National Diploma Quantity Surveying
National Diploma Quantity Surveying
National Diploma Quantity Surveying
NATIONAL DIPLOMA IN
QUANTITY SURVEYING
INTRODUCTION TO MEASUREMENT
COURSE CODE:
CODE QUS 101
YEAR I - SE MESTER I
THEORY/MEASUREMENT
www.TechnicalBooksPdf.com
GENERAL OBJECTVES:
www.TechnicalBooksPdf.com
TABLE OF CONTENTS
General Objectives
1.0 History of quantity surveying and the duties of the quantity surveyor
4.1 Quantities
4.2 Descriptions
www.TechnicalBooksPdf.com
5.0 Building and engineering standard method of measurement general rules II
6.0 Building and engineering standard method of measurement general rules III
7.1 Taking-off
7.2 Descriptions
8.1 Introduction
10.1 Introduction
www.TechnicalBooksPdf.com
WEEK 1: HISTORY OF QUANTITY SURVEYING & DUTIES OF
THE QUANTITY SURVEYOR
The Quantity Surveying profession has its root in Britain during the 17th century although the
earliest recorded firm, Henry Cooper and Sons of Reading was established in 1785. The first
recorded use of the term “quantity surveyor” was in 1858.
www.TechnicalBooksPdf.com
System of building procurement gained strength
INDUSTRIAL
REVOLUTION Advent of the general contractor who submitted
inclusive estimates covering all the trades
Full drawings and specifications were prepared before
tenders were called for
Contractors tendered in competition with one another
based on the full drawings and specifications
THE
With time, the building owner found it to be to his own
INDEPENDENT advantage to appoint and pay the fees of the quantity
QUANTITY surveyor.
SURVEYOR
This was the origin of the independent and impartial quantity surveyor as it is found today.
1.2 Development of the Standard Method of Measurement
Up to the middle of the nineteenth century, it was the practice to measure and value
the building work after it had been completed and bills of quantities were not
prepared.
Dispute points in connection with building works were decided by the Surveyor’s
Institution and the Quantity Surveyors’ Association.
The frequency with which they were called to decide on areas of conflict pointed at
the necessity of achieving greater accuracy of work and uniformity of method.
1927 - 1998 Subsequently, revisions were made and other editions were
published the most current for measurement of building works
being the 7th edition (SMM 7). First published in 1988 and a
revised edition in 1998.
www.TechnicalBooksPdf.com
1.2.1 Standard Methods of Measurement for Other Classes of Work
www.TechnicalBooksPdf.com
1.4 The Nigerian Standard Methods of Measurement
The practice of the profession of quantity surveying has evolved dramatically starting from
the 1970s from that of measurement and valuation to cover much wider areas of expertise in
the procuring and management of various types of construction projects. This evolution has
come about as a result of changes in:
Construction markets
Construction industry
Clients’ needs
Professions
Advent of ICT
www.TechnicalBooksPdf.com
Today the quantity surveyor is the financial consultant to the construction industry and more,
providing services ranging from:
Cost management
Project management
Construction management
Procurement
Value management
2. Cost Planning
Cost planning is a specialist technique used by quantity surveyor’s, which aims to help all
members of the design team to arrive jointly at practical and efficient designs for the project
and to keep within the budget. Once a realistic estimate is set from the cost plan, constant
monitoring reduces the risk of overspending by noting problem areas at an early stage and
applying prompt corrective action.
www.TechnicalBooksPdf.com
3. Contractual Methods
The quantity surveyor can advise on the best type of tendering and the best form of contract
that will best suit a specific project. The quantity surveyor prepares the documents for
obtaining the tenders and arranging the contract.
4. Bill of Quantities
Competitive tendering remains a common basis for selection of contractor and bills of
quantities are fundamental to the process. Bills translate the drawings into a document listing
in detail all the component parts required for a project so that each contractor can calculate
tender prices on exactly the same basis as his competitors.
During construction, the bill forms the basis for preparing interim valuations, pricing of
variations and effective cost control.
5. Choice of contractor
The quantity surveyor analyses tenders and makes recommendations to the client for
contractor selection after taking into consideration other factors such as the contractors
reputation and past performance.
6. Contract Administration
The quantity surveyor acts with the architect or engineer to ensure that the financial
provisions of the contract are properly interpreted and applied so that the client’s financial
interest is safeguarded and that the builder is paid the proper price for the work.
He also exercises control during construction so that the cost is not exceeded without
authority.
www.TechnicalBooksPdf.com
8. Construction management
Construction management uses latest management techniques and other applications of
programming, network analysis, risk analysis, cash flow forecasting, budgeting and other
control mechanisms.
10. Dilapidations
The quantity surveyor prepares schedule of conditions at the beginning of a tenancy or lease
and a schedule of dilapidations at the end giving details of an outgoing tenant’s liability.
11. Arbitration
This is a formal process for settling disputes
The main function of the contractor’s quantity surveyor is to secure maximum payment for
work done by the contractor at the earliest possible time to avoid cash flow problems and to
maximise profits. These however have to be done within the provisions of the contract. The
contractor cannot receive more than he is entitled to by the contract.
In contrast with the consultant quantity surveyor who claims impartiality between the client
and the contractor, the contractor’s quantity surveyor will be representing his employer’s
interests alone. Wise contractors therefore always employ quantity surveyors to look after
their interests and in particular rely on them in the most controversial contractual areas.
The quantity surveyor working in a contractor’s organisation will therefore carry out the
following functions among others:
www.TechnicalBooksPdf.com
• For design and build contracts or civil engineering contracts, the quantity surveyor
works with other professionals in the contractor’s organisation to produce initial plans,
drawings and estimates for the project and helps to calculate the most economical way
to do the job.
• Prepares bills of quantities from which an estimation of the cost of a project can be
drawn up by the contractor
• Assessing the “quantity” of labour, materials and equipment required to complete the
project
• Follow the progress of the work to ensure that it is completed within budget
• Represents the contractor when interim valuations and final accounts are prepared
• Ensure that they receive the correct payment at the appropriate time for the work done
on site.
• Site measurements for internal and external valuations, final accounts, cost and
bonusing, sub-contract payments and final accounts.
• Interpreting and progressing contractual issues and settlement of disputes and claims
• Plant control
www.TechnicalBooksPdf.com
WEEK 2: THE ROLE OF VARIOUS PROFESSIONALS IN THE
CONSTRUCTION PROCESS
The quantity surveyor is essentially an expert on construction cost and construction contracts
whose prime task is to ensure that the project is kept within budget and that the client gets
value for money. Although the quantity surveyor is employed by the client and is part of the
architect’s team, he must have a close relationship with the contractor during construction. He
must ensure that in his valuations of payments due to the contractor, he remains impartial to
both the client and the contractor and so produce harmony in his role as project accountant.
• The quantity surveyor works with the architect or engineer to ensure that the financial
provisions of the contract are properly interpreted and applied so that the client’s
financial interest is safeguarded and that cost is not exceeded without authority.
• Values variations
• Evaluates all financial claims made by the contractor who is allowed to be present at
such times so that agreement is ensured and disputes are avoided
• He also prepares financial statements that keep the client informed as to the running
cost of the project.
www.TechnicalBooksPdf.com
2.1.4 Completion
• He prepares the final account, again, with the assistance of and in agreement with the
contractor.
The architect is regarded as the leader of the building team. However, project managers and
other professionals are currently taking over this traditional role. He often receives the
commission to design and supervise the construction of the building.
• Prepares the preliminary designs based on the brief with inputs from quantity
surveyors on comparative costs of alternative design proposals and from consulting
structural and service engineers on aspects of complex buildings.
• After approval from the client, he produces detailed architectural designs while the
engineers produce detailed structural and service designs and the quantity surveyor
produces a cost plan based on which he ‘cost checks’ to keep costs within client’s
budget.
• Decides which aspects of the work are to be carried out by nominated subcontractors
and suppliers.
www.TechnicalBooksPdf.com
When design is completed:
• He obtains all necessary planning approvals
• Calls for tenders from suitable contractors either based on a bill of quantities or other
contractual arrangement.
• He receives the tenders and advises the client on selection of contractor usually based
on quantity surveyor’s recommendation.
• Chairs site meetings, which are held regularly on site where problems and difficulties
are discussed and resolved.
• Issues instructions to the contractor in relation to the work execution and any
variations required.
2.2.3 Completion
At the end of the project the architect issues:
• The certificate of making good defects usually six months after practical completion
• The final certificate not later than two months after the end of the defects liability
period.
www.TechnicalBooksPdf.com
2.3 The Structural, Services & Building Engineers
On large complex building projects the architect will recommend to the client the
employment or appointment of consulting engineers, usually specialist in structural work and
mechanical and electrical services.
2.3.2 Post-contract
• During construction, the consulting engineers assist the architect by supervising their
specialist area of the work, modifying or re-designing work as may become necessary.
www.TechnicalBooksPdf.com
The professional holds himself or herself out as an expert in a specified field. The person
must have the training, skills and experience to back up such a claim.
Professionals usually come together to form associations to protect members and advance
their interests. Governments on the other hand seek to regulate professions in a bid to protect
members of the public in relation to the activities of the professionals.
In some countries, the government allows the professional groups self-regulation whereas in
others, the government sets up a government agency that has the responsibility of regulating
the practice of the profession in that country.
www.TechnicalBooksPdf.com
2.5.3 The Nigerian Institute of Quantity Surveyors (NIQS)
The Nigerian Institute of Quantity Surveyors was founded in 1969 by Nigerians who had
trained, qualified and practised quantity surveying in the United Kingdom but who returned to
Nigeria and felt the need to develop the profession in Nigeria.
The regulated and other Provisions) Act of 1978 recognised quantity surveying as one of the
scheduled professions. Decree No. 31 of 1986 gave legal backing and recognition to the
quantity surveying profession and also established the Quantity Surveyors Registration Board
of Nigeria (QSRBN) to regulate the profession.
The vision of the NIQS is “To be the profession in Nigeria responsible for total cost and
procurement management, for the achievement of client’s objectives in all types of capital
projects and developments, from conception to commissioning and maintenance, in all sectors
of the economy, for the attainment of sustainable national development and goals.”
(a) To promote the science and practice of the quantity surveying profession in all its
ramifications.
(b) To provide a platform or forum for meeting and discussing matters of mutual interest
to quantity surveyors in Nigeria and to preserve and further the interest of quantity
surveyors.
(c) To promote and stimulate the improvement of the technical and general knowledge of
persons engaged in the profession of quantity surveying.
(d) To organise continuing education and professional training of those seeking to become
professional quantity surveyors and assist and procure its members to be registered by
the QSRBN.
(e) To undertake research study and to collate information from any quantity surveying
bodies from any part of the world on the latest developments and technologies in the
practice of quantity surveying and to make available such information to its members.
www.TechnicalBooksPdf.com
(f) To cooperate with the QSRBN in training of quantity surveyors and regulating and
controlling the practice of quantity surveying in Nigeria.
(h) The maintenance of the highest standards of discipline and professional conduct.
The vision of the NIOB is to provide Nigeria with the profession that will be responsible for
the complete construction of new buildings, maintenance of existing buildings and building
production management utilising high standards of practice and provide modern and
appropriate construction techniques with more emphasis on improved training, safety, quality
and value management for the benefit of the fatherland.
www.TechnicalBooksPdf.com
2.5.5 Council of Registered Builders of Nigeria (CORBON)
CORBON was established by Builders’ (Registration etc.) Decree No. 45 of 1989 to control
and regulate the practice of the Building Technology profession in all its aspects and
ramifications.
Statutorily, a professional builder cannot practice the profession in Nigeria unless he/she is
registered with CORBON and remains registered throughout his/her professional career.
Aeronautical
Agricultural
Chemical
Civil
Electrical
www.TechnicalBooksPdf.com
Environmental
Geotechnical
Industrial
Mechanical
Metallurgical
Petroleum
Structural
The objective NSE is to promote the advancement of engineering education, research and
practice in all its ramifications. This is with a view to maintaining and enhancing the
professional capabilities of its members so as to better equip them to fulfil the needs of the
profession for the good of the public and the nation.
www.TechnicalBooksPdf.com
• Provide leadership in a fragmented construction industry
• Accept that it is the commercial world that is the leading edge but use its position and
authority to influence and create and spot trends
• Reflect the need for individuals to remain champions of property and fairness and
uphold the charter
• Constantly upgrade professional skills, business skills and knowledge to a level which
is envied by other professionals
• Promote the benefits of employing a chartered surveyor so that the currency value of
belonging to the RICS is as high as possible
• Improve communications and develop the single profession culture among its
members
www.TechnicalBooksPdf.com
WEEK 3: THE STANDARD METHOD OF MEASUREMENT
Definition
The standard method of measurement is a document that sets out the rules for the
measurement and description of construction works.
Purpose
Its main purpose is to provide a uniform basis for measuring construction work. When bills of
quantities are prepared based on a particular standard method of measurement, all the parties
concerned are aware of what is included, assumed or not included. All contractors tendering
therefore tender on the same basis and their tenders can easily be evaluated and compared.
The BESMM3 is made up of two main parts. The measurement and description rules in each
part are grouped under main headings as follows:
1A Preliminaries/General Conditions
C Existing site/Buildings/Services
D Ground work
F Masonry
H Cladding/Covering
J Waterproofing
K Linings/Sheathing/Dry Partitioning
www.TechnicalBooksPdf.com
L Windows/Doors/Stairs
M Surface finishes
N Furniture/Equipment
Q Paving/Planting/Fencing/Site furniture
R Disposal systems
X Transport systems
2A General items
D Ground work
Q Paving – Highways
X Transport systems
The section preceding the two chapters contains general rules guiding the use of the standard
method. These rules need to be properly understood by the student before commencing actual
measurement and will therefore be treated studied in detail in for the next three weeks.
For this course we shall be treating the general rules covering the measurement and
description of building works only.
www.TechnicalBooksPdf.com
General Rules Introduction
The Bill of Quantities (BOQ) should contain all the items of cost required to complete a
construction project. The bill should therefore fully describe and accurately represent the
quantity and quality of the works to be carried out. Carefully following the rules prescribed in
the Standard Method of Measurement should ensure this.
The use of the SMM will be studied under the following headings:
Tabulated Rules
Quantities
Descriptions
Drawn Information
Cross referencing
Tabulated Rules
The rules of the BESMM3 are set out in tables. Rules covering each work group or section are
set out under three headings:
Information to be provided
Classification tables
Supplementary rules
The horizontal lines divide the classification tables and supplementary rules into zones to
which different rules apply. Fig 1 shows a typical page from the BESMM3.
www.TechnicalBooksPdf.com
C90 Alterations – spot Items
INFORMATION PROVIDED MEASUREMENT RULES DEFINITION RULES COVERAGE RULES SUPPLEMENTARY INFORMATION
P1 The following information is shown either on location drawings under 1A Preliminaries/General conditions M1 The rules within this D1 Materials arising from C1 Shoring and scaffolding S1 Method of operation, where by
or on further drawings which accompany the bills of quantities: section apply to works in alterations – spot items incidental to the work and making specific means
(a) the scope and location of the work relative to the existing layout indicating the existing structure existing buildings as are the property of the good all work disturbed is deemed
defined in the General rules Contractor unless to be included within each item S2 Setting aside and storing materials
otherwise stated remaining the property of the Employer
M2 any operation to C2 Alterations – spot items are or those for re-use
existing buildings involving D2 Location is stated deemed to include:
removal of existing relative to the existing (a0 disposal of the materials other S3 Employer’s restrictions on methods
materials (other than for building than those remaining the property of disposal of materials
bonding purposes or of the Employer or those for re-use
renewal) is measured within (b) work incidental to alterations – S4 Employer’s restrictions on methods
this Section spot items which is at the of shoring and scaffolding to be used
discretion of the Contractor
(c) all new fixing or joining
materials required
CLASSIFICATION TABLE
1 Removing 1. Details Item 1. Making good structures
components, fittings sufficient for
and fixtures identification 2. Extending and making
stated good finishes
2. Removing plumbing
and engineering 2. Dimensioned 3. Inserting new work, details
installations description stated
sufficient for
3. Removing finishing identification 4. Toxic/Hazardous materials,
including type and type stated
4. Removing coverings thickness of
existing building
5. Cutting openings or
recesses
6. Cutting back
projections
7. Cutting to reduce
thickness
8. filling openings
9. Temporary roads 1. Dimensioned tem 1 Providing and erecting
description
10 Temporary screens 2. maintaining, duration state
Fig 1
www.TechnicalBooksPdf.com
Information to be provided
This section ensures that details about the work at hand which the tenderer requires to make accurate
estimates are provided either in location drawings, bill diagrams, specifications or preambles as the
case may be.
E.g. E05 In-situ concrete states that the relative position of concrete members, size of members,
thickness of slabs and permissible loads in relation to casting time must be clearly shown on location
drawings or bill diagrams.
Classification Tables
This section has five columns. The fourth column from the left which contains units of measurement
is usually not referred to when cross-referencing. For this reason, the classification table is in some
texts said to have four columns.
Unit of measurement column states the unit of measurement appropriate for each item or unit
of work
Column 4 contains more descriptive features that are meant to enhance the quality of the
descriptions of work built up from columns 1, 2 & 3
In building up a description for an item, one descriptive feature is taken from each of the first three
columns and as many as are applicable from the fourth column.
Supplementary Rules
Measurement rules
Definition rules
Coverage rules
Supplementary information
www.TechnicalBooksPdf.com
These rules are meant to guide the user of the SMM to properly measure the physical quantities and
to compose and phrase the work item descriptions appropriately.
These set out when work is to be measured and how the quantities are to be calculated. It states for
instance the voids in quantities that are to be deducted and those to be ignored, when to measure an
item separately or when to treat as part of some other item, etc.
These define the extent and limits of the work represented by a word or expression used in the rules
and in the bills prepared in accordance with the rules. For instance the expression “slabs” in relation
to in-situ concrete would include the slab itself and any beams attached to it and any column drop
heads also attached to it.
Suspended slab with attached beam & suspended slab with column drop heads
www.TechnicalBooksPdf.com
Column 7 – Coverage Rules
These draw attention to incidental items which are deemed to be included or excluded from the item
of work being measured. For instance, coverage rule C1 on page 50 states that bar reinforcement is
deemed to include hooks, tying wire, spacers and chairs. This means that the contractor in estimating
his cost for bar reinforcement should include the cost of any hooks, tying wires, spacers and chairs
that he may require for that item of work. These items will not be measured separately or mentioned
elsewhere in the bill.
These rules govern the information to be given in addition to the information given in accordance
with the classification rules. It may contain directives to measure an item separately as a different
work item. For instance, additional information is required by the supplementary rules in relation to
in-situ concrete suspended slabs on the kind and quality of materials to be used and their mix ratios.
www.TechnicalBooksPdf.com
WEEK 5: BESMM3 GENERAL RULES I
4.1 Quantities
Quantities of work are taken net, that is, as they will be when fixed in position in the building unless
the rules state otherwise. Dimensions used in calculating quantities are taken to the nearest 10mm. In
other words, measurements are taken to two places of decimal when calculating quantities.
When calculations have been completed, quantities are entered into the bills as whole unit with
decimal points rounded up to the nearest whole number. The exceptions are:
• Quantities that are less than one unit which are always rounded up to one unit
4.2 Descriptions
Each measured item consists of a quantity and a description. As a general rule, where an item is
measured:
www.TechnicalBooksPdf.com
4.3 Framing Work Item descriptions
In building up a description for an item, one descriptive feature is taken from each of the first three
columns and as many as are applicable from the fourth column. Headings of groups of items in the
SMM are read as part of the description.
Example 1:
Classification table:
Supplementary information:
Example 2:
Classification table:
www.TechnicalBooksPdf.com
Description should then read something like this:
Example 3:
Classification table:
Supplementary information:
Mild steel bar reinforcement, 16mm diameter, straight horizontal length 12.00-15.00m
The SMM requires that the bills should be read in conjunction with drawings which are provided in
the form of location drawings, component drawings, dimensioned diagrams and schedules.
www.TechnicalBooksPdf.com
1. Location drawings include:
• Block plans which identify the site in relation to the town
• Site plans which show the position of construction in relation to setting out points, access to
the site and general site layout
• Plans, sections and elevations which show the various spaces and location of the principal
elements
2. Component drawings show information required for the manufacture and assembly of a
component
3. Dimensioned diagrams that show the space and shape of work items which may be used in a bill
of quantities in place of a dimensioned description
4. Schedules deemed to be drawings when they provide required information
A precise and unique cross-reference to a catalogue or standard specification can reduce or replace
the requirements for an item description or component drawing. For instance, a precise reference to a
British standard (BS) or Cope of Practice (CP) can take the place of a detailed description for a work
item.
www.TechnicalBooksPdf.com
4.7 Procedure when inadequate information is provided
Where work can be fully defined as to description but the quantity of work cannot be accurately
determined, an estimate of the quantity is given and marked as a “provisional quantity”.
Where work cannot be described and the quantities cannot be adequately determined, it shall be
given as a “provisional sum”. Provisional sums may be of two types:
This covers work that though not completely designed, the following information is available:
In such cases, the Contractor is expected to make allowance for the work in his programming,
planning and pricing of preliminaries
This covers work for which none of the above information can be provided. in this case, it is
assumed that the contractor has not made any allowance for it in his programming, planning and
pricing of preliminaries.
During the process of “taking-off” or measurement words entered in the description column are
abbreviated to shorten descriptions, save space and also save time. The symbols and abbreviations
range from those in general use to those that are specifically used by quantity surveyors.
www.TechnicalBooksPdf.com
Those in common use include:
M Metre
m2 Square metre
m3 Cubic metre
Mm Millimetre
Nr or No. Number
Kg Kilogram
T Tonne
H hour
Specialised abbreviations
av. average
Blk Block
blkwk Blockwork
c/c Centres
col. Column
conc. Concrete
ddt Deduct
dp Deep
ditto/do As above
exc. Excavate
www.TechnicalBooksPdf.com
fdn Foundation
fwk Formwork
hwd Hardwood
Int. Internal
isol. Isolated
Jt. Joint
matl. Material
max. Maximum
o/a Overall
reinfd Reinforced
sprd Spread
susp. Suspended
thk Thick
vert Vertical
wdw Window
wk Work
wrot Wrought
wt. Weight
xtg existing
www.TechnicalBooksPdf.com
WEEK 5: BESMM3 GENERAL RULES II
Cross Referencing
Cross referencing or coding of work item descriptions within the classification tables are given in the
form:
Example 1:
D20: 2.1.1.0
NOTE!
An asterisk (*) within a cross reference represents all entries in the column in which it appears
A zero (0) within a cross reference represents no entries from the column in which it appears
Cross referencing of descriptions is useful for abstracting and billing using the computer.
Example 2
D20:2.6.3.1
www.TechnicalBooksPdf.com
Excavating and filling Work section number
www.TechnicalBooksPdf.com
Example 3
D20:7.2.1.1
Example 4
E05:9.1.2.1
www.TechnicalBooksPdf.com
In situ concrete Work section number
Example 5
E20:1.1.2.1
Example 6
E30:4.1.0.0
www.TechnicalBooksPdf.com
Column 3, no entry
Column 4, no entry
www.TechnicalBooksPdf.com
Example 7
M10:5.1.1.1
www.TechnicalBooksPdf.com
CLASSROOM EXERCISE
Identify the relevant clauses in the BESMM3 to measure the following items, frame appropriate
descriptions and insert sample dimensions of the appropriate units:
4. Hardcore filling of broken blocks to make up levels under floors 300mm thick
5. White glazed vitreous china wash hand basin size 460 x 405
www.TechnicalBooksPdf.com
WEEK 6: BESMM3 GENERAL RULES III
Example 8
F10:1.1.1.2
www.TechnicalBooksPdf.com
Example 9
F10:2.1.1.0
Column 4, no entry
Example 10
G20:9.2.1.1
www.TechnicalBooksPdf.com
Roof members Column 1, number 9
www.TechnicalBooksPdf.com
Example 11
H72:1.1.0.0
Column 3, no entry
Column 4, no entry
www.TechnicalBooksPdf.com
Example 12
J41:2.1.0.0
Column 3, no entry
Column 4, no entry
Example 13
L10.1.0.1.0
www.TechnicalBooksPdf.com
Windows and window frames Column 1, number 2
Column 2, no entry
Column 4, no entry
www.TechnicalBooksPdf.com
Example 14
L20.1.0.1.0
Column 2, no entry
Column 4, no entry
www.TechnicalBooksPdf.com
Example 15
M60.1.0.1.0
Column 2, no entry
Column 4, no entry
www.TechnicalBooksPdf.com
CLASSROOM EXERCISE
Identify the relevant clauses in the BESMM3 to measure the following items, frame appropriate
descriptions and insert sample dimensions of the appropriate units:
www.TechnicalBooksPdf.com
WEEK 7: MEASUREMENT PROCEDURES
7.1 Taking-Off
This implies reading off dimensions form drawings and setting them down in a specific order on
special paper known as dimension paper and inserting an appropriate description.
1. 2. 3. 4. 1. 2. 3. 4.
On the left-hand side is a narrow binding margin. The remainder of the sheet is divided into two
identical halves each containing three narrow columns and a wider one; the timesing column, the
dimension column, the squaring column and the description column respectively. The columns are
used as follows:
1. Timesing column is used for multiplying (timesing) the dimensions when necessary, each
multiplying factor followed by an oblique stroke. A factor followed by a dot indicates
addition instead of multiplication.
4 3.45
7.59
0.15
2
. 2.08
4.44
1
0.15
2. Dimension column is used for recording the dimensions in metres and centimetres.
Each linear dimension is underlined.
7.59 Length
LINEAR
www.TechnicalBooksPdf.com
A pair of dimensions, one above the other:
3.45 Length
AREA 7.59 Width
NUMBER 2
1. Length
2. Width
Item indicates an item of cost for which a quantity cannot be calculated. A sum of money is usually
estimated and allowed for in the bills.
www.TechnicalBooksPdf.com
ITEM Item Allow for bringing to site
and removing from site
all plant required for this
work section
3. Squaring column: the resulting areas and volumes inserted in the timesing and dimension
columns are subsequently calculated and entered into the squaring column opposite their
respective dimensions.
4 3.45
7.59
15.71
0.15
2 2.08 4.16
. 4.44
0.15
1
4. Description column: This wide column is for entering descriptions of the measured work.
. 4.44
0.15
1
www.TechnicalBooksPdf.com
5. Waste column: This is an imaginary column occupying the right had side of the description
columns in which the taker-off inserts any preliminary calculations (waste) which may be
necessary in order to arrive at his dimensions.
All preliminary calculations must be shown in waste. They need to be set down accurately
and carefully so they can be checked. They should be written either above or below the
description not level with it to avoid confusion.
Waste calculation is necessary for each dimension except in the following situations:
a) When a scaled or figured dimension can be transferred direct from the drawing to the
dimension column
b) When a dimension has been derived from a previous waste calculation
c) When a dimension has been copied from a previous dimension
d) In all other instances the preliminary calculation however simple should be shown on
waste.
Waste calculation should be done in millimetres or to three places of decimal. Final figures
are then rounded off to the nearest 10mm before being transferred to the dimension column.
7.2 Descriptions
The first line of each description should start at the same level as its first dimension. Standard or
common abbreviations are allowed in taking off but descriptions must be written in full in BOQs.
Descriptions must be concise, brief and free from grammatical errors. Terms used must comply with
current technical usage and an estimator must be able to read, understand and price it quickly and
accurately.
The following points should be noted:
• Descriptions should not be broken at the bottom of the page or column to continue overleaf
• Do not write ‘ditto’at the top of a column as this has no meaning
• Instead, repeat the first phrase in the description followed by “… as before described” or
“abd”,
Anding-on: Where two descriptions apply to one dimension, they are separated by an & in the centre
of the description column. Any number of descriptions may be anded-on in this way but not so as to
extend to another column.
www.TechnicalBooksPdf.com
15.67 Plain in-situ
0.68 conc (1:3:6) abd
0.23
7.89 &
0.68
0.23 Ddt
13.99 Backfill exc.
0.45 matl. Abd
0.15
&
Add
Remove excvtd
matl. from site
Deductions
Each item to be deducted requires the description to start with the word Deduct or Ddt (underlined).
A description must follow the word Ddt. It should not be written on its own. The next positive
description should be preceded with the word Add (underlined) in order to emphasise the change
from deductions to additions.
Bracketing
A bracket should be used wherever:
(a) More than one dimension applies to a description
(b) More than on description applies to a dimension
The bracket is written in the description column just next to the squaring column.
www.TechnicalBooksPdf.com
Niling
In order to delete, cancelling of dimensions is not allowed. Instead, the word “NIL” is written in the
squaring column opposite the offending dimension or dimensions. Arrows are usually used to denote
the extent of the deletion.
32.89
0.68
0.23
15.67
0.68
0.23
7.89
0.68 NIL
0.23
13.99
0.45
0.15
25.54
0.45
0.15
www.TechnicalBooksPdf.com
Annotations
Annotations are short or abbreviated words written beside waste calculations and dimensions to
denote from where the figures have been derived.
Side notes to dimensions require a single bracket on the left hand side only.
Example:
5.89 ( BDR 1
4.40 (BDR 2
(BDR 3
3.60
4.50 (BDR 4
3.77
4.55
3.45
Spacing of dimensions
All measurements and descriptions should be spaced well apart so that it is quite clear where one
begins and the other ends. Moreover it is not unusual for the taker-off to realise an omission and to
want to insert it in its proper place. If dimensions are well spaced out, he will be able to squeeze it in,
but otherwise he will have to insert it elsewhere and resort to cross-referencing which only confuses
things.
www.TechnicalBooksPdf.com
WEEK 8: APPLIED MENSURATION I
8.1 Introduction
Determination of quantities for work items in construction work involves calculating geometric
quantities such as lengths, areas and volumes from dimensions and angles that are known. Doing this
will require a healthy knowledge of the formulae for calculating the perimeters, areas and volumes
for various shapes.
These various shapes form the building blocks for most components found in construction work.
For instance, the area of the concrete floor slab below is a combination of rectangles of different
sizes.
www.TechnicalBooksPdf.com
The archway below is made up of a half circle and a rectangle and the gabled wall is made up of a
triangle and a rectangle.
The hipped roof below is made up of two triangles and two rectangles
www.TechnicalBooksPdf.com
The following are useful formulae for calculating volumes, areas and perimeters of various shapes
SHAPE FIGURE VOLUME TYPICAL BUILDING
COMPONENTS
www.TechnicalBooksPdf.com
SHAPE FIGURE AREA PERIMETER
Circle
π x (radius)2 π x radius x 2
www.TechnicalBooksPdf.com
SHAPE FIGURE AREA PERIMETER
Arc of circle
2 x π x radius x θ/3600
Chord
www.TechnicalBooksPdf.com
SHAPE FIGURE AREA PERIMETER
Ellipse a A
0.7854 x (A x a)
Sphere
4 x π x (radius)2
www.TechnicalBooksPdf.com
SHAPE FIGURE AREA Perimeter
A
Trapezoid Height x ½(base + top)
C
C x ½(A + B)
B
Hexagon
2.6 x (side)2
Octagon
4.83 x (side)2
www.TechnicalBooksPdf.com
WEEK 9: APPLIED MENSURATION II
For instance, measuring the volume of excavation for a foundation trench involves calculating the
area of a rectangle (cross section of the trench) and multiplying by the length of trench.
d
l
5m 3m 7m
2.5m
5m 4m
www.TechnicalBooksPdf.com
The surface area of the floor would naturally divide into three rectangles. If the thickness of the floor
was 150mm (0.15m), then,
5.00
5.00
0.15 3.75
3.00
2.50
0.15 1.13
7.00
4.00
0.15 8.40
13.28
An area of a component of wall would usually be the area of a rectangle, length of wall multiplied by
the height. If the wall is a gable wall then it would be rectangle topped by a triangle.
www.TechnicalBooksPdf.com
A wall would also usually have openings for windows, doors, arches, fixed lights, etc. The usual
thing is to measure the whole wall overall as if there were no openings and then systematically
deduct for openings that are rectangles, triangles and circles or parts thereof.
8m
0.9m
0.9m 0.9m
Area of wall = (8m x 3m) – { (1.2 x 0.9) + (0.9 x 2.1) + (1.2 x 0.9)}m2
= 24m2 – (1.08 + 1.89 + 1.08)m2
= 24m2 – 4.05m2 = 19.95m2
8.00 225 mm hollow
3.00 24.00 sandcrete block wall in
c.m (1:4)
2 1.20 Ddt
0.90 2.16 Ditto
0.90
2.10 1.89
4.05
www.TechnicalBooksPdf.com
Formwork to an isolated concrete column 225 x 225mm sectional size, 3m long. Formwork will go
round all four sides.
225mm
225mm
Perimeter of rectangle or square
= 225 + 225 + 225 + 225mm
= 2.7m2
On dimension sheets:
4 0.23
3.00 2.76
www.TechnicalBooksPdf.com
Formwork to attached column 225 x 450 mm sectional size, 3.00m long
In this case, formwork is only on three faces of the concrete, on the two sides and on the wide face
face.
= 0.900m2
= 2.7m2
On dimension sheets:
Length
225
450
225
900
www.TechnicalBooksPdf.com
Any irregular-shaped area to be measured is usually best divided into triangles, the triangles being
measured individually and added to give the area of the whole. A line can be drawn through an
irregular or curved boundary in such a way that the area excluded by the line is compensated for by
the area that is included by it.
www.TechnicalBooksPdf.com
WEEK 10: CENTRE LINE GIRTH I
10.1 Introduction
The perimeter of a shape without thickness is simple to compute arithmetically using the principle of
(length + breadth) x 2. Whilst the simple arithmetic concept is always to be used, the computation
often proves to be somewhat complex for most students when a thickness is attributed to the shape as
is always the case when the perimeter of a wall or a trench is required to be computed.
To compute the perimeter of a wall, we will need to work out the perimeter of the internal line of the
wall and the perimeter of the external line of the wall and then compute the average of the two
perimeters. This procedure will turn out to be clumsy if not cumbersome. Hence the need for the
systematic computation of centre line as set out in the foregoing examples.
The importance of centre line computation cannot be over-emphasised as the result of the
computation will subsequently be found to be useful for the measurement of several items all
through the take-off stages.
10m
Centre line
www.TechnicalBooksPdf.com
Centre Line
As this is a longer
than the perimeter
of the line running
through the centre
of the width of the
wall, Deduction
should be made as
follows:
Ddt At a corner, we
lose
4/2/½ /200 0.800 1 x ½ the thickness
in each of two
35.20 directions. This is
repeated in all the 4
x corners
www.TechnicalBooksPdf.com
Rectangular plan shape with a recess at corner(s)
2m
3m
10m
www.TechnicalBooksPdf.com
Centre Line
Ddt
Student should
note that
regardless of how
dimensions are
This explains why an irregular shape is recorded in the
likely to be more expensive to build than a drawings,
regular shape as the same amount of quantities when
excavation and foundation work is required transferred to the
whilst the irregular shape provides a lesser waste calculation
usable floor area. column shall be
recorded to 3
places of decimal
or in millimetres (if
recorded without
decimal) without
any indication given
of the actual unit of
measurement
CLASS EXERCISE
Give students a rectangular shape with recesses at two corners (all dimensions given) to work out the
centre line for the recessed shape.
www.TechnicalBooksPdf.com
WEEK 11: CENTRE LINE GIRTH II
8m
3m
2m
www.TechnicalBooksPdf.com
Centre Line
+6 x external corners
-2 x internal corners
www.TechnicalBooksPdf.com
RULE 2
www.TechnicalBooksPdf.com
CLASS EXERCISE
1. Give students a couple of rectangular shapes with recesses at two or more locations along the
wall (all dimensions given) to work out the centre line for the recessed shape.
www.TechnicalBooksPdf.com
WEEK 12: CENTRE LINE GIRTH III
Rectangular plan shape with a recess along the wall and recess at a corner
2m
200mm thick walls
3m
8m
3m
2m
10m
www.TechnicalBooksPdf.com
Centre Line
+7 x external corners
-3 x internal corners
This gives us a net +4
corners
www.TechnicalBooksPdf.com
RULE 3
A MIX OF A CORNER
RECESS AND AN ALONG
THE WALL RECESS ALTERS
THE PERIMETER OF THE OF
THE SHAPE BY 2 X THE
DEPTH OF THE ALONG
WALL RECESS. THE
CORNER RECESS DOES
NOT HAVE ANY AFFECT.
www.TechnicalBooksPdf.com
CLASS EXERCISES
1. Give students a couple of plan shapes with complicated recesses asking them to count how
many external and internal corners are present. Do this until the lecturer is confident that
students have a clear understanding of this concept
2. Give students a rectangular shape with recesses at two or more locations along the wall (all
dimensions given) to work out the centre line for the recessed shape.
www.TechnicalBooksPdf.com
WEEK 13: BESMM3 RULES FOR EXCAVATION AND
EARTHWORK I
Filling holes and excavations other than those for services, etc. and
D20 Rule C2 This rule refers to the measurement of working space and apart from the
additional excavation needed, all the additional items such as earthwork
support, disposal, backfilling, work below water level, and breaking out
required as a result of the excavation of working space are deemed to be
included in the with the item.
www.TechnicalBooksPdf.com
Deemed to be included items
The term ‘deemed to be included’ is used extensively in BESMM3 and
indicates that this particular work is covered in the billed item without the
need for specific mention. The estimator needs to be aware of these items
since he will have to include for them while building up the unit rates.
D20 Rule S1-S9 These are supplementary information that provide additional information to
the contractor and could be given in specifications but must be referenced in
the description of relevant items
Classification Rules
D20:1.1-2 Site preparation, removing trees and tree stumps
D20 Rule M2
Stumps, girth
D20 Rule M1
measured at top Ground level (gl)
Trees, girth measured
1.00m above gl
D20.1.3.4 Clearing site vegetation is defined in D20 Rule D1. A full description is required with
sufficient detail to allow identification of vegetation types. These items are measured
over area (i.e. in square metres)
D20.1.4.1 Turf is apiece of grass sod cut from the ground and preserved for future use. The
method of preserving should be given in the specification and referred to in the
description.
www.TechnicalBooksPdf.com
D20.2.1.1 excavating topsoil for preservation need not be given as a separate item except where
it is specified that topsoil is to be preserved.
Ground level
Topsoil depth
(if for preservation) (say 250mm)
If topsoil is not to be preserved then reduce level excavations commence at existing ground level (gl)
Ground level
Maximum depth
ranges of reduce
reduce levels n.e. 0.25m
excavating
Formation level
Formation level
www.TechnicalBooksPdf.com
D20.2.3 A basement is a useable area of a building below ground level. These are areas which
can be occupied areas, car parks and plant rooms.
n.e 0.25m
Maximum
depth stages
n.e.1.00m
n.e. 2.00m
Reduced level
n.e. 0.25m
n.e. 2.00m
n.e. 4.00m
www.TechnicalBooksPdf.com
D 20.2.8 Excavating “to bench sloping ground to receive filling” This is done in the face of
sloping ground to prevent slippage
D20.3 The rules under this clause cover items extra over any type of excavation irrespective
of depth.
The items under this rule are measured as extra over previously measured
excavations:
Excavating below
ground water
table level
The excavation is measured as if there was no water and then the bit excavated below water level is
then measured as extra over the excavation in which it occurs.
www.TechnicalBooksPdf.com
D20.3.4.1 Excavating next to existing services
Excavating next to existing services is measured in metres as extra over any types of
excavating stating the type of service, such as gas or water mains, electricity or
telephone cables or sewers.
Excavation
Gas service
pipe
Electricity
Cable duct
Excavation
Gas service
pipe crossing
excavation
www.TechnicalBooksPdf.com
EXERCISE
Go through all the Groundwork rules and identify the following:
1. All deemed to be included items
2. All extra over items
www.TechnicalBooksPdf.com
WEEK 14: BESMM3 RULES FOR EXCAVATION AND
WEEK 14 EARTHWORK II
The measurement is taken as the girth or length of the formwork, rendering, tanking
or protective wall, multiplied by the height measured from the commencing level of
excavation to the bottom of the formwork, etc.
Note: An area is measured not a volume as the estimator is left to make a judgement
as to the width required giving due regard to the nature of the work involved.
www.TechnicalBooksPdf.com
A
B
E
Less than 600mm
www.TechnicalBooksPdf.com
F
More than 600mm
Ground level
If the formwork is required to face B, the edge of the concrete foundation, then the
working space is measured to the full depth of the pit/trench. If no formwork is required
to face b then no working space allowance to excavation is measured.
www.TechnicalBooksPdf.com
D20.7 Earthwork Support
Earthwork support must be measured to the face of any excavation to be upheld
whether it will actually be required or not. This is to cover the contractor’s
responsibility to uphold the sides of excavations. It is left to the contractor’s discretion
to decide the extent and strength of support required or to use no support at all after
due consideration of the nature of the soil.
Earthwork support left in, curved, next to a roadway, below ground water level or to
unstable ground shall be described and measured separately.
The various classifications of depth and distance between faces are illustrated as follows:
A B
Maximum depth not exceeding 1.00m, distance between opposing faces not exceeding 2.00m
www.TechnicalBooksPdf.com
2. A is less than 1.00m and B is greater than 2.00m, but less than 4.00m
A B
Maximum depth not exceeding 1.00m, distance between opposing faces 2.00m – 4.00m
A B
Maximum depth not exceeding 1.00m, distance between opposing faces exceeding 4.00m
www.TechnicalBooksPdf.com
4. A is greater than 1.00m but less than 2.00m and B is less than 2.00m
A B
Maximum depth not exceeding 2.00m, distance between opposing faces not exceeding 2.00m
5. A is greater than 1.00m but less than 2.00m and B is greater than 2.00m but less than 4.00m
A B
Maximum depth not exceeding 2.00m, distance between opposing faces 2.00-4.00m
www.TechnicalBooksPdf.com
6. A is greater than 1.00m but less than 2.00m and B is greater than 4.00m
A B
Maximum depth not exceeding 2.00m, distance between opposing faces exceeding 4.00m
7. A is greater than 2.00m but less than 4.00m and B is less than 2.00m
A B
Maximum depth not exceeding 4.00m, distance between opposing faces not exceeding 2.00m
www.TechnicalBooksPdf.com
8. A is greater than 2.00m but less than 4.00m and B is greater than 2.00m but less than 4.00m
A B
Maximum depth not exceeding 4.00m, distance between opposing faces 2.00m – 4.00m
A B
Depth classification increases in stages of 2.00m thereafter, while for each class the distance between
opposing faces alternates between not exceeding 2.00m, 2.00m – 4.00m and exceeding 4.00m
www.TechnicalBooksPdf.com
CLASSROOM EXERCISE
1. A pit has been excavated for a reinforced concrete column base, 1000mm x 2500mm size on
plan. Column base will require formwork. Depth of excavation from ground level to
underside of column base is 1.85 metres:
(a) Sketch a section of the pit excavation
(b) Work out the allowance for working space
(c) Calculate the area for earthwork support and identify the classifications for maximum
depth and distance between opposing faces.
2. A foundation trench excavation has a mean length of 56.78m, width, 675mm and depth,
2.20m:
Calculate the area for earthwork support and identify the classifications for maximum depth
and distance between opposing faces.
www.TechnicalBooksPdf.com
WEEK 15: BESMM3 RULES FOR EXCAVATION AND
EARTHWORK III
Unless there are specific handling requirements in the specifications or for health
and safety regulations in connection with active material’ or ‘toxic/hazardous
material’ then the handling of the excavated material will be at the discretion of the
contractor.
Where materials are disposed of on site the information provided under the fourth
column should state specific requirements for the location of such deposits and the
average distance from the excavation in metres.
www.TechnicalBooksPdf.com
D20.9-11 Filling
Filling to excavations
Filling can be obtained from different sources, these should be referred to in the specification
particularly in respect of material obtained off site
Surface Treatments
D20.13.1 Applying herbicides is measured over the surface area of the excavation and `relates
to the use of chemicals to stop the growth of vegetation. Application of anti termite
treatment can as well be measured under this rule.
D20.13.2 Compacting
acting would include the former traditional description ‘level and ram’. This
includes the compacting of bottoms of excavations and compacting of filling and
subsequently levelling their surfaces in readiness to receive concrete. Compacting is
classified into:
Compacting ground
Compacting filling
www.TechnicalBooksPdf.com
D20.13.2.*.1 Where blinding is intended to fill the interstices in the filling material only and has no
specific thickness then it can be included with surface treatment
Specific blinding beds of a given thickness should be measured as ‘filling’ under item
D20.10.3
D20.13.3.1.1 Trimming sloping surfaces is only measured where the slope is greater than 150 from
horizontal. If trimming in rock, this should be stated in the description
D20.13.4 & 5 Trimming to produce fair or exposed face & preparing subsoil for topsoil
The specification should include the requirements and how to achieve these. This
should then be referred to in the descriptions.
www.TechnicalBooksPdf.com
CLASSROOM EXERCISE
Extract the quantities for excavation, filling and disposal in a few bills of quantities and cross check
that:
www.TechnicalBooksPdf.com