LINXON EXPANSION OF LAYLA BSP (NG) NATIONAL GRID

ID Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 339 days? Mon 9/12/22 Wed 10/11/23
EXPANSION OF LAYLA BSP
2 50 days Mon 9/12/22 Tue 11/8/22
PRELIMINARY CONSTRUCTION
3 Mobilization 26 days Mon 9/12/22 Tue 10/11/22
4 Site Clearing 7 days Tue 11/1/22 Tue 11/8/22 If we received AFC drawing (Assume start Date: 01.11.2022). Note: This schedule base on Tender drawing after Receiving of AFC Drawing the schedule will be revise.
5 If we received AFC drawing (Assume start Date: 01.11.2022). Note: This  1 day Tue 11/1/22 Tue 11/1/22
schedule base on Tender drawing after Receiving of AFC Drawing the schedule
will be revise.
6 92 days? Wed 11/2/22 Thu 2/16/23
Construction of Extention Substation Area
7 92 days Wed 11/2/22 Thu 2/16/23
CABLE TUNNEL
8 Survey & Layout 1 day Wed 11/2/22 Wed 11/2/22
9 Excavation 5 days Thu 11/3/22 Tue 11/8/22
10 Compaction & Earthing 4 days Wed 11/9/22 Sun 11/13/22
11 Lean Concrete & Water Proofing & Screed 7 days Mon 11/14/22Mon 11/21/22
12 Formworks & Reinforcement of Foundations 15 days Tue 11/22/22 Thu 12/8/22
13 Pouring of Concrete Foundation 1 day Sat 12/10/22 Sat 12/10/22
14 Formworks & Reinforcement of Wall First Portion 13 days Sun 12/11/22 Sun 12/25/22
15 Pouring of Concrete in Wall 1st Portion 1 day Mon 12/26/22Mon 12/26/22
16 Formworks & Reinforcement 2nd Portion wall 13 days Tue 12/27/22 Tue 1/10/23
17 Pouring of Concrte 2nd Portion 1 day Wed 1/11/23 Wed 1/11/23
18 Formworks & Reinformcement of Roof Slab 10 days Thu 1/12/23 Mon 1/23/23
19 Pouring Concrete of Roof Slab 1 day Tue 1/24/23 Tue 1/24/23
20 Waterproofing, Backfilling & Compaction 10 days Wed 1/25/23 Sun 2/5/23
21 Finishing/painting of Floor & Wall 10 days Mon 2/6/23 Thu 2/16/23
22 Ready for Erection 0 days Thu 2/16/23 Thu 2/16/23 2/16
23 49 days Wed 11/2/22 Wed 12/28/22
OUT DOOR FOUNDATION
24 Reactor Foundations & Pedestal 49 days Wed 11/2/22 Wed 12/28/22
25 Survey & Layout 1 day Wed 11/2/22 Wed 11/2/22
26 Excavation 5 days Thu 11/3/22 Tue 11/8/22
27 Compaction & Earthing 1 day Wed 11/9/22 Wed 11/9/22
28 Lean Concrete  1 day Thu 11/10/22 Thu 11/10/22
29 Form Works & Reinforcement 14 days Sat 11/12/22 Sun 11/27/22
30 Pouring of Concrete Foundation 1 day Mon 11/28/22Mon 11/28/22
31 Formworks & Reinforcement of Pedestal 10 days Tue 11/29/22 Sat 12/10/22
32 Intsallation of Anchor Bolts 3 days Sun 12/11/22 Tue 12/13/22
33 Pouring of Pedestal 1 day Wed 12/14/22Wed 12/14/22
34 Finishing  5 days Thu 12/15/22 Tue 12/20/22
35 Backfilling & Compaction 7 days Wed 12/21/22Wed 12/28/22
36 Ready for Erection 0 days Wed 12/28/22Wed 12/28/22 12/28
37 32 days Thu 12/29/22 Sat 2/4/23
DUCT BANK
38 Survey & Layout 1 day Thu 12/29/22 Thu 12/29/22
39 Excavation 3 days Sat 12/31/22 Mon 1/2/23
40 Compaction & Earthing 1 day Tue 1/3/23 Tue 1/3/23
41 Lean Concrete & Water Proofing & Screed 4 days Wed 1/4/23 Sun 1/8/23
42 Installation of PVC Pipe 5 days Mon 1/9/23 Sat 1/14/23
43 Form Works & Reinforcement 10 days Sun 1/15/23 Wed 1/25/23
44 Pouring of Concrete 1 day Thu 1/26/23 Thu 1/26/23
45 Backfilling & Compaction 7 days Sat 1/28/23 Sat 2/4/23
46 Ready for Erection 0 days Sat 2/4/23 Sat 2/4/23 2/4
47 18 days? Tue 12/27/22 Mon 1/16/23
CABLE TUNNEL STAIRCASE
48 Formworks of Staircase 7 days Tue 12/27/22 Tue 1/3/23
49 Reinforcement of Staircase 7 days Wed 1/4/23 Wed 1/11/23
50 Inspection 1 day Thu 1/12/23 Thu 1/12/23
51 Pouring Concrete of Staircase 2 days Sat 1/14/23 Sun 1/15/23
52 Finishing 1 day? Mon 1/16/23 Mon 1/16/23
53 288 days Wed 11/2/22 Tue 10/3/23
CONSTRUCTION OF NEW SUBSTATION AREA
54 REACTOR TRANSFORMER  57 days Wed 11/2/22 Sat 1/7/23
55 Survey & Layout 1 day Wed 11/2/22 Wed 11/2/22
56 Excavation 5 days Thu 11/3/22 Tue 11/8/22
57 Compaction & Earthing 3 days Wed 11/9/22 Sat 11/12/22
58 Lean Concrete & Water Proofing & Screed 5 days Sun 11/13/22 Thu 11/17/22
59 Form Works & Reinforcement of Foundation 10 days Sat 11/19/22 Tue 11/29/22
60 Formworks & Reinforcement of Catch Basin Wall 10 days Wed 11/30/22Sun 12/11/22
61 Installation of Embedded Items 1 day Mon 12/12/22Mon 12/12/22
62 Pouring of Concrete Wall 1 day Tue 12/13/22 Tue 12/13/22
63 Firewall Foundation Lean Concrete & Coaltar  1 day Wed 12/14/22Wed 12/14/22
64 Firewall Foundation Formworks & Reinforcement 7 days Thu 12/15/22 Thu 12/22/22
65 Pouring of Concrete 1 day Sat 12/24/22 Sat 12/24/22
66 Formworks & Reinforcement of Fire Wall 4 days Sun 12/25/22 Wed 12/28/22
67 Pouring of Concrete Fire Wall 1 day Thu 12/29/22 Thu 12/29/22
68 Backfilling & compaction 5 days Sat 12/31/22 Wed 1/4/23
69 Installation of Transformer Rail 2 days Thu 1/5/23 Sat 1/7/23
70 Ready for Erection 0 days Sat 1/7/23 Sat 1/7/23 1/7
71 HYBRID GIS FOUNDATIONS 36 days Sun 1/8/23 Sat 2/18/23
72 Survey & Layout 1 day Sun 1/8/23 Sun 1/8/23
73 Excavation 5 days Mon 1/9/23 Sat 1/14/23

Page 1
LINXON EXPANSION OF LAYLA BSP (NG) NATIONAL GRID
ID Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
74 Compaction & Earthing 1 day Sun 1/15/23 Sun 1/15/23
75 Lean Concrete, Waterproofing & Screed 1 day Mon 1/16/23 Mon 1/16/23
76 Formworks & Reinforcement 5 days Tue 1/17/23 Sun 1/22/23
77 Pouring of Concrete Foundation 2 days Mon 1/23/23 Tue 1/24/23
78 Formworks & Reinforcement of Pedestal 5 days Wed 1/25/23 Mon 1/30/23
79 Intsallation of Anchor Bolts 3 days Tue 1/31/23 Thu 2/2/23
80 Pouring of Pedestal 1 day Sat 2/4/23 Sat 2/4/23
81 Finishing 5 days Sun 2/5/23 Thu 2/9/23
82 Backfilling & Compaction 7 days Sat 2/11/23 Sat 2/18/23
83 Ready for Erection 0 days Sat 2/18/23 Sat 2/18/23 2/18
84 OUTDOOR FOUNDATIONS 40 days Sun 2/19/23 Wed 4/5/23
85 Survey & Layout 1 day Sun 2/19/23 Sun 2/19/23
86 Excavation 3 days Mon 2/20/23 Wed 2/22/23
87 Compaction & Earthing 2 days Thu 2/23/23 Sat 2/25/23
88 Lean Concrete, Waterproofing & Screed 2 days Sun 2/26/23 Mon 2/27/23
89 Formworks & Reinforcement 10 days Tue 2/28/23 Sat 3/11/23
90 Pouring of Concrete Foundation 1 day Sun 3/12/23 Sun 3/12/23
91 Formworks & Reinforcement of Pedestal 10 days Mon 3/13/23 Thu 3/23/23
92 Pouring of Pedestal 1 day Sat 3/25/23 Sat 3/25/23
93 Finishing 5 days Sun 3/26/23 Thu 3/30/23
94 Backfilling & Compaction 5 days Sat 4/1/23 Wed 4/5/23
95 Ready for Erection 0 days Wed 4/5/23 Wed 4/5/23 4/5
96 DUCT BANK  23 days Sun 2/19/23 Thu 3/16/23
97 Survey & Layout 1 day Sun 2/19/23 Sun 2/19/23
98 Excavation 3 days Mon 2/20/23 Wed 2/22/23
99 Compaction & Earthing 2 days Thu 2/23/23 Sat 2/25/23
100 Lean Concrete & Water Proofing & Screed 3 days Sun 2/26/23 Tue 2/28/23
101 Installation of PVC Pipe 2 days Wed 3/1/23 Thu 3/2/23
102 Formworks & Reinforcement of Duct Bank  6 days Sat 3/4/23 Thu 3/9/23
103 Pouring of Concrete 1 day Sat 3/11/23 Sat 3/11/23
104 Backfilling & Compaction 5 days Sun 3/12/23 Thu 3/16/23
105 Ready for errection 0 days Thu 3/16/23 Thu 3/16/23 3/16
106 MANHOLE 46 days Sun 2/19/23 Wed 4/12/23
107 Survey & Layout 1 day Sun 2/19/23 Sun 2/19/23
108 Excavation 3 days Mon 2/20/23 Wed 2/22/23
109 Compaction & Earthing 2 days Thu 2/23/23 Sat 2/25/23
110 Lean Concrete, Waterproofing & Screed 2 days Sun 2/26/23 Mon 2/27/23
111 Formworks & Reinforcement of Foundations 10 days Tue 2/28/23 Sat 3/11/23
112 Pouring of Concrete Foundations 1 day Sun 3/12/23 Sun 3/12/23
113 Frmworks & Reinforcement of Wall 10 days Mon 3/13/23 Thu 3/23/23
114 Installationof PVC Pipe Sleeves 1 day Sat 3/25/23 Sat 3/25/23
115 Installation of embedded Items 1 day Sun 3/26/23 Sun 3/26/23
116 Pouring of Concrete Wall 1 day Mon 3/27/23 Mon 3/27/23
117 Installation of Frames & Covers 2 days Tue 3/28/23 Wed 3/29/23
118 Waterproofing of wall Outside Wall 2 days Thu 3/30/23 Sat 4/1/23
119 Backfilling & Compaction 5 days Sun 4/2/23 Thu 4/6/23
120 Finishing/Painting 5 days Sat 4/8/23 Wed 4/12/23
121 Ready for Erection 0 days Wed 4/12/23 Wed 4/12/23 4/12
122 CABLE TRENCH 43 days Sun 2/19/23 Sun 4/9/23
123 Survey & Layout 1 day Sun 2/19/23 Sun 2/19/23
124 Excavation 3 days Mon 2/20/23 Wed 2/22/23
125 Compaction & Earthing 2 days Thu 2/23/23 Sat 2/25/23
126 Lean Concrete, Waterproofing & Screed 2 days Sun 2/26/23 Mon 2/27/23
127 Formworks & Reinforcement of Foundations 10 days Tue 2/28/23 Sat 3/11/23
128 Pouring of Concrete Foundations 1 day Sun 3/12/23 Sun 3/12/23
129 Formworks & Reinforcement of Wall 10 days Mon 3/13/23 Thu 3/23/23
130 Installationof PVC Pipe Sleeves 1 day Sat 3/25/23 Sat 3/25/23
131 Pouring of Concrete Wall 1 day Sun 3/26/23 Sun 3/26/23
132 Installation of Precast Cover Slab 2 days Mon 3/27/23 Tue 3/28/23
133 Backfilling & Compaction 5 days Wed 3/29/23 Mon 4/3/23
134 Finishing/Painting 5 days Tue 4/4/23 Sun 4/9/23
135 Ready for Erection 0 days Sun 4/9/23 Sun 4/9/23 4/9
136 PRECAST BOUNDARY WALL 72 days Mon 4/10/23 Sun 7/2/23
137 Survey & Layout 1 day Mon 4/10/23 Mon 4/10/23
138 Excavation 10 days Tue 4/11/23 Sat 4/22/23
139 Compaction & Earthing 5 days Sun 4/23/23 Thu 4/27/23
140 Lean Concrete, Waterproofing & Screed 4 days Sat 4/29/23 Tue 5/2/23
141 Installation of Precast Foundation 8 days Wed 5/3/23 Thu 5/11/23
142 Installation of Precast Columns 10 days Sat 5/13/23 Tue 5/23/23
143 Installation of Precast Panels 7 days Wed 5/24/23 Wed 5/31/23
144 Backfilling & Compaction 15 days Thu 6/1/23 Sun 6/18/23
145 Intallation of Boundary Wall Gates & Ramps 5 days Mon 6/19/23 Sat 6/24/23
146 Installation Boundary Wall Spiral Barbed Wire 7 days Sun 6/25/23 Sun 7/2/23
147 SITE GRADING 42 days Sun 6/25/23 Sat 8/12/23
148 Survey & Layout 2 days Sun 6/25/23 Mon 6/26/23
149 Backfilling & Compaction 10 days Tue 6/27/23 Sat 7/8/23
150 Installation of Crush Barriers 5 days Sun 7/9/23 Thu 7/13/23

Page 2
LINXON EXPANSION OF LAYLA BSP (NG) NATIONAL GRID
ID Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
151 Kerb Stone 8 days Sat 7/15/23 Sun 7/23/23
152 Internal Asphalt Road 2 days Mon 7/24/23 Tue 7/25/23
153 Gravelling Unpave Area 7 days Wed 7/26/23 Wed 8/2/23
154 Installation of Singnages 5 days Thu 8/3/23 Tue 8/8/23
155 Road Marking 3 days Wed 8/9/23 Sat 8/12/23
156 MISC WORKS 45 days Sun 8/13/23 Tue 10/3/23
157 Core Holes 15 days Sun 8/13/23 Tue 8/29/23
158 Closing of Openings 10 days Wed 8/30/23 Sun 9/10/23
159 Re‐Installation of External Civil Works in Existing BSP (9049) 10 days Mon 9/11/23 Thu 9/21/23
160 Modification of Any Additional Coreholes at Existing Building (As per Site  10 days Sat 9/23/23 Tue 10/3/23
Time Duration will be change)
161 SITE HANDING OVER 2 days Wed 10/4/23 Thu 10/5/23
162 DEMOBILIZATION 5 days Sat 10/7/23 Wed 10/11/23