Project Example
Project Example
Project Example
EMPLOYER:- CONTRACTOR:-
CONSULTANT:- PROJECT:-G+2 RESIDENTIAL BUILDING
NO DIMENSION QUANTITY UNIT DESCRIPTION
A.SUB STRUCTURE
1.EXCAVATION AND EARTH WORK
1.1 site clearing
25 clear the site at a depth of 20 cm or remove the top 20cm soil. Site
clearing includes total area of the site or compound
10
250.00 m2 Total area of site clearing
8.75
5.05
0.5
22.09 m3 A1
8
2.6
0.5 A3
10.40 m3 A2
1.15
3.1
0.5
1.783 m3 A3
8.75
3.2
0.5
14 m3 A4
48.28 m3 Total volume of bulk excavation
1.3 pit excavation
11.5
total perimeter of partition wall including door and window opening (that
2.66 ends on first floor beam soffit) at a height of 2.66m =
30.59 m2 (3.10+0.80+2.19+0.85+0.9+1.41+2.25) = 11.5m
45.72 m2 Area including door and window openings
ddt area of door and window openings
internal doors
3 2.1
0.85
5.36 m2
1 2.1
0.7
1.47 m2
6.83 m2 area of window & door opening
38.90 m2 area of 15 cm thick HCB work for ground floor
b. for first floor
total perimeter of partition wall including door and window opening (that
ends on first floor slab soffit) at a height of 2.91m =
9.54 (2.40+4.15+1.50+1.49) m = 9.54m
2.91
27.76 m2
total perimeter of partition wall including door and window opening (that
ends on first floor beam soffit) at a height of 2.66m =
13.34 (1.45+2.19+3.95+2.2+3.55) = 13.34m
2.66
35.48 m2
63.25 m2 Area including window and door opening
ddt area of door and window opening
5 2.1 internal doors
0.8
8.4 m2 Area of window & door opening = 8.4 m2
54.85 m2 area of 15 cm thick HCB work for first floor
b. for second floor
hollow concrete block (HCB) of thickness 15cm to be bonded wth cement
mortar of 1:3
total perimeter of partition wall including door and window opening (that
ends on first floor slab soffit) at a height of 2.91m =
9.54 (2.40+4.15+1.50+1.49) m = 9.54m
2.91
27.76 m2
total perimeter of partition wall including door and window opening (that
ends on first floor beam soffit) at a height of 2.66m =
13.34 (1.45+2.19+3.95+2.2+3.55) = 13.34m
2.66
35.48 m2
63.25 m2 area including window and door openig
ddt area of door and window opening
5 2.1 internal doors
0.8
8.4 m2 Total area of window & door opening = 8.4 m2
54.85 m2 area of 15 cm thick HCB work for second floor
Total area of 15cm thick HCB work class''c'' with cement
148.59 m2 mortar of 1:3
4.ROOF WORK
4.1. Roof cover
EGA sheet roof cover
7.6
5.3
40.28 m2 A1
7.6
4.05
30.78 m2 A2
2.2
0.9
1.98 m2 A3
73.04 m2 TOTAL
1.6 m2 ddt
71.44 m2 Total area of EGA SHEET roof cover
4.2 Gutter
G-28 galvanized flat metal sheet of gutter.
7.6 ML at ''A1'' at the back
8.02 ML at ''A2'' front side =(3.5+1.41+1.41+1.7)=8.02m
2 0.9 1.8 at ''A3'' back & front side
17.42 ML Total length of Gutter
4.3 Down pipe
100mm diameter PVC down pipe.
10 9.3 93 ML Total length of down pipe
5.CARPENTARY AND JOINERY
wooden door
2 2.1 D1 size (2.10m*0.85m)
0.85
3.57 m2
1 2.1 D2 size (2.10m*0.70m)
0.7
1.47 m2
11 2.1 D3 size (2.10m*0.80m)
0.8
18.48 m2
23.52 m2 Total area of wooden doors
65.52 m2 Top ceiling (chipwood)
76 ML Dia 8 ceiling battens (wooden)
40.74 ML Dia 8 Diagonal members
83.6 ML 5*7cm wooden purlins(Tid)
22.86 ML Dia 10 vertical members
114.24 ML Dia 10 Diagonal rafter
6. FINISHING WORKS
6.1 Wall Finish
6.11 external wall plastering
Apply three coats of external wall plastering with cement mortar 1:3 mix
ratio
a. Ground floor
total perimeter (girth) = 37.69m
37.69 (8+4.20+0.85+2.60+0.85+2.95+1.65+2.39+1.10+0.3+4.4+8.4)
3.06
115.33 m2
16.58 m2 ddt area of door and window opening = 16.58 m2
(Refer C. block work ,1.1 for ground floor external HCB work)
98.75 m2 area of external wall plastering for ground floor
b. First floor
Total perimeter (girth)= 37.61m
37.61 (8+4.20+0.85+2.60+0.85+2.95+1.65+2.07+1.10+2.26+3.40+1.35+8.40)m
3.06
115.09 m2
ddt area of door and window opening = 15.92 m2
(Refer C. block work ,2.1 for first floor external HCB work)
(115.09-15.92)m2 = 99.17m2
99.17 m2 area of external wall plastering for first floor
C. Second floor
Total perimeter (girth)= 37.61m
37.61 (8+4.20+0.85+2.60+0.85+2.95+1.65+2.07+1.10+2.26+3.40+1.35+8.40)m
3.06
115.09 m2
ddt area of door and window opening = 15.92 m2
(Refer C. block work ,3.1 for second floor external HCB work)
(115.09-15.92)m2 = 99.17m2
99.17 m2 area of external wall plastering for second floor
297.09 m2 Total area of external wall plastering
6.12 Internal wall plastering
a. Ground floor
Apply three coats of internal wall plastering with cement mortar 1:3 mix
ratio
internal side of the external wall at a height of 2.91m
35.19 T.P = (7.4+8+5.15+2.39+1.40+6.75+0.95+0.95+2.2)m=35.19 m
2.91
102.40 m2
partition wall that ends at slab soffit
10.4 T.P = 2*(3.45+0.9+0.85) m =10.4 m
2.91
30.26 m2
partition wall that ends at beam soffit including above beam
23.84 T.P=3.21+2.90+0.8+0.85(2)+2.19(2)+0.9(3)+2.25(2)+1.40+1.50+
0.15(5)=23.84 m
2.91
69.37 m2
Add column intersection (internal)
0.8 T.P = 0.05(5)+ 0.1(2)m+0.2+0.15m = 0.8m
2.91
2.33 m2
A.SUB STRUCTURE
Reinforcement for footing pad
F-1 14 2.3 12 2 1 24
14 2.3 12 2 1 24
12 1.9 11 1 1 11 20.90
12 1.6 9 4 1 36 57.60
10 1.7 10 3 1 30 51.00
Total Length 105.60 157.00
Weight/Kg 0.222 0.395 0.617 0.888
C-1
14 3.35 8 4 1 32
C-2
14 3.35 6 6 1 36
F1 C1
8 0.9 8 2 1 16 14.4
F2C1
8 0.9 9 1 1 9 8.1
F3C2
8 0.9 9 4 1 36 32.4
F4C1
8 0.9 7 1 1 7 6.3
F4C2
8 0.9 7 2 1 14 12.6
Total Length 73.80 -
Weight/Kg 0.222 0.395 0.617 0.888
8 1.1 21 1 1 1 23.10
8 1.1 18 1 1 1 19.80
AXIS-B
14 9.65 2 1 1 2
14 8.95 2 1 1 2
8 1.1 21 1 1 1 23.10
8 1.1 18 1 1 1 19.80
AXIS-A"
14 5.45 2 1 1 2
14 4.75 2 1 1 2
8 1.1 21 1 1 1 23.10
AXIS-A'
14 5.15 2 1 1 2
14 4.45 2 1 1 2
8 1.1 21 1 1 1 23.10
AXIS-A
14 4.55 2 1 1 2
14 3.85 2 1 1 2
8 1.1 18 1 1 1 19.80
AXIS-1
14 10.4 2 1 1 2
14 9.7 2 1 1 2
8 1.1 7 1 1 7 7.70
8 1.1 20 1 1 20 22.00
8 1.1 21 1 1 21 23.10
AXIS-2
14 10.4 2 1 1 2
14 9.7 2 1 1 2
8 1.1 7 1 1 7 7.70
8 1.1 20 1 1 20 22.00
8 1.1 21 1 1 21 23.10
AXIS-3
14 10.4 2 1 1 2
14 9.7 2 1 1 2
8 1.1 15 1 1 15 16.5
8 1.1 12 1 1 12 13.2
8 1.1 21 1 1 21 23.1
Total Length 310.20
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 122.49 - -
Reinforcement for Ground floor slab
AXIS B-C
B/N AXIS
1-2 8 4.002 22 1 1 22 88.04
AXIS 1-2
B/N AXIS
B-C 8 4 21 1 1 21 84.00
AXIS B-C
B/N AXIS
2-3 8 3.4 18 1 1 18 61.20
AXIS 2-3
B/N AXIS
B-C 8 4.002 22 1 1 22 88.04
AXIS A'-B
B/N AXIS
1-2 8 3.8 20 1 1 20 76.00
AXIS 1-2
B/N AXIS
A'-B 8 4 21 1 1 21 84.00
AXIS A"-B
B/N AXIS
2-3 8 2.2 12 1 1 12 26.40
AXIS 2-3
B/N AXIS
A"-B 8 3.4 18 1 1 18 61.20
AXIS A-A"
B/N AXIS
2-3 8 2.75 15 1 1 15 41.25
AXIS 2-3
B/N AXIS
A-A" 8 3.4 18 1 1 18 61.20
Total Length 671.34
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 265.10 - -
SUMMARY OF BAR SCHEDULE FOR SUB STRUCTURE
DIA Total weight (kg)
8 416.73
10 65.16
12 139.49
14 708.66
B. SUPER STRUCTURE
Reinforcement for Ground floor column
C-1
14 3.62 8 4 1 32
8 0.9 15 4 1 4 54.00
C-2
14 3.62 6 6 1 36
8 0.9 15 6 1 6 81.00
Total Length 135.00
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 53.31 - -
8 1.1 28 1 1 28 30.80
8 1.1 24 1 1 28 26.40
AXIS-B
16 9.65 3 1 1 3
16 2.6 1 1 1 1
16 8.95 3 1 1 3
8 1.1 28 1 1 28 30.80
8 1.1 28 1 1 28 30.80
AXIS-A"
16 5.45 3 1 1 3
16 4.75 3 1 1 3
8 1.1 28 1 1 28 30.80
AXIS-A'
16 5.15 3 1 1 3
16 4.45 3 1 1 3
8 1.1 28 1 1 28 30.80
AXIS-A
16 8.75 3 1 1 3
16 2.6 1 1 1 1
16 8.05 3 1 1 3
8 1.1 28 1 1 28 30.80
8 1.1 24 1 1 24 26.40
AXIS-1
16 10.4 3 1 1 3
16 2.99 1 1 1 1
16 2.7 1 1 1 1
16 9.7 3 1 1 3
8 1.1 9 1 1 9 9.90
8 1.1 26 1 1 26 28.60
8 1.1 27 1 1 27 29.70
AXIS-2
16 10.4 3 1 1 3
16 2.99 1 1 1 1
16 2.7 1 1 1 1
16 9.7 3 1 1 3
8 1.1 9 1 1 9 9.90
8 1.1 10 1 1 10 11.00
8 1.1 43 1 1 43 47.30
AXIS-3
16 3.85 3 1 1 3
16 3.15 3 1 1 3
16 5.1 3 1 1 3
16 4.4 3 1 1 3
8 1.1 19 1 1 19 20.90
8 1.1 27 1 1 27 29.70
AXIS-3' 14 3.4 3 1 1 3
14 2.65 3 1 1 3
8 1.1 16 1 1 16 17.6
Total Length 442.20
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 174.62 - -
Reinforcement for first floor slab
AXIS 1-3
B/N AXIS
B-C 10 10.14 28 1 1 28 283.92
NEGATIVE
BAR ON
AXIS 2 10 2.6 14 1 1 14 36.40
AXIS A"B
B/N AXIS
1-3 10 6.66 16 1 1 16 106.56
NEGATIVE
BAR ON
AXIS 2 10 2.6 12 1 1 12 31.20
NEGATIVE
BAR ON
AXIS 2 10 2.76 16 1 1 16 44.16
AXIS A'-A"
B/N AXIS
1-3
10 10.14 11 1 1 11 111.54
NEGATIVE
BAR ON
AXIS 2 10 2.6 7 1 1 7 18.20
AXIS A- A'
B/N AXIS
1-3
10 10.14 9 1 1 9 91.26
NEGATIVE
BAR ON
AXIS -2 10 2.6 7 1 1 7 18.20
AXIS A- C
B/N AXIS
1-2 8 10.82 28 1 1 28 302.96
NEGATIVE
BAR ON
AXIS B 10 2.7 28 1 1 28 75.60
NEGATIVE
BAR ON
AXIS A' 8 2.915 28 1 1 28 81.62
AXIS 2-3
B/N AXIS
A-C
8 10.82 2 1 1 2 21.64
NEGATIVE
BAR ON
AXIS B 10 2.7 2 1 1 2 5.40
AXIS B-C
B/N AXIS
2-3 8 6.64 24 1 1 24 159.36
AXIS A-A"
B/N AXIS
2-3 8 4.79 24 1 1 24 114.96
NEGATIVE
BAR ON
AXIS A' 8 2.915 24 1 1 24 69.96
Total Length 750.50 822.44
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 296.36 507.45 -
Reinforcement for first floor column
C-1
14 3.62 8 4 1 32
8 0.9 15 4 1 60 54.00
C-2
14 3.62 6 6 1 36
8 0.9 15 6 1 90 81
Total Length 135.00
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 53.31 - -
Reinforcement for second floor beam
AXIS-C
16 8.75 3 1 1 3
16 2.6 1 1 1 1
16 8.05 3 1 1 3
8 1.1 28 1 1 28 30.80
8 1.1 24 1 1 24 26.40
AXIS-B
16 9.65 3 1 1 3
16 2.6 1 1 1 1
16 8.95 3 1 1 3
8 1.1 28 1 1 28 30.80
8 1.1 28 1 1 28 30.80
AXIS-A"
16 5.45 3 1 1 3
16 4.75 3 1 1 3
8 1.1 28 1 1 28 30.80
AXIS-A'
16 5.15 3 1 1 3
16 4.45 3 1 1 3
8 1.1 28 1 1 28 30.80
AXIS-A
16 8.75 3 1 1 3
16 2.6 1 1 1 1
16 8.05 3 1 1 3
8 1.1 28 1 1 28 30.80
8 1.1 24 1 1 24 26.40
AXIS-1
16 10.4 3 1 1 3
16 2.99 1 1 1 1
16 2.7 1 1 1 1
16 9.7 3 1 1 3
8 1.1 9 1 1 9 9.90
8 1.1 26 1 1 26 28.60
8 1.1 27 1 1 27 29.70
AXIS-2
16 10.4 3 1 1 3
16 2.99 1 1 1 1
16 2.7 1 1 1 1
16 9.7 3 1 1 3
8 1.1 9 1 1 9 9.90
8 1.1 26 1 1 26 28.60
8 1.1 27 1 1 27 29.70
AXIS-3
16 3.85 3 1 1 3
16 3.15 3 1 1 3
16 5.1 3 1 1 3
16 4.4 3 1 1 3
8 1.1 19 1 1 19 20.90
8 1.1 27 1 1 27 29.70
AXIS-3'
14 3.45 3 1 1 3
14 2.65 3 1 1 3
8 1.1 16 1 1 16 17.60
Total Length 442.20
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 174.62 - -
Reinforcement for second floor slab
AXIS 1-3
B/N AXIS
B-C 10 10.14 28 1 1 28 283.92
NEGATIVE
BAR ON
AXIS 2 10 2.6 14 1 1 14 36.40
AXIS A"B
B/N AXIS
1-3 10 6.66 16 1 1 16 106.56
NEGATIVE
BAR ON
AXIS 2 10 2.6 12 1 1 12 31.20
NEGATIVE
BAR ON
AXIS 2 10 2.76 16 1 1 16 44.16
AXIS A'-A"
B/N AXIS
1-3
10 10.14 11 1 1 11 111.54
NEGATIVE
BAR ON
AXIS 2 10 2.6 7 1 1 7 18.20
AXIS A- A'
B/N AXIS
1-3
10 10.14 9 1 1 9 91.26
NEGATIVE
BAR ON
AXIS -2 10 2.6 7 1 1 7 18.20
AXIS A- C
B/N AXIS
1-2
8 10.82 28 1 1 28 302.96
NEGATIVE
BAR ON
AXIS B 10 2.7 28 1 1 28 75.60
NEGATIVE
BAR ON
AXIS A' 8 2.915 28 1 1 28 81.62
AXIS 2-3
B/N AXIS
A-C
8 10.82 2 1 1 2 21.64
NEGATIVE
BAR ON
AXIS B 10 2.7 2 1 1 2 5.40
AXIS B-C
B/N AXIS
2-3
8 6.64 24 1 1 24 159.36
AXIS A-A"
B/N AXIS
2-3
8 4.79 24 1 1 24 114.96
NEGATIVE
BAR ON
AXIS A' 8 2.915 24 1 1 24 69.96
Total Length 750.50 822.44
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 296.36 507.45 -
Reinforcement for second floor column
C-1
14 3.62 8 4 1 32
8 0.9 15 4 1 60 54.00
C-2
14 3.62 6 6 1 36
C-3
8 0.9 15 6 1 90 81.00
Total Length 135.00
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 53.31 - -
8 1.1 21 1 1 21 23.10
8 1.1 18 1 1 18 19.80
AXIS-B
14 9.45 2 1 1 2
14 8.95 3 1 1 3
8 1.1 21 1 1 21 23.10
8 1.1 21 1 1 21 23.10
AXIS-A"
14 5.25 2 1 1 2
14 4.75 3 1 1 3
8 1.1 21 1 1 21 23.10
AXIS-A'
14 4.95 2 1 1 2
14 4.45 3 1 1 3
8 1.1 21 1 1 21 23.10
AXIS-A
14 8.55 2 1 1 2
14 8.05 3 1 1 3
8 1.1 21 1 1 21 23.10
8 1.1 18 1 1 18 19.80
AXIS-1
14 10.2 2 1 1 2
14 9.7 3 1 1 3
8 1.1 26 1 1 26 28.60
8 1.1 21 1 1 21 23.10
AXIS-2
14 10.2 2 1 1 2
14 9.7 3 1 1 3
8 1.1 8 1 1 8 8.80
8 1.1 33 1 1 33 36.30
AXIS-3
14 3.65 2 1 1 2
14 3.15 3 1 1 3
14 4.9 2 1 1 2
14 4.4 3 1 1 3
14 3.25 2 1 1 2
14 2.65 3 1 1 3
8 1.1 15 1 1 15 16.50
8 1.1 12 1 1 12 13.20
8 1.1 21 1 1 21 23.10
Total Length 344.74
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - 136.13 - -
SECTION B-
B TOP BAR
12 2.62 8 2 1 16 41.92
12 2.48 8 2 1 16 39.68
12 0.55 6 16 1 96 52.80
SECTION B-
B BOTTOM
BAR
12 6.14 8 2 1 16 98.24
12 1.6 8 2 1 16 25.60
12 1.77 8 2 1 16 28.32
SECTION A-
A TOP BAR
12 2.48 8 2 1 16 39.68
12 2.62 8 2 1 16 41.92
12 0.55 6 16 1 96 52.80
SECTION A-
A BOTTOM
BAR
12 6.14 8 2 1 16 98.24
12 1.77 8 2 1 16 28.32
12 1.6 8 2 1 16 25.60
Total Length 573.12
Weight/Kg 0.222 0.395 0.617 0.888
Total weight - - - 509.21
SUMMARY OF BAR SCHEDULE FOR SUPER STRUCTURE
DIA TOTAL WEIGHT (KG)
8 1238.00
10 1014.89
12 509.21
14 1335.55
16 1280.30
h of Bars (m) for Each Diameter
Ø 14 (mm) Ø 16 (mm) Ø 20 (mm) Ø 24 (mm)
14 16 20 24
55.20
55.20
110.40
1.209 1.580 2.468 3.554
133.51 - -
107.20
120.60
227.80
1.209 1.580 2.468 3.554
275.48 - -
17.50
16.10
19.30
17.90
10.90
9.50
10.30
8.90
9.10
7.70
20.80
19.40
20.80
19.40
20.80
19.40
247.80
1.209 1.580 2.468 3.554
299.67 - -
115.84
130.32
246.16
1.209 1.580 2.468 3.554
297.69 - -
26.25
2.60
24.15
28.95
2.60
26.85
16.35
14.25
15.45
13.35
26.25
2.60
24.15
31.20
2.99
2.70
29.10
31.20
2.99
2.70
29.10
11.55
9.45
15.30
13.20
10.20
7.95
18.15 405.28
1.209 1.580 2.468 3.554
21.95 640.15 -
1.209 1.580 2.468 3.554
- - -
115.84
130.32
246.16
1.209 1.580 2.468 3.554
297.69 - -
26.25
2.60
24.15
28.95
2.60
26.85
16.35
14.25
15.45
13.35
26.25
2.60
24.15
31.20
2.99
2.70
29.10
31.20
2.99
2.70
29.10
11.55
9.45
15.30
13.20
10.35
7.95
18.30 405.28
1.209 1.580 2.468 3.554
22.13 640.15 -
1.209 1.580 2.468 3.554
- - -
115.84
130.32
246.16
1.209 1.580 2.468 3.554
297.69 - -
17.10
24.15
18.90
26.85
10.50
14.25
9.90
13.35
17.10
24.15
20.40
29.10
20.40
29.10
7.30
9.45
9.80
13.20
6.50
7.95
329.45
1.209 1.580 2.468 3.554
398.41 - -
Bulck excavation
1.2
Bulk excavation in ordinary soil to a depth of up to 500
m3 48.28 197.90 9,553.96
mm from reduced level.
4 Reinforcement ……………………………………………………………………….
……………. 25,196.61 ETB
5 Masonary work ……………………………………………………………………………………. 25,196.61 ETB
B-SUPER STRUCTURE
VAT……………….15%
volume of work = 30 m3
bulk excavation to a depth of 50cm for the main building by leaving 61.52 m2 Total volume of backfill under hard core
0.25m working spacefrom the edge of the footing pad( where
necessary).A4 includes the area for verendah (entrance porch). 1.7 Cart away
0.5
3.1 2 1.6
0.5 1.6
8.75 1 1.4
3.2 1.4
14 m3 A4 4 1.2
3 1.5
1
pit excavation for footing pad at a depth of 1.55m by leaving 0.25m
working space each side(no working space for F4 to the left side) 4.5 m2 for F4
1 1.9 (4+3.4+3.85+3.65+4+1.35+3.6+2.65+2.2+3.9)m
1.55 0.4
1.55 0.8 m2
0.2
0.66 m2
trench excavation at a depth of 1.00m below the bulk excavation by
leaving 0.25m working space only to one side 0.85 b/n ''3-3' ''
1 5.1m-1m = 4.1m
2.67 m3
(trench excavation exclude the pad excavation and working space for
pad excavation)
15.31 m3 Total volume of trench excavation
4 on axis ''C ''
0.8 m2
0.2
0.68 m2
0.27 m2
0.2
0.73 m2
0.2
0.77 m2
0.23 m2
0.2
0.74 m2
0.2
0.77 m2
0.53 m2
0.2
0.44 m2
0.2
0.7802 m2
0.2
0.44 m2
(Derba)
>5km
(Gojjam,Sa
ba &
Welega)
(Ethio ceramics)
(Tid)
(Weira)
(Ethiopia)
(Nefas Silk)
(Nefas Silk)
"
"
"
(Kadisko)
(Kadisko)
(Kadisko)
(Kadisko)
(Nefas Silk)
"
"
"
Cost of Skilled and Unskilled Labour
Working Daily Indexed Hourly Indexed
No. Type of Labour Hours/day Rate Rate
1 Carpenter 8 250.00 31.25
9 Welder 8 200.00 25
11 Plasterer 8 200.00 25
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
0 D/L 1 1 10 10 Tool 2 1.00 2
0 G.Chief 1 1 15.00 15 0
0 forman 1 0.5 31.25 15.625 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 0 Total (1:02) 40.625 Total (1:03) 2
A= Materials Unit Co 0 Birr/m2 B= Manpower Unit Cost 45.65 Birr/m2 C= Equipment Unit Cost 2.25 Birr/m2
Total of (1:02) 1.44 Total of (1:03)
Hourly Output: 0.89 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 47.89 Birr/m2
Over head cost : 15% 7.18 "
Profit Cost: 15% 7.18 "
Total Unit Cost : 62.26 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 0.28 m3/hr.
WORK ITEM: ( 1.1 ) 0.5m depth bulck excavation on loose & dry soil. EQUIPEMENT: Tool
TOTAL QANTITY OF WORK ITE 1 m2 RESULT: 197.90 Birr/m3
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
0 D/L 1 1 10 10 Tool 2 1.00 2
0 G.Chief 1 1 15.00 15 0
0 L.forman 1 0.5 31.25 15.625 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 0 Total (1:02) 40.625 Total (1:03) 2
A= Materials Unit Co 0 Birr/m3 B= Manpower Unit Cost 145.09 Birr/m3 C= Equipment Unit Cost 7.14 Birr/m3
Total of (1:02) 1.44 Total of (1:03)
Hourly Output: 0.89 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 152.23 Birr/m2
Over head cost : 15% 22.83 "
Profit Cost: 15% 22.83 "
Total Unit Cost : 197.90 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 0.15 m3/hr.
WORK ITEM: ( 1.7) Excavation foundation pits to adepth of 150-300cm. In loose soil. EQUIPEMENT: Tool
TOTAL QANTITY OF WORK ITE 1 m3 RESULT: 360.75 Birr/m3
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
0 DL 1 1 10.00 10 Tools 1 1.00 1
0 G.Chief 1 1 15.00 15 0
0 L.forman 1 0.5 31.25 15.625 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 0 Total (1:02) 40.625 Total (1:03) 1
A= Materials Unit Co 0 Birr/m3 B= Manpower Unit Cost 270.83 Birr/m3 C= Equipment Unit Cost 6.67 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _____________
Direct Cost of Work Item = A+B+C = 277.50 Birr/m3
Over head cost : 15% 41.63 "
Profit Cost: 15% 41.63 "
Total Unit Cost : 360.75 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
0 DL 1 1 10.00 10 Tools 1 1.00 1
0 G.Chief 1 1 15.00 15 0
0 L.forman 1 0.5 31.25 15.625 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 0 Total (1:02) 40.625 Total (1:03) 1
A= Materials Unit Co 0 Birr/m3 B= Manpower Unit Cost 270.83 Birr/m3 C= Equipment Unit Cost 6.67 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _____________
Direct Cost of Work Item = A+B+C = 277.50 Birr/m3
Over head cost : 15% 41.63 "
Profit Cost: 15% 41.63 "
Total Unit Cost : 360.75 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 2 m3/hr.
WORK ITEM: ( 1.13)Back fill excavated materials from the site. EQUIPEMENT: Tool
TOTAL QANTITY OF WORK ITE 1 m3 RESULT: 51.28 Birr/m3
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
0 foreman 1 0.5 31.25 15.63 tool 2 1.00 2
0 DL 2 1 10.00 20 compactor 1 26.27 26
0 G.CHIEF 1 1 15.00 15 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 0 Total (1:02) 50.63 Total (1:03) 28.27
A= Materials Unit Co 0 Birr/m3 B= Manpower Unit Cost 25.3125 Birr/m3 C= Equipment Unit Cost 14.14 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 39.45 Birr/m3
Over head cost : 15% 5.92 "
Profit Cost: 15% 5.92 "
Total Unit Cost : 51.28 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
0 forman 1 0.25 31.25 7.81 loader wit 1 550.00 550
0 G.chief 1 1 15.00 15.00 dump truc 4 330 1320
0 DL 4 1 10 40 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 0 Total (1:02) 62.81 Total (1:03) 1870
A= Materials Unit Co 0 Birr/m3 B= Manpower Unit Cost 0.87 Birr/m3 C= Equipment Unit Cost 25.97 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _____________
Direct Cost of Work Item = A+B+C = 26.84 Birr/m3
Over head cost : 15% 4.03 "
Profit Cost: 15% 4.03 "
Total Unit Cost : 34.90 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
** Indexed Type of
Cost per Labour Hourly Hourly Equipme Hourly Hourly
Type of Material Unit Qty * Rate Unit by Grade No. UF Cost Cost nt No. Rental Cost
basaltic stone m2 0.4 165.00 66 foreman 1 0.33 31.25 10.31 tools 3 1.00 3
0 mason 1 1 31.25 31.25
0 DL 4 1 10.00 40 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:-01) 66 Total (1:02) 81.56 Total (1:03) 3
A= Materials Unit Co 66 Birr/m2 B= Manpower Unit Cost 40.78 Birr/m2 C= Equipment Unit Cost 1.50 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 108.28 Birr/m2
Over head cost : 15% 16.24 "
Profit Cost: 15% 16.24 "
Total Unit Cost : 140.77 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT U
PROJECT: CONCRETE WORK
WORK ITEM: ( 3.1 ) C-5 Lean Concrete (Hand mix) 1:2:7
TOTAL QUANTITY OF WORK ITEM: 1 m2 0.05 m. thick
**
Indexed
Hourly Hourly Type of Hourly Hourly
UF Cost Cost Equipment No. Rental Cost
1 31.25 31.25 tool 2 1.00 2
1 10.00 20 - 0
0.5 31.25 15.625 0
0 0
0 0
0 0
0 0
Total (1:02) 66.875 Total (1:03) 2
**
Indexed
Hourly Hourly Type of Hourly Hourly
UF Cost Cost Equipment No. Rental Cost
1 12.5 12.50 mixer 1 85.00 85
1 10 60.00 vibrator 1 25.00 25
0.33 31.25 10.31 0
1 31.25 31.25 0
1 12.5 12.50 0
0.00 0
0.00 0
0.00 0
0.00 0
Total (1:02) 126.56 Total (1:03) 110
**
Indexed
Hourly Hourly Type of Hourly Hourly
UF Cost Cost Equipment No. Rental Cost
0.33 31.25 10.3125 Mixer 1 85.00 85
1 31.25 62.5 Vibrator 1 25.00 25
1 10.00 450 0
1 12.5 12.5 0
1 12.5 12.5 0
0 0
0 0
0 0
Total (1:02) 547.81 Total (1:03) 110
**
Indexed
Hourly Hourly Type of Hourly Hourly
UF Cost Cost Equipment No. Rental Cost
1 12.5 12.50 mixer 1 85.00 85
1 10 120.00 vibrator 1 25.00 25
0.5 31.25 15.63 0
1 31.25 62.50 0
1 12.5 12.50 0
0.00 0
0.00 0
223.13 110
**
Indexed
Hourly Hourly Type of Hourly Hourly
UF Cost Cost Equipment No. Rental Cost
1 12.5 12.50 mixer 1 85.00 85
1 10 60.00 vibrator 1 25.00 25
0.5 31.25 15.63 0
1 31.25 31.25 0
1 12.5 12.50 0
0.00 0
0.00 0
Total (1:02) 131.88 Total (1:03) 110
**
Indexed
Hourly Hourly Type of Hourly Hourly
UF Cost Cost Equipment No. Rental Cost
1 12.50 12.50 mixer 1 85.00 85
1 10.00 60.00 vibrator 1 25.00 25
0.33 31.25 10.31 0
1 31.25 31.25 0
1 12.5 12.50 0
0.00 0
0.00 0
0.00 0
0.00 0
Total (1:02) 126.5625 Total (1:03) 110
Cost per
Type of Material Unit Qty * Rate Unit Labor by Trade
Flush wooden door m2 1 1000.00 1000.00 Foreman
Cylindrical lock Pcs. 1 420.00 420.00 Carpenter I
Helper
**
Indexed Type of
Hourly Equipme Hourly
No. UF Cost Hourly Cost nt No. Hourly Rental Cost
0.25 1 31.25 7.81 Tools 3 1.00 3
1 1 31.25 31.25 0
1 1 10.00 10 0
1 1 10.00 10 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 59.06 Total (1:03) 3
ED TO TARGETED OUTPUT.
ED TO TARGETED OUTPUT.
**
Indexed Type of
Hourly Equipme Hourly
No. UF Cost Hourly Cost nt No. Hourly Rental Cost
1 0.167 31.25 5.21875 0.00
1 1 31.25 31.25 0.00
1 1 10.00 10 0.00
3 1 10.00 30 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
Total ( 1: 02 ) 76.47 Total (1:03) 0.00
ED TO TARGETED OUTPUT.
**
Indexed Type of
Hourly Equipme Hourly
No. UF Cost Hourly Cost nt No. Hourly Rental Cost
1 0.25 31.25 7.8125 0.00
1 1 31.25 31.25 0.00
2 1 10.00 20 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
Total ( 1: 02 ) 59.06 Total (1:03) 0.00
6.88 Birr/ml. C= Equipment Unit Cost
Total of (1:03)
tput: _________________ Hourly output: __________________
ork Item = A+B+C = 34.03 Birr/ml.
15% 5.10 "
15% 5.10 "
44.24 Birr/ml.
ED TO TARGETED OUTPUT.
**
Indexed Type of
daily Equipme Daily
No. UF wage Daily wage nt No. Daily Rental Cost
1 0.25 31.25 7.81 tools 2 1.00 2.00
1 1 31.25 31.25 5.00
1 1 10 10.00
ED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UN
PROJECT: FINISHING WORKS.
WORK ITEM: (11.1) 3 Coats of cement plastering ( 1:3 ) (both external and internal wall)
TOTAL QANTITY OF WORK ITEM: 1 m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
0
0
0
Total (1:01) 714.64 Total (1:02)
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT
PROJECT: FINISHING WORKS.
WORK ITEM: (11.27) ceramic tile skirting (1:3).
TOTAL QANTITY OF WORK ITEM: 1 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT
DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 1.08 m2/hr
rnal and internal wall) EQUIPEMENT:
RESULT : 154.56 Birr/m2
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.5 31.25 15.63 tools 2 1.00 2
1 1 25.00 25 0
1 1 18.75 18.75 0
1 1 10.00 10 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 69.38 Total (1:03) 2
wer Unit Cost 64.24 Birr/m2 C= Equipment Unit Cost 1.85 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 125.15 Birr/m2
Over head cost : 15% 18.77 "
Profit Cost: 15% 18.77 "
Total Unit Cost : 162.69 Birr/m2
wer Unit Cost 95.62 Birr/m2 C= Equipment Unit Cost 2.99 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 130.12 Birr/m2
Over head cost : 15% 19.52 "
Profit Cost: 15% 19.52 "
Total Unit Cost : 169.15 Birr/m2
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 Tools 2 1.00 2
1 1 25.00 25 0
1 1 10.00 10 0
0 0
0 0
0 0
0 0
Total (1:02) 42.81 Total (1:03) 2
wer Unit Cost 17.13 Birr/m2 C= Equipment Unit Cost 0.80 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 37.98 Birr/m2
Over head cost : 15% 5.70 "
Profit Cost: 15% 5.70 "
Total Unit Cost : 49.38 Birr/m2
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 Tools 2 1.00 2
1 1 31.25 31.25 0
1 1 10.00 10 0
2 1 16.25 32.5 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 81.56 Total (1:03) 2
wer Unit Cost 65.25 Birr/m2 C= Equipment Unit Cost 1.60 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 451.73 Birr/m2
Over head cost : 15% 67.76 "
Profit Cost: 15% 67.76 "
Total Unit Cost : 587.24 Birr/m2
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 tools 1 1.00 1
1 1 31.25 31.25 0
2 1 10 20 0
0 0
0 0
0 0
0 0
Total (1:02) 59.06 Total (1:03) 1
wer Unit Cost 17.12 Birr/m2 C= Equipment Unit Cost 0.29 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 162.79 Birr/m2
Over head cost : 15% 24.42 "
Profit Cost: 15% 24.42 "
Total Unit Cost : 211.63 Birr/m2
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 grinder 1 10.00 10
1 1 31.25 31.25 0
1 1 10.00 10 0
2 1 16.25 32.5 0
0 0
0 0
0 0
0 0
Total (1:02) 81.56 Total (1:03) 10
wer Unit Cost 92.68 Birr/m2 C= Equipment Unit Cost 11.36 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 1374.65 Birr/m2
Over head cost : 15% 206.20 "
Profit Cost: 15% 206.20 "
Total Unit Cost : 1787.05 Birr/m2
wer Unit Cost 67.12 Birr/m2 C= Equipment Unit Cost 11.36 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 1351.46 Birr/ml
Over head cost : 15% 202.72 "
Profit Cost: 15% 202.72 "
Total Unit Cost : 1756.90 Birr/ml
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 grinder 1 10.00 10
1 1 31.25 31.25 0
2 1 10 20 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 59.06 Total (1:03) 10
wer Unit Cost 52.27 Birr/ml C= Equipment Unit Cost 8.85 Birr/ml
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 437.01 Birr/ml
Over head cost : 15% 65.55 "
Profit Cost: 15% 65.55 "
Total Unit Cost : 568.12 Birr/ml
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 1 16.25 16.25 Tools 2 1.00 2
1 1 31.25 31.25 0
1 0.25 31.25 7.81 0
0
0
0 0
0 0
0 0
0 0
Total (1:02) 55.31 Total (1:03) 2
wer Unit Cost 9.22 Birr/m2 C= Equipment Unit Cost 0.33 Birr/m2
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 724.19 Birr/m2
Over head cost : 15% 108.63 "
Profit Cost: 15% 124.92 "
Total Unit Cost : 957.74 Birr/m2
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 grinder 1 10.00 10
1 1 31.25 31.25 0
1 1 10.00 10 0
1 1 10.00 10 0
0 0
0 0
0 0
Total (1:02) 59.06 Total (1:03) 10
wer Unit Cost 23.63 Birr/ml C= Equipment Unit Cost 1.50 Birr/ml
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 404.86 Birr/ml
Over head cost : 15% 60.73 "
Profit Cost: 15% 60.73 "
Total Unit Cost : 526.32 Birr/ml
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 grinder 1 10.00 10
1 1 31.25 31.25 0
1 1 10 10 0
1 1 10 10 0
0 0
0 0
0 0
Total (1:02) 59.06 Total (1:03) 10
wer Unit Cost 23.63 Birr/ml C= Equipment Unit Cost 1.50 Birr/ml
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 326.49 Birr/ml
Over head cost : 15% 48.97 "
Profit Cost: 15% 48.97 "
Total Unit Cost : 424.44 Birr/ml
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 tools 1 1.00 1
1 1 31.25 31.25 0
1 1 10.00 10 0
0 0
0 0
0 0
0 0
Total (1:02) 49.06 Total (1:03) 1
wer Unit Cost 24.53 Birr/ml C= Equipment Unit Cost 0.50 Birr/ml
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 41.34 Birr/ml
Over head cost : 15% 6.20 "
Profit Cost: 15% 6.20 "
Total Unit Cost : 53.74 Birr/ml
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.25 31.25 7.81 tools 1.00 1.00 1
1 1 31.25 31.25 0
1 1 10 10 0
0 0
0 0
0 0
0 0
Total (1:02) 49.06 Total (1:03) 1
wer Unit Cost 16.35 Birr/ml C= Equipment Unit Cost 0.33 Birr/ml
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 55.77 Birr/ml
Over head cost : 15% 8.36 "
Profit Cost: 15% 8.36 "
Total Unit Cost : 72.49 Birr/ml
**
Indexed Type of
Hourly Hourly Equipmen Hourly Hourly
No. UF Cost Cost t No. Rental Cost
1 0.33 31.25 10.31 grinder 1 10.00 10
1 1 31.25 31.25 0
2 1 10.00 20 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 61.56 Total (1:03) 10
wer Unit Cost 32.75 Birr/ml C= Equipment Unit Cost 1.99 Birr/ml
l of (1:02) Total of (1:03)
rly Output: _______________________ Hourly output: _________________
of Work Item = A+B+C = 116.71 Birr/ml
Over head cost : 15% 17.51 "
Profit Cost: 15% 17.51 "
Total Unit Cost : 151.72 Birr/ml
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.5 31.25 15.63 tool 2 1.00 2
1 31.25 31.25 0
1 10.00 10.00 0
1 10.00 10.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
Total (1:02) 66.88 Total (1:03) 2
TO TARGETED OUTPUT.
TO TARGETED OUTPUT.
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.33 31.25 10.31 tool 2 1.00 2
1 31.25 31.25 0
1 10.00 10.00 0
1 10.00 10.00 0
0.00 0
0.00 0
0.00
0.00
0.00
0.00
Total (1:02) 61.56 Total (1:03) 2.00
TO TARGETED OUTPUT.
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.33 31.25 10.31 tool 2 1.00 2
1 31.25 31.25 0
1 10.00 10.00 0
1 10.00 10.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
Total (1:02) 61.56 Total (1:03) 2.00
TO TARGETED OUTPUT.
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.33 31.25 10.31 tool 2 1.00 2
1 31.25 31.25 0
1 10.00 10.00 0
1 10 10.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
Total (1:02) 61.56 Total (1:03) 2
C=Equipment Unit Cost
111.9318 Birr/m2 Total of (1:03) 3.64 Birr/m2
Hourly output: _________________
em = A+B+C = 212.97 Birr/m2
15% 31.95 Birr/m2
15% 31.95 Birr/m2
276.86 Birr/m2
TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COS
PROJECT: WALLING
WORK ITEM: ( 6.9 ) 15 cm. thick HCB Wall Both Sides Left For Plastering.
TOTAL QANTITY OF WORK ITEM: 1 m2
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
Cost Cost nt No. Rental Cost
31.25 15.63 Tools 2 1.00 2
31.25 31.25 0
10.00 20 0
0 0
0 0
0 0
0 0
:02 ) 66.88 Total (1:03) 2.00
O TARGETED OUTPUT.
O TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT
PROJECT: MASONRY WORKS
WORK ITEM : ( 400 mm thick stone masonry bedded in cement mortar (1:3) mix
TOTAL QANTITY OF WORK ITEM: 1 m3
**
Indexed
Hourly Type of Hourly Hourly
Cost Hourly Cost Equipment No. Rental Cost
31.25 15.63 tools 1 1.00
31.25 62.50
18.75 18.75
10.00 60.00
**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
0 6 - 0 8 mm plain bars kg 1.05 25.0 26.25 Foreman 1 0.50 31.25 15.63 0
1.5 mm black anneald wire " 0.05 33.00 1.65 Barbender 1 1 18.75 18.75 0
0 D/L 3 1 10.00 30.00 0
0 0.00 0
0 0.00 0
0 0.00 0
0 0.00 0
Total (1:-01) 27.90 Total (1:02) 64.38 Total (1:03) 0
A= Materials Unit Cost 27.90 birr/kg B= Manpower Unit Cost 6.44 Birr/kg. Equipment Unit Cost 0.00 Birr/kg.
Total of (1:02) Total of (1:03)
hourly output: 7.08/9=0.79 Hourly output: ____________
Direct Cost of Work Item = A+B+C = 34.34 Birr/kg.
Over head cost : 15% 5.15 "
Profit Cost: 15% 5.15 "
Total Unit Cost : 44.64 Birr/kg.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
0 10- 0 16 mm deformed bars kg 1.05 20.02 21.021 foreman 1 0.5 31.25 15.63 0
1.5 mm black Annealed wire " 0.0125 33.00 0.4125 bar bender 1 1 18.75 18.75 0
0 D/L 6 1 10.00 60.00 0
0 0
0
0 0
0 0
0 0
0 0
0 0
Total (1:-01) 21.4335 Total (1:02) 94.375 Total (1:03) 0
A= Materials Unit Cost 21.4335 Birr/kg. B= Manpower Unit Cost 7.55 Birr/kg. C= Equipment Unit Cost 0 Birr/kg.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________11.25/12.5=0.90 Hourly output: ___________
Direct Cost of Work Item = A+B+C = _ 28.9835 Birr/kg.
Over head cost : 15% 4.348 "
Profit Cost: 15% 4.348 "
Total Unit Cost : 37.679 Birr/kg.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT C
PROJECT: ROOFING WORKS
WORK ITEM: ( 7.10 ) EGA 300 & 4mm. Thick Roof cover
TOTAL QANTITY OF WORK ITEM: 1 m2
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.2 31.25 6.25 Tools 2 1.00 2.00
1 31.25 31.25 0.00
1 10.00 10 0.00
1 10.00 20 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
Total ( 1: 02 ) 67.50 Total (1:03) 2.00
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.2 31.25 6.25 Tools 2 1.00 2
1 31.25 31.25 0
1 10.00 10.00 0
1 10.00 10.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
Total (1:02) 57.50 Total (1:03) 2.00
0
0
0
Total (1:-01) 13.60 Total (1:02)
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.5 31.25 15.63 tools 1 1.00 1
1 18.75 18.75
1 10 10 0
0 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 44.375 Total (1:03) 1
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.5 31.25 15.63 Tools 2 1.00 2
1 18.75 18.75 0
1 10 10 0
0 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 44.375 Total (1:03) 2
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.2 35 7.00 tools 1 1 1
1 18.75 18.75 0
1 10 10 0
0 0
0 0
0 0
0 0
0 0
0 0
Total (1:02) 35.75 Total (1:03) 1
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
UF Cost Cost nt No. Rental Cost
0.25 31.25 7.81 tools 1.00 1.00 1.00
1.00 25.00 25.00 0.00
1.00 10.00 10.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
42.81 Total (1:03) 1.00
**
Indexed Type of
Hourly Hourly Equipme Hourly Hourly
Cost Cost nt No. Rental Cost
31.25 10.3125 tools 2 1.00 2
18.75 18.75 0
10 10 0
0 0
0 0
0 0
0 0
1:02) 39.06 Total (1:03) 2
**
Indexed
Hourly Type of Hourly Hourly
Cost Hourly Cost Equipment No. Rental Cost
31.25 7.8125 tool 1 1.00 1
25 25 0
12.5 25 0
0
0
0
0
1:02) 57.8125 Total (1:03) 1
TO TARGETED OUTPUT.
**
Indexed
Hourly Type of Hourly Hourly
Cost Hourly Cost Equipment No. Rental cost
31.25 31.25 Weld mach 1 32.00 32
25.00 75 tools 5 1.00 5
10.00 30
12.5 63
31.25 31.25
18.75 18.75
0
0
1:02) 248.75 Total (1:03) 37