Lift Master Schedule R1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Task Name Duration Start Finish September 2023 October 2023 November 2023 D

Mode 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 7 12 17 22 27
1 C_S_Work_-_Build_New_outdoor_elevator_lift_for_P5A 76 days Mon 11/9/23 Sat 25/11/23
2 Preliminaries 28 days Mon 11/9/23 Sun 8/10/23
3 CIDB and DOSH Registration 7 days Mon 11/9/23 Sun 17/9/23
4 Organization Chart 7 days Mon 11/9/23 Sun 17/9/23
5 Insurance 7 days Mon 11/9/23 Sun 17/9/23
6 Permit Approval (SIPP) 7 days Mon 11/9/23 Sun 17/9/23
7 Shop Drawing Submission and Approval 7 days Mon 11/9/23 Sun 17/9/23
8 Material Submission and Approval 14 days Mon 11/9/23 Sun 24/9/23
9 Material Delivery 14 days Mon 25/9/23 Sun 8/10/23
10 Surveyor and Utility Mapping 7 days Mon 18/9/23 Sun 24/9/23
11 Hoarding Site Preparation 7 days Mon 18/9/23 Sun 24/9/23
12 Existing Awning Demolation 3 days Mon 18/9/23 Wed 20/9/23
13 Ground Work 16 days Mon 25/9/23 Tue 10/10/23
14 Excavation and Demolation 2 days Mon 25/9/23 Tue 26/9/23
15 Piling 7 days Wed 27/9/23 Tue 3/10/23
16 Lift Pit Construction 7 days Wed 4/10/23 Tue 10/10/23
17 Structure Installation 33 days Wed 11/10/23 Sun 12/11/23
18 Scaffolding Installation 3 days Wed 11/10/23 Fri 13/10/23
19 Structure Installation 14 days Sat 14/10/23 Fri 27/10/23
20 Remove Existing wall Cladiing and Glass Window 3 days Sat 28/10/23 Mon 30/10/23
21 Platform Installation 3 days Tue 31/10/23 Thu 2/11/23
22 Roof Installation 3 days Fri 3/11/23 Sun 5/11/23
23 Tempered Glass Installation 10 days Fri 3/11/23 Sun 12/11/23
24 Architecture Work 13 days Mon 13/11/23 Sat 25/11/23
25 Plaster Ceiling and Painting 3 days Mon 13/11/23 Wed 15/11/23
26 External wall Cladding finish 2 days Mon 13/11/23 Tue 14/11/23
27 Platform Floor Finish 2 days Thu 16/11/23 Fri 17/11/23
28 ID finishing 8 days Sat 18/11/23 Sat 25/11/23
29 M&E Work 16 days Mon 6/11/23 Tue 21/11/23
30 Aircond Installation 3 days Thu 16/11/23 Sat 18/11/23
31 lighting 3 days Thu 16/11/23 Sat 18/11/23
32 Essential power Supply 14 days Mon 6/11/23 Sun 19/11/23
33 Testing and Commissioning 2 days Mon 20/11/23 Tue 21/11/23
34 Fire System 13 days Mon 13/11/23 Sat 25/11/23
35 Smoke Detector 7 days Mon 13/11/23 Sun 19/11/23
36 Lift Tripping Signal 2 days Mon 20/11/23 Tue 21/11/23
37 Fire Alarm panel and Mimic diagram upgrade 11 days Mon 13/11/23 Thu 23/11/23
38 Testing and Commissioning 2 days Fri 24/11/23 Sat 25/11/23

Task Project Summary Manual Task Start-only Deadline

Project: Lift Master Schedule Split Inactive Task Duration-only Finish-only Progress
Date: Mon 4/9/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone