Jadwal Proyek Ms Project

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022

Mode Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Jembatan darurat 28 days Mon Sun 5/9/21
BH 122 4/12/21
2 Jembatan darurat 28 days Mon Sun 6/20/21 1FS+14 days
BH 122 5/24/21
3 Bore pile diameter 63 days Mon 6/7/21 Sun 8/8/21 2FS-14 days
100 cm
4 Pengadaan Mini 49 days Mon Sun 7/18/21 3SS-7 days
Pile Squere 25 x 25 5/31/21
5 Pemancangan Mini 77 days Mon 7/5/21 Sun 9/19/21 4FS-14 days
Pile Squere 25 x 25
6 Kupas Kepala Mini 56 days Mon 8/2/21 Sun 9/26/21 5FS-49 days
Pile
7 Memancang SSP 49 days Mon 8/2/21 Sun 9/19/21 6SS
untuk Shoring
Penahan Tanah
8 Pemasangan 42 days Mon Sun 7FS+21 days
H-Beam untuk 10/11/21 11/21/21
Bracing Keliling
Shoring
9 Memotong / bobok 14 days Mon 9/6/21 Sun 9/19/21 10SS+28 days
borepile diameter
100 cm
10 Urugan pasir 49 days Mon 8/9/21 Sun 9/26/21 7SS+7 days
11 Pembesian u-32 168 days Mon 7/12/21Sun 12/26/2110SS-28 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 4/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
Mode Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
12 Bekesting Pondasi 49 days Mon 8/16/21Sun 10/3/21 11SS+35 days
13 Lantai kerja beton 49 days Mon Sun 10/3/21 12SS
k-175 8/16/21
14 Pembesian BJTD 84 days Mon Sun 12/5/21 13SS+7 days
40 8/23/21

15 Bekesting Dinding, 77 days Mon 9/6/21 Sun 14SS+14 days


Wingwall dan 11/21/21
Parapet

16 Beton K 300 147 days Mon 9/6/21 Sun 1/30/22 15SS

17 Bekesting Lantai 84 days Mon Sun 16SS+28 days


10/4/21 12/26/21

18 Beton K 350 28 days Mon Sun 2/6/22 17FS+14 days


1/10/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 4/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
Mode Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
19 Drainase 28 days Mon Sun 1/16/22 17SS
Suling-Suling Pipa 11/29/21
Galvanis 2"

20 Mencabut SSP 42 days Mon Sun 17SS+42 days


untuk Shoring 11/15/21 12/26/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 4/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3