SOP For CCM Operation
SOP For CCM Operation
SOP For CCM Operation
Location:
Pre-requisites:
Safety Requirements: 1. only trained person must carry out checks.
2. Usage of necessary PPEs.
3. Usage of standard tools
Checks to be carried out before casting
1. Check for the presence of oxygen cylinders. One trolley containing 50 numbers of
cylinder must be present at CCM area. Pressure of cylinder should be 120kg/cm2. Spare
trolleys two numbers must be present at the site .In case same is not there, report it to
oxygen department for the replacement of trolleys.
2. Check for the presence of LPG cylinder .Five numbers of cylinder must be present.
3. Check for the presence of cutting torch. Operator will light and check whether torch is
operational or not.
4. Check for the working of oxygen regulator .Pressure of same should be 2.5-3 kg/cm2.
5. Shift in charge /engineer of CCM will check availability of CI cone plug 30 X 60 .Minimum
10 numbers of CI cone must be present.
6. Check for the availability of copper cone plug, 2-4 numbers must be at site.
7. Check for the availability of rapeseed oil in the tank.200 litrs of oil must be present.
Standard rod to be kept for measuring level.
8. Check for the availability of casting powder - 10 bags must be present at site.
9. Check for the availability of slag bari of 8 mm.
10.Check for the availability of chillers - 5 kgs minimum must be present at site.
Approved By:
G S Bansal Sr VP
Issued By:
G S Bansal Sr VP
Issued By:
G S Bansal Sr VP
When level is more than half teamer man tells shift in charge to open tundish nozzle. SIC
tells mould operator to open tundish nozzle. Mould operator opens all nozzle sequentially.
Fitter notices speed meter of casting in case it shows some reading he starts secondary
cooling water.
Mould operator then control casting speed using knob.
Mould operator maintains distance of 150 mm of liquid metal from the top and
accordingly he maintains speed.
Once dummy bar is cut mould operator maintains the speed and removes slag by using
slag bari.
Then gas cutter will cut head of billet to make it free from dummy bar. When billet
reaches 4 meter or 6 meter gas cutter cuts the piece and then SBO pushed same to
cooling bed from where billet is lifted using crane.
Mould Tube replacement after Campaign
CCM 01 Mould tube to be replaced after 450 heats.
CCM 02 Mould tube to be replaced after 600 heats.
Replaced mould shall be checked against standard parameter. In case it is
within permissible limits it will be reused else it will be discarded
Approved By:
G S Bansal Sr VP
Issued By:
G S Bansal Sr VP