Chapter 2 Quantity Survey
Chapter 2 Quantity Survey
Chapter 2 Quantity Survey
Chapter 2
Quantity Survey
May 2024
5. Taking-off Work
A. Example
B. Project
industry to:
estimate the cost of works either for each trade of work or for the whole
project.
rates)
of payment certificates
9. Valuation of property
either from drawings or the building itself for defining the extent of
Method of Measurement for Building Works. Adds Ababa, Ethiopia. (71 Pages)
B. SUPER-STRUCTURE
2.2 Super-Structure Concrete
Reinforced concrete class C-25 cast into formwork and
2.2.1 vibrated around reinforcement bars (formwork and
reinforcement measured separately);
3
a) In elevation columns m 9.32 4692.33 43,732.52
3
b) In top-tie beams m 29.76 4692.33 139,643.74
Supply, cut and fix in position sawn structural timber or steel
2.2.2
formwork whichever is appropriate; 0.00
a) In elevation columns m2 126.83 549.86 69,738.74
2
b) In top-tie beams m 272.80 549.86 150,001.81
Steel reinforcement bar according to structural drawing. Price
2.2.3
includes cutting, bending, placing in position and tying wires;
0.00
a) 8mm diameter deformed bar Kg 1,018.57 71.48 72,807.38
b) 14mm diameter deformed bar Kg 2,146.45 69.95 150,144.18
TOTAL CARRIED TO SUMMARY 626,068.37
3. MASONRY WORK
400mm thick basaltic or equivalent stone masonry bedded in
3.1 3
cement sand mortar mix (1:3). m 97.10 2052.46 199,293.87
TOTAL CARRIED TO SUMMARY 199,293.87
4. HCB WORK
Supply and construct class B HCB walls both sides left for
4.1 plastering, bedded in cement mortar (1:3). Price shall include
mortar bed.
a) 200 mm thick class B HCB wall. m2 527.68 617.63 325,911.00
TOTAL CARRIED TO SUMMARY 325,911.00
5. ROOFING
Roof cover in galvanized EGA 500, t=0.6mm fixed to steel truss
5.1 purlins placed to c/c 150cm. (purlin measured separately and
2
roof measured in horizontal projection). m 476.00 511.99 243,707.24
Supply and fix water gutter made of flat sheet metal with other
5.2
necessary accessories. ml 42.40 550.43 23,338.23
TOTAL CARRIED TO SUMMARY 267,045.47
34.01(b)i
Grouted Stone Pitching (minor drainages) m2 1,471.00 2472.03 3,636,361.13
34.01(b)ii Grouted Stone Pitching (Side ditches) m2 4,443.00 2472.03 10,983,244.40
Outline 1 2 3 4 5
34.03 Stone Masonry wall Quantity Survey 21 of 83
34.03(b) Cement mortared stone masonary m3 24,438.00 2472.03 60,411,552.23
TOTAL FOR SERIES 3000 : DRAINAGE 100,611,928.39
Typical Work Items
Sign faces with painted background, symbols, lettering and borders in Engineering
94.01
grade retro-reflective material with signboard constructed from:
94.01(a) Sign faces made by aluminum alloy of thickness 2mm and fixed on post complete,area not
exceeeding 2sq.m. m2 19.00 535.00 10,165.00
94.01(b) Sign faces made by aluminum alloy of thickness 2mm and fixed on post complete,area exceeding
2sq.m but not exceeding 10sq.m,as shown on the drawing. m2 43.00 535.00 23,005.00
94.02 Sign supports:
94.02 (b) Steel posts No 59.00 400.00 23,600.00
3
94.03 Concrete in road sign footing including excavation and backfilling m 15.00 1,754.61 26,319.12
9500 Road Traffic Markings and Road Studs
95.01 Paint
Paint, white broken line for centre line, width 100mm (thermoplastic),3.0m painted and 9.0m
95.01(a)(i)
gap or unbroken Km 30.00 1,000.00 30,000.00
Paint, White line broken for Parking lane, width 100mm (thermoplastic), 2.0m painted and 2.0m
95.01(a)ii 9.00
gap Km 1,200.00 10,800.00
95.01(a)iii Zebra Crossing (see road marking detail) No 8.00 500.00 4,000.00
95.01(b) Paint, yellow unbroken line for road edges, width 100mm (road marking/ thermoplastic), Km 52.00 800.00 41,600.00
9900 Walk Way 0.00
Non Slippery terrazo tiles, Constructed with (221mmx220mmx70mm) Pre colored, size
99.01(a)
(400mm*400mm*50mm) m2 19,813.00 1,300.00 25,756,900.00
Cement stabilized sand bed (max. 4% by weight of cement) including the necessary jointing
99.01(b) m3 955.00 1,411.72 1,348,195.29
Outline
works 1 2 3 4 5 Quantity Survey 26 of 83
TOTAL FOR SERIES 9000 : ANCILLARY WORKS 32,122,230.01
Typical Work Items
D.2 Materials
D.2.1 Portland cement tonne 40 1,740.00 69,600.00
3
D.2.2 Coarse crushed aggregate m 750 95.40 71,550.00
3
D.2.3 Fine aggregate m 500 104.00 52,000.00
D.2.4 tonne 5 0.00
D.2.5 Mild steel reinforcement tonne 2 39,000.00 78,000.00
D.2.6 Timber for formwork sqm 250 712.00 178,000.00
D.2.7 Formwork Steel sqm 300 1,158.00 347,400.00
D.2.8 Cutback bitumen MC-30 litre 1,500 29.00 43,500.00
D.2.9 Cutback asphalt MC-3000 litre 2,000 27.00 54,000.00
Subtotal D.2 894,050.00
2. Squaring
3. Abstracting
and materials necessary for the work and entering the items on
The standard form used for entering the dimensions taken or scaled
The take off used for taking off is usually double – ruled as shown
Consultant Contractor
3. timising,
6. waste calculations,
7. deduction of items,
the case may be, multiplied by the timising factor, and the
Show Video
➢ Shall be measured in 𝑚3
➢ Measured by (𝑚3 )
Outline 1 2 3 4 5 Quantity Survey 52 of 83
b) Formwork
➢ A temporary structural element which gives concrete
it’s shape & size
Footing reinforcement
Outline 1 2 3 4 5 Quantity Survey 55 of 83
3. Masonry work
a) Foundation wall
➢ Is undressed stone wall constructed under grade beams
for the purpose of supporting the grade beam &
stiffening the foundation
➢ Measured in (𝑚3 )
Slab reinforcement
Outline 1 2 3 4 5 Quantity Survey 59 of 83
Formwork to Column Formwork to Staircase
Plastering Pointing
Outline 1 2 3 4 5 Quantity Survey 65 of 83
4. Electrical Installation
Deliverables
2. Bill of Quantities