1
3 1
S BAT
G
2
MTR
NOTICE
De-energize any source of inputs (customer PLC,
etc.) to the ECU prior to cycling the power or
pressing the reset switch on the PDB. Failure to do Figure 2: Power Distribution Box (P/N 309204C)
so may produce a voltage or current into the ECU
that is out of range, causing the circuit to disable. To 1 - Reset Switch 2 - Internal Fault LED
de-energize the inputs to the ECU, disconnect the
customer interface cable at the ECU. NOTE: After completing the PDB reset procedure, if
the problem is not corrected, contact your local
Waukesha Distributor for technical support.
RESETTING POWER DISTRIBUTION BOX
P/N 309204B (NO RESET BUTTON) ESTABLISHING AND MAINTAINING
1. Stop the engine. WATER INTEGRITY
2. Disconnect the power source to the power The PDB has been factory-tested and proven to be
distribution junction box. watertight under reasonable conditions. For proper
3. Reconnect the power source. engine operation and to maintain the factory warranty,
it is imperative to preserve the watertight integrity of
RESETTING THE POWER DISTRIBUTION BOX the PDB.
P/N 309204C (WITH RESET BUTTON)
As shipped from the factory, the PDB has several
1. Stop the engine. openings meant for unused electrical options and/or
2. Press and hold the reset switch about 3 seconds customer connections. These openings are factory-
until all LEDs turn off. sealed with either a push-in, self-centering, rubber
plug (1-1/2 in.) or a steel with rubber gasket plug that
3. Release the switch. must be manually centered and tightened with an
internal wing nut (3/4 in.).
NOTE: Only the B version has the metal plug.
12/19/2014
Copyright © 2014, General Electric Co. Page 2 of 3
Service Bulletin No. 17-3048A
These plugs must remain firmly in place at all times INSTALLING PDB COVER
unless the opening is used for wiring.
Be sure to properly reinstall the PDB cover any time
ADDING CUSTOMER-SUPPLIED WIRING that it has been removed (see Figure 4) for wiring or
TO PDB troubleshooting using the internal LEDs. DO NOT
leave the cover off when work is not actively being
When adding customer-supplied wiring to the PDB, all done. This includes indoors or overnight. When
connectors, fittings and grommets used must have a reinstalling the cover, all six latches must properly
rating equivalent to NEMA 4 or CSA type 4. Using engage the cover and the latch screws must be tight.
connectors, fittings or grommets that do not meet this
standard could allow water to enter the PDB, causing
problems up to and including failure of the PDB. See
Figure 3 for examples of both good and bad practice.