Pressure Decay Leak Test Method: Standard Practice For
Pressure Decay Leak Test Method: Standard Practice For
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
1
E2930 − 13
required test sensitivity or accuracy (see Annex A1 and Annex
A2). If the test is used to certify that the vessel has a minimum
specified leakage rate, then the test equipment and test duration
should be chosen to have a resolution ten times less than the
specification and an accuracy which is four times less than the
specification. The test should be designed so that the total
pressure change is less than 10 % of the starting pressure. Leak
test specifications should specify the vessel test pressure or
differential pressure. If the test specification does not specify a
test pressure, then a safe test pressure should be used that
complies with the applicable safety standards8.
6. Basis of Application
6.1 The following items are subject to contractual agree-
ment between parties using or referencing this practice.
6.2 Personnel Qualification:
6.2.1 If specified in the contractual agreement, personnel FIG. 1 Test Apparatus
performing examinations to this practice shall be qualified in
accordance with a national or internationally recognized NDT 11. Sampling, Test Specimens, and Test Units
personnel qualification practice or standard such as ANSI/
11.1 The units for test should be in mol/s or pressure based
ASNT-CP-189, SNT-TC-1A, NAS-410, or a similar document
units of Pa m3/s or std cc/s with the units referenced to a
and certified by the employer or certifying agency, as appli-
standard temperature of 0°C or 273.15 K (unless otherwise
cable. The practice or standard used and its applicable revision
specified in the test specification). The actual test temperatures
shall be identified in the contractual agreement between the
can vary over the specified operable ranges of the
using parties.
instrumentation, as long as the temperature is stable enough to
6.3 Qualification of Nondestructive Agencies—If specified meet the test resolution requirements.
in the contractual agreement, NDT agencies shall be qualified
and evaluated as described in Practice E543. The applicable 12. Preparation of Apparatus
revision of Practice E543 shall be in the contractual agreement. 12.1 Vessel Preparation—The test vessel should be clean
and dry. Hydrostatic, bubble, and liquid penetrant testing
7. Interferences should not be performed prior to a pressure decay test. All
7.1 Interferences in the reported leak values could result internal components subject to deformation or failure should be
from desorption of gases from the vessel or adsorption of gases removed. Care should be taken where trapped or poorly
into the vessel. In addition, the effect of permeation of gases accessible volumes may be encountered (double gasket seals)
out of the test vessel may be significant for very low leak rate because they can increase the uncertainty of the test.
measurements. Eq A2.3 of Annex A2 can be modified to
incorporate these additional effects if appropriate. This test 13. Calibration and Standardization
assumes a nominal isothermal testing environment. 13.1 The test equipment (pressure measurement, tempera-
ture measurement, and time measurement) must be appropri-
8. Apparatus ately calibrated and traceable to national or international
8.1 The required test equipment includes a pressure gauge/ standards. The accuracy of the method depends on the deter-
transducer of the appropriate range, automated or manual mination of the test vessel volume as outlined in Annex A3.
timing system for data collection, and a temperature measure- 13.2 Commercial pressure decay systems often use an
ment device along with proper fixtures as shown in Fig. 1. internal leak standard to determine the volume of the test
system. In this case the manufacturer should specify the
9. Reagents and Materials accuracy of the determined volume as outlined in Annex A3.
9.1 A non-condensable, inert gas is required for pressuriza-
tion of the test vessel. If air is used, the dew point temperature 14. Conditioning
must be lower than the tested temperature range. 14.1 The volume and test equipment should be allowed to
thermally equilibrate before commencing the test. The test
10. Hazards vessel should not be pressurized beyond the pressure specifi-
10.1 In no instance should the test pressure exceed the cations (or design limits).
maximum allowed vessel design limits.
15. Procedure
15.1 Assemble the test system and determine the system
8
See ASME Boiler and Pressure Vessel Code Section V Article 10 (paragraph volume (see Annex A3). An isolation valve should be used
T-1044) between the test vessel and test system for isolation purposes.
2
E2930 − 13
15.2 Perform a leak test of the test system with the isolation V = the vessel volume
valve closed and ensure that the leakage of the test system is R = the universal gas constant 8.3144 J/mol K (8.3144 Pa
less than 1 % of the target test value for the test vessel. m3/(mol K)
15.3 Determine the test parameters (initial pressure and test T = the vessel temperature, K
time) and calculate the test resolution and accuracies according TR = the reference temperature for the units (typically
to Annex A1 and Annex A2. Ensure that the calculated test 273.15 K)
resolution is at least ten times less than the target leakage rate. ∆P = the change in pressure between successive points
t = the change in time in seconds between successive
Ensure that the test accuracy is at least four times less than the
points
target leakage rate.
Examples are provided in Eq 3 and 4
15.4 Pressurize the vessel to the target pressure and close
the isolation valve 2. where:
15.5 Stabilization Time (Setting Time)—After P = 10000 Pa (0.1 atm)
pressurization, the temperature and pressure should be moni- V = 0.0001 m3
tored as a function of time over the test duration previously t = 100 sec.
established in 5.1. The pressure should be recorded at a TR = 273.15
minimum of ten time intervals during the test sequence. The T = 298 K
temperature should be recorded at the beginning and end of the ~ 10000 Pa! ·0.0001m 3 ·273.15K
N5 5 9.3 3 1023 Pa m 3 ⁄s (3)
test to ensure that the temperature is stable to within the 100s·293K
previously assumed limits. Illustrative pressure decay leak test ~ 0.1 atm! ·100cm3 ·273.15K
data is shown in Fig. 2. During the charge phase, gas is added N5 5 9.3 3 1022 Std cm3 ⁄s (4)
100s·293K
to the test system. The pressure in the test system will naturally
decay due to a number of factors (pressure equilibrating within 15.6 Depending upon the test conditions, it may require
the test system, gas temperature equilibrating, and so forth). seconds to hours for the indicated leak rate to stabilize.
The settling time will be dependent on the geometry of the test Stabilization criteria should be based on point to point varia-
system, the test pressures, filling times, type of gas used, and tions in the measured leak rate with a target of less than three
other environmental factors. times the calculated test resolution. The test data used in the
The leak rate should be calculated from the individual leak calculation in Section 16 will utilize data collected after
measurements with the following equations: stabilization.
N 5 ~ ∆ PV! ⁄ ~ RT ~ ∆ t !! ,mol/s (1) 15.7 The leak rate calculation can be calculated using one of
two methods. Method A is preferred as it also allows for
N 5 ~~ ∆ PV! ⁄ ~ ∆ t !!~ T R ⁄ T ! ,Pa m 3 ⁄s, or Std cc/s (2)
estimation of the precision of the test from the standard
where: deviation of the measurements.
3
E2930 − 13
15.7.1 Method A—The average of the calculated leak rates 16.4 It is important to perform multiple tests if possible to
determined from successive pressure measurements after sta- understand the stability of the measurements. Leak rate mea-
bilization. surements can be affected by environmental variables and these
15.7.2 Method B—The leak rate is calculated from a single effects can be significant; particularly when testing large
pressure reading obtained after stabilization and the pressure at volumes (greater than 100 L).
the end of the test.
17. Report
15.8 Once the stabilization time has been determined for a
17.1 Report of Test—The report of the test should have the
particular test system, it is not required to perform multiple
following information:
pressure measurements when utilizing Method A. The initial
17.1.1 Test Date
pressure after stabilization and the final pressure are sufficient.
17.1.2 Test Time
17.1.3 Test Technician
16. Calculation or Interpretation of Results 17.1.4 Test Accuracy
16.1 The leak rates should be calculated with equation 4 in 17.1.5 Beginning vessel test pressure
15.5. The significance of the measured leak rates should be 17.1.6 Ending vessel test pressure
interpreted from the computed test resolution and test accuracy. 17.1.7 Average reference test pressure (pressure outside of
Measured leak rates which are less than or equal to either the vessel)
test accuracy or test resolution are not significant. 17.1.8 Average test temperature
16.2 Method A—The leak rate should be calculated using Eq 17.1.9 Duration of test
1 and 2 in 15.5 with the pressure change, P, calculated as the 17.1.10 Test gas
difference between the pressure after stabilization from the 17.1.11 Average test leak rate in standard units
pressure at the end of the test. The change in time, t, is the 18. Precision and Bias
difference in elapsed time between the pressure measurements.
18.1 Precision and Bias—The bias should be calculated
The temperature, T, should be the average of the beginning and
using Eq A2.4 in Annex A2. The precision may be calculated
ending temperature of the test system.
with either of two methods.
16.3 Method B—The leak rate should be calculated using Eq 18.1.1 Single Test—If only one test is performed, the stan-
1 and 2 in 15.5 with the pressure change, P, calculated as the dard deviation of the calculated flows should be used to
difference between the successive pressure readings after estimate the test precision (assumes Method B is used).
stabilization. The change in time, t, is the difference in 18.1.2 Multiple Tests—If five or more tests are performed,
elapsed time between successive pressure measurements. The the average and the standard deviation of the five tests should
temperature, T, should be the average of the beginning and be computed. The standard deviation can be used to estimate
ending temperature of the test system. If the temperature is the test precision.
recorded with each pressure measurement, the average tem-
perature between successive pressure measurements may be 19. Keywords
used. The reported leak rate should be the average of the 19.1 leak; leakage; mass flow; pressure; pressure change;
computed leak rates. pressure decay; rate of change; vessel
ANNEXES
(Mandatory Information)
4
E2930 − 13
9
ISO/IEC Guide 98-3.
A3.1 The volume of the test vessel can be determined in a gas input into the vessel while monitoring the vessel pressure
number of ways. Two methods will be described in this and temperature. The volume can be calculated by Eq A2.4 and
practice. A3.2.
A3.1.1 Method A—Volume determined using a flow stan- V 5 ~~ total mass flow! R T! ⁄∆P, mol/s (A3.1)
dard V 5 ~~ total mass flow! R T! ⁄ ~ T R ∆ P ! ,Pa m 3 ⁄s or Std cc/s
A3.1.1.1 The most straightforward method for volume de-
(A3.2)
termination is to connect a mass flow measurement device to
the vessel, as depicted in Fig. A3.1, and measure the amount of where:
5
E2930 − 13
S
V D 5 V S1
P s1 2 P F
PF 2 PD D (A3.3)
6
E2930 − 13
FIG. A3.3 Test System for Volume Determination with Stray Volume
7
E2930 − 13
ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.
This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.
This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 610-832-9585 (phone), 610-832-9555 (fax), or service@astm.org (e-mail); or through the ASTM website
(www.astm.org). Permission rights to photocopy the standard may also be secured from the Copyright Clearance Center, 222
Rosewood Drive, Danvers, MA 01923, Tel: (978) 646-2600; http://www.copyright.com/