QUS 210 - Tendering & Estimating II
QUS 210 - Tendering & Estimating II
QUS 210 - Tendering & Estimating II
NATIONAL DIPLOMA IN
QUANTITY SURVEYING
YEAR 2- SE MESTER 2
THEORY
WEEK 1:
1.0 PRICING OF PRELIMINARIES I
1.1 What are Preliminary Items?
1.2 Estimating for Typical Preliminary Items
WEEK 2:
2.0 PRICING OF PRELIMINARIES II
WEEK 3:
3.0 PRELIMINARIES ANALYSIS WORKSHOP
3.1 Preliminary Bill
3.2 Class Workshop
WEEK 4:
4.0 PREPARATION OF TENDER
4.1 Decision to Tender
4.2 Collection of Information
4.3 Enquiries and Quotations
4.4 Visit to Site
4.5 Visit to Consultants Offices
4.6 Receipt of quotations
4.7 Planning and Mid Tender Review
4.8 Preparation Of The Estimate
4.9 Final Review
4.10 Action after Submitting a Tender
4.10.1 Action with a successful tender
4.10.2 Action with an Unsuccessful Tender
4.11 Factors in Pricing General and Special Attendance on Subcontractors
2
Course: Tendering and Estimating II
Course Code: QUS 210
Contact Hours: 2hrs
Course Specification: Theoretical Content
General Objective for Week 1: Appreciate the Build-up for Preliminary
Items
WEEK 1: PRICING OF PRELIMINARIES I (1.0)
3
WEEK 2: PRICING OF PRELIMINARIES II
4
WEEK 3: PRELIMINARIES ANALYSIS WORKSHOP (3.0)
Procedures:
The work book will be made available to students at the beginning of the lecture. Time
will be allowed for students to read and comprehend the notes. Students will then be
5
GENERAL OBJECTIVE FOR WEEK 4:
Know the tendering procedures.
Reference: CIOB (1997) Code of Estimating Practice, 6th Edition. Ascot: CIOB
The preparation of a tender can be divided into six stages.
6
GENERAL OBJECTIVE FOR WEEK 5:
Know factors affecting tender figures.
“Construction cost” is a broad phrase or term and can be interpreted to mean cost of any
sort to anyone associated with construction work. It depends on the point of view let us
say you are a contractor, your costs are your expenditure on labour, materials and plant.
The client’s cost of land, consultant fees and so on.
The base cost of construction therefore comprises of expenditure on materials, labour and
plant, the quantities of materials, labour and plant required for a job are determined &
attaching prices to these defines the basic construction cost, but to these are also a variety
of factors that affect this basic cost: -
7
GENERAL OBJECTIVE FOR WEEK 6:
Unit Rate
Overheads Profit
8
WEEK 7: BUILD-UP HOURLY RATE FOR PLANT & EQUIPMENT (7.0)
You may use the Wessex Price Book, or other similar price book, for information on the
output/productivity of labour and plant. Materials and plant prices can be obtained from
builders' merchants and plant hire firms.
In practice estimators must always use productivity outputs analysed from site feedback
and the current cost o f other resourcs.
In the following unit rate calculations the hourly labour rates used are £9.50 for craft
operatives and £7.00 for labour operatives.
7.2 Groundworks
SAQ 2
Explain how the following factors may affect unit rates for groundworks?
• Type of excavation e.g. trenches, pits, basements
• Ground conditions e.g. clay, sand, soil, rock
• Depth of excavation
• Ground water
• Time of year when excavating
• Mechanical or hand excavation
• Distance and availability of tips
• Estimated bulking of materials
7.2.1 Hand Excavation
Excavation work is usually measured in cubic metres (m3)
9
WEEK 8: BUILD-UP UNIT RATE FOR SURFACE EXCAVATION (8.0)
Bulking
Sand 12.5%
Gravel 10%
Clay 133 1/3%
Rock 50%
Multiplier
Medium labour constant multiplier
Sand and gravel 0.75
Natural soil 1.00
Stiff clay 1.50
Soft rock 3.00
Hard rock 8.00
OUTPUT
Excavation 2.5m3 / labour /day
Spreading and leveling 4.5m3 / labour / day
Wheeling / haulage 8.0m3 / labour / day
Placing of concrete 4m3 / labour / day
10
WEEK 9: BUILD-UP UNIT RATE FOR CONCRETE WORK I (9.0)
TQ 7
Calculate the cost of mixing a m3 of Grade 15 concrete on site using the following
information ;
To produce 1m3 of mixed Grade 15 concrete requires ;
250Kg of cement at £80 per tonne
600Kg of sand at £10 per tonne
1200Kg of aggregate at £9 per tonne
Waste say 5%
Concrete mixer all-in rate £2-50 per hour, output 2m3 per hour
Labour rate £7.20 per hour
Labour out put 0.5m3 per hour
Ready-Mixed Concrete
11
WEEK 10: BUILD-UP UNIT RATE FOR CONCRETE WORK II
12
WEEK 11: BUILD UP UNIT RATES FOR REINFORCEMENT (11.0)
Fixing/tonne
Diameter 6 8 10 12 16 20 25 32 40 50
Hours 63 45 35 27.2 22.5 15 12.5 10 8 6
NOTE:
1. Assume 3hrs for unloading 1 tonne of reinforcement
2. Allow 5% waste for cutting form straight length
3. Allow 1% waste reinforcement already cut to shape
4. for bars in short length e.g links and stirrups, allow 33% for extra labour
Tying wire/tonne
Diameter 6 8 10 12 16 20 25 32 50
Hours 15 15 12 10 8 8 6 5 4
13
WEEK 12: BUILD-UP UNIT RATE FOR FORMWORK (12.0)
12.1 Formwork
formwork
2. The kind of finishes required i.e sawn faced or smooth finish, ground finish,
biscuit etc. This determine the types of materials to be used as formwork and
3. the height to be supported. This determine the height of props and types of
props.
experience.
In small contract it may be possible to reuse the same formwork twice depending
Materials
2 x 4 x 12 Length 120
14
WEEK 13: BUILD-UP UNIT RATE FOR ROOFING (13.0)
13.1 Roofing
Corrugated roofing sheet, operation output /gang / day
Aluminium of galvanized iron unloading + fixing 40m2
Fixing ridge cap 35m
Raking and cutting 30m
Straight cutting 30m
TASK I
0.7mmm thick corrugated aluminium long span roof covering fixed to timber purlins
(m.s) @900mm c/c with 50mm galvanized drive screw with felt and metal washer
including 100mm side laps (measured net) in m-square i.e (100mm2)
15
WEEK 14: BUILD UP UNIT RATE FOR MASONRY (14.0)
Task One
In the box below, finish the list of possible variables which could impact on the
eventual cost for masonry works.
4. Type of pointing
16
WEEK 15: PRACTICE QUESTIONS FOR TUTORIAL CLASS (15.0)
15.1 Questions
Q1. Calculate the difference in cost per metre (m) for laying 100mm diameter flexible
jointed clay drain pipes and the cost per metre (m) for laying 100 flexible jointed
uPVC drain pipes in runs not exceeding 5.00m
Labour:
Productivity rate: 0.20hrs / m for 100mm diameter flexible jointed clay drainage. And
0.14hrs/m for 100mm diameter flexible jointed PVCu drainage. All - in rate £8.01 per
hour plus £2.03 / hour enhancement for additional skill and responsibility.
Materials:
100mm diameter flexible jointed clay drain pipe cost £5.50 each and are 1.60m long.
100mm diameter flexible jointed PVC drain pipe costs £21.00 each and are 3.0m
long. Flexible joints cost £4.23 each assume one joint for every 1.4m for clay
drainage and one joint for every 2.0m of pipe for uPVC drainage.
Waste
Allow 10% waste on pipes and 5% waste on couplings
Q2. Calculate the unit rate / m2 for earthwork support in moderately firm earth not
exceeding 2.0m apart and a maximum of 2.0m deep. As illustrated in the sketch,
given:
Labour:
Productivity rate 1.28hrs / m2, Unloading timber 1.00hrs / m3. All - in rate £8.01 per
hour plus £2.03 / hour enhancement for additional skill and responsibility.
Materials:
Timber supply price is £325.00 / m3 therefore:
100 x 100 Costs £3.25 150 x 100 Costs £4.88
150 x 150 Costs £7.31 200 x 50 Costs £3.25
Additional Information
Allow 5% waste on materials and allow for all materials to be used Eight times
Q3. Calculate the gross rate per square metre (m2) for brick wall: half brick thick skim
of hollow walls built entirely of concrete common bricks in mortar (1:1:6) pointed with
bucket handle joint using directly employed labour given:
Labour:
2 + 1 gang – Bricklayers £11.53 per hour & Labourers £8.68 per hour
17