MR - PRIYANTHA VILLA 1 For Bidding

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 45

BILL OF QUANTITIES OF THE

PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA
@ PARAMULLA, MATARA.
VILLA - I

Architectural, Structural Design & Consulting

No;63/1/1, Akuressa road, Matara, Sri Lanka


Tel / Fax : 94 41-2 234 433, Mob : 94 71 0 554 654
clustereng@gmail.com, cluster@sltnet.lk
Mr.Uyanahewage Priyantha Sub Structure

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I
SUB STRUCTURE
ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

A PRELIMINARIES

A1 Provide Lump Sum to construct equip and maintain


temporary buildings for protection and storage of
materials and plants and work shops. Contractor's Staff
accommodation. Including toilet, septic system and other
sanitary fascilities with plumbing Item 1.000 500,000.00 500,000.00

A2 Provide Lump Sum to construct and maintain temporary


covering fence specially for safety and security purpose
to avoiding un authorized entry, student safety and Item 1.000 500,000.00 500,000.00

A3 Demolishing Existing building and remove all unnecessary


trees, roots and debris as directed from the site Item Nill -

A4 Allow a Lump Sum for providing scaffolding and self


climbing platforms during the Works Item 1.000 100,000.00 100,000.00

A5 Provide Lump Sum for supplying water for use in the


works. Item 1.000 100,000.00 100,000.00

A6 Provide Lump Sum for supplying electricity for use in


the works. Item 1.000 150,000.00 150,000.00

A7 Provide Lump Sum for removal of all rubbish & debris


and clearing up site on completion, leaving all in good
order & handing over. Item 1.000 150,000.00 150,000.00

PRELIMINARIES CARRIED TO SUMMARY Rs. 1,500,000.00

B EXCAVATION & EARTHWORKS

B1 Allow for clearing of site Item 1.000 50,000.00 50,000.00

B2 Excavate over site to remove average 150mm thick top


soil, stack the same for future use and remove surplus
materials from site. Item 1.000 100,000.00 100,000.00

B3 Excavation for wall foundation, tie beams, column


footings & staircase footings depth not exceeding 2m
part back fill & remove surplus earth m3 174.152 875.00 152,383.00

B4 Filling and making up levels with selected excavated


earth or imported soil under floor, ramps, well watered
and compacted in layers not exceeding 150mm thick. m3 25.555 2,975.00 76,026.13

Cluster Engineering Consultants (Pvt) Ltd. 1


Mr.Uyanahewage Priyantha Sub Structure

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT
Excavation & Earthworks to Collection 378,409.13

EXCAVATION & EARTHWORKS (Cont'd)

Earthwork Supports

B5 Allow for timber earth work supports as instructed by


the Engineer. (Provisional) Item 1.000 50,000.00 50,000.00

Dewatering

B6 Allow for dewatering and keeping site free from water


through out the period of construction. Item 1.000 50,000.00 50,000.00

Termite Treatment

B7 Termite treatment to soil in excavated surfaces, under


foundations & under floors on ground. (to be done by a
specialized contractor & a guarantee should be
submitted. - Approximate plinth area 1100 m2) m2 225.371 581.00 130,940.55

EXCAVATION & EARTH WORKS CARRIED TO


SUMMARY Rs. 609,349.68

C CONCRETE WORKS

Grade 15 Concrete (1:3:6)

C1 50mm thick blinding layer under column footings,


stair footings etc. m2 102.734 1,600.00 164,374.40

Grade 20 Concrete (1:2:4)

C2 Floor slab on grade including 1000 gauge polythene damp


proof membrane under floor slab on compacted soil layer m3 9.148 32,000.00 292,731.20

Grade 25 Concrete (1:11/2:3)

Reinforced cement concrete in grade 25, fill into formwork and


well packed around Reinforcement. Rate to be included with
curing. It should be kept voids for service ducts as shown in
the drawing.

C3 Column footings m3 16.891 33,100.00 559,099.71

C4 Columns shafts up to Ground floor level m3 2.608 33,350.00 86,966.38

C5 Plinth beams m3 4.069 34,400.00 139,970.16

C6 Ground floor slab beams m3 10.875 34,200.00 371,933.98

C7 Concrete wall m3 17.115 34,400.00 588,748.52

C8 Sump & balancing tank slab m3 1.241 34,400.00 42,675.61

C9 Staircase up to ground floor level m3 2.020 34,400.00 69,481.30

Cluster Engineering Consultants (Pvt) Ltd. 2


Mr.Uyanahewage Priyantha Sub Structure

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Concrete works to Collection 2,315,981.25

CONCRETE WORKS (Cont'd)

Form Work

Temporary form work. Rate to be


included for fixing & removing.

C10 Sides of column footings m2 21.890 1,740.00 38,088.60

C11 Sides of Columns shafts up to Ground floor level m2 26.176 4,850.00 126,955.42

C12 Sides of plinth beams m2 29.592 1,875.00 55,485.00

C13 Sides of slab beams m2 37.759 4,350.00 164,249.48

C14 Side of concrete wall m3 152.131 1,750.00 266,229.95

C15 Side and soffit of sump & balancing tank slab m3 13.100 4,350.00 56,983.70

C16 Side and soffit of the Staircase up to ground floor level m3 7.577 4,350.00 32,961.17

Reinforcement for RCC Work

Note: Rate shall include for bends, hooks, tying wires,


distance blocks and ordinary spacers etc.

C17 Column footings (12mm bars) kg 752.878 515.00 387,732.36

C18 Columns shafts up to Ground floor level (12mm bars) kg 36.124 555.00 20,048.73

C19 Columns shafts up to Ground floor level (16mm bars) kg 338.891 555.00 188,084.66

C20 Plinth beams (12mm bars) kg 328.471 515.00 169,162.67

C21 In beams at ground floor level. (12mm bars) kg 476.900 555.00 264,679.72

C22 In beams at ground floor level. (16mm bars) kg 367.342 555.00 203,874.92

C23 In slab at ground floor level. (10mm bars) kg 1198.376 555.00 665,098.59

C24 In Staircase at basement floor to ground floor level


(Including supporting Beams) (10mm bars) kg 75.753 555.00 42,043.03

C25 In Staircase at basement floor to ground floor level


(Including supporting Beams) (12mm bars) kg 145.604 555.00 80,809.99

Cluster Engineering Consultants (Pvt) Ltd. 3


Mr.Uyanahewage Priyantha Sub Structure

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT
C26 6mm mild steel for Beams and Columns stirrups up to ground
floor level kg 280.808 520.00 146,020.06

CONCRETE WORKS CARRIED TO SUMMARY Rs. 5,224,489.30

D MASONRY WORK

D1
Random Rubble masonry in cement mortar 1:5 in foundation.
m3 68.477 26,100.00 1,787,254.82

MASONRY WORK CARRIED TO SUMMARY Rs. 1,787,254.82

E BRICK / BLOCK WORK

Common burnt clay bricks/block bedded


and jointed in 1: 5 cement and sand
mortar.

E1 150mm thk Brick walls. m2 2.172 4,600.00 9,989.36

BRICK / BLOCK WORK CARRIED TO SUMMARY Rs. 9,989.36

F DOORS & WINDOWS


DOORS

F1 Fixed Glazed Timber Window Type W8 as per drawing with


necessary fittings and locking arrangements.(01 No's) m2 2.622 29,500.00 77,349.00

DOORS & WINDOWS CARRIED TO SUMMARY Rs. 77,349.00

G METAL WORK

G1 Supply & fix steel hand railing overall height


of 900mm for the stair case up to first floor
level as per given details and working order. m 4.360 8,750.00 38,150.00

G2 Supply & fix steel hand railing overall height


of 900mm for the disable ramp
as per given details and working order. m 12.350 8,500.00 104,975.00

METAL WORK CARRIED TO SUMMARY Rs. 143,125.00

H FLOOR FINISHES

Note
Isolated areas, narrow widths such as
returns, reveals jambs etc., are not
measured separately.
All tile edges shall be jointed with
miter joints
Homogeneous ceramic tiling laid to pattern
as per drawing on 0-20mm thick 1:3

Cluster Engineering Consultants (Pvt) Ltd. 4


Mr.Uyanahewage Priyantha Sub Structure

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT
cement sand mix bedding and joints
pointed to match tiling and consultants
approval. Rate for the tilling should be
included for skirtings where necessary.

Floor finishes to continue

FLOOR FINISHES (Cont'd)

H1
homogeneous heavy duty ceramic floor tiles laid to a given
pattern in basement floor area. (Size and pattern approved by
architecture) -(USE 600x600 mm Rocel at the cost of Rs.2000)
m2 24.944 9,400.00 234,476.90

H2 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in staircase and landing area. (Size and pattern
approved by architecture) -(USE 600x600 mm Rocel at the
cost of Rs.2000) m2 11.810 9,400.00 111,010.24

H3 homogeneous heavy duty cement floor tiles laid to a given


pattern in ramp area. (Size and pattern approved by
architecture) -(USE 600x600 mm Rocel at the cost of
Rs.2000) m2 10.460 9,400.00 98,326.82

FLOOR FINISHES CARRIED TO SUMMARY Rs. 443,813.96

I WALL AND CEILING FINISHES

Note:

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs and
alike are not measured separately.

Internally

16 mm Thick 1:1:5 cement lime and sand


plaster finished smooth with lime putty.

I1 To internal walls & columns. m2 51.483 1,875.00 96,530.63

I2 To sides and soffits of beams, slabs and


staircase. m2 39.071 2,350.00 91,816.19

Externally

16 mm Thick 1:1:5 cement lime and sand


plaster finished semi rough.

I3 To walls & columns m2 24.607 1,550.00 38,140.54

WALL AND CEILING FINISHES CARRIED TO


SUMMARY Rs. 226,487.36

J PAINTING AND DECORATING

Cluster Engineering Consultants (Pvt) Ltd. 5


Mr.Uyanahewage Priyantha Sub Structure

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Note:-

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs
and alike are not measured separately.

Floor finishes to continue

PAINTING AND DECORATING (Cont'd)

Internally

Apply one coat of filler and two coats


emulsion paint to Architects approval.

J1 To all plastered internal & columns. m2 51.483 1,980.00 101,936.34

J2 To all plastered sides and soffits of beams,


slabs and staircase. m2 39.071 1,980.00 77,360.03

Externally

Apply one coat of primer and two coats


weather proof emulsion paint to
Architects approval.

J3 To all plastered walls with flush columns m2 24.607 975.00 23,991.63

PAINTING AND DECORATING CARRIED TO


SUMMARY Rs. 203,288.00

Cluster Engineering Consultants (Pvt) Ltd. 6


Mr.Uyanahewage Priyantha Sub Structure

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 7


Mr.Uyanahewage Priyantha Sub Structure Summary

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

SUB STRUCTURE

SUMMARY

A PRELIMINARIES Rs. 1,500,000.00

B EXCAVATION & EARTHWORKS Rs. 609,349.68

C CONCRETE WORKS Rs. 5,224,489.30

D MASONRY WORK Rs. 1,787,254.82

E BRICK / BLOCK WORK Rs. 9,989.36

F DOORS & WINDOWS Rs. 77,349.00

G METAL WORK Rs. 143,125.00

H FLOOR FINISHES Rs. 443,813.96

I WALL AND CEILING FINISHES Rs. 226,487.36

J PAINTING AND DECORATING Rs. 203,288.00

SUB STRUCTURE CARRIED TO GRAND SUMMARY Rs. 9,121,093.79

Cluster Engineering Consultants (Pvt) Ltd. 7


Mr.Uyanahewage Priyantha Ground Floor To First Floor Level

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I
GROUND FLOOR LEVEL TO FIRST FLOOR LEVEL

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

A CONCRETE WORKS

Grade 20 Concrete (1:2:4)

Lintels
Grade 20 cement concrete
including reinforcement & form work

In lintels reinforced with 4 Nos. 10 mm dia. Tor steel bars &


6 mm mild steel stirrups at 150 mm centers. Including
formwork bar bending & concreting

A1 a) 225mm x 200mm Lintel m 24.725 7,290.00 180,245.25

A2 b) 150mm x 200mm Lintel m 1.220 5,925.00 7,228.50

A3 100mm thick Special concrete frame work at FG1 m3 0.535 34,350.00 18,378.97

A4 100 mm thick canopy at selected window m 5.620 6,500.00 36,530.00

Grade 25 Concrete (1:11/2:3)

Reinforced cement concrete in grade 25, fill into formwork


and well packed around Reinforcement. Rate to be included
with curing. It should be kept voids for service ducts as shown
in the drawing.

A5 In columns up to First floor level. m3 3.809 34,350.00 130,828.42

A6 In beams at First floor level. m3 12.077 39,750.00 480,056.78

A7 In slab at First floor level. m3 14.508 39,750.00 576,697.97

A8 In Staircase ground floor to first floor level


(Including supporting Beams) m3 2.678 39,750.00 106,458.53

Form Work

Temporary form work. Rate to be


included for fixing & removing.

A9 Sides of columns up to to First floor level. m2 46.410 6,475.00 300,504.75

A10 Sides & soffit of beams up to to First floor level. m2 101.983 4,840.00 493,595.30

A11 Sides & soffit of the slabs up to to First floor level. m2 120.472 4,125.00 496,947.83

A12 Sides and soffit of staircase up to First floor level.


(Including supporting Beams) m2 16.013 4,950.00 79,264.94

Concrete works to Collection 2,906,737.23

Cluster Engineering Consultants (Pvt) Ltd. 8


Mr.Uyanahewage Priyantha Ground Floor To First Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

CONCRETE WORKS (Cont'd)

Reinforcement for RCC Work

Note: Rate shall include for bends, hooks, tying wires,


distance blocks and ordinary spacers etc.

A13 In columns up to First floor level. (12mm bars) kg 64.824 575.00 37,273.80

A14 In columns up to First floor level. (16mm bars) kg 575.970 560.00 322,543.20

A15 In beams at First floor level. (12mm bars) kg 446.321 575.00 256,634.71

A16 In beams at First floor level. (16mm bars) kg 647.450 575.00 372,283.89

A17 In slab at First floor level. (10mm bars) kg 1769.339 560.00 990,829.76

A18 In Staircase up to First floor level (10mm bars)


(Including supporting Beams) kg 89.945 610.00 54,866.60

A19 In Staircase up to First floor level (12mm bars)


(Including supporting Beams) kg 172.882 610.00 105,457.87

A20 6mm mild steel for Beams and Columns stirrups kg 376.465 600.00 225,878.78

CONCRETE WORKS CARRIED TO SUMMARY Rs. 5,272,505.84

B BRICK / BLOCK WORK

Common burnt clay bricks/block bedded


and jointed in 1: 5 cement and sand
mortar.

B1 225mm thk Brick walls. m2 143.351 7,300.00 1,046,462.30

B2 150mm thk Brick walls. m2 12.128 5,400.00 65,491.20

BRICK / BLOCK WORK CARRIED TO SUMMARY Rs. 1,111,953.50

C DOORS & WINDOWS

DOORS

Supply & fix Paneled timber Door type D1 with necessary


C1
fittings and locking arrangements.(01 No's)
m2 2.130 29800.00 63,474.00

Supply & fix Paneled timber Door type D2 with necessary


C2
fittings and locking arrangements.(02 No's)
m2 4.260 29800.00 126,948.00

Cluster Engineering Consultants (Pvt) Ltd. 9


Mr.Uyanahewage Priyantha Ground Floor To First Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Doors & Windows to Collection 190,422.00

DOORS & WINDOWS (Cont'd)

Supply & fix Paneled timber Door type D3 with necessary


C3
fittings and locking arrangements.(01 No's)
m2 1.938 29,800.00 57,752.40

C4 Fixed Glazed Timber Window Type W1 as per drawing with


necessary fittings and locking arrangements.(01 No's) m2 2.560 29,500.00 75,520.00

C5 Fixed Glazed Timber Window Type W2 as per drawing with


necessary fittings and locking arrangements.(02 No's) m2 2.976 29,500.00 87,792.00

C6
Fixed Glazed Timber Window Type W3 as per drawing with
necessary fittings and locking arrangements.(01 No's)
m2 1.854 29,500.00 54,693.00

C7 Fixed Glazed Timber Window Type W4 as per drawing with


necessary fittings and locking arrangements.(01 No's) m2 1.769 29,500.00 52,185.50

C8
Fixed Glazed Timber Window Type W5 as per drawing with
necessary fittings and locking arrangements.(01 No's)
m2 5.432 29,500.00 160,244.00

C9 Four Nos. Timber Casement Folding Glazed Door Type DW1


With 12" Slats with necessary fittings and locking
arrangements. (01 No's) m2 2.407 29,500.00 71,006.50

C10 fixed glass FG1 as per drawing and necessary fittings


arrangements.(01 No's) m2 2.130 31,000.00 66,030.00

C11 glass door GD1 as per drawing and necessary fittings


arrangements.(01 No's) m2 5.836 31,000.00 180,916.00

DOORS & WINDOWS CARRIED TO SUMMARY Rs. 996,561.40

D METAL WORK

D1 Supply & fix steel hand railing overall height


of 900mm for the stair case up to first floor
level as per given details and working order. m 7.310 9,000.00 65,790.00

METAL WORK CARRIED TO SUMMARY Rs. 65,790.00

E FLOOR FINISHES

Note
Isolated areas, narrow widths such as
returns, reveals jambs etc., are not

Cluster Engineering Consultants (Pvt) Ltd. 10


Mr.Uyanahewage Priyantha Ground Floor To First Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


measured separately.

Floor finishes to continue

FLOOR FINISHES (Cont'd)

All tile edges shall be jointed with


miter joints

Homogeneous ceramic tiling laid to pattern


as per drawing on 0-20mm thick 1:3
cement sand mix bedding and joints
pointed to match tiling and consultants
approval. Rate for the tilling should be
included for skirtings where necessary.

E1 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in restaurant and verandah floor area. (Size and pattern
approved by architecture) m2 65.154 9,850.00 641,764.47

E2 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in kitchen floor area. (Size and pattern approved by
architecture) m2 9.101 9,850.00 89,646.82

E3 2'x2' gloss heavy duty ceramic floor tiles laid to a given


pattern in apartment floor area. (Size and pattern approved by
architecture) m2 61.231 9,850.00 603,121.25

E4 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in bath room area. (Size and pattern approved by
architecture) m2 6.563 9,975.00 65,461.94

E5 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in staircase and landing area. (Size and pattern
approved by architecture) m2 12.717 9,975.00 126,852.08

FLOOR FINISHES CARRIED TO SUMMARY Rs. 1,526,846.55

F WALL AND CEILING FINISHES

Note:

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs and
alike are not measured separately.

Internally

16 mm Thick 1:1:5 cement lime and sand


plaster finished smooth with lime putty.

F1 To internal walls & columns. m2 262.788 1,990.00 522,948.12

Cluster Engineering Consultants (Pvt) Ltd. 11


Mr.Uyanahewage Priyantha Ground Floor To First Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


F2 To sides and soffits of beams, slabs and
staircase. m2 172.373 2,585.00 445,583.48

Doors & Windows to Collection 968,531.60

DOORS & WINDOWS (Cont'd)

Externally

16 mm Thick 1:1:5 cement lime and sand


plaster finished semi rough.

F3 To walls & columns m2 176.595 1,705.00 301,094.48

WALL AND CEILING FINISHES CARRIED TO


SUMMARY Rs. 1,269,626.08

G PAINTING AND DECORATING

Note:-

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs
and alike are not measured separately.

Internally

Apply one coat of filler and two coats


emulsion paint to Architects approval.

G1 To all plastered internal & columns. m2 262.788 2,180.00 572,877.84

G2 To all plastered sides and soffits of beams,


slabs and staircase. m2 172.373 2,180.00 375,772.53

Externally

Apply one coat of primer and two coats


weather proof emulsion paint to
Architects approval.

G3 To all plastered walls with flush columns m2 176.595 1,075.00 189,839.63

PAINTING AND DECORATING CARRIED TO


SUMMARY Rs. 1,138,489.99

Cluster Engineering Consultants (Pvt) Ltd. 12


Mr.Uyanahewage Priyantha Ground Floor To First Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 13


Mr.Uyanahewage Priyantha Ground Floor to First Floor level Samarry

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

GROUND FLOOR LEVEL TO FIRST FLOOR LEVEL

SUMMARY

A CONCRETE WORKS Rs. 5,272,505.84

B BRICK / BLOCK WORK Rs. 1,111,953.50

C DOORS & WINDOWS Rs. 996,561.40

D METAL WORK Rs. 65,790.00

E FLOOR FINISHES Rs. 1,526,846.55

F WALL AND CEILING FINISHES Rs. 1,269,626.08

G PAINTING AND DECORATING Rs. 1,138,489.99

GROUND FLOOR LEVEL TO FIRST FLOOR LEVEL


CARRIED TO GRAND SUMMARY Rs. 11,381,773.35

Cluster Engineering Consultants (Pvt) Ltd. 13


Mr.Uyanahewage Priyantha First Floor to Second Floor Level

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I
FIRST FLOOR LEVEL TO SECOND FLOOR LEVEL

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

A CONCRETE WORKS

Grade 20 Concrete (1:2:4)

Lintels
Grade 20 cement concrete
including reinforcement & form work

In lintels reinforced with 2 Nos. 10 mm dia.


Tor steel bars & 6 mm mild steel stirrups
at 150 mm centers.

A1 a) 225mm x 200mm Lintel m 25.960 8,015.00 208,069.40

A2 b) 150mm x 200mm Lintel m 5.780 6,520.00 37,685.60

A3 100mm thick Special concrete frame work at FG1 m3 0.535 36,100.00 19,315.31

A4 100 mm thick canopy at selected window m 5.620 6,800.00 38,216.00

Grade 25 Concrete (1:11/2:3)

Reinforced cement concrete in grade 25, fill into formwork


and well packed around Reinforcement. Rate to be included
with curing. It should be kept voids for service ducts as shown
in the drawing.

A5 In columns at First floor to Second floor level. m3 3.857 36,100.00 139,233.19

A6 In beams at Second floor level. m3 11.916 41,750.00 497,481.00

A7 In slab at Second floor level. m3 13.268 41,750.00 553,931.69

A8 In Staircase up to First floor to Second floor level.


(Including supporting Beams) m3 2.678 41,750.00 111,814.93

Form Work

Temporary form work. Rate to be


included for fixing & removing.

A9 Sides of columns at First floor to Second floor level.. m2 53.610 6,800.00 364,548.00

A10 Sides & soffit of beams at Second floor level. m2 98.706 5,100.00 503,398.85

A11 Sides & soffit of the slabs at Second floor level. m2 110.584 4,330.00 478,826.99

A12 Sides and soffit of staircase at Second floor to


First floor level. (Including supporting Beams) m2 16.013 5,200.00 83,268.22

Concrete works to Collection 3,035,789.18

Cluster Engineering Consultants (Pvt) Ltd. 14


Mr.Uyanahewage Priyantha First Floor to Second Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

CONCRETE WORKS (Cont'd)

Reinforcement for RCC Work

Note: Rate shall include for bends, hooks, tying wires,


distance blocks and ordinary spacers etc.

A13 Columns at first to second floor level.(10mm bars) kg 62.955 610.00 38,402.67

A14 Columns at first to second floor level.(12mm bars) kg 64.824 590.00 38,246.16

A15 Columns at first to second floor level.(16mm bars) kg 529.892 605.00 320,584.90

A16 Beams at Second floor level. (12mm bars) kg 440.540 605.00 266,526.91

A17 Beams at Second floor level. (16mm bars) kg 645.379 590.00 380,773.68

A18 Slab at Second floor level. (10mm bars) kg 1,534.335 640.00 981,974.31

A19 In Staircase at First to Second floor level


(Including supporting Beams) (10mm bars) kg 89.945 640.00 57,564.95

A20 In Staircase at First to Second floor level


(Including supporting Beams) (12mm bars) kg 172.882 640.00 110,644.33

A21 6mm mild steel for Beams and Columns stirrups kg 383.451 630.00 241,574.12

CONCRETE WORKS CARRIED TO SUMMARY Rs. 5,472,081.21

B BRICK / BLOCK WORK

Common burnt clay bricks/block bedded


and jointed in 1: 5 cement and sand
mortar.

B1 225mm thk Brick walls. m2 121.045 7,675.00 929,020.37

B2 150mm thk Brick walls m2 55.760 5,675.00 316,438.00

BRICK / BLOCK WORK CARRIED TO SUMMARY Rs. 1,245,458.37

C WATER PROOFING

Water proofing in membrane type on


toilet and other necessary areas as per
Consultant's approval. 10 years written
guarantee should be provided

C1 bath room floor area, including walls height


up to 2m. m2 44.698 3,000.00 134,093.70

C2 Verandah floor area exposed to direct weather m2 42.864 4,000.00 171,456.80

C3 External wall exposed to direct weather m2 93.925 3,000.00 281,775.00

Cluster Engineering Consultants (Pvt) Ltd. 15


Mr.Uyanahewage Priyantha First Floor to Second Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


WATER PROOFING CARRIED TO SUMMARY Rs. 587,325.50

D DOORS & WINDOWS

Supply & fix Paneled timber Door type D3 with necessary


D1 fittings and locking arrangements. (02 No's)
m2 3.876 29975.00 116,183.10

Supply & fix Paneled timber Door type D5 with necessary


D2 fittings and locking arrangements. (01 No's)
m2 1.938 29975.00 58,091.55

Supply & fix Paneled timber Door type D6 with necessary


D3 fittings and locking arrangements. (02 No's)
m2 3.578 29975.00 107,250.55

Fixed Glazed Timber Window Type W2 as per drawing with


D4
necessary fittings and locking arrangements.(03 No's) m2 4.464 29800.00 133,027.20

Fixed Glazed Timber Window Type W3 as per drawing with


D5
necessary fittings and locking arrangements.(01 No's) m2 1.853 29800.00 55,219.40

Fixed Glazed Timber Window Type W4 as per drawing with


D6
necessary fittings and locking arrangements.(01 No's) m2 1.769 29800.00 52,716.20

Fixed Glazed Timber Window Type W6 as per drawing with


D7
necessary fittings and locking arrangements.(02 No's) m2 2.140 29800.00 63,772.00

Fixed Glazed Timber Window Type DW2 as per drawing with


D8
necessary fittings and locking arrangements.(01 No's) m2 3.557 29800.00 105,998.60

Fixed Glazed Type FG1 as per drawing with necessary


D9
fittings and locking arrangements.(01 No's) m2 1.259 29800.00 37,518.20

Fixed Glazed Type FG2 as per drawing with necessary


D10
fittings and locking arrangements.(01 No's) m2 2.130 29800.00 63,474.00

Fixed Glazed Type FG3 as per drawing with necessary


D11
fittings and locking arrangements.(01 No's) m2 5.985 29800.00 178,353.00

Glazed timber Door Type GD2 With necessary fittings and


D12
locking arrangements. (01 No's) m2 5.836 29800.00 173,912.80

DOORS & WINDOWS CARRIED TO SUMMARY Rs. 1,145,516.60

E METAL WORK

E1 Supply & fix steel hand railing overall height


of 900mm for the stair case up to Second floor
level as per given details and working order. m 5.380 9,300.00 50,034.00

E2 Supply & fix steel & Glass hand railing overall height
of 900mm for the balcony and terrace up to Second floor
level as per given details and working order. m 14.210 9,300.00 132,153.00

Cluster Engineering Consultants (Pvt) Ltd. 16


Mr.Uyanahewage Priyantha First Floor to Second Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


METAL WORK CARRIED TO SUMMARY Rs. 182,187.00

F FLOOR FINISHES

Note
Isolated areas, narrow widths such as
returns, reveals jambs etc., are not
measured separately.

All tile edges shall be jointed with


miter joints

Homogeneous ceramic tiling laid to pattern


as per drawing on 0-20mm thick 1:3
cement sand mix bedding and joints
pointed to match tiling and consultants
approval. Rate for the tilling should be
included for skirtings where necessary.

F1 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in balcony and verandah floor area. (Size and pattern
approved by architecture) m2 65.154 10,350.00 674,341.35

F2 2'x2' gloss heavy duty ceramic floor tiles laid to a given


pattern in apartment floor area. (Size and pattern approved by
architecture) m2 87.826 10,350.00 909,002.88

F3 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in bath room area. (Size and pattern approved by
architecture) m2 12.190 10,475.00 127,689.20

F4 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in staircase and landing area. (Size and pattern
approved by architecture) m2 16.060 10,475.00 168,226.41

FLOOR FINISHES CARRIED TO SUMMARY Rs. 1,879,259.84

G WALL AND CEILING FINISHES

Note:

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs and
alike are not measured separately.

Internally

16 mm Thick 1:1:5 cement lime and sand


plaster finished smooth with lime putty.

G1 To internal walls & columns. m2 314.582 2,290.00 720,392.78

G2 To sides and soffits of beams, slabs and

Cluster Engineering Consultants (Pvt) Ltd. 17


Mr.Uyanahewage Priyantha First Floor to Second Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


staircase. m2 165.650 2,290.00 379,338.98

Concrete works to Collection 1,099,731.76

CONCRETE WORKS (Cont'd)

G3 Ceramic wall tiles laid to a given pattern in bath room wall


area. (Size and pattern approved by architecture) m2 32.508 10,600.00 344,584.80

Externally

16 mm Thick 1:1:5 cement lime and sand


plaster finished semi rough.

G4 To walls & columns m2 163.785 1,130.00 185,077.05

WALL AND CEILING FINISHES CARRIED TO


SUMMARY Rs. 1,629,393.61

H PAINTING AND DECORATING

Note:-

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs
and alike are not measured separately.

Internally

Apply one coat of filler and two coats


emulsion paint to Architects approval.

H1 To all plastered internal wall & columns. m2 314.582 2,290.00 720,392.78

H2 To all plastered sides and soffits of beams,


slabs and staircase. m2 165.650 2,290.00 379,338.98

Externally

Apply one coat of primer and two coats


weather proof emulsion paint to
Architects approval.

H3 To all plastered External walls with flush columns including


above part of tiled area. m2 163.785 1,130.00 185,077.05

PAINTING AND DECORATING CARRIED TO


SUAMMARY Rs. 1,284,808.81

Cluster Engineering Consultants (Pvt) Ltd. 18


Mr.Uyanahewage Priyantha First Floor to Second Floor Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 19


Mr.Uyanahewage Priyantha First Floor to Second Floor Level Summary

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

FIRST FLOOR LEVEL TO SECOND FLOOR LEVEL

SUMMARY

A CONCRETE WORKS Rs. 5,472,081.21

B BRICK / BLOCK WORK Rs. 1,245,458.37

C WATER PROOFING Rs. 587,325.50

D DOORS & WINDOWS Rs. 1,145,516.60

E METAL WORK Rs. 182,187.00

F FLOOR FINISHES Rs. 1,879,259.84

G WALL AND CEILING FINISHES Rs. 1,629,393.61

H PAINTING AND DECORATING Rs. 1,284,808.81

FIRST FLOOR LEVEL TO SECOND FLOOR LEVEL


CARRIED TO GRAND SUMMARY Rs. 13,426,030.94

Cluster Engineering Consultants (Pvt) Ltd. 19


Mr.Uyanahewage Priyantha Second Floor Level To Roof Level

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I
SECOND FLOOR LEVEL TO ROOF LEVEL
ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

A CONCRETE WORKS

Grade 20 Concrete (1:2:4)

Lintels
Grade 20 cement concrete
including reinforcement & form work

In lintels reinforced with 2 Nos. 10 mm dia. Tor steel


bars & 6 mm mild steel stirrups at 150 mm centers.

A1 a) 225mm x 200mm Lintel m 25.960 8,425.00 218,713.00

A2 b) 150mm x 200mm Lintel m 5.780 6,875.00 39,737.50

A3 100mm thick Special concrete frame work at FG1 m 0.535 37,900.00 20,278.40

A4 100 mm thick canopy at selected window m 5.620 7,150.00 40,183.00

Grade 25 Concrete (1:11/2:3)

Reinforced cement concrete in grade 25, fill into formwork


and well packed around Reinforcement. Rate to be included
with curing. It should be kept voids for service ducts as
shown in the drawing.

A5 In columns at second floor to roof terrace level. m3 3.704 37,925.00 140,469.46

A6 In beams at roof terrace level. m3 10.795 43,850.00 473,348.14

A7 In slab at roof terrace level. m3 12.340 43,850.00 541,125.88

A8 In Staircase up to second floor to roof terrace level.


(Including supporting Beams) m3 2.678 43,850.00 117,439.16

Form Work

Temporary form work. Rate to be


included for fixing & removing.

A9 Sides of columns at second floor to roof terrace level.. m2 49.020 7,150.00 350,493.00

A10 Sides & soffit of beams at roof terrace level. m2 91.620 5,350.00 490,166.50

A11 Sides & soffit of the slabs at roof terrace level. m2 101.870 4,550.00 463,510.32

A12 Sides and soffit of staircase at second floor to roof terrace


level. (Including supporting Beams) m2 16.013 5,475.00 87,671.83

Concrete works to Collection 2,983,136.19

Cluster Engineering Consultants (Pvt) Ltd. 20


Mr.Uyanahewage Priyantha Second Floor Level To Roof Level

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

CONCRETE WORKS (Cont'd)

Reinforcement for RCC Work


Note: Rate shall include for bends, hooks, tying wires,
distance blocks and ordinary spacers etc.

A13 Columns at second floor to roof terrace level. (10mm


bars) kg 35.974 645.00 23,203.49

A14 Columns at second floor to roof terrace level. (12mm


bars) kg 259.296 620.00 160,763.52

A15 Columns at second floor to roof terrace level. (16mm


bars) kg 184.310 640.00 117,958.66

A16 Beams at roof terrace level. (12mm bars) kg 398.732 640.00 255,188.18

A17 Beams at roof terrace level. (16mm bars) kg 491.751 620.00 304,885.84

A18 Slab at roof terrace level. (10mm bars) kg 1,369.478 675.00 924,397.97

A19 In Staircase at second floor to roof terrace level


(Including supporting Beams) (10mm bars) kg 50.019 675.00 33,762.96

A20 In Staircase at second floor to roof terrace level


(Including supporting Beams) (12mm bars) kg 96.092 675.00 64,861.79

A21 6mm mild steel for Beams and Columns (stirrups) second
floor to roof terrace kg 346.595 665.00 230,485.37

CONCRETE WORKS CARRIED TO SUMMARY Rs. 5,098,643.96

B BRICK / BLOCK WORK

Common burnt clay bricks/block bedded


and jointed in 1: 5 cement and sand
mortar.

B1 225mm thk Brick walls. m2 121.045 8,060.00 975,622.70

B2 150mm thk Brick walls m2 55.760 5,960.00 332,329.60

BRICK / BLOCK WORK CARRIED TO SUMMARY Rs. 1,307,952.30

C WATER PROOFING

Water proofing in membrane type on


toilet and other necessary areas as per
Consultant's approval. 10 years written
guarantee should be provided

C1 Bath room floor area, including walls height


up to 2m. m2 44.698 3,075.00 137,446.04

C2 Verandah floor area exposed to direct weather m2 29.359 4,125.00 121,106.70

C3 External wall exposed to direct weather m2 93.925 3,075.00 288,819.38

Cluster Engineering Consultants (Pvt) Ltd. 21


Mr.Uyanahewage Priyantha Second Floor Level To Roof Level

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

WATER PROOFING CARRIED TO SUMMARY Rs. 547,372.12

D DOORS & WINDOWS

Supply & fix Paneled timber Door type D3 with necessary


D1
fittings and locking arrangements. (02 No's)
m2 3.876 30275.00 117,345.90

Supply & fix Paneled timber Door type D5 with necessary


D2
fittings and locking arrangements. (01 No's)
m2 1.938 30275.00 58,672.95
Supply & fix Paneled timber Door type D6 with necessary
D3
fittings and locking arrangements. (02 No's)
m2 3.578 30275.00 108,323.95

D4 Fixed Glazed Timber Window Type W2 as per drawing with


necessary fittings and locking arrangements.(03 No's) m2 4.464 30100.00 134,366.40

D5 Fixed Glazed Timber Window Type W3 as per drawing with


necessary fittings and locking arrangements.(01 No's) m2 1.853 30100.00 55,775.30

D6 Fixed Glazed Timber Window Type W4 as per drawing with


necessary fittings and locking arrangements.(01 No's) m2 1.769 30100.00 53,246.90

D7 Fixed Glazed Timber Window Type W6 as per drawing with


necessary fittings and locking arrangements.(02 No's) m2 2.140 30100.00 64,414.00

D8 Fixed Glazed Timber Window Type DW2 as per drawing


with necessary fittings and locking arrangements.(01 No's) m2 3.557 30100.00 107,065.70

D9 Fixed Glazed Type FG1 as per drawing with necessary


fittings and locking arrangements.(01 No's) m2 1.259 30100.00 37,895.90

D10 Fixed Glazed Type FG2 as per drawing with necessary


fittings and locking arrangements.(01 No's) m2 2.130 30100.00 64,113.00

D11 Fixed Glazed Type FG3 as per drawing with necessary


fittings and locking arrangements.(01 No's) m2 5.985 30100.00 180,148.50

D12 Glazed timber Door Type GD2 With necessary fittings and
locking arrangements. (01 No's) m2 5.836 30100.00 175,663.60

DOORS & WINDOWS CARRIED TO SUMMARY Rs. 1,157,032.100

E METAL WORK

E1 Supply & fix steel hand railing overall height


of 900mm for the stair case up to Second floor
level as per given details and working order. m 5.380 9,400.00 50,572.00

E2 Supply & fix steel & Glass hand railing overall height
of 900mm for the balcony and terrace up to Second floor
level as per given details and working order. m 15.130 9,400.00 142,222.00

Cluster Engineering Consultants (Pvt) Ltd. 22


Mr.Uyanahewage Priyantha Second Floor Level To Roof Level

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

METAL WORK CARRIED TO SUMMARY Rs. 192,794.00

F FLOOR FINISHES

Note
Isolated areas, narrow widths such as
returns, reveals jambs etc., are not
measured separately.

All tile edges shall be jointed with


miter joints

Homogeneous ceramic tiling laid to pattern


as per drawing on 0-20mm thick 1:3
cement sand mix bedding and joints
pointed to match tiling and consultants
approval. Rate for the tilling should be
included for skirtings where necessary.

F1 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in balcony and verandah floor area. (Size and pattern
approved by architecture) m2 28.952 10,875.00 314,853.00

F2 2'x2' gloss heavy duty ceramic floor tiles laid to a given


pattern in apartment floor area. (Size and pattern approved by
architecture) m2 87.826 10,875.00 955,111.73

F3 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in bath room area. (Size and pattern approved by
architecture) m2 12.190 11,000.00 134,088.90

F4 homogeneous heavy duty ceramic floor tiles laid to a given


pattern in staircase and landing area. (Size and pattern
approved by architecture) m2 16.060 11,000.00 176,657.80

FLOOR FINISHES CARRIED TO SUMMARY Rs. 1,580,711.43

G WALL AND CEILING FINISHES

Note:
Isolated areas, staircase area, narrow
widths such as returns, reveals jambs and
alike are not measured separately.

Internally
16 mm Thick 1:1:5 cement lime and sand
plaster finished smooth with lime putty.

G1 To internal walls & columns. m2 314.582 2,405.00 756,569.71

G2 To sides and soffits of beams, slabs and


staircase. m2 149.395 2,405.00 359,295.00

Cluster Engineering Consultants (Pvt) Ltd. 23


Mr.Uyanahewage Priyantha Second Floor Level To Roof Level

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT
G3 1'x2' gloss ceramic wall tiles laid to a given pattern in
bathroom wall area. As per the architect instruction (Size and
pattern approved by architecture) m2 32.508 11,130.00 361,814.04

Wall & ceiling finishes to Collection 1,477,678.75

WALL AND CEILING FINISHES (Cont'd)

Externally
16 mm Thick 1:1:5 cement lime and sand
plaster finished semi rough.

G4 To walls & columns m2 163.785 1,190.00 194,904.15

WALL AND CEILING FINISHES CARRIED TO


SUMMARY Rs. 1,672,582.90

H PAINTING AND DECORATING

Note:-

Isolated areas, staircase area, narrow


widths such as returns, reveals jambs
and alike are not measured separately.

Internally

Apply one coat of filler and two coats


emulsion paint to Architects approval.

H1 To all plastered internal & columns. m2 314.582 2,405.00 756,569.71

H2 To all plastered sides and soffits of beams,


slabs and staircase. m2 149.395 2,405.00 359,295.00

Externally

Apply one coat of primer and two coats


weather proof emulsion paint to
Architects approval.

H3 To all plastered External walls with flush columns including


above part of tiled area. m2 163.785 1,190.00 194,904.15

PAINTING AND DECORATING CARRIED TO


SUAMMARY Rs. 1,310,768.86

Cluster Engineering Consultants (Pvt) Ltd. 24


Mr.Uyanahewage Priyantha Second Floor Level To Roof Level

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 25


Mr.Uyanahewage Priyantha Second Floor level to Roof level Summary

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

SECOND FLOOR LEVEL TO ROOF LEVEL

SUMMARY

A CONCRETE WORKS Rs. 5,098,643.96

B BRICK / BLOCK WORK Rs. 1,307,952.30

C WATER PROOFING Rs. 547,372.12

D DOORS & WINDOWS Rs. 1,157,032.10

E METAL WORK Rs. 192,794.00

F FLOOR FINISHES Rs. 1,580,711.43

G WALL AND CEILING FINISHES Rs. 1,672,582.90

H PAINTING AND DECORATING Rs. 1,310,768.86

FIRST FLOOR LEVEL TO SECOND FLOOR LEVEL


CARRIED TO GRAND SUMMARY Rs. 12,867,857.66

Cluster Engineering Consultants (Pvt) Ltd. 25


Mr.Uyanahewage Priyantha Roof Terrace Level

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

ROOF TERRACE LEVEL

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

A CONCRETE WORKS

Grade 20 Concrete (1:2:4)

Lintels
Grade 20 cement concrete
including reinforcement & form work

In lintels reinforced with 2 Nos. 10 mm dia.


Tor steel bars & 6 mm mild steel stirrups
at 150 mm centers.

A1 a) 225mm x 200mm Lintel m 1.510 8,850.00 13,363.50

Grade 25 Concrete (1:11/2:3)

Reinforced cement concrete in grade 25, fill into formwork and


well packed around Reinforcement. Rate to be included with
curing. It should be kept voids for service ducts as shown in the
drawing.

A3 In columns at above roof terrace level. m3 1.668 39,825.00 66,411.67

A4 In beams at above roof terrace level. m3 6.875 46,050.00 316,587.99

A5 In slab at above roof terrace level. m3 6.898 46,050.00 317,651.17

Form Work

Temporary form work. Rate to be


included for fixing & removing.

A6 Sides of columns above roof terrace level. m2 25.596 7,525.00 192,609.90

A7 Sides & soffit of beams above roof terrace level. m2 56.402 5,625.00 317,262.30

A8 Sides & soffit of the slabs above roof terrace level. m2 57.200 4,775.00 273,129.76

Reinforcement for RCC Work

Note: Rate shall include for bends, hooks, tying wires, distance
blocks and ordinary spacers etc.

A9 Columns at above roof terrace level. (12mm bars) kg 138.315 680.00 94,054.12

A10 In beams at above roof terrace level.. (12mm bars) kg 253.240 675.00 170,936.89

Concrete works to Collection 1,762,007.32

Cluster Engineering Consultants (Pvt) Ltd. 26


Mr.Uyanahewage Priyantha Roof Terrace Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

CONCRETE WORKS (Cont'd)

A11 In beams at above roof terrace level.. (16mm bars) kg 34.653 675.00 23,390.69

A12 In slab at above roof terrace level. (10mm bars) kg 749.313 710.00 532,012.28

6mm mild steel for Beams and Columns stirrups at above roof
A13 terrace level. kg 165.753 700.00 116,026.82

CONCRETE WORKS CARRIED TO SUMMARY Rs. 2,433,437.11

B BRICK / BLOCK WORK

Common burnt clay bricks/block bedded


and jointed in 1: 5 cement and sand
mortar.

B1 225mm thk Brick walls. m2 99.592 8,700.00 866,450.40

BRICK / BLOCK WORK CARRIED TO SUMMARY Rs. 866,450.40

C WATER PROOFING

Water proofing in membrane type on


toilet and other necessary areas as per
Consultant's approval. 10 years written
guarantee should be provided

C1 roof terrace open area m2 96.963 4,250.00 412,094.45

C2 Roof slab m2 63.494 4,250.00 269,848.65

WATER PROOFING CARRIED TO SUMMARY Rs. 681,943.10

D DOORS & WINDOWS

Supply & fixing aluminum Paneled Door type D7 with necessary


D1 fittings and locking arrangements. (01 No's)
m2 1.938 30600.00 59,302.80

DOORS & WINDOWS CARRIED TO SUMMARY Rs. 59,302.80

E METAL WORK

E1 Supply & fix steel hand railing overall height


of 3'-0" for the balcony from first floor level
as per given details and working order. m 23.010 9,500.00 218,595.00

Cluster Engineering Consultants (Pvt) Ltd. 27


Mr.Uyanahewage Priyantha Roof Terrace Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


METAL WORK CARRIED TO SUMMARY Rs. 218,595.00

F FLOOR FINISHES

Note
Isolated areas, staircase areas, narrow widths such as returns,
reveals jambs etc., to be included to the rate.
All tile edges shall be jointed with mortar joints

Homogeneous ceramic tiling laid to pattern as per drawing on


0-20mm thick 1:3 cement sand mix bedding and joints pointed
to match tiling and consultants approval.

F1
Heavy duty cement floor tiles laid to a given pattern in terrace
area. (Size and pattern approved by architecture)
m2 67.513 11,500.00 776,401.80

F2
homogeneous heavy duty ceramic floor tiles laid to a given
pattern in floor area. (Size and pattern approved by architecture)
m2 46.593 11,500.00 535,819.50

FLOOR FINISHES CARRIED TO SUMMARY Rs. 1,312,221.30

G WALL AND CEILING FINISHES

Note:

Isolated areas, staircase area, narrow widths such as returns,


reveals jambs and alike are not measured separately.

Internally

16 mm Thick 1:1:5 cement lime and sand plaster finished


smooth with lime putty.

G1 To internal walls & columns & beams m2 49.814 2,525.00 125,781.36

G2 To sides and soffits of beams, slabs and


staircase. m2 65.526 2,525.00 165,453.66

Externally

16 mm Thick 1:1:5 cement lime plaster finished semi rough

G3 To walls & with flush columns m2 207.175 1,250.00 258,968.75

WALL AND CEILING FINISHES CARRIED TO


SUMMARY Rs. 550,203.76

H PAINTING AND DECORATING

Note:-

Isolated areas, staircase area, narrow widths such as returns,


reveals jambs and alike are not measured separately.

Cluster Engineering Consultants (Pvt) Ltd. 28


Mr.Uyanahewage Priyantha Roof Terrace Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Painting & Decorating to continue

PAINTING AND DECORATING (Cont'd)

Internally

Apply one coat of filler and two coats emulsion paint to


Architects approval.

H1 To all plastered internal walls with flush columns including


above part of tiled area. m2 49.814 2,525.00 125,781.36

H2 To sides and soffits of beams, slabs and


staircase. m2 65.526 2,525.00 165,453.66

Externally

H3 To all plastered External walls with flush columns including


above part of tiled area. m2 207.175 1,250.00 258,968.75

PAINTING AND DECORATING CARRIED TO


SUMMARY Rs. 550,203.76

I ROOF WORK

I1 Supply and fix Zn/Aluminum down pipes with necessary special


brackets etc., m 26.820 950.00 25,479.00

ROOF WORK CARRIED TO SUMMARY Rs. 25,479.00

Cluster Engineering Consultants (Pvt) Ltd. 29


Mr.Uyanahewage Priyantha Roof Terrace Level

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 30


Mr.Uyanahewage Priyantha Roof Terrace Level

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

ROOF TERRACE LEVEL

SUMMARY

A CONCRETE WORKS Rs. 2,433,437.11

B BRICK / BLOCK WORK Rs. 866,450.40

C WATER PROOFING Rs. 681,943.10

D DOORS & WINDOWS Rs. 59,302.80

E METAL WORK Rs. 218,595.00

F FLOOR FINISHES Rs. 1,312,221.30

G WALL AND CEILING FINISHES Rs. 550,203.76

H PAINTING AND DECORATING Rs. 550,203.76

I ROOF WORK Rs. 25,479.00

ROOF TERRACE LEVEL Rs. 6,697,836.24

Cluster Engineering Consultants (Pvt) Ltd. 30


Mr.Uyanahewage Priyantha Electrical Work

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

ELECTRICAL WORK
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

The wiring shall be in full rigid PVC conduits with the conduit
system providing a continuous and effective means of protection
for the wiring. The conduit system shall be concealed in the
A
building fabric and where provided under a roof the conduit
shall be clipped to the roof members. Any visible surface wiring
shall be carried in PVC flat casings approved by the Engineer.

Supply all material and provide final sub circuit point wiring
only for the following outlets with one way switch and
connector, lamp fitting fixing charges with all materials and
excluding the cost of fitting wiring shall be in 1.0 mm2 PVC/CU
cables + 2.5mm2 E as specified and as shown in electrical
drawings.

A1 Wall Bracket Lamp - CFL Nos. 20 7,200.00 144,000.00

A2 Pendant LED Lamp Nos. 6 6,650.00 39,900.00

A3 LED Mirror Lamp Nos. 3 7,500.00 22,500.00

A4 Slab Mounted LED down light Nos. 25 4,100.00 102,500.00

Supply and install ceiling fan 1400mm dia. 280 RPM, 3.5m3/S/
Air Delivery 65W, 230V, 50Hz with speed regulator aluminum
A5 Nos. 7 30,300.00 212,100.00
blade & accessories (KDK, National or approved equivalent
type).

ELECTRICAL INSTALLATION

A6 13A Socket Outlets Ring


Supply and install 2.5mm2 CU/PVC/PVC cable and 2.5mm2
earth Cu conductor with all accessories required to make
complete installations and wire 230 volts, 13Amp. single switch
Nos. 10 7,900.00 79,000.00
socket outlet in ring circuit as specified specifications &
illustrated in the electrical drawings. (including 13A switch
socket outlet)

A7 15A Socket Outlets Direct


Supply and install 2.5mm2 CU/PVC/PVC cable and 2.5mm2
earth Cu conductor with all accessories required to make
complete installations and wire 230 volts, 15Amp. single switch
Nos. 4 7,900.00 31,600.00
socket outlet in direct circuit as specified specifications &
illustrated in the electrical drawings. (including 15A switch
socket outlet)

Electrical works to Collection 631,600.00

Cluster Engineering Consultants (Pvt) Ltd. 31


Mr.Uyanahewage Priyantha Electrical Work

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

ELECTRICAL WORK (Cont'd)

A8 Ceiling Fan Outlets

Supply and install 1 mm2 CU/PVC/PVC cable and 2.5mm2


earth Cu conductor and wire, for ceiling fan outlets as per the
specifications and illustrated in the electrical drawings.
Including fixing charges with cost of connectors , hooks , Nos. 1 29,995.00 29,995.00
control switches or regulators and other all accessories required
to make complete installation. (Excluding cost of ceiling fan
fitting)

TV Socket Outlet wired with 5C2Vcable and accessories with


A9 Nos. 1 7,000.00 7,000.00
Socket outlet

Shaver outlet

Supply and install 1mm2 PVC cable, 2.5mm2 earth and wire for
A10 Nos. 1 7,000.00 7,000.00
shaver socket outlet. (including shave socket outlet).

Telephone Outlet

Supply and install two pair points .5mm cable and accessories
A11 and wire for telephone socket outlets from DF (including Nos. 1 7,000.00 7,000.00
telephone outlets).

Supply and install telephone distribution frame complete with all


A12 Nos. 1 7,000.00 7,000.00
accessories. 16 Pair

Single Phase Distribution Board


(Flush type, plastic enclosure)

A13 10 Way SPN MCB D/B Nos. 1 25,000.00 25,000.00


(c/w 1x20A, 1x16, 8x6A SP MCB's, 32A DP Isolator, 40A DP
RCCB c/o 30mA RCCB's)

Main Wires + Earth Wires

Supply all materials and install termination following PVC/CU


feeder cables drawn through and protect by rigid conduits.

A14 PVC/PVC/CU cable 2x6mm2 +PVC/CU cable 6mm2 sum 150,000.00

FEEDER CABLES

Supply all materials and install termination following PVC/CU


feeder cables drawn through and protect by rigid conduits.

A15 10mm2 cable 2 wire and earth 10mm2 sum 100,000.00

EARTH

Cluster Engineering Consultants (Pvt) Ltd. 32


Mr.Uyanahewage Priyantha Electrical Work

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Supply and install Earth Electrical 20mm dia: copper or copper


A16 sum 100,000.00
bond rod length 2100mm Earth cable with accessories.

Electrical works to Collection 1,064,595.00

ELECTRICAL WORK (Cont'd)

Supply and install PVC Type CEB Meter panel complete with
A17 sum 200,000.00
all accessories.

Inspection and Testing

Testing the total electrical installation and submit a test


certificate issued by a charted engineer including detail test
A18 Item sum 150,000.00
report acceptable to the supply authority and commissioning of
the system.

ELECTRICAL WORK CARRIED TO GRAND SUMMARY Rs. 1,414,595.00

Cluster Engineering Consultants (Pvt) Ltd. 33


Mr.Uyanahewage Priyantha Electrical Work

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 34


Mr.Uyanahewage Priyantha Plumbing Work

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

PLUMBING WORK
ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Sanitary fixtures and fittings

A Unless otherwise specified all sanitary fittings and fixtures shall be of


white color American standard, Toto or equivalent approved type.
All fittings to be completed with water supply and disposal
connections to working order.

A1
Supply and fix semi pedestal type of water closet including cistern
accessories such as WC connector, flush pipe, seat cover approved
Nos. 1 50,000.00 50,000.00
angle valves and flexible connector installed. Completed to working
order for the disable toilet with the disable relevant accessories .

Supply and fix Pedestal type of water closet including cistern


accessories such as WC connector, flush pipe, seat cover approved
A2 Nos. 4 58,000.00 232,000.00
angle valves and flexible connector installed. Completed to working
order.

A3 Supply and fix semi pedestal type of wash basin for the disable type No
(size approx.: 615x415 mm) color to the architect's approval with all
accessories such as base plug, chain approved type of plastic bottle /
p trap, angle valve flexible single tap connection installed. Complete 1 65,000.00 65,000.00
to working order. for the disable toilet with the disable relevant
accessories .

A4 Supply and fix Vanity type of wash basin on concrete vanity slab
finished with 3/4" thick approved polished granite tile in black color.
(size approx.: 615x415 mm) color to the architect's approval with all
Nos. 4 100,000.00 400,000.00
accessories such as base plug, chain approved type of plastic bottle /
p trap, angle valve flexible single tap connection installed. Complete
to working order.

A5 Supply and fix Chromium plated single level wash basin disable
personal mixer tap with pop-up waste, flexible connection of
"GROHE" or approved equivalent with 25 year written warranty Nos. 1 75,000.00 75,000.00
from the authorized agent. for the disable toilet with the disable
relevant accessories .

A6
Supply and fix Chromium plated single level wash basin mixer tap
with pop-up waste, flexible connection of "GROHE" or approved Nos. 4 75,000.00 300,000.00
equivalent with 25 year written warranty from the authorized agent.

A7 Supply and fix single bowl double drain board stainless steel wash
basin approved type including stainless steel bottle trap/ p trap, swell
type pillar tap, angle valve flexible connector waste plugs, chains Nos. 4 100,000.00 400,000.00
overflow connections installed complete to working order for kitchen
and pantry.

Cluster Engineering Consultants (Pvt) Ltd. 33


Mr.Uyanahewage Priyantha Plumbing Work

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT
Sanitary fixtures and fittings to Collection 1,522,000.00

PLUMBING WORK (Cont'd)

A8 Supply and fix mirror above wash basin comprising pencil edge
mirrors size: 3'-0"x2'-0" with stainless steel screws with rubber Nos. 5 15,000.00 75,000.00
bushes.

A9 Supply and fix approved quality hand spray bidet comprising flexible
chromium plated hose, angle valve and installed complete to working Nos. 5 15,000.00 75,000.00
order.

A10 Supply and fix head shower spray with hand shower and mixture
shower valve including wall mounted tap at the bottom, installed Nos. 5 20,000.00 100,000.00
complete to working order.

A11 Supply and fix chromium plated towel rail 32 dia and 600mtr long
including fix to wall with fiber plugs and chromium plated brass Nos. 5 16,000.00 80,000.00
screws.

A12 Supply and fix stainless steel soap tray fixed to wall with fiber plugs
Nos. 5 16,000.00 80,000.00
and chromium plated brass screws.

A13 Supply and fix chromium plated Robe Hook of "Rocell" or approved
Nos. 5 15,000.00 75,000.00
equivalent.

A14 Supply and fix chromium plated Toilet Paper Holder of "Rocell" or
Nos. 5 10,000.00 50,000.00
approved equivalent.

Water supply system from sump to over head tank

Piping shall be measured to the not length along the center line of the
pipes over all bends. Junctions, tees and the similar pipe fittings and
shall be given in feet. The size of PVC pipes and specials are
specified by the external dimensions. All water supply pipes shall be
of UPVC type 1000, SLS147 with solid welded joints. All drainage
pipes shall be UPVC type 800 with solvent welded joints. The prices
to include for screws, nails, pipes hooks, saddias, brackets
connections nipples and the like holes, chasing etc., Unless otherwise
specified. Separately should be deemed to have included in the
relevant item.

A15 Supply and install plastic water tank to the capacity of 2 x 2000 ltr.
At the roof terrace level with over flow, wash out valve etc., Item 1 60,000.00 60,000.00
complete to working order.

A16 Supply & fixing of approved quality water pump with flow rate 2000
Item 1 100,000.00 100,000.00
gal/hr, 50 ft head, 230v/50 Hz/ 1" dia.

A17 Supply & fixing of approved quality pressure pump with flow rate
Item 1 100,000.00 100,000.00
2000 gal/hr, 50 ft head, 230v/50 Hz/ 1" dia.

A18 25 mm dia, supply to water tanks from main road. Item 1 30,000.00 30,000.00

A19 Allow provisional sum to obtaining NWS & DB 25 mm water


Provisional 75,000.00 75,000.00
connection from road main.

Cluster Engineering Consultants (Pvt) Ltd. 34


Mr.Uyanahewage Priyantha Plumbing Work

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Plumbing works to Collection 2,422,000.00

PLUMBING WORK (Cont'd)

Water supply system from over head tank

A20 Distribution pipe system as per drawings laid through ducts, buried
150,000.00 150,000.00
and chased in to walls as indicated from the storage tank. Item

A21 Water supply pipe system as drawings laid underground sewer pipe,
150,000.00 150,000.00
rain water pipe. Item

Pegler - England brass stop valves as indicated below.

A22 1 1/2" dia. Gate valve Nos. 2 30,000.00 60,000.00

A23 1 " dia. Gate valve Nos. 5 25,000.00 125,000.00

A24 3/4 " dia. Gate valve Nos. 5 20,000.00 100,000.00

Internal Drainage

Rates shall include excavation, sand/concrete bedding, surrounding


pipes with concrete where necessary and back filling etc.

A25 Supply and fix all pipe into Drainage line Item 150,000.00 150,000.00

A26 UPVC Trap moulded floor gully of good quality. Fixed to toilet floor
slab with stainless steel grated cover with water proofing on top and Nos. 20,000.00
sides complete with no leak inlet and outlet connection. 5 100,000.00

A27 Sewer & waste water manhole size internally 2'-0" x 2'-0" depth not
exceeding 3'-0" including excavation. Built in 5" thick brick walls 1:3
Nos. 100,000.00
cement rendering 12 mm thick with 50 mm thick R.C cover slab, and
as per detail. 6 600,000.00

A28 Installation of P.c septic tank to 8'-0" dia 10'-0"


length rate to include excavation. Item 1 200,000.00 200,000.00

A29 Supply & construct brick soakage pit internal size 4'-0"
dia x 8'-0" height depth to suit site. Rate to include
for excavation etc. Item 3 150,000.00 450,000.00

A30 Installation of rain water harvesting tank to 4'-0" dia 8'-0"


length rate to include excavation. Item 1 200,000.00 200,000.00

PLUMBING WORK CARRIED TO SUMMARY Rs. 4,707,000.00

Cluster Engineering Consultants (Pvt) Ltd. 35


Mr.Uyanahewage Priyantha Plumbing Work

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT

Cluster Engineering Consultants (Pvt) Ltd. 36


Mr.Uyanahewage Priyantha Grand Summary

BILL OF QUANTITIES OF THE PROPOSED VILLA PROJECT FOR


MR. UYANAHEWAGE PRIYANTHA @ PARAMULLA, MATARA.
VILLA - I

GRAND SUMMARY

SUB STRUCTURE Rs. 9,121,093.79

GROUND FLOOR LEVEL TO FIRST FLOOR LEVEL Rs. 11,381,773.35

FIRST FLOOR LEVEL TO SECOND FLOOR LEVEL Rs. 13,426,030.94

SECOND FLOOR LEVEL TO ROOF LEVEL Rs. 12,867,857.66

ROOF TERRACE LEVEL Rs. 6,697,836.24

ELECTRICAL WORK Rs. 1,414,595.00

PLUMBING WORK Rs. 4,707,000.00

GRAND TOTAL Rs. 59,616,186.99

Cluster Engineering Consultants (Pvt) Ltd. 36