Cont. Equipment
Cont. Equipment
Cont. Equipment
Introduction..................................................................................................................................................... - 2 -
1. Site clearance work ..................................................................................................................................... - 4 -
2. Bulk excavation work: ................................................................................................................................ - 5 -
2.1 Bulk Excavation in ordinary soil not exceeding 1.5m ........................................................................ - 7 -
2.2 Bulk Excavation in ordinary soil exceeding 1.5m but not exceeding 3m ......................................... - 7 -
2.3 Bulk Excavation in ordinary soil exceeding 3m but not exceeding 6m ............................................ - 7 -
2.4 Bulk Excavation in ordinary soil exceeding 6m but not exceeding 10m .......................................... - 8 -
3. Loading hauling work: ............................................................................................................................... - 9 -
1. Wheel loaders...................................................................................................................................... - 9 -
2. Rear Dump trucks ............................................................................................................................- 10 -
4. Finishing work: .........................................................................................................................................- 13 -
5. Equipment scheduling ..............................................................................................................................- 15 -
References: ....................................................................................................................................................- 17 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
Introduction
-2-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
Item
Description UN
No Quantity
IT
A. SUB-STRUCTURE
01. EXCAVATION AND EARTH WORK
1.1 M2
Site clearing to an average depth of 200mm 185,409.00
1.2 Bulk Excavation
1.2.1 M3
Bulk Excavation in ordinary soil not exceeding 1.5m 217,145.39
Bulk Excavation in ordinary soil exceeding 1.5m but not
1.2.2 M3
exceeding 3m 188,830.70
Bulk Excavation in ordinary soil exceeding 3m but not
1.2.3 M3
exceeding 6m 269,137.32
Bulk Excavation in ordinary soil exceeding 6m but not
1.2.4 M3
exceeding 10m 118,337.92
Select fill for site work with selected material and compact in
1.2.5 M3
layers with the interval of 200mm 115,406.00
1.3 Load and cart away surplus materials to an appropriate place M3 1,008,493.8
(less than 5km) 0
-3-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
-4-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
Excavator model 345C caterpillar used for extreme excavation foe Europe, African
and middle east standard with bucket capacity≈4-cy.
-5-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
-6-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
2.2 Bulk Excavation in ordinary soil exceeding 1.5m but not exceeding 3m
-7-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
2.4 Bulk Excavation in ordinary soil exceeding 6m but not exceeding 10m
The total volume excavation work is the sum of the bulk excavation works. The
excavation work is beginning after the site clearance is done or along with the
excavation work. so, the excavation is start after five day of the site clearing.
= 793,451.33m3
793451.33m3
Total time needed to excavate by 1 excavator = = 175 days
4534𝑚3/𝑑𝑎𝑦
Total work is done in 85 days but after 5 days of the site clearing
175𝑑𝑎𝑦
No. of excavator = = 2.66 ≈ 3
85𝑑𝑎𝑦
-8-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
-9-
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
The haul route from loading point to the waste site is 4.5km(3.12mile)
Dump time 3min, the common soil has a loose unit weight of 1,960 lb./cy
A. For 16 buckets:
- 10 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
B. For 17 buckets:
C. Haul time
Since we want to get maximum productivity, we are going to use number of buckets.
▪ Gross weight = Empty truck net weight + Weight of load= 134,064 + 142443
▪ The speed of truck loaded = 17mph and haul distance is taken less than 5km
we take maximum at 4.5km cart away distance
2.8𝑚𝑖𝑙𝑒
▪ Haul time loaded = = 0.12hr. = 7.2min.
23.94𝑚𝑖𝑙𝑒/ℎ𝑟
2.8𝑚𝑖𝑙𝑒
▪ Haul time return = = 5.26min
31.92𝑚𝑖𝑙𝑒/ℎ𝑟
▪ Dump time = 3min.
▪ Total truck cycle time (16 bucket) = 8.8 + 3 + 7.2 + 5.26 = 24.26min
▪ Total truck cycle time (17 bucket) = 9.35 + 3 + 7.2 + 5.26 = 24.81min
𝑡𝑟𝑢𝑐𝑘 𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 24.26𝑚𝑖𝑛
➢ Number trucks (17 bucket) = = = 2.76
𝑙𝑜𝑎𝑑𝑒𝑟 𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 8.8𝑚𝑖𝑛
trucks/loader/hr.
𝑡𝑟𝑢𝑐𝑘 𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 24.81𝑚𝑖𝑛
➢ Number trucks (17 bucket) = = = 2.65
𝑙𝑜𝑎𝑑𝑒𝑟 𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 9.35𝑚𝑖𝑛
trucks/loader/hr.
➢ Total number of trucks = no. of loader*no. of truck/loader =4*2.38 =9.52 trucks
D. Calculate productivity of trucks:
- 11 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
60𝑚𝑖𝑛 50𝑚𝑖𝑛
P = 72.68cy*2 trucks*24.81𝑚𝑖𝑛*60𝑚𝑖𝑛 = 292.95 cy/hr.
60𝑠𝑒𝑐 50𝑚𝑖𝑛
P = 72.68cy*9.35𝑠𝑒𝑐*60𝑚𝑖𝑛 = 388.66cy/hr.
E. Comparing the hourly production of the loader and the dump trucks and
selecting appropriate number of trucks.
For (2 truck/loader):
380.864𝑡𝑜𝑛/ℎ𝑟∗2000𝑙𝑏/𝑡𝑜𝑛
Loader production per hour = 1960𝑙𝑏/𝑐𝑦
=388.64cy/hr.
The dump truck production is less than loader production so we need additional
dump trucks.
For (3 truck/loader)
380.864𝑡𝑜𝑛/ℎ𝑟∗2000𝑙𝑏/𝑡𝑜𝑛
Loader production per hour = 1960𝑙𝑏/𝑐𝑦
=388.64cy/hr.
The dump truck production is equal loader production it satisfies our requirement.
- 12 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
4. Finishing work:
1 Grader: are commonly used in the construction
and maintenance of dirt and gravel roads for
creating a flat surface where the asphalt will be
placed.
Table-3
Le = 3.66m*cos30 = 3.17m
- 13 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
9⋅7𝑘𝑚/ℎ𝑟+14⋅5𝑘𝑚/ℎ𝑟
The operatizing speed for spreading Vavg = = 12.1km/hr.
2
- 14 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
5. Equipment scheduling
Equipment scheduling of the project with 90 calendar days beginning in July-1-
2023 and end in September-28-2023.
- 15 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
Site Clerance
Excavarion Stage I
Excavation Stage II
Excavation Stage IV
Site Finishing
- 16 -
CONSTRUCTION EQUIPMENT PRODUCTIVITY AND SCEDULING
References:
▪ Caterpillar performance handbook, 36 edition.
▪ Construction equipment handout.
- 17 -