 259.503
259.503 m2 celling for area 6 b/n axis BC''&23
2161.6464 m2 total area of painting work
8.4 FLOOR FINISH
8.4.1.ground floor finish
A. shop 1 (cement screed A=39.98m2)
2 39.98
79.96 m2 cement screed F.F
B. shop 2 (cement screed A=24.23m2)
2 24.23
48.46 m2 cement screed F.F
C. shop 3 (cement screed A=31.51m2)
2 31.51
63.02 m2 cement screed F.F
D. bath room (ceramic f.f Total area=16.85m2)
1 16.85
16.85 m2 ceramic F.F
E. circulation area(terrazzo tile)
1 41.44
41.44 m2 terrazzo tile F.F
8.4.2 first floor finish
A. bed room(cement screed total Area=59.1m2)
1 59.1
59.1 m2 cement screed F.F
B. living room(ceement screed total Area=13.6m2)
1 104.32
104.32 m2 cement screed F.F
C. kitchen(ceramic tiles total Area=31.46m2)
1 31.46
31.46 m2 ceramic tile F.F
D. Circulation area (terrazzo tiles A=39.5m2)
1 39.5
39.5 m2 terrazzo tiles F.F
E. bath room (ceramic tiles A=3.9)
1 17.25
17.25 m2 ceramic tile F.F
9.SANITARY INSTALLATION WORKS
For ground floor
1 1 Supply & fix ceramic hand wash basins
1 pcs for the toilet on basement floor
1 1 Supply & fix ceramic toilet seat
1 pcs for the toilet on basement floor
2 1 Supply & fix ceramic dish washer basins
2 pcs for the kitchen on ground floor
first floor
3 1 Supply & fix ceramic hand wash basins
3 pcs for the toilet on first floor
3 1 Supply & fix ceramic toilet seat
3 pcs for the toilet on first floor
3 1 Supply & fix ceramic bath
3 pcs on first floor
1 1 Supply & fix ceramic stand shower
1 pcs on first floor
10.1 sewage disposal system
5 1 Elbo 90° Dia.110mm
5 pcs
3 1 T-sahpe elbo dia.110 mm
3 pcs
15 1 elbo 45°dia.110 mm
15 pcs
disposal pipe
1 7
7 m Galvanized steel pipe dia.110mm on s1
1 12
12 m Galvanized steel pipe dia.110mm on s2
1 9
9 m Galvanized steel pipe dia.110mm on s3
10.2 water supply
water supply pipe
A. main water supply
10,000L plastic water tank
1 12.5
12.5 m Galvanized steel pipe dia. 20mm
1 19.5 B. water supply to room
19.5 m PVC pipe dia. 15mm
10.3 manhole work
1 6 For spectic tank excavation
6 L=6 , w=6, D=4
4
144.00 m3
1 0.4 For spectic Tank masonary wall
6
4
9.60 m3
2 6 Slab floor concrete cover
6 c-15 used
0.15
10.80 m3 for concrete cover floor slab
13.ELECTRICAL INSTALLATION WORKS
ELECTRICAL INSTALLATION
A. GROUND FLOOR
2 1 lighting
2 pcs single florecent
38 1
38 pcs sceiling light
4 1
4 pcs decorative chadlier
switch
2 1
2 pcs single switch
14 1
14 pcs double switch
socket
18 1
18 pcs single socket
11 1
11 pcs telephone socket
B. FIRST FLOOR
lighting
41 1
41 pcs sceiling light
4 1
4 pcs decorative chadlier
switch
3 1
3 pcs single switch
14 1
14 pcs double switch
socket
18 1
18 pcs single socket
11 1
11 pce telephone socket
40*50 zigba
ay.corner list
No. of bar total no of total le
structure location Diam (mm) shape No.of bars member length bar 6 8
ground floor column 1 16 8 6 3.52 48
elevation
column column 2 20 8 6 3.68 48
column 3 20 12 4 3.68 48
column 4 14 8 6 3.44 48
column 5 16 8 2 3.52 16
first floor column 1 16 8 6 3.52 48
elevation
column column 2 16 8 6 3.52 48
column 3 20 12 4 3.68 48
column 4 14 8 6 3.44 48
column 5 16 8 2 3.52 16
first floor and 14 2 4 7.52 8
top tie beam
14 2 4 7.73 8
14 4 4 3.04 16
14 2 4 1.57 8
axis A
14 2 4 5.42 8
14 1 4 3.88 4
14 1 4 3.89 4
14 2 4 9.61 8
14 2 2 7.73 4
14 2 2 4.84 4
14 2 2 8.38 4
14 2 2 4.84 4
14 1 2 3.04 2
14 2 2 7.73 4
14 2 2 5.38 4
axis C
14 1 2 3.875 2
14 1 2 2.84 2
14 2 2 9.39 4
14 2 2 8.38 4
14 1 2 2.848 2
14 2 2 9.42 4
14 1 2 3.875 2
16 2 4 11.17 8
14 2 4 10.51 8
axis 14 1 4 1.7 4
1,2,7&8 14 3 4 2.89 12
14 1 4 3.58 4
14 3 4 3.31 12
20 2 4 9.84 8
16 3 4 9.18 12
axis 20 1 4 1.7 4
3,4,5&6 20 3 4 2.89 12
16 1 4 3.58 4
axis
3,4,5&6
20 1 4 1.61 4
14 2 2 6.06 4
axis A'
14 2 2 5.4 4
14 2 2 6.06 4
axis A'
14 4 2 5.4 8
slab axis AA' 6 4 1 5.2 4 20.8
reinfocement
axis AB 6 10 2 14.29 20 285.8
axis BC 6 12 1 31.46 12 377.52
axis 2,3,6&7 14 6 4 3.04 24
axis 12&78 6 13 2 10.26 26 266.76
axis 24&57 6 23 2 10.26 46 471.96
axis 45 6 8 1 4.63 8 37.04
column for C 1 8 14 12 1.2 168 201.6
stirrup
for C 2 8 13 12 1.2 156 187.2
for C 3 8 13 8 1.2 104 124.8
for C 4 8 16 12 1.2 192 230.4
for C 5 8 14 4 1.2 56 67.2
beam stirrup axis A 8 43 4 0.86 172 147.92
axis A 8 47 4 1.1 188 206.8
axis C 8 158 2 1.1 316 347.6
axis1,2,7,8 8 52 8 1.1 416 457.6
axis3,4,5,6 10 35 8 1.1 280
axis3,4,5,6 8 23 8 1.1 184 202.4
axisA' 8 26 4 1.1 104 114.4
total length(m) 1459.88 2287.92
unit weight(kg/m) 0.222222 0.395062
weight(kg) 324.4178 903.8696
12
11 2 4.17 22
12 11 2 1.9 22
12 11 2 0.96 22
12 11 2 1.503 22
total length(m) 0 0
unit weight(kg/m) 0.222222 0.395062
weight(kg) 0 0
total length
10 12 14 16 18 20
168.96
176.64
176.64
165.12
56.32
168.96
168.96
176.64
165.12
56.32
60.16
61.84
48.64
12.56
43.36
15.52
15.56
76.88
30.92
19.36
33.52
19.36
6.08
30.92
21.52
7.75
5.68
37.56
33.52
5.696
37.68
7.75
89.36
84.08
6.8
34.68
14.32
39.72
78.72
110.16
6.8
34.68
14.32
6.44
24.24
21.6
24.24
43.2
72.96
308
cement
total length f
10 12 14 16 18 20
60.5
91.74
41.8
21.12
33.066
0 248.226 0 0 0 0
0.617284 0.888889 1.209877 1.580247 2 2.469136
0 220.6453 0 0 0 0
Item No Description Unit
A-SUB STRUCTURE
1. EXCAVATION & EARTH WORK
1.01 Site clearing and removing of the top 200 mm thick soil. m2
1.02 bulk excavation oridenry soil m3
1.03 Pit excavation in ordinary soil m3
1.04 Trench excavation in ordinary soil m3
1.05 back Fill in non expansive material from the site well rolled and compact in layers
not exceeding 200 mm thick. m3
1.06 load Cart away surplus excavated materials from the site as per the Engineer's m3
instruction.
1.07 25 cm thick basaltic or equivalent stone hardcore well rolled, consolidated and m3
blinded with crushed
TOTAL stone.TO SUMMARY ....................
CARRIED Birr
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, mix ratio: under
a) Footing m2
b) grade beam m2
2.02 Reinforced concrete quality C-25,mix ratio filled in to form work and vibrated
around rod reinforcement (formwork and reinforcement measured separately).
a) In footing pad m3
b) In foundation column m3
c) In grade beam m3
d) in groun floor beam m3
TOTAL CARRIED TO SUMMARY .................... Birr
3. FORMWORK
3.00 Provide, cut and fix in position sawn zigba wooden formwork
a) In footing pad m2
b) In foundation column m2
d) In grade beam m2
TOTAL CARRIED TO SUMMARY .................... Birr
4.REINFORCEMENT BAR
4.00 Mild steel reinforcement according to structural drawings. Price includes cutting,
bending, placing in position and tying wire and required spacers.
a) Φ 6 mm deformed bar kg
b) Φ 8 mm deformed bar kg
c) Φ 10 mm deformed bar kg
d) Φ 12 mm deformed bar kg
e) Φ 14 mm deformed bar kg
f) Φ 16 mm deformed bar kg
g) Φ 20 mm deformed bar kg
TOTAL CARRIED TO SUMMARY ......... Birr
B-SUPER STRUCTURE
1. CONCRETE WORK
C-25 reinforced concrete to be poured into formwork around reinforcement bar
1.01
formwork and reinforcement measured separately
a) In elevation columns m3
b) In floor and top tie beams m3
c) In floor slab m2
d) in stair case m3
TOTAL CARRIED TO SUMMARY ......... Birr
2. FORMWORK
2.01 Provide, cut and fix in position sawn zigba wood which ever appropriate for column,
beam, slab and columns
a) In elevation stair. m2
b) In floor and top tie beams m2
c) In floor slab m2
d) in stair case m2
TOTAL CARRIED TO SUMMARY ......... Birr
REINFORCEMENT BAR
Mild steel reinforcement according to structural drawings. Price includes cutting,
bending, placing in bar
a) Dia. 6 deformed position and tying wire and required spacers. Labor cost only. kg
b) Dia. 8 deformed bar kg
d) Dia. 10 deformed bar kg
e) Dia. 12 deformed bar kg
f) Dia. 14 deformed bar kg
g) Dia. 16 deformed bar kg
g) Dia. 20 deformed bar kg
TOTAL CARRIED TO SUMMARY ......... Birr
3. BLOCK WORK
3.01 200mm and 150mm thick HCB wall which can satisfy the designed strength , bedded
in cement mortar (1:3).Price shall include mortar bed
20cm HCB work m2
15cm HCB work m2
Construct 10cm thick HCB masonry wall with cement mortar of (1:3)mix m2
TOTAL CARRIED TO SUMMARY .........
4. ROOFING
6. PLASTERING
Two Coats of Cement Platering
5.01 a. To Internal Wall Surface m2
5.02 b. To External Wall surface m2
c. To RC ceiling m2
TOTAL CARRIED TO SUMMARY .........
7. PAINTING
Three Coats of Platic Emulsion Painting
a. To Internal Wall Surface m2
b. To External Wall surface m2
c. To soffit painting m2
TOTAL CARRIED TO SUMMARY .........
8. with
7.01 for window and door METAL,DOOR & WINDOW
LTZ, profil approved WORK
quality of locks, 1 coats of antirust & 2
coats of synthetic and door stopper
Door pcs
Window pcs
TOTAL CARRIED TO SUMMARY .........
9. GLAZING
Supply and fix 4 mm thick clear sheet glass to metal beds and puttied with approved m2
quality of putty.CARRIED TO SUMMARY .........
TOTAL
0.00
0.00
373.78 0.00
552.80 0.00
259.50 0.00
0.00
0.00
598.18 0.00
1044.46 0.00
259.50 0.00
0.00
0.00
0.00
0.00
44.00 0.00
75.00 0.00
0.00
0.00
0.00
166.98 0.00
0.00
0.00
0.00
0.00
65.56 0.00
80.94 0.00
43467.26 0.00
354.86 0.00
0.00
0.00
0.00
4.00 0.00
4.00 0.00
1.00 0.00
1.00 0.00
1.00 0.00
0.00
7.00 0.00
9.00 0.00
0.00
12.50 0.00
19.50 0.00
0.00
0.00
0.00
0.00
38.00 0.00
4.00 0.00
0.00
2.00 0.00
14.00 0.00
0.00
36.00 0.00
11.00 0.00
MANUAL EXCAVATION & EARTH WORK
Summery Page
ANALYSIS SHEET FOR DIRECT & INDIRECT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 100 m2/Dy
WORK ITEM: ( 1.1 ) Clearing of 20 cm thick top organic soil EQUIPEMENTOUT PUT : 100 m2/Dy
TOTAL QANTITY OF WORK 1 m2 RESULT: 26.22 Birr/m2
A= Materials Unit Cos Birr/m2 B= Manpower Unit Cost 21.2 Birr/m2 C= Equipment Unit Cost 1.60 Birr/m2
Total of (1:02) Total of (1:03) 160.00
Daily Output: Daily output: 100
Direct Cost of Work Item = A+B+C = 22.80 Birr/m2
Over head cost : 8% 1.82 "
Profit Cost: 7% 1.60 "
Total : 26.22 Birr/m2
Remark ____________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 26.22 Birr/m2
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 3.00 m3/Dy
WORK ITEM: ( 1.2) Bulk excavation in ordinary soil to a depth < 1.5m (manual) EQUIPEMENTOUT PUT : 3.00 m3/Dy
TOTAL QANTITY OF WORK 1 m3 RESULT: 187.28 Birr/m3
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 152.18 Birr/m3 C= Equipment Unit Cost 10.67 Birr/m3
Total of (1:02) Total of (1:03) 32
Daily Output: Daily Outp 3
Direct Cost of Work Item = A+B+C = 162.85 Birr/m3
Over head cost : 8% 13.03 "
Profit Cost: 7% 11.40 "
Total : 187.28 Birr/m3
Remark _________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost 187.28 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 2.6 m3/Dy
WORK ITEM: ( 1.3 ) Bulk excavation in ordinary soil to a depth 1.5m< x <3.0m EQUIPEMENTOUT PUT : 2.6 m3/Dy
TOTAL QANTITY OF WORK ITEM: 1 m3 RESULT: 216.09 Birr/m3
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 175.60 Birr/m3 Unit Cost 12.31 Birr/m3
Total of (1:02) Total of (1:03) 1.6
Daily output: Daily output: 2.6
Direct Cost of Work Item = A+B+C = 187.90 Birr/m3
Over head cost : 8% 15.03 "
Profit Cost: 7% 13.15 "
Total : 216.09 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 216.09 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 169.09 Birr/m3 C= Equipment Unit Cost 11.85 Birr/m3
Total of (1:02) Total of (1:03)
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 320.65 Birr/m3 C= Equipment Unit Cost 28.89 Birr/m3
Total of (1:02) Total of (1:03)
Daily Output: Daily Output:
Direct Cost of Work Item = A+B+C = 349.54 Birr/m3
Over head cost : 8% 27.96 "
Profit Cost: 7% 24.47 "
Total : 401.97 Birr/m3
Remark _________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 401.97 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 360.73 Birr/m3 C= Equipment Unit Cost 32.50 Birr/m3
Total of (1:02) Total of (1:03)
Daily out put Daily output:
Direct Cost of Work Item = A+B+C = 393.23 Birr/m3
Over head cost : 8% 31.46 "
Profit Cost: 7% 27.53 "
Total : 452.22 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 452.22 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 480.98 Birr/m3 C= Equipment Unit Cost 43.33 Birr/m3
Total of (1:02) Total of (1:03) 52
Daily Output: Daily Outp 1.20
Direct Cost of Work Item = A+B+C = 524.31 Birr/m3
Over head cost : 8% 41.95 "
Profit Cost: 7% 36.70 "
Total : 602.96 Birr/m3
Remark _________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 602.96 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 577.18 Birr/m3 C= Equipment Unit Cost 52.00 Birr/m3
Total of (1:02) Total of (1:03)
Daily out put Daily output:
Direct Cost of Work Item = A+B+C = 629.18 Birr/m3
Over head cost : 8% 50.33 "
Profit Cost: 7% 44.04 "
Total : 723.55 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 723.55 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 641.31 Birr/m3 C= Equipment Unit Cost 57.78 Birr/m3
Total of (1:02) Total of (1:03) 52
Daily Output: Daily Outp 0.90
Direct Cost of Work Item = A+B+C = 699.08 Birr/m3
Over head cost : 8% 55.93 "
Profit Cost: 7% 48.94 "
Total : 803.95 Birr/m3
Remark _________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 803.95 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 824.54 Birr/m3 C= Equipment Unit Cost 74.29 Birr/m3
Total of (1:02) Total of (1:03)
Daily out put Daily output:
Direct Cost of Work Item = A+B+C = 898.82 Birr/m3
Over head cost : 8% 71.91 "
Profit Cost: 7% 62.92 "
Total : 1033.64 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 1033.64 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 53.18 Birr/m3 C= Equipment Unit Cost 87.13 Birr/m3
Total of (1:02) Total of (1:03)
Daily output: Daily output:
Direct Cost of Work Item = A+B+C = 140.31 Birr/m3
Over head cost : 8% 11.22 "
Profit Cost: 7% 9.82 "
Total : 161.35 Birr/m3
Remark ___________________________________ VAT : 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost 161.35 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 158 Birr/m3 B= Manpower Unit Cost 53.18 Birr/m3 C= Equipment Unit Cost 87.13 Birr/m3
Total of (1:02) Total of (1:03)
Daily output: Daily output:
Direct Cost of Work Item = A+B+C = 298.43 Birr/m3
Over head cost : 8% 23.87 "
Profit Cost: 7% 20.89 "
Total : 343.20 Birr/m3
Remark ___________________________________ VAT : 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost 343.20 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 104.63 Birr/m3 C= Equipment Unit Cost 62.75 Birr/m3
Total of (1:02) Total of (1:03)
Daily output: Daily output:
Direct Cost of Work Item = A+B+C = 167.38 Birr/m3
Over head cost : 8% 13.39 "
Profit Cost: 7% 11.72 "
Total : 192.49 Birr/m3
Remark ___________________________________ VAT : 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost 192.49 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 4.95 Birr/m3 C= Equipment Unit Cost 77.33 Birr/m3
Total of (1:02) Total of (1:03)
Daily output: Daily output:
Direct Cost of Work Item = A+B+C = 82.28 Birr/m3
Over head cost : 8% 6.58 "
Profit Cost: 8% 6.58 "
Total : 95.44 Birr/m3
Remark _________________________________________________________VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 95.44 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 48.17 Birr/m3 C= Equipment Unit Cost 379.66 Birr/m3
Total of (1:02) Total of (1:03)
Daily output: Daily output:
Direct Cost of Work Item = A+B+C = 427.83 Birr/m3
Over head cost : 8% 34.23 "
Profit Cost: 8% 34.23 "
Total : 496.28 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 496.28 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 62.83 Birr/m3 C= Equipment Unit Cost 495.21 Birr/m3
Total of (1:02) Total of (1:03)
Daily output: Daily output:
Direct Cost of Work Item = A+B+C = 558.04 Birr/m3
Over head cost : 8% 44.64 "
Profit Cost: 8% 44.64 "
Total : 647.33 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 647.33 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 769.57 Birr/m3 C= Equipment Unit Cost 69.33 Birr/m3
Total of (1:02) Total of (1:03) 52
Daily Output: Daily Outp 0.75
Direct Cost of Work Item = A+B+C = 838.90 Birr/m3
Over head cost : 8% 83.89 "
Profit Cost: 8% 67.11 "
Total : 989.90 Birr/m3
Remark _________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 989.90 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost 1154.35 Birr/m3 C= Equipment Unit Cost 104.00 Birr/m3
Total of (1:02) Total of (1:03)
Daily out put Daily output:
Direct Cost of Work Item = A+B+C = 1258.35 Birr/m3
Over head cost : 8% 100.67 "
Profit Cost: 8% 100.67 "
Total : 1459.69 Birr/m3
Remark ________________________________________________ VAT: 15% 0.00
UF: UTILIZATION FACTOR Total Unit Cost : 1459.69 Birr/m3
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
Summery Page