This document outlines a master project schedule to rectify a 1000mm underground chilled water pipe leak at Kuala Lumpur International Airport. The project will involve engineering, procurement, construction, re-instatement works, monitoring, and handover over an 82 day period from August 5th to November 26th. Key tasks include applying for work permits, site preparation, open cut excavation, welding repairs, backfilling, repairing damage to the site, and monitoring the pipe and road settlement after completion.
This document outlines a master project schedule to rectify a 1000mm underground chilled water pipe leak at Kuala Lumpur International Airport. The project will involve engineering, procurement, construction, re-instatement works, monitoring, and handover over an 82 day period from August 5th to November 26th. Key tasks include applying for work permits, site preparation, open cut excavation, welding repairs, backfilling, repairing damage to the site, and monitoring the pipe and road settlement after completion.
This document outlines a master project schedule to rectify a 1000mm underground chilled water pipe leak at Kuala Lumpur International Airport. The project will involve engineering, procurement, construction, re-instatement works, monitoring, and handover over an 82 day period from August 5th to November 26th. Key tasks include applying for work permits, site preparation, open cut excavation, welding repairs, backfilling, repairing damage to the site, and monitoring the pipe and road settlement after completion.
This document outlines a master project schedule to rectify a 1000mm underground chilled water pipe leak at Kuala Lumpur International Airport. The project will involve engineering, procurement, construction, re-instatement works, monitoring, and handover over an 82 day period from August 5th to November 26th. Key tasks include applying for work permits, site preparation, open cut excavation, welding repairs, backfilling, repairing damage to the site, and monitoring the pipe and road settlement after completion.
TO PROVIDE ALL NECESSARY MANPOWER, EXPERTISE, TOOLS, EQUIPMENT, MATERIALS AND CONSUMABLE TO RECTIFY 1000MM UNDERGROUND CHILLED WATER
PIPE LEAKED AT JALAN CP9,
KUALA LUMPUR INTERNATIONAL AIRPORT MASTER PROJECT SCHEDULE
ID Task Name Duration Start Finish P
1 August 1 September 1 October 1 November
25/7 8/8 22/8 5/9 19/9 3/10 17/10 31/10 14/11 28/11 1 PROJECT DURATION 82 days Thu 5/8/21 Fri 26/11/21 2 Contract Award 1 day Thu 5/8/21 Thu 5/8/21 3 Contract Duration 81 days Fri 6/8/21 Fri 26/11/21 2 4 ENGINEERING 25 days Fri 6/8/21 Thu 9/9/21 5 Kick Off Meeting 1 day Fri 6/8/21 Fri 6/8/21 2 6 Insurane - CAR/WCR 8 days Fri 6/8/21 Tue 17/8/21 2 7 Apply Work Permit To MAB KLIA 14 days Mon 23/8/21 Thu 9/9/21 2 8 Notification Letter to Utilities 7 days Mon 9/8/21 Tue 17/8/21 5 9 Site Visit - Utilities 7 days Wed 18/8/21 Thu 26/8/21 8 10 Prepare Traffic Management Plan 3 days Wed 18/8/21 Fri 20/8/21 6 11 Prepare RNP drawing 3 days Fri 6/8/21 Tue 10/8/21 2 12 PROCUREMENT 8 days Mon 9/8/21 Wed 18/8/21 13 Bending Plate 8 days Mon 9/8/21 Wed 18/8/21 5 14 CONSTRUCTION 15 days Fri 10/9/21 Thu 30/9/21 8 15 Site Preparation 1 day Fri 10/9/21 Fri 10/9/21 7 16 Open Cut/Crossing 14 days Mon 13/9/21 Thu 30/9/21 17 Trial Excavation 3 days Mon 13/9/21 Wed 15/9/21 1 18 Preparation Of pit 3 days Thu 16/9/21 Mon 20/9/21 1 19 Welding Works- Pacthing 2 days Tue 21/9/21 Wed 22/9/21 1 20 NDT 1 day Mon 20/9/21 Tue 21/9/21 1 21 Check Leak weldment & 2 days Thu 23/9/21 Fri 24/9/21 1 Surrounding area
22 Backfilling 4 days Mon 27/9/21 Thu 30/9/21 2
23 Re-instatement Works 14 days Fri 1/10/21 Wed 20/10/21 24 Repair damage of site walk 10 days Fri 1/10/21 Thu 14/10/21 2 25 Premix Works 4 days Fri 15/10/21 Wed 20/10/21 2 26 Monitoring Condition Site 20 days Thu 21/10/21 Wed 17/11/21 27 Pipe leak 20 days Thu 21/10/21 Wed 17/11/21 2 28 Road Settelment 20 days Thu 21/10/21 Wed 17/11/21 2 29 Hand Over Project 2 days Thu 18/11/21 Fri 19/11/21 30 Site Visit With MSB 1 day Thu 18/11/21 Thu 18/11/21 2 31 Site Visit With MAB 1 day Fri 19/11/21 Fri 19/11/21 3