Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

New Program Henties Bay

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Name Duration Start Finish Predecessors June July August September October November December

M E B M E B M E B M E B M E B M E B M E B
1 CONSTRUCTION OF SERVICES (ELECTRICAL RETICULATION AND STREET LIGHTING ) IN OMDEL 180 days Mon 5/31/21 Fri 11/26/21
EXTENSION 7

2 Material procurement 163 days Mon 5/31/21 Tue 11/9/21

3 Setting out and survey 3 days Mon 5/31/21 Wed 6/2/21 2SS

4 Main Substation 23 days Mon 10/18/21 Tue 11/9/21

5 Installation of Switch gear in substation 15 days Mon 10/18/21 Mon 11/1/21 2SS+140 days

6 Testing and Commisioning of Substation 7 days Tue 11/2/21 Mon 11/8/21 5

7 Connection of Power to Substation from overhead line 1 day Tue 11/9/21 Tue 11/9/21 6

8 Electrical Reticulation 78 days Wed 6/30/21 Wed 9/15/21

9 Excavations 20 days Wed 6/30/21 Mon 7/19/21 15

10 Bedding 5 days Tue 7/20/21 Sat 7/24/21 9

11 Laying of cables 20 days Sun 7/25/21 Fri 8/13/21 10

12 Back filling of cable trenches 30 days Sat 8/14/21 Sun 9/12/21 11

13 Installation of cable Marker Blocks 3 days Mon 9/13/21 Wed 9/15/21 12

14 Kiosks 75 days Thu 6/10/21 Mon 8/23/21

15 Wiring of kiosks 20 days Thu 6/10/21 Tue 6/29/21 3FS+7 days

16 Installation of Kiosks 7 days Sat 8/14/21 Fri 8/20/21 11

17 Termination and commisioning of Kiosks 3 days Sat 8/21/21 Mon 8/23/21 16

18 Street lighting 27 days Sat 8/14/21 Thu 9/9/21

19 Excavations 10 days Sat 8/14/21 Mon 8/23/21 16SS

20 planting 7 days Tue 8/24/21 Mon 8/30/21 19

21 Termination and commisioning 3 days Tue 8/31/21 Thu 9/2/21 20

22 As-built drawings 7 days Fri 9/3/21 Thu 9/9/21 21

23 PROJECT COMPLETION 17 days Wed 11/10/21 Fri 11/26/21 18,14,8,4,2

24 Inspection of works 1 day Wed 11/10/21 Wed 11/10/21

25 Snagging 7 days Thu 11/11/21 Wed 11/17/21 24

26 Cleaning of site occupied by contractor 5 days Thu 11/18/21 Mon 11/22/21 25

27 Demobilisation 3 days Tue 11/23/21 Thu 11/25/21 26

28 Site Hand-over 1 day Fri 11/26/21 Fri 11/26/21 27

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: new program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 5/25/21
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1

You might also like