QUS 202 - Principles of Engineering Measurement
QUS 202 - Principles of Engineering Measurement
QUS 202 - Principles of Engineering Measurement
NATIONAL DIPLOMA IN
QUANTITY SURVEYING
PRINCIPLES OF ENGINEERING
MEASUREMENT
COURSE CODE: QUS202
YEAR 2- SE MESTER 2
THEORY/PRACTICAL
PRESENTED BY
TO
NATIONAL BOARD FOR TECHNICAL EDUCATION
(NBTE) / UNESCO
NASIRU JIBRIN
ABDULLHAKEM GARBA
VINCENT MARTINS (SNR)
DECEMBER 2008 .
2
QUS 202 PRINCIPLES OF ENGINEERING MEASUREMENT
TABLE OF CONTENT
4
WEEK 1: 1.0 INTRODUCTION TO MEASURMEN T OF ELECTRICAL
ENGINEERING SERVICES
Fig 1
Construction
Specification
5
The following represents a brief specification to indicate the general requirements for the
installation but in order to price work in the commercial world a fully detailed specification
would be prepared and issued with the Bill. Such a detailed document is beyond the scope of
this book but referenced to a hypothetical full specification are made in some of the items in
the worked example where this would happen in practice.
Enclosure Heavy gauged mild steel screwed conduit which acts as earth
continuity.
Cable PVC insulated single core cables drawn into conduit and clolour coded
as appropriate.
Consumer Unit Surface type metal clad with 60amp main swich and 6 ways ( 5 per
distribution sheet and one spare way).
Accessories Switches, ceiling roses and power outlets to be white plastic pattern.
Regulations The installations will comply with the latest IEE Regulations for
6
Lighting Power Water Heater Remarks
Location
Points Switches Lamps Circ. no 13amp 13amp Circ.no 15amp
Circuit Single Double Spur
Type Nr One wayTwo way Nr Watts SSO SSO
Fig. 2
General Background
The measurement of electrical services poses many of the same problems as the
measurement of mechanical services. In fact the two are often grouped together and referred
to as ‘m and e services’ as a collective term. It is unusual, however, for the work to be
carried out as separate contracts and to be designed by separate specialist engineers. It is quite
common for the surveying duties within a quantity surveying or consulting engineer’s
practice to be handled by separate specialist surveyors. There is a good deal of commonality
in the approach to bill preparation.
Measurement Procedures
The procedure for taking off electrical work is similar to that described for mechanical
services (chapter 8) and therefore has not been repeated. A sound, systematic and
logical approach with, possibly, the use of measurement schedules are the main
requirements.
Where circuits are to be measured in detail, such as circuits other than lighting and
small power, the route of the conduit and/or cable must be plotted on the plan or tracing
overlay and the number of cables indicated. This sketch will then form a record of what
is taken. An isometric sketch is often useful (as with pipework) to illustrate complex
7
runs. Conduit and/or cable runs should be plotted using a standard nomenclature to
illustrate high Level, low level, rise, fall and number of cables. A suggested notation
system is shown in the schedule overleaf.
When plotting conduit and cables it is usual to draw runs at right angles to each other
rather than running diagonally. This is usually necessary because of the nature of the
structure through which the conduits and cables are passing, as for example following
joists or beams. Conduits and cables can sometimes be laid diagonally where running in
floor screeds or in pitched roof spaces. Once the route has been plotted and the
specification fully understood, the measurement is, as with mechanical services,
relatively straightforward comprising basically enumerated items of equipment and
final circuits and linear items of conduit, cable trunking, cable tray and cable, on more
complex systems, all measured in accordance with the rules prescribed in SMM7.
Within the constraints of space in this book the worked example can only be an
introduction to the subject although it introduces as many variations as possible. The
main task facing the traditionally trained quantity surveyor is to develop his knowledge
of technology as the measurement techniques involved are comparatively simple.
Before going into the procedures of measurement, let us briefly identify the items often
contained in electrical installation in line with section 4 of the SMM which classified
electrical work as follows:-
8
Meter
This measure the extent of power used by the consumer on the basic of which NEPA
prepares the consumer bills.
Statutorily, no person other than NEPA official is allowed to temper with the above stated
items which are generally referred to as NEPA installations
The mains is a continuation of NEPA incoming upto and including a point where the first
distribution is made. Thus, in a small domestic installation with only consumer unit or
distribution board the mains is from the main switch upto and including the consumer unit or
distribution board.
But for large installation with medium voltage (M.V). Boards which supplies say six
distribution boards, the mains is from where the NEPA equipment stopped up to and include
the M.V board. The distance from the M.V board (excluding the M.V board) up to and
including the distribution boards are often referred to as submains. Hence for industrial or
large electrical installation the basic items often contained within the mains and submains
include:-
· Transformers
· Busbas trunking
9
Please note that trunking is better ise for horizontal movement of large cables and also
vertical movement where very limited number of cables is involved. The cable cable tray is
mainly used for vertical movement of cables where large number of power cables are
involved. The generator set, H.T panel and transformers usually require some solid support
details of which are worked out by the structural engineer. Generally, what constitutes mains
and submains depend to a large extent on the size and complexity of the electrical installation
More than not, clients, with particular reference to the private ones, do request for schedule of
materials to enable them procure most of the materials (if not all) at the onset of electrical
installation works to be executed by labour only contract. It will be absurd for a practicing
Quantity Surveyor to say such work does not fall within his field or duties as a Quantity
Surveyor. Hence, there is every need for the Quantity Surveyor to understand every bit of
electrical installation drawings so that he can pick the quantities with ease and certainty. It
may be necessary to state here, although briefly, that the routes of the conduit which is the
same for cable is often not shown. This usually makes the exercise more difficult, leaving the
taker off to use his experience. Hence if five engineers or Quantity Surveyors are given the
same set of drawings, it is rare for them to come up with exactly the same quantity for each
size of cable. The above not withstanding, there is a reasonable assumption that the routing
which could result in good measurement. The items involved in powers final subcircuit are as
follows:-
· Cables
· Socket
The routes of the conduit is determined by, the circuit. All power outlets i.e. socket
outlets having the same symbol number, belong to the same circuit and should be linked
together with a conduit.The number of cables in a circuit as shown in the schematic
drawing for the distribution board or consumer unit determines the number of cables to be
combined in a conduit pipe.
10
Socket outlets represent points where electrical appliances are plugged. The type and
make are usually specified. Note that socket outlets are usually 450mm average high
above the floor level.
The conduit and cable make up the final subcircuit for power installation In other words
power final suhcircuit covers the distance from the distribution board or consumer unit
(excluding the D/B or C. U.) up to the socket outlet point but excluding the socket. The
number of cables in circuit depends on the type of installation, whether surface or
conduit. If conduit, the type- metal or PVC. In surface wiring, the cables are usually 3
core cables with one core being live, the second being neutral while the third serves as
earth. The live; supplies current from the distribution board or consumer unit and it
contains current at all times when the power source is on. The neutral is the return path
fort the Current and it only contains current the circuit is on. The earth cable only conveys
current to earth when there any leakage within the circuit. Such current is conveyed to
earth to rninimise any damage that might be caused
If the installation is in conduit, then multi core cable is not used. Rather, single core
cables are used. Three number of single core cable is used if PVC conduit is used. But if
galvanized or any other metallic conduit is used, only two cables are used with the
conduit acting as earth continuity conductor. The type of circuit may also determine the
number of cables within a circuit. The circuit could be radial or ring mains. The radial
circuit, depending on the type of wiring earlier discussed starts from the distribution
board or consumer unit and serve all the socket outlet(s) within, the circuit, unlike the
radical circuit, it does not terminate at the last or socket outlet in the circuit but returns to
the distribution board or consumer unit there after. Ring circuit is commonly used for
socket outlets. It is pertinent to state here that radial or ring circuit is usually not
mentioned in the drawings but only Indicated in terms of the number of cables leaving the
distribution board or consumer unit.
11
Lighting installation. Lighting Installation include: Conduits
Cables Switches for Controlling the Lights Lighting Fittings
Like power final subcircuit, lighting final subcircuit covers the distance from
distribution board or consumer unit (excluding the D/B or C.S.) up to the lighting stint
but excluding the lighting fitting. The, number of Cables in a circuit also depends on
the type of installation and circuit. Unlike, the power final subcircuit, lighting final
subcircuit often contains two cables live and neutral. Earthing is usually restricted to
heavy lighting fitting such as chandelier lighting fittings, sun lighting fittings etc
Radial circuit is mostly used for lighting fitting and lighting points are connected by
looping-in many cable joints are only effected at in outlets or junction boxes, with
connectors and not inside the conduit or along the length of surface wiring. The number
of switches within a circuit depends on the function of the spaces to which the circuit is
connected. For instance if there are four switches within a circuit, it should, be noted
that the two cables from the distribution board or consumer unit will first stop at the
nearest lighting point within the circuit, the live will be dropped at the switch
controlling the light point(s) from where two cables will be taken up to the same
lighting point. One of the ‘two cables contains live from the D/board while the other
which is called “branch” is tapped from the former and it is controlled by the switch.
The latter is connected to all the lighting points that switch is to control while the
former (the continuous one) is taken to the next switch. The same thing is repeated until
the last switch which terminates the continuous line. The neutral does not come to the
switch, rather, it is looped from one lighting point to another without any break in
continuity.
Switches are described terms of rating the number of gangs and ways. The gang is the
nob with which the switch is switched off or on. Some switches contain one, two, three or
more gangs with each
gand controlling different light(s). The ways define the ‘on position(s) of the switch. If
light point(s) are controlled by a switch with just one “on’ position, such switch is
regarded as one way switch. But if a set of Lights are controlled by two switches each
with no fixed on position, such switches are called 2 way switches. If between the two
way switches there is a third switch which controls the same set of light points, such
12
switch is called intermediate switch. Lighting fittings are often described in line with their
support. For instance you have ceiling mounted fitting, wall mounted fitting, wall
brackets etc.
The pipes, duct work, boiler or heater more often than note are included under
mechanical or plumbing measurement.
Electrical Appliances
Electrical appliances include among others cooker units, dish washing machine, laundry
machine, etc.
Electrical Work Associated With Plumbing And Mechanical Engineering
Installations
This aspect of the work include the connection of the following to electrical installation:-
Cold Water Pumps
Hose Reel Pumps
Air Conditioner Condensing Unit,
Air Handling Unit
Connection to Heavy Machines e.t.c
13
Telephone Installations
The items under this section of work often include:
Conduit Coaxial Cables
Telephone Panels
Distribution Frames
Hand set and
Uninterrupted power supply (UPS) and Others.
The schematic for telephone usually shows the number of pairs of cables that serve each
of the telephone equipment. The cable is often distributed using conduit or trunking
sketing. The type specified should be carefully noted.
Clock Installation
The items involved include:
Conduit work if not surface
Wiring
Cables
Clocks
Uninterrupted Power Supply including charger.
The installation of the conduit and cable are similar to the ones stated earlier.
14
Thus, the cables and conduit invoved do not fall under the final subcircuits stated under
section S.21.2 of the NIQS SMM.
Fire alarm panel. The panel contains some zones which are similar to the number of ways
of the distribution board. The zoning system helps to indicate problems area within the
premises for easy control. For instance, in high rise buildings say 14 storey office block,
if there is fire in any of the floors, the moment the glass in that floor is broken, alarm is
raised in the building with the panel showing the floor where such was detected. Smoke
or heat detectors may also be incorporated into the alarm system. They trigger the
moment heat or smoke is sensed in any of the zones.
The drawing may only indicate the location of the equipment, break glass, alarm bell,
heat and smoke detectors but detailed description could be obtained from the
specification and in case there is one, request to that effect should be sent the service
engineer.
Earthing System
Installation
Earth (soil) offers least resistance to the flow of electricity. Each circuit within the
distribution board, medium voltage panel including other distribution equipments are
protected with circuit breaker. Each circuit breaker has a predetermined level of current it
can carry and any excess current breaks the fuse thereby breaking the circuit which means
stoppage of electricity flow. All the equipments are connected the earth cable or metal
conduit which in turn is connected to the earth through earth rod or directly as the case
may be. When there is any leakage, i.e. if the live wire is touching any undesired metal
within the circuit and it gets in touch with the earth cable or galvanizes conduit, the
15
current flows at a faster rate into the earth. The flow could be such as to cause the fuse to
break before much harm is done. Hence all electricity installations are always required to
to be earthed as a safety device. The period within which the whole process happens
could be few seconds or minutes. The items usually required include:
Earth rod
Test clamps
Conduit
Earth cables
Copper earth tape and other
Accessories
16
Procedure for the Measurement of Electrical Installation.
Like the main bills of quantities, the measurement of electrical installation could be base
on trade or function of thee installation. Under trade system, all the cables require for
installation are classified and grouped together. While under the function system similar
to the elemental system, the measurement is carried out under sub-headings previously
discussed. The advantage of the later is that the problem of cross checking under
measurement often complained about by the services contractor as well as in term
valuation are made easier in addition to others including material control on the part of
the contract or labour only contract. The advantage of trade system is that it make it
difficult for the client or any of his agents to discover any under or over measurement in
such items as conduit and cables as quantities from different sections are lumped
together. Hence the system is the most services engineers and in experienced quantity
surveyors.
Our discussions shall be based on the SMM, which prefers measurement under the
system similar to elemental system.
Sections S.I.
This deals with the basic information which prefers be provided and were previously
discussed.
Plant
Under section S.2. The services sub-contractor is expected to allow for bringing to site as
well as the removal from site the plant required for the work such as bending and dicing
machine, and others. In to make valuation easier, the bringing to site and removal from
site of all the plant required for the work could each be made an item. An item is also
required to be allowed for maintenance on site with plant required for the work.
17
Equipment and Controls
Under this sub-heading such items as generator set, H.T. panel. M.V. panel, transformer.
Distribution Boards, etc, could be measured. The distribution of equipment is usually not
difficult as it is based on the specification.
Where the specification for an item is too voluminous, a precise description of it
including reference to the specification or manufacturer catosole in the bill of quantities
could be adequate. The description M.V. panel and distribution boards should include the
incoming and the outgoings. Fig1 shows schematic drawing for a distribution board.
The incomer to the distribution board in fig1 is 60 A300MA trip ELCB while the
outgoing are:
4 No 10A TPEN MCB
3 No 15A TPEN MCB
3 No 20A TPEN MCB
2 No spares.
In addition, the description should include fixing of the D/Board to wall and the
nature of the wall (see section S.6.).
Having measured all the equipment including the distribution boards, the associated
cables area then measured.
You should note the drop of the cable from the source of supply as well as the rise at
the point of entering into the equipment or distribution board to which it is connected.
Ensure that an allowance of 0.6m is added for each point of entering or leaving the
equipment including distribution board (see section S.17.b). For external work requiring
cable joined to make up the distance, such joints are enumerated stating the type and size
of the cable including joint boxes, sealing boxes and the like required by the cable
jointers. (See section S.174).
The cable termination glands used to ensure earthing continuity of the armoured cable at
the point of entering the feeder pillar or busar chamber is numerated (see section S.17.6).
It is usually one per feeder pillar or busbar chamber. Please note that it is the wire in the
armored cable that is exposed and passed through the cable gland, which is fixed, to the
cable entry or exit point in the casing. The three conductors in the armored cable are each
connected to the bars in the feeder pillar or busbar chamber with the aid of line taps often
called cable lugs. The line taps or cable lugs are enumerated stating the type and size of
the cable including the shrouds. (Sections.17.5).
18
The conduit, Trunking and cable trays, like cable are measured in metres expects that
there is no allowance at each equipment point. For trunking and cable trays, the finding
such as extra over the trunking or cable trays in which they occur. Busbar trunking serves
as a substitute for cable risers and it is measured in metres in line with section S. 13. 1
with the fittings such as the tap off boxes, tray feeder units and the like enumerated as
extra over the busbar trunking in which they occur.
19
WEEK TWO:
Very often, all switches, socket out lets, Television outlets, T.V. outlet, water heater
outlets, cooker control unit e.t.c. Are grouped together under switches and sockets
and short coming of this system was explained earlier. Thus, for ease of
understanding, power installation should include all the sockets outlet and should
be measured in the following order:
Socket Outlets
Conduct
Cables
The socket conduit outlets are enumerated stating if single or twin. Single socket
outlet has provision for one adaptor at a time while twin has provision for two
adaptors.
As earlier mentioned, the conduit a cables from the distribution board or consumer
unit to the socket outlets constitute final sub circuit and are enumerated stating the
number of socket outlets points (section S.21.2e).
Thus, the description should include the type and size of conduit stating if
concealed or surface, conduit boxes, type and size of cable including connectors,
draw wire and other accessories.
20
But if cable required to be specially measured separately, the following steps should
be taken:
Stating from the distribution board, take the horizontal measurements upto and
including all including all socket outlets within the circuit.
Add the vertical measurement from the distribution board concrete slab often
between 2.4-2.6m. Add the heights of the socket outlets from the concrete slab.
A&B should give the net conduit required forte circuit, repeat same for all other
circuit.
For cables, the same procedure used for conduit is adapted. As shown in figure 1
the schematic for distribution board shows the connection to the different socket
outlets as well as the number of cables which is a reflection of the type of circuit.
For instance, figure 1 shows 3xc2.mm2PVC Cu cable for F1-F2 meaning three
number of single core 2.5mm2PVC copper cable. Thus, the measured distance the
circuit covers is multiplied by three in order to arrive at the total quantity of
2.5mm2 single cable required. Note that you have to add allowance f 3x0.60 for the
distribution board point and 3x0.30m for each socket outlet point.
The three with which all measurement are multiplied signifies that it is a ring
circuit. i.e. live and neural plus the live that returns back to the D/B from the last
socket outlets within the circuit. This again shows that there is no separate earthing
meaning the circuit itself is serving as earthing. i.e. it is galvanized conduit or the
like. If it were to be charged to PVC conduit, all measured lengths would have been
multiplied by four as against three or the former quantity is divided by 3 to arrive at
the quantity of earth cable.
Lightning Installation
The following order could be adopted;-
a) Lightning fittings
b) Switches
c) Conduit
d) Cables
21
The legend shows the type of lighting fittings details of which are given in the
specification. The description of the lightening fittings should be very detailed
including references to the catalogue of the manufacturer (s). Measurement of the
conduit work under power installation earlier discussed. The final sub circuits are to
be enumerated.
If otherwise is required as earlier discussed under power installation, the followings
should be noted.
The conduit to lighting point leaves the distribution to the ceiling from where it is
connected to all the lighting point within the circuit.
The conduit is dropped from one of the lighting points controlled by a switch to the
switch outlets.
Thus, the measurement of conduit work includes taking all the horizontal
measurements as well as the vertical one. The latter include the distance between
the distribution board and the suspended floor or ceiling and the drop to the
switches. Fig 1 shows 2xc 1.5mm2 PVC Cu cable meaning two number of single
core PVC copper cable in the circuit live and neutral cables. Thus, all
measurements including allowance are multiplied by two to arrive at the list switch
within a circuit, al horizontal and vertical measurement to switches should be
multiplied by three as against two.
The reason is that to the lighting point from where a cable (Live) is run to a switch,
two cables are returned from the switch, one controlled by the switch while the
other is not. The uncontrolled live with neutral is connected to a lighting point
controlled by another switch as earlier discussed while the controlled one with
neutral is connected to the various lighting point controlled by the switch. Be
reminded that the neutral cable only connects all the lighting points and does not
get to the switches.
Electrical Appliances
More often than no, the supply of electrical appliances as well as their installation is
excluded from the bill of quantities. But where such are required to be measured,
22
the description should be based absolutely on the specification including the
necessary preparations required for their installation.
The conduit and cables are measured in inches. The starters and the like are
enumerated stating the type and rating. For heavy machines, provision for flexible
conduit may be necessary as earlier discussed and like other conduits, the flexible
conduit is measured in meters. This may range from 0.50m to 1.50m per machine
depending on the type of the machine.
Telephone Installation
The aspect of telephone installation that is included in the bill of quantities for
electrical installation include the conduit work and telephone outlets. For high
rise building constructed for commercial purposes, the exact telephone
requirements of the potential tenants may not be known, thus by installation in
that regard should be flexible. Hence the size of cable and telephone equipment
are left at the description of the tenants. But where everything about telephone is
required, the items required are as previously discussed.
The conduit is measured in metre and not as part of the final subcircuits which is
required to be enumerated under section S.21.2. The description should be as
previously discussed under power and lighting installation. The cables are
measured metres stating the type and the number of pairs including if surface or
drawn in conduit (section S.17.2) complete with all accessories.
The telephone outlets, panel distribution frames, hand sets, UPS and other are
enumerated. Note that the description for each of the items must be based on the
specification including reference to the specification and or manufacturer in the
bill of quantities.
23
Clock Installation
The conduit and cable in the final subcircuit to clock installation are measured in
meters except where such is connected to a socket outlet. The clock including
other items required for the installation are enumerated. Again, the description
should be based on the specification and where non is available, request to that
effect should be communicated to the services engineer in charge.
Alarm System
The conduit work as well as the cables are measured in metres. All other items
including the equipment are enumerated. In the case of fire alarm system, the
description for alarm bell and a break glass should include the manufacturer.
Same goes for the fire alarm panel which number of zones must be stated.
Earthing System
Earthing cables and conduit including copper tapes are given in metres stating the
type and size as well as other accessories in the description (section S22.2). the
connection of copper tapes (conductor) to the equipment and earth rod including
junctions are enumerated separately stating the type and size of the conductor
(section S.22.2).
Test clamps, earth electrode (earth rod) are enumerated stating type and size
including method of connection where necessary. Radius bend and in the wide
dimensions of tape conductors are enumerated as extra over the conductor in
which they occur.
24
the air terminal and earth rod including junctions are enumerated. Radius bend
and bend in wide dimensions of tape conductors are enumerated separately as
extra over the conductor in which they occur. The air termination once again, is
located at the roof top.
Trunking, Ducting and Cable Trays Associated with more than one
Installation
All the trunking, ducting and cable trays associated with more than one
installation are measured in metres stating the type and size in the description.
The fittings such as tees, bends and the likes are enumerated as extra over the
trunking, ducting and cable trays in which they occur.
Preliminaries
This aspect of the write up was deliberately kept until this point otherwise, it
supposed to have been the first item in the bill of quantities. It was so term
because of the general nature of the items which come under it. The items to be
allowed by the contractor under preliminaries includes:
(a). Bring to site all plant requires for the work as earlier mentioned (section
R.2.1)
(b). Removal from site ditto
(c). Maintaining on site all plant required for this section of the work (section
R.2.2)
(d). Provision of working/shop drawing by the services subcontractor (this should
be an amendment to the SMM to reflect what prevails in our environment)
(e). Provision of performance bond
(f). Provision of all necessary insurance covers stipulated in the contract
conditions
(g). Preparation of “as installed drawings” (usually four sets) section S. 25.6
25
(h). Marking the position of holes, mortices, chases and the like in the structure
(section R.37.2.), this is similar to setting out which is carried cut by the main
contractor.
(i). Testing each aspect of installation as may be requested by the services
Engineers or Architects during construction and at practical completion stages
(section R 37. 5.) the preliminaries should from the first part of the bill of
quantities.
External Works
For small residential installation, external works comprises security lighting
fittings including the associated cables and conduit. For installations such as
electrical installation in an industrial or residential estate, external work may
include equipment such as H.T. panel, transformers, cables, etc. all external
work should be clearly defined (section S. 5.b).
Builder’s Work
It should be remembered that such work as the provision of scaffolding, storage
area, hoisting, lighting for the work etc are not given under builder’s work as
they are covered by attendance on the nominated subcontractor work in the
main bill of quantities for the project (section B9.2-4). Builder’s work
comprises the aspect of actual execution of electrical installation that concerns
the builder and such include:
(a). Excavation of trenches for large cables usually between power source
such as
plant/machine room located outside the building and the main
building. The
measurement is as stated under section S.27.1.
(b). Cables covers in trenches often called cable tiles are measured in
metres stating the type and size (Section S.27.2.)
26
(c). Inspection chambers may be located at a point along the running
length of
external cable, where the earth rods for earthing and lighting
prevention
systems are driven into the ground etc. the measurement is as stated in
(section S.27.3.)
(d). Equipment supports and or bedding are usually not given details
design until at the post contract stage when the necessary information
on weight and size could be supplied to the structural engineer by the
Services subcontractor. Plate work and supporting steel work are
measured in accordance with section S.6.6. Bedding and pointing
components are enumerated stating the size, composition and mix of
the bedding material. (section S.27.4)
(e). Pylons, poles, hut-posts, wall brackets, pole stays and the like are
enumerated separately stating the size, the method of fixing and the
nature of the structure. (section S.27.8)
(f). Any other work involving the cutting of the structure such as cutting
and printing ends of supports for equipment, fittings, trunking, tray and
the like are enumerated stating the size of the support and the nature of
the structure (section S.27.5)
(g). Allowance for cutting away and making good after the electrician on
new structures is enumerated as electrical points stating the type of
conduits or cable and whether concealed or exposed. Details of the
measurement is as indicated under section S.27.6.
i. Boring or excavating holes in ground for poles and stay are
enumerated stating the depth, the nature of filling and treatment of
surplus soil (section S.27.9)
ii. Excavating pits and forming concrete bases for pylons are measured in
line with section and F of the SMM (section S.27.10)
(h). Catenary cables are given in metres stating the type and size, Eye bolts,
shackles and straining screws are given in the description stating the
method of fixing.
Further explanation of the builder’s work stated above is not given much attention because
the S.M.M section in that regard seems simplified enough until otherwise is proved.
27
Protection
Protecting the work in this section should be given as an item (section
S.28.) Thus from the foregoing, a typical bill of quantities could be
summarized as follows:
·Preliminaries
·Equipment and Controls
·Power Installation
·Lighting
·Electrical heating installation (if any)
·Electrical appliances (if required)
·Telephone installation
·Clock installation (if any)
·Sound distribution installation (if required)
·Alarm system installation (if required)
·Earthing system installation (if required)
·Lighting prevention installation (if required)
Trunking, ducting cable trays associated with more than one installation.
Having discussed the basic information required for electrical installation, the various
classes of work therein as well as the procedure for measurement, our next topic shall
be measurement of plumbing installation in addition to responses to any request for
clarification emanating from this write up.
28
ITEM NO. DESCRIPTION UNIT QTY
100 watt nr 2
Store/toilet
150 watt nr 2
Shop
Accessories
5 amp single pole silent action white plastic plate
switches, include steel conduit box plugged and screwed
to masonry.
nr 2
One way
Store/toilet
nr 2
Two way
Shop
General LV power
29
Cables and conduits in final circuits
ACCESSORIES
nr 4
13 amp switched double socket outlets otherwise as
item 4/4 above
item 1
30
Water heater control switch double pole 15 amp rating
white plastic plate pattern embossed ‘WATER
HEATER’ with warning neon and outlet for flexible
cord, include, conduit box with earth connector as
described in item 4/4 above. item 6
Testing 7
Identification and sundries
N.B. items in this section of the bill refer to the whole of nr 1
the foregoing installation.
1
Additional bonding to extraneous metal in accordance
with the IEE regulations to be priced on a lump sum
basis to cover the bonding required for the plumbing item
and heating installations and the roller shutter to the
shop front.
31
Luminaire points
32
WEEK 3: 3.0 INTRODUCTION TO MEASURMENT OF PLUMBING
AND MECHANICAL SERVICES
Fig. 1
33
Fig.2
34
General Background
The measurement of mechanical services installations requires a detailed knowledge of
technology. The drawings from which the quantity surveyor must work are those that are
prepared by the consulting services engineer. Consulting engineers are required by their scale
of charges to prepare drawings and specifications ‘sufficient to obtain tenders’. The drawings
are schematic only, as it is trade practice for the contractor to prepare all necessary working
drawings and to include in his tender for a complete working installation. The exact routeing
of pipework and ductwork is often left to the craft operatives doing the work and the
contractor will have in mind such factors as the location of other services, restrictions on
space and the ease of maintenance of the completed work. In essence, the quantity surveyor
must put himself in the position of the operative and include in the bill of quantities all items
necessary for the complete installation. A good practical knowledge of the technology of
services installations is therefore essential.
Many quantity surveying practices employ engineers within their organizations either to give
advice to the taker off or to take off the quantities themselves. It is, however, generally
believed that the traditionally trained quantity surveyor can acquire the necessary additional
knowledge of technology by private study, attending courses, observing site installations and
taking measurements on site and is then competent to prepare accurate bills of quantities for
mechanical services.
Measurement Procedures
The first task in taking off, as with any other work section, is fully to study and understand
the drawings and specifications provided. A study of these documents will inevitably lead to
queries. These queries must first be scrutinised by the in-house engineer and/or the
appropriate partner to eliminate any obvious discrepancies and must then be submitted to the
consulting services engineer in the usual way. The query/answer procedure is essential for the
preparation of good bills. The consulting services engineer may not be very familiar with the
process and may regard the completion of the query sheets as an additional burden for which
he receives no payment. Skill, tact and diplomacy are needed to limit the number and
frequency of queries and to stress their benefits to the engineer, namely, that they help to
remove anomalies that could cause future problems on site.
The taker off will need to make sensible approximations on occasions, where the method of
working is left to the operative on site. Two examples of such approximations are firstly
35
whether to measure made bends or fittings and secondly what allowance to make for co-
ordination of services. In the first instance one approach in practice is to measure bends only
in the bill of quantities and to insert a suitable preamble to the effect that the contractor must
allow in his prices for the provision of made bends or fittings as required. Another option is
to state in the preambles the proportion of made bends to fittings for different classes of
pipework and that the contractor must allow in his prices for any additional fittings required.
The consulting services engineer should be consulted in the preparation of this schedule,
and/or be requested to give guidance on likely requirements.
Approach to Measurement
Having acquired adequate information and a full understanding of the scheme, taking off can
begin. Firstly, the drawings should be coloured up using a suitable colour code to illustrate
the various services to be measured. The drawings are mainly in the form of floor plans and it
is often helpful to draw a sketch of complicated sections of the work to he taken off in
isometric projection to illustrate the full extent of the work involved. These sketches provide
a valuable record of the work measured and are often useful for final account purposes.
A good workmanlike method of booking dimensions and striking through work on the
drawings is essential to make sure that nothing is missed. Since the work is of a repetitive
nature, a schedule approach is often favoured with the items listed across the top of a sheet of
abstract-sized paper and with location information given on the left-hand side. The use of
schedules however has the disadvantage that the dimensions are less easy to follow and read.
The traditional quantity surveying approach tends to produce reams of paper and to be time-
36
consuming. A sensible compromise used by some practices is to take off on traditional
dimensions paper with abbreviated descriptions and to use a cut and shuffle abstract system
which will cope effectively with the constant repetition of items.
A good library of reference information is absolutely essential. This will include textbooks on
technology, trade literature, relevant British Standards and Codes of Practice, the current
edition of the IHVE (Chartered Institute of Building Services) guide and the current edition
of the Heating and Ventilating Contractors’ Association’s Specification for Sheet Metal
Ductwork.
Work in plant rooms is identified separately because of the restricted working conditions
(SMM Y10120/30.M2). Everything necessary for jointing is deemed to be included (SMM
Y10/20/30.C1), and full requirements of materials shall be given as prescribed in SMM
Y10/20/30.S1—6. Thermal insulation to pipelines and ducting is measured in metres giving
the nominal size of the pipeline or ducting, while insulation to equipment is enumerated
giving the overall size or measured in m2 (SMM Y50.1.1, 3 & 4.1.0).
Section Y of SMM7 must be read in conjunction with the appropriate sections of the Code of
Procedure. The Code of Procedure gives examples of items which are not included in the
text of SMM7. For instance, Y1O/1 1:2.4 in the Code states that examples of pipe fittings
would include bends, springs, offsets, swan necks, Y-junctions, double Y-junctions, blank
flanges, puddle flanges, bushes, reducers, elbows, twin elbows, tees, crosses and unions. The
special significance of this item is that pipe fittings 65 mm diameter are grouped together
irrespective of type, sting the number of ends. With larger fittings the type is stated (5MM
Y10.2.3—4.2—6.1—2). In section Y10:8.1, the Code gives examples of pipework ancillaries
which include draw-off taps, stop valves, control valves, regulating valves, safety valves,
reducing valves, non-return valves, drain cocks, stop cocks, air cocks, mixing valves, steam
traps, strainers, gauges and thermometers, and automatic controls.
37
The worked example in this chapter provides a fully annotated take off covering the
measurement of services for a particular project, selected to give a good range of different
features. Care must be taken not to apply the descriptions and other data to another project,
without careful reference to the particular specification and engineering requirements of the
scheme in hand.
Work Sections
The rules for the measurement of mechanical services given in Work Group Y arc billed
under separate work sections as listed in Appendix B of SMM7. the requisite work sections
are as follows: R Disposal systems, which include sewage pumping and refuse chutes. S.
Piped supply systems, which include cold water, hot water, steam fire hose reels, dry risers,
wet risers and sprinklers. T Mechanical heating/cooling/refrigeration systems which includes
gas /oil fried boilers, coal fried boilers, heat pumps, solar collectors, warm air heating and
central refrigeration plant. U Ventilation/air conditioning systems, which include toilet and
kitchen extracts, smoke extract/smoke control and various form of air conditioning.
38
WEEK 4: 4.0
MECHANICAL/PLUMBING SERVICES
Pipework Generally
Pipes are classified under appropriate headings, such as hot water supply (S11 in Appendix B
of SMM7 and the Common Arrangement), and measured over all fittings and branches in
meters, stating the type, nominal size, method of jointing and type, spacing and method of
fixing supports and distinguishing between straight and curved pipes (SMM Y10.1.1.1.0 and
Y 10.MB). Pipes are deemed to include joints in their running lengths (SMM Y 10. CB), and
the provision of every thing necessary for jointing (SMM Y 10. C1), without the need for
specific mention. The type of background to which the pipe supports are fixed will be
classified in the categories listed in SMM General Rule 8.3
Details of the kind of kind and quality of materials used in the pipes, gauge and other relevant
particulars listed in SMM Y.10.S1-6, are likely to be included in preamble clause or a project
specification.
Made bends, special joints and connections and fittings such as Y-junctions, reducers,
elbows, tees and crosses, are all enumerated as items extra over the pipes in which they occur
(SMM Y 10.2.1-4). In the case of special joints, the type and method of jointing is to be
stated and they comprise joints which differ from those generally occurring in the running
length or are connections to pipes of a different profile or material, connections to existing
pipes of a different profile or material, connections to existing pipes or to equipment,
appliances or ends of flue pipes (SMM Y10. D2).
Pipe fittings ≤ 65mm diameter are classified according to the number of ends, while those of
larger diameter are described. The method of jointing is stated where different from the pipe
in which the fitting occurs.
Valves and pipes are classified as pipe work ancillaries and are enumerated stating the type,
nominal size method of jointing, type, number and method of fixing support and type of pipe
to be connected (SMM Y.11.8.1.1.0). Those located in ducts and trenches are each kept
separate and so described.
39
Cutting holes through the structure for pipes and making good surfaces are enumerated,
stating the nature and thickness of the structure and the shape of the hole, and classifying the
pipes as to size in accordance with SMM P 31.20.2.1-3.2 & 4; for example pipes ≤ 55mm
nominal size, 55 -110mm and > 110mm. the cutting of holes for pipes is best picked up when
the various lengths of pipe work are taken off, rather than leaving all the holes to be taken off
after the pipe work has been measured complete. By contrast, painting of pipes may often,
with advantage, be left to the end of the taking off.
Adequacy of Measurement
It is quite usually for parallel flow and return pipes to be shown by a single line on the
engineer schematic drawings and annotated F and R with a note of dissimilar sizes that often
occur. When measuring, adequate allowance must be made for bends, circumventing
obstructions, and even for cold feed vent and air release pipes, plant room drains and pump
by-passes, where not shown in the detail.
Equipment
When measuring mechanical equipments, such details as type, size and pattern, rated duty,
capacity, loading as appropriate and method of fixing are stated. Specification cross
references are often inserted from mechanical equipments as provided for in SMM Y 20/40
.1.1.1.0. How ever, the excessive use of cross references to the specification can be
inconvenient to the estimator and fuller descriptions in the bill may sometimes form the better
approach, although this runs contrary to the wider use of project specifications. Where
insufficient data are available, the work can be covered by PC or provisional sums or bill of
approximate quantities may be prepared.
Examples of equipment are listed in the code of procedure and include boilers, generators,
water treatment and pressurization plant, tanks, cylinders, calorifiers, pumps, compressors,
fans, filters, humidifiers, and refrigeration units.
Air Ductlines
Ducting is classified as to whether straight, curved stating radil or flexible, and giving the
type, shape, size, method of jointing and spacing and method of fixing supports, and
background, and is measured in meters as SMMY30.1.1.5.1.1. Like pipes, it is measured over
all fittings and branches (SMMY30.M3), and is deemed to include joints in running lengths
and stiffeners (SMMY30.C3).
40
Items measured extra over the ducting in which they occur include the following:
1. Lining ducting internally in meters, stating the type and thickness of lining material
and internal size, ducting (SMMY30.2.1.1.0).
2. Special joints and connections, as described in SMMy30.D2, enumerated, stating the
type, size, ducting size and method of jointing (SMMY30.2.2.1.1.);
3. Fittings, such as stop ends, bends, offsets, diminishing pieces, change of section
pieces and junction places access opening and covers and doors; and test holes and
covers are each enumerated, stating the type as SMM Y30.3-6.1.1.
Ancillaries to deducting, such as grelles, diffusers, dampers, shutters, cowls,
terminals, root ventilators, attenuators and anti-vermin screens, are enumerated giving the
information prescribed in SMM Y30.4.1.1.1.0,while breaking into existing ducting is
given as an item, stating the type, size and location of duct and purpose of breaking in
(SMM Y30.5.1.1.1-4).
Ducting sleeves are enumerated and classified and described as for pipes (SMM
Y30.71-2.1.1.2).
41
WORKED EXAMPLE
The worked example covers the element of low-pressure hot water heating and ventilation
system as illustrated on drawing 13 and described in the following extract from the
specification of the engineering works, which the student is advised to study carefully.
The drawing shows more work than it is actually measured in this example, but it is
considered that this provides a more realistic approach and will give the students practice in
identifying specific parts of the work. In like manner extracts from an convector and grille
schedules have been Inserted to illustrate their usual format even though one item is actually
taken from each to avoid considerable repetition of similar items.
42
ITEM NO DESCRIPTION UNIT QTY
TAKING-OFF IN PRESPECT OF A
SERVICE PLUMBING WORK; IN
ACCORDANCE WITH SMM7.
43
copper pipes in which they occur.
44
ITEM NO DESCRIPTION UNIT QTY
3/1
Cold water storage as tern comprising 275 litre nr. 1
actual capacity plastic cisform made and model
as specified complete with plastic lid, holed for
and provided with 13mm diameter brass
ballwalve with male tail, jam nuts and in se back
plate 350mm brass shank and 175mm plastic
standing waste overflow with plastic screwed
outlet, 28mm diameter brass make outlet bosses
with jam nuts support shelf by others.
45
WEEK 5: 5.0 INTRODUCTION TO CIVIL ENGINEERING WORKS
Worked examples :-
Excavation and Filling
Introduction
The worked example above covers the measurement of excavation and filling to
cerate a level playing field 72 x 36m within an area of slopping ground. The work
involves creating stopping sites banks to the excavations and the filling to suit the
contours, with the banks specified to be set to a slope of 1 in 2.5. Side bankings
compound with naturally sloping ground create a problem in accessing the
horizontal component of the banks. To make the task more straight forward, the
existing ground is assumed to slope evenly throughout.
The excavation is reduced to formation datum 150.00 with the whole of the level
area and the banks being top soiled 150mm deep, thus the level playing surface will
finish at datum 150:150
There is just sufficient fill material resulting from the excavation to complete the
filling work but there is an overall short fall of top soil requiring some importation.
Excavation of top soil is in cubic meters while filling to stated levels is in square
meters, making the reconciliation of the existing available volumes with the
required importation volumes slightly awkward. This problem is solved by
46
calculating the area of existing 150mm thick
topsoil excavated over the plan area of the new banks and deducing it from the item
for the area of top soiling the new sloping banks.
The method of working adopted here is to calculate the volumes of excavation and fill in the
main area (that is 72m x 36m) from calculated average depths and to follow with the volumes
of the banks. The average depths of excavation and fill are most convenient found by suitably
weighing the depth at each point on the grid of levels, according to the area that it affects.
Depths at the extreme corners of the area are multiplied by 1. Intermediate points on the
boundary are multiplied twice and all other intermediate points are multiplied by four. The
sum of the weighted depths is derived by the total number of weightings (number of squares
x 4) to give the average weighted depth for the whole area.
47
WEEK 6
1.258
49
128 worked Examples
50
150mm at the
end
rather than
adding it
to each
individual
depth.
Class E: Earthwork
1 Gen. Excavan.topsoil, max. Area of dig where filling
2 72.00 depth n.e. 0.25m required therefore excav.
36.00 E411.1 complete & rule A4 does not
0.15 (level area require further description.
1 72.00
2 11.10
0.15 (west slope
1 36.00
2 11.20
0.25 (north slope
1 72.00
2 12.10
0.15 (east slope
1 36.00
2 11.90
0.15 (south slope
51
2-5m comncg. Surf. U/s of (Rule A4)
top soil Paragraph 5.21.
52
WEEK 7: 7.0 TAKING OFF IN RESPECT OF MASS CONCRTETE
RETAINING WALL
Introduction
This worked example covers the measurement of a simple mass concrete retaining wall.
This example demonstrates the basic requirements of civil engineering standard method
of measurement 3, classes F and G and their application in a piece of construction
53
WEEK 8 Mass Concrete
Retaining Wall
For the purpose of this example a 30m length Note: the principle adopted
of wall has taken and the earthwork in this example would apply
dimensions have been omitted. equally wall to the
` measurement of reservoirs,
setting tanks bridge
abutments, etc, built in
concrete.
55
4.00 to Bs 882, min ct. content breadth and height.
3
180kg/m references can be made in
7/ 0.75 F263 the item description to
0.30 Sampling requirements as a
specification clause .
4.00 (piers pier are taken from both ends
of retaining wall.
Placg. of conc.
30.00 mass bases. Thickness: it is good practice to adopt
2.40 ex. 500 mm. The appropriate standard
0.90 F524 terminology (F52*).
56
1
MASS CONCRETE RETAINING WALL(Contd.)
has
9
to be carried out for a
given
av. thickness voume of concrete - this
500 300 affect the price and the
1.200 500 thickness is therefore
2l 1.700 21 800 classify in accordance
with
850` 400 the ranges in the third
ht. of wall ex. 500th. dvision of Class F: the
wall
4.000 has to be subdivided into
the
890 part not exceeding
500mm
3.110 thick and that exceeding
it.
30.00 Mass wall, thickness: Attached piers are
0.40 300-500 mm. included with the wall in
0.89 acordance with rule M3 of
57
Class F.
F543 Assumed that concrete in
7/ 0.75 wall foundation will e cast
0.30 against excavated surfaces.
0.89 (piers wrot formwork has been
Taken for the full height of
Mass wall thickness Ex the wall as it will probably
30.00 500mm be difficult to use sawn
0.85 formwork for the botton
3.11 Fwk. Fair finish section below ground
only
and it will avoid any
snags
30.00 G225 arising from variation in
the
0.85 finished ground level
3.11 Formwork shall be
deemed
0.75 to be to plane areas and to
58
Less piers 30.000
7/750 0.250
24.750
Fwk ro finish.
24.75 vert. G145
4.00
Measured as inserts in
Inserts accordance with G832.
17/ 1 100 mm clay ware land separate items are not
Drains, 1m lg, cast in on required for adapting
Rake, totally within conc. Formwork, as the inserts are
Vol. G832 not require to be grouted
Into performed openings
(rule M16 of Class G).
Note. If expansion Jointing
was required between the
various sections of wall, the
on-extruding expansion
jinting for the full cross
sectional are would be
59
measured in square metres
with the scrip of sealing
compound on the outer face
of the wall taken as a linear
item.
CLASS E: Earthwork
24.75 granular fill in coetaneous
0.60 pocket behind wall.
0.45 E618
60
WEEK 9: STUDY DRAWINGS AND TAKE OFF BILLING OF ESTATE
61
ESTATE ROAD
Item
Earth carriageway av. Depth of The excavation has been
excavation taken separately for
CSI CS2 carriageway, kerbs and
361.920 361.367 footways, because of
361.217 361.366 varying depths in each
add. 703 301 case. The measurement
rules are prescribed in class
Road thickness 225 225 E and the sequence adopted
928 526 is as follows:
928 1.Excavation for cuttings
for carriageway and
2 1.454 disposal
av. Depth of excavn. 727 2. Adjustment for kerbs
3. Excavation for cuttings
width for footways and
carriageway 5,000 disposal
4. excavation for cuttings
2/3/4 41.00 add kerbs 2/225 = 450 for banks and disposal
5.45 5,450 5. Adjustment for topsoil
6. Soiling and seeding
0.73 bellmouth depths banks and verges.
- 70 East side (fill ) The additional area of one
side of the bellmouth = 1 ¾
10.70 350 W. side x radius2 (area of square
2/ 10.70 2 280 with side equal to length of
radius less area of quadrant
0.37 add road 140 or ¼ circle of same radius).
thickness 225 Topsoil will be adjusted
later. Alternatively, the
30.30 365 whole area of topsoil to be
0.23 Excavation. For cuttings; coming. Surf. U/s stripped could be measured
of topsoil. E220 & (bell mouth) Disposal of at the outset. With
2/ 1/2/22/7 0.08
excavated. Mat E532 excavation for cuttings, it is
41,000 not necessary to state depth
ranges. Excavated materials
10.70 less rad. Kerb 10,700 is deemed to be other than
0.23 30,300 topsoil, rock or artificial
material, unless otherwise
0.08 Excavation. For foundations; max. Depth: ne described (rule D1). Fill is
0.25m; Coming. Surf. Road formation. & a separate item. The
additional excavation for
(kerbs E321.1 (bellmouth) Disposal of kerb foundation below
excavated. Mat. E532. road formation is kept
separate from excavation
for cuttings as it will be a
more expensive item,
possibly involving hand
excavation.
62
Item
Footways E. side W.side The fill required under
Av. Depth at CS1 60 900 footways and verge on the
east side will be made up of
Add thickness of path or verg 135 non-selected excavated
195 materials. The whole of the
av. Depth at CS2 – 250 (fill 700 less area of paths and verges is
normally stripped of topsoil,
thickness of path or verg 135 - 115 so that some excavation is
(fill – 21.600 = 800 required even in places
which will subsequently
add thickness of path or verge 939 E. receive fill.
side Excavation forkerbs and
backing has already been
CS1 195 taken with the carriage way
CS2 topsoil 150 and so needs deducting from
the overall width of path and
2345 verge. All excavated
172 materials for disposal is
30.30 taken as material other than
width path 1.500 topsoil, rock or other hard
3.38
verge 2.100 material in the first instance,
0.94 and the necessary adjustment
3.375 will be made later.
excavn. For cuttings; (W.side commg. The depth to surface of
30.00 paving extreme ends of apths
Surf. U/s of topsoil. E220 & (E.side are calculated thus:
3.38
diaposal of excvtd. Mat. E532 E. side w. side
0.17 Channel 360.770 362.170
footways at bellmouth E.side W.side Lev. Add depth of kerb + ½
CS2 -250 700 fall 137 137
On path 360.907
Extremity - 407 543 362.307
2-657 2 1.243
Ground lev. At centre of path
-328 622 (interpolated) less finished
add thickness of path of verge 360.500 362.850
Level 360.907 362.307
135 135 Depth - 407 (fill) .543
-193 (fill) 757
63
Item
12.60 Excavn. For cuttgs commg. Surf. U/s of The additional 40mm depth
topsoil E220 paths of bellmouth
of excavation over the areas
Disposal of excvtd. E 532 mat. (topsoil
5.20 on E. side) of the two crossings is not
Width of banks (inc. 150mm additnl.
0.76 large enough to justify
Excavn. For topsoil)
12.60 E.side W.side separate measurement.
CSI 150 2,.650
5.20 Similarly the extra
CS2 850 2.850
0.15 21.0 25.500 excavation for quadrants
av. Width 500 (fill) 2.750
over that required for kerbs
bellmouth
850 2.850 would be largely offset by
1.750 750
the smaller quantity of
2 2.600 23.600
1.300 (fill) 1.800 excavation required for the
height of banks E.side W.side
granite setts- a sense of
CS1 150 1.050
CS2 450 950 proportion must be
2.600 22.000
maintained .
300 1.000
bellmouth the build-up dimensions for
450 950 the bank excavation is
1.000 750 inserted in waste, to obtain
21.450 21.700 the average widths and
725 850 heights. The top soil
30.30
component will require
½/ 2.75 Excavn. For cuttgs; (w.side commg. Surf. subsequent adjustment.
U/s of topsoil E220 & (bellmouth w. side). Disposal of excavated
1.00
material is deemed to be
disposal off the site unless
otherwise stated in the item
10.00
Disposal of excavated. Mat. E532 description (rule D4).
½/ 1.80 Slopes of 1 in 2 to banks
hove been assumed. The
0.85
volume of bank excavation =
length x average width x
average depth.
64
Item
30.30 Filling to enhancements is
Fillg. Embankment; kept separate from general
½ 0.50
fill. The description must
Selected excvtd. Mat. Other than topsoil or
0.30 contain the appropriate third
(E. side rock) division classification.
E624 bellmouth E. side)
½/ 10.00
1.30
0.73
Adjustment of topsoil
excavation over area of
Ddt. Excavn. For cuttgs; Commg. Surf. u/s
41.00 carriageway, paths and
topsoil. (carrgway. & E220
verges. The depositing and
5.00
spreading of the of the
0.15 topsoil will be picked up in
subsequent verge and bank
slop items. The small surplus
2 3/14/ 10.70 Ddt. Disposal of excvtd. Mat. (bellmth quantity of topsoil can
E532 & (paths & verges) remain on the site and make
10.70
up surface irregularities.
0.15
65
Item
27.70 Two items arise in
Fillg. Thickness 150mm, excvtd topsoil; to connection with the banks:
2.85
1 soiling of slopes
surfs. Unclined at an < of 100 to 450 to the
2 grass seeding.
hor. E641.2 The filling item is measured
ion m2 as it is to a stated
10.00 depth or thickness; stating
& the appropriate inclination
1.90
category from rule A14. the
Landscapg., grass seedg. To surfs. Inclined
grass seeding on banks has a
at ann < ex. 100 to the hor. E830.2 separate classification that
of the verges, as it falls into
(E. side) ( bellmth. E. side)
27.70 the inclined category under
rule A18.
0.65
Rule C4 states that items for
Roads And Pavings landscaping shall be deemed
Base granular mat. DTP specfd.type 1, to include fertilizing,
10.00 trimming and preparation of
depth: 75mm. R113
surfaces. Thus neither
1.00
& trimming nor preparation is
measured where grass
seeding applies. However
41.00
any excavation or filling
5.00 which receives roads or
carriageway slab of (bellmth. DTP
paving requires preparation
2 3/14/
specifd.pavg.qual. conc., depth; 150mm to be given as rules M11 and
M23.
R414
10.70
Many details of road
10.70 construction can be obtained
from the department of
transport specification for
highway works, to which
reference can be made in the
item descriptions. The actual
thickness of slabs and
courses should be given
instead of the third division
depth ranges in accordance
with rule A1 of class R.
66
Item
41.00 The waterproof membrane is
Steel fabric reinft. To BS 4483, nom. likely to be of waterproof
2/3/14 5.00
paper or Impermeable
Mass 3-4 kg/m2; type A252. R443
plastic sheeting (250 or 500
& grade). Preparation of
excavated or filled surfaces
waterproof membrane below conc.
10.70 to receive permant works is
Pavement; waterproof paper ot BS 1521 measured under class E
10.70
(rules M11 and M23).
class BIF. R480
& Expansion joints are always
measured but construction
excavn.ancillaries, prepn.of
joints only when they are
excvtd.surfaces. E522 expressly required (rule
M7). No formwork is
measured (rule C1).
joints in conc.pavements
5/ 5.00
The length of kerb is
expansion jts. (transverse depth: 150mm;
10.80 adjusted in ‘waste’ for the
as jts. Detail J, drawing (bellmouth. crossings on both sides of
the road. The kerb section is
WE17. (do. Do. R524)
4.40 identified by reference to BS
7263. kerbs laid to a radius
2/ 5.00
exceeding 12m are included
kerbs, channels & edgings less
with those laid straight.
30.200
Details of concrete beds and
setts 2.500
2/ 27.10 backings to kerbs are
quads.2/300 3.100 included in the kerb
descriptions (rule C3).
27.100
precast conc. Kerb to BS 7263 pt. 12, fig.
1(do), st. or curved to rad.ex. 12m;
2/1/2/22/7/ 10.70
bedded and backed w. conc. Grade C10 as
detail X; Dwg We17. R611
67
Item
2.50 This item is not listed in
Granite setts class R and hence the figure
2/ 10.70
Granite sett edging (2 crossings.) 100 x 9 is used in the second
2/ division to represents a non-
100mm,st. or curved to rad.junctn. w
standard item.
5.00
ex12m; bedded(xtg.road on conc. grade
(do C10 as detail Y, R691 Dwg.We17.
68
Item
3.50
2/ 2.50 Excavn.ancillaries, prepn. Of
excvtd.surfs. E522
Footways
30.200
Each course constitutes a
less crossings. 2.500 separate item and the
27.700 particulars are obtained from
the department of transport
verges crossgs. specification of highways
Verg 2.100 works, with the thickness
given in each case.
Less kerb 125 Locational notes are given in
1.975 waste for identification
purposes. All preliminary
gran.base,DTP specfd.type 1., depth: calculations are also inserted
75mm. R713 to prevent errors and provide
the facility for checking.
2/ 27.70 &
1.50 Dense bit.macadam base course DTP
2/ 1.98 specfd. clause 906,depth: (bellmouth
1.50 50mm. R752
2/ 12.60 &
5.20 dense bit.macadam basecourse DTP
specfd. clause 912,depth: (bellmouth
10mm. R751 Precast concrete falg
description include the types
& f slab in BS 7263 and the
excavn. ancillaries, prepn. Of excvtd.surfs. thickness. Precast concrete
edging is measured and
E522 described in a similar manner
edgings to precast concrete kerbs.
Figure 1 (m) of BS 7263
precast conc.edging to BS 7263 PT.1,fig.1 shows three sets of
(m) 50 x 150mm; st. or curved to dimensions for the round top
rad.ex.12m, bedded & backed variety and so dimensions
2/ 27.70 w.conc.grade C10 as detail E.Dwg. WE17. have to be included in the
R651. description. First calculate
2/ 10.00
the average depth of the
surface water gully
connections.
69
Item
70
WEEK 10: TAKING OFF BILLING OF ESTAE ROAD CONTINUED
Item
30.30 Filling to enhancements is
Fillg. Embankment; kept separate from general
½ 0.50
fill. The description must
Selected excvtd. Mat. Other than topsoil or
0.30 contain the appropriate third
(E. side rock) division classification.
E624 bellmouth E. side)
½/ 10.00
1.30
0.73
Adjustment of topsoil
excavation over area of
Ddt. Excavn. For cuttgs; Commg. Surf. u/s
41.00 carriageway, paths and
topsoil. (carrgway. & E220
verges. The depositing and
5.00
spreading of the of the
0.15 topsoil will be picked up in
subsequent verge and bank
slop items. The small surplus
2 3/14/ 10.70 Ddt. Disposal of excvtd. Mat. (bellmth quantity of topsoil can
E532 & (paths & verges) remain on the site and make
10.70
up surface irregularities.
0.15
71
Item
27.70 Two items arise in
Fillg. Thickness 150mm, excvtd topsoil; to connection with the banks:
2.85
1 soiling of slopes
surfs. Unclined at an < of 100 to 450 to the
3 grass seeding.
hor. E641.2 The filling item is measured
ion m2 as it is to a stated
10.00 depth or thickness; stating
& the appropriate inclination
1.90
category from rule A14. the
Landscapg., grass seedg. To surfs. Inclined
grass seeding on banks has a
at ann < ex. 100 to the hor. E830.2 separate classification that
of the verges, as it falls into
(E. side) ( bellmth. E. side)
27.70 the inclined category under
rule A18.
0.65
Rule C4 states that items for
Roads And Pavings landscaping shall be deemed
Base granular mat. DTP specfd.type 1, to include fertilizing,
10.00 trimming and preparation of
depth: 75mm. R113
surfaces. Thus neither
1.00
& trimming nor preparation is
measured where grass
seeding applies. However
41.00
any excavation or filling
5.00 which receives roads or
carriageway slab of (bellmth. DTP
paving requires preparation
2 3/14/
specifd.pavg.qual. conc., depth; 150mm to be given as rules M11 and
M23.
R414
10.70
Many details of road
10.70 construction can be obtained
from the department of
transport specification for
highway works, to which
reference can be made in the
item descriptions. The actual
thickness of slabs and
courses should be given
instead of the third division
depth ranges in accordance
with rule A1 of class R.
72
Item
41.00 The waterproof membrane is
Steel fabric reinft. To BS 4483, nom. likely to be of waterproof
2/3/14 5.00
paper or Impermeable
Mass 3-4 kg/m2; type A252. R443
plastic sheeting (250 or 500
& grade). Preparation of
excavated or filled surfaces
waterproof membrane below conc.
10.70 to receive permant works is
Pavement; waterproof paper ot BS 1521 measured under class E
10.70
(rules M11 and M23).
class BIF. R480
& Expansion joints are always
measured but construction
excavn.ancillaries, prepn.of
joints only when they are
excvtd.surfaces. E522 expressly required (rule
M7). No formwork is
measured (rule C1).
joints in conc.pavements
5/ 5.00
The length of kerb is
expansion jts. (transverse depth: 150mm;
10.80 adjusted in ‘waste’ for the
as jts. Detail J, drawing (bellmouth. crossings on both sides of
the road. The kerb section is
WE17. (do. Do. R524)
4.40 identified by reference to BS
7263. kerbs laid to a radius
2/ 5.00
exceeding 12m are included
kerbs, channels & edgings less
with those laid straight.
30.200
Details of concrete beds and
setts 2.500
2/ 27.10 backings to kerbs are
quads.2/300 3.100 included in the kerb
descriptions (rule C3).
27.100
precast conc. Kerb to BS 7263 pt. 12, fig.
1(do), st. or curved to rad.ex. 12m;
2/1/2/22/7/ 10.70
bedded and backed w. conc. Grade C10 as
detail X; Dwg We17. R611
73
WEEK 11: TAKING OFF FOR ESTATE ROAD (CONTINUED)
Item
2.50 This item is not listed in
Granite setts class R and hence the figure
2/ 10.70
Granite sett edging (2 crossings.) 100 x 9 is used in the second
2/ division to represents a non-
100mm,st. or curved to rad.junctn. w
standard item.
5.00
ex12m; bedded(xtg.road on conc. grade
(do C10 as detail Y, R691 Dwg.We17.
74
Item
3.50
2/ 2.50 Excavn.ancillaries, prepn. Of
excvtd.surfs. E522
Footways
30.200
Each course constitutes a
less crossings. 2.500 separate item and the
27.700 particulars are obtained from
the department of transport
verges crossgs. specification of highways
Verg 2.100 works, with the thickness
given in each case.
Less kerb 125 Locational notes are given in
1.975 waste for identification
purposes. All preliminary
gran.base,DTP specfd.type 1., depth: calculations are also inserted
75mm. R713 to prevent errors and provide
the facility for checking.
2/ 27.70 &
1.50 Dense bit.macadam base course DTP
2/ 1.98 specfd. clause 906,depth: (bellmouth
1.50 50mm. R752
2/ 12.60 &
5.20 dense bit.macadam basecourse DTP
specfd. clause 912,depth: (bellmouth
10mm. R751 Precast concrete falg
description include the types
& f slab in BS 7263 and the
excavn. ancillaries, prepn. Of excvtd.surfs. thickness. Precast concrete
edging is measured and
E522 described in a similar manner
edgings to precast concrete kerbs.
Figure 1 (m) of BS 7263
precast conc.edging to BS 7263 PT.1,fig.1 shows three sets of
(m) 50 x 150mm; st. or curved to dimensions for the round top
rad.ex.12m, bedded & backed variety and so dimensions
2/ 27.70 w.conc.grade C10 as detail E.Dwg. WE17. have to be included in the
R651. description. First calculate
2/ 10.00
the average depth of the
surface water gully
connections.
75
Item
76
WEEK 13: TAKE OFF FOR PUMPING CHAMBER
79
MPING CHAMBER (CONTD)
Placg. Of conc.
Reinforced
It is deemed describe to
80
WEEK 14:
Placg. Of conc.
Reinforced
Conc. Accessories
2.80 Finishg. Of top surfs. Steel To obtain smooth finish
to
2.40 trowel. G812 concrete base.
3.60
0.30
Conc. Ancillaries Note build up of external
KWK. Ro. Fin girth of pumping station.
81
11.600 Alternatively, the
external
Add 4/300 1.200 dimensions of the
chamber
12.800 could be taken: 3.400
Less pt. 4.250 3.000
Above G.I 225
2/6.400
4.025 12.800
82
1.20 Ddt ditto. Formwork to underside of
1.20 G215 openings deducted as they
0.90 (cover exceed the large void areas
0.60 opgs. Prescribed in rule D3 of class G.
1.200 900
1.200 600
2/ 2.400 2/ 1.500
4.800 3.000
83
WEEK 15
Worked Examples
Conc. Accessories.
Inserts
84
(walls otherwise specified and
the normal allowance
for hooked
Ends is an addition of 12
4/ 3.30 Diam. 12mm (R3 times the diameter of the
bar
For each hooked end. The
7/ 2.90 (R4 total length of bar will be
Weighted up and billed in
4/ 1.40 (R5 tonnes. Separate items are
Not required for
supporting
Reinforcement (rule CI of
class G)
8/ 1.10
Bars exceeding 12m in
10 0.80 Length are given
separately (R7 in stages of 3m
(rule A7 of
5/ 0.60 (R8 clad G).
G514
(Cover slab
85
REFERENCES
Hampshire. London
86