Project: Layyah Combined Cycle Power Plant: Sub Station: Equipment: Panel Type Bay Ref: Date
Project: Layyah Combined Cycle Power Plant: Sub Station: Equipment: Panel Type Bay Ref: Date
Project: Layyah Combined Cycle Power Plant: Sub Station: Equipment: Panel Type Bay Ref: Date
B
1
1
k
u
s
P
1
1 2
2
1 S
1 2 S S S
S S 12
12 12 12
12 12
B
CORE 1 2
C
MAKE ABB
T
TYPE TPU 40.23
0 RΦ 1VLT5120060688
4Sr.No. YΦ 1VLT5120060686
L BΦ 1VLT5120060695
1 Pri. 400 A 400 A
RATIO
Sec. 1A 1A
CLASS 5P20 0.2FS5
Vk (V) - ..
Io mA) ≤ 0.016 A ≤ 0.01 A
R ct (Ohms) ≤ 7.7 Ω ≤ 4.3 Ω
Burden (VA) 20 5
RΦ 1S1 – 1S2 2S1 – 2S2
CT TB
YΦ 1S1 – 1S2 2S1 – 2S2
No.
BΦ 1S1 – 1S2 2S1 – 2S2
FUNCTION PROTECTION METERING
P 2. GENERAL CHECKS.
2
DESCRIPTION R Phase Y Phase B Phase
VISUAL INSPECTION OK OK OK
NAME PLATE OK OK OK
TIGHTNESS CHECK AT CT SEC. TB – LV Compartment OK OK OK
Contractor:
B Sub Station: 6.6 kV GT MV SWITCHGEAR Manufacture:
C Equipment: CURRENT TRANSFORMER
T Panel Type 6.6 kV SWGR PANEL UNIGEAR ZS1
0 Bay Ref: 10BBA09-EDG LV TR.1
6 Date: 23/06/2021 Page 2 of 3
L
3 3. INSULATION RESISTANCE MEASUREMENT.
IR Values shall be measured up CT terminal blocks. (1min Value) Amb.Temp(t0C): 23.4 0C
Description DC V applied R Phase Y Phase B Phase
Primary to Earth 5000V 410.00 GΩ 457.00 GΩ 491.00 GΩ
Primary to Core-1 2500V 689.00 GΩ 1.32 TΩ 416.00 GΩ
Primary to Core-2 2500V 688.00 GΩ 805.00 GΩ 701.00 GΩ
Core-1 to Earth 500V 17.81 GΩ 15.34 GΩ 11.52 GΩ
Core-2 to Earth 500V 18.00 GΩ 15.56 GΩ 16.08 GΩ
Core-1 to Core-2 500V 29.08 GΩ 26.06 GΩ 29.01 SGΩ
4. POLARITY CHECKS.
PHASE R PHASE Y PHASE B PHASE
1S1-1S2
CT ANALYZER TEST REPORT ATTACHED
2S1-2S2
MAIN
TESTED BY WITNESSED BY APPROVED BY
CONTRACTOR
SIGNATURE
ALA
NAME: R.VENKATESH AHMED BASIONY
VENKATESWARLU
DATE: 23/06/2021 23/06/2021 23/06/2021
COMPANY ABB ELSEWEDY POWER ILF SEWA
Client Site Acceptance Test Report - Test Report Contractor:
Contract No: 5002
7. RATIO TEST:
R Phase Y Phase B Phase
1S1-1S2 400/1A
CT ANALYZER TEST REPORT ATTACHED
2S1-2S2 400/1A
Acceptance Criteria: Shall be compared with FAT results and Name plate data.
8. INSTRUMENTS DETAILS:
INSTRUMENT Make/Model Sr. No. Cal. Due Date
OMICRON/CT
CT Analyzer RH090Q 02/11/2021
ANALYZER
IR Tester MEGGER/MIT1025 102059599 02/04/2022
MAIN
TESTED BY WITNESSED BY APPROVED BY
CONTRACTOR
SIGNATURE
ALA
NAME: R.VENKATESH AHMED BASIONY
VENKATESWARLU
DATE: 23/06/2021 23/06/2021 23/06/2021
COMPANY ABB ELSEWEDY POWER ILF SEWA