Linear Programing (Inequalities & Constraints)
Linear Programing (Inequalities & Constraints)
CONTENTS
1.0 Introduction
2.0 Objectives
3.0 Main Content
3.1 Method of Linear Programming
3.2 Step in Linear Programming
3.3 Slack
4.0 Conclusion
5.0 Summary
6.0 Tutor-Marked Assignment
7.0 References/Further Readings
1.0 INTRODUCTION
2.0 OBJECTIVES
1. Mixing problems.
2. Limited capacity is allocated to products so as to yield maximum
profits.
3. Transportation problem.
4. Purchasing.
6. Production scheduling.
6. Job assignments problem, etc.
144
BUSINESS MATHEMATICS
Similarly, the total time required to construct x chalets and y roads is (4x
+ 8y) hours.
145
BUSINESS MATHEMATICS
The best way of setting out the constraints is to place the units available
on the left and those utilized on the right; the inequality sign is the link.
These simply states that there cannot be negative amounts of chalets and
roads. Hence, the constraints are:
i. 6x + 3y 36.
ii. 4x + 8y 48.
Thus, x and y are each set to zero in turn and value of y and x computed
in those circumstances.
36
When x 0, y 12.
3
36
When y 0, x 6.
6
48
When x 0, y 6.
8
48
When y 0, x 12.
4
It is then necessary to decide which side of the equality represents the
feasible solution space. Where the constraint is of the form ax by c ,
as in both of the above cases, the values of x and y can lie anywhere on
the line or below it.
146
BUSINESS MATHEMATICS
i.e. Not below the x-axis and not to the left of the y-axis. The
constraints can now be represented graphically:
12
11
10
6x + 3y = 36
9
8
7
6 P
5
Q
4
4x + 8y = 48
3
2
1 R
0 x
1 2 3 4 5 6 7 8 9 10 11 12
The area OPQR which is shaded represents the feasible solutions i.e.
Combinations of the two products which are achievable given the
constraints. The problem is to find the optimum solution.
147
BUSINESS MATHEMATICS
3.3 Slack
This can be checked from the constraint inequalities by solving the two
simultaneous equations for the two constraints boundaries.
6x + 3(4) =36.
6x = 36 – 12=24.
x = 24/6 = 4
x = y = 4.
Thus, the maximum contribution is obtained when four chalets and four
roads per week are constructed.
C = 50x + 40y,
C = 50(4) + 40(4),
C = 200 + 160.
C = N360T.
148
BUSINESS MATHEMATICS
If, however, the optimum had been at P(x = 0, y = 6), then because P
does not lie on the material purchase time line, there would be slack
material purchasing time.
Example 2
Solution
149
BUSINESS MATHEMATICS
100
80
70
60
50 Feasible region
40
30 B
10g + 20n = 700
20 A
10 C g + n = 40
0 x
10 20 30 40 50 60 70
150
BUSINESS MATHEMATICS
4.0 CONCLUSION
5.0 SUMMARY
1. 3x 7 y 28
x y 6
9x 2 y 36
x 6 y 48
2. 3x 4 y 5
x y 8
Proportion of Metal
Metal Alloy Alloy Daily supply
151
BUSINESS MATHEMATICS
A1 A2 (tons)
m1 0.5 0.25 10
m2 0.5 0.75 15
Net profit 30 25 -
(N per ton)
152