The document provides cost estimates for RCC hume pipes of various diameters ranging from 200mm to 750mm. For each pipe diameter, it lists the quantities and costs for excavation, concrete, supply and installation of the pipe, backfilling, and labor. The total costs per 7m length and cost per running meter of each pipe diameter are calculated at the bottom including additional charges.
The document provides cost estimates for RCC hume pipes of various diameters ranging from 200mm to 750mm. For each pipe diameter, it lists the quantities and costs for excavation, concrete, supply and installation of the pipe, backfilling, and labor. The total costs per 7m length and cost per running meter of each pipe diameter are calculated at the bottom including additional charges.
The document provides cost estimates for RCC hume pipes of various diameters ranging from 200mm to 750mm. For each pipe diameter, it lists the quantities and costs for excavation, concrete, supply and installation of the pipe, backfilling, and labor. The total costs per 7m length and cost per running meter of each pipe diameter are calculated at the bottom including additional charges.
The document provides cost estimates for RCC hume pipes of various diameters ranging from 200mm to 750mm. For each pipe diameter, it lists the quantities and costs for excavation, concrete, supply and installation of the pipe, backfilling, and labor. The total costs per 7m length and cost per running meter of each pipe diameter are calculated at the bottom including additional charges.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 9
S.
NO Description Unit QTY Rate Amount
A RCC Hume Pipe of 200mm Inner diameter for one length 200 Material 1 Excavation Cum 10.381 250 2595.15 2 PCC Cum 0.117 6000 702
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 500 3750 4 Backfilling Cum 10.2222 200 2044.438 5 Mortar used on collar for Jointning Cum 0 Cement Bags 0.529364 320 169.3965 Sand MT 0.052936 2500 132.341 6 Concrete used over collar for Jointning Cum 0.052936 6000 317.6185 Labour 7 Mason(For 8hours) MD 1 800 800 8 Helper(For 8 Hours ) MD 1 700 700 Sub Total 11210.94 Tools & Tackles @2% 224.2189 Contengencies @3% 336.3283 Rtae per 7 rm 11771.49 Rate per RMT RMT 1681.642
B RCC Hume Pipe of 300mm Diameter for one Length 300
1 Excavation Cum 12.028 250 3006.9 2 PCC Cum 0.162 6000 972
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 630 4725 4 Backfilling Cum 11.8242 200 2364.838 5 Mortar used on collar for Jointning Cum 0 Cement Bags 0.671885 320 215.0033 Sand MT 0.067189 2500 167.9713 Concrete used over collar for Jointning Cum 0.067189 6000 403.1312 Labour 7 Mason(For 8hours) MD 1 800 800 8 Helper(For 8 Hours ) MD 1.5 700 1050 Sub Total 13704.84 Tools & Tackles @2% 274.0969 Contengencies @3% 411.1453 Rtae per 7 rm 14390.09 rate per RMT RMT 2055.726
C RCC Hume Pipe of 450mm Diameter for one Length 450
1 Excavation Cum 16.519 250 4129.65 2 PCC Cum 0.230 6000 1377
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 900 6750 4 Backfilling Cum 16.2477 200 3249.538 5 Mortar used on collar for Jointning Cum 0 Cement Bags 0.977288 320 312.7321 Sand MT 0.097729 2500 244.3219 Concrete used over collar for Jointning Cum 0.097729 6000 586.3726 Labour 7 Mason(For 8hours) MD 1.2 800 960 8 Helper(For 8 Hours ) MD 2.5 700 1750 Sub Total 19359.61 Tools & Tackles @2% 387.1923 Contengencies @3% 580.7884 Rtae per 7 rm 20327.59 rate per RMT RMT 2903.942
D RCC Hume Pipe of 600 mm Diameter for one Length 600
1 Excavation Cum 21.701 250 5425.125 2 PCC Cum 0.293 6000 1755
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 1300 9750 4 Backfilling Cum 21.3666 200 4273.318 5 Mortar used on collar for Jointning Cum 0 Cement Bags 1.32341 320 423.4913 Sand MT 0.132341 2500 330.8526 Concrete used over collar for Jointning Cum 0.132341 6000 794.0462 Labour 7 Mason(For 8hours) MD 1.5 800 1200 8 Helper(For 8 Hours ) MD 2.5 700 1750 Sub Total 25701.83 Tools & Tackles @2% 514.0367 Contengencies @3% 771.055 Rtae per 7 rm 26986.92 rate per RMT RMT 3855.275
E RCC Hume Pipe of 750 mm Diameter for one Length 750
1 Excavation Cum 23.460 250 5865 2 PCC Cum 0.360 6000 2160
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 1600 12000 4 Backfilling Cum 23.0586 200 4611.718 5 Mortar used on collar for Jointning Cum 0 Cement Bags 1.628813 320 521.2201 Sand MT 0.162881 2500 407.2032 Concrete used over collar for Jointning Cum 0.162881 6000 977.2877 Labour 7 Mason(For 8hours) MD 2 800 1600 8 Helper(For 8 Hours ) MD 3 700 2100 Sub Total 30242.43 Tools & Tackles @2% 604.8486 Contengencies @3% 907.2729 Rtae per 7 rm 31754.55 rate per RMT RMT 4536.364 Nos L B H QTY