HT Panel Qap
HT Panel Qap
HT Panel Qap
15. The tests to be carried out following erection shall include but not be limited to
the following (List the tests that can be done at site to be separated):
a) Dielectric tests of main circuits.
b) Continuity tests of each joint on the bus bar system to confirm adequate low
impedance electrical continuity. These tests shall be performed with a low
tension, high current d.c. supply and the resistance of each bus bar joint shall
be measured with a micro ohm resistance meter.
c) Each protection relay shall be checked for its operation against the standard
curve by means of primary injection currents.
d) Each circuit breaker shall be operated to prove the full correct operation of all
features.
e) Tightness of bus bar joint screws (using torque wrench)
f) Relay coordination from MRS to end point, including setting of VCBs. Relays
shall be tested at site
g) High voltage test on panels
h) Insulation resistance test - Megger for 1 Min with 2.5 kV. (taking value for 10
sec & 60 sec)
i) Mechanical operation tests
j) Electrical operation test
k) Verification of CT ratio and polarity of CTs
l) Safety interlocks and protection against electric shock and short circuits
m) Operational & interlock test for open/close operations, tripping, interlocks &
anti-pumping.
n) All protection CTs in substations& MRS and incomer metering CTs of MRS&
substations shall be tested at site. Manufacturer‟s test certificates of all CTs
shall also be furnished