OPEN Hole 3 Cement Plug Job Procedures. 9900-9150: Operation Sequence
OPEN Hole 3 Cement Plug Job Procedures. 9900-9150: Operation Sequence
OPEN Hole 3 Cement Plug Job Procedures. 9900-9150: Operation Sequence
9900-9150
Operation Sequence:
1. SPOT W/ 21 BBLS HI-VIS-PILL @10200 FT & DISPLACE SAME BY 164 BBL
- POOH W/ 3 1/2'' D/P CMT STINGER T/ 9900 FT ( STD N 90) .
- Connect - SLBCement Surface Lines with T-Valve.
- PJSM, Flush line W/ 5 BBL Water, P/T same to 3000 psi.
2. Start Cement Plug Job.
Pumped 38.5 BBl's Mud Push as Spacer ahead.
Pumped 54 BBl's 15.8 PPG Cement Slurry.
Pumped11 BBl's Mud Push as Spacer Behind.
Displace with Mud by Cement Unit 130 BBL's - Under displace 13 BBL's.
3. Close Low Torque Valve then Break out Connection & Check for Swab Effect.
4. POOH ( 15 STD ) , NORMAL CIRC , THEN POOH TO SURFACE ,
Mud Engineer, Derrick man:
1. Total Pump 103 BBL’s Mud Push + Slurry.
2. OBM for Displacement: 130 BBL’s (Need Separate Tank).
3. Calculate Losses While Cement JOB.
4. If Spacer & Cement appear on Shale Shakers, Dump to Water Waste Pit through
Dump Line.
- Check Weight of Cement slurry (15.8 ppg) & Mud Push II (12 ppg)
- Check Take 2 Samples For Each Slurry & Write on Same.
- One Man on Shale Shaker all the Time to Check Return & Contact with SLB
Operator on Unit.