WEEKLY PROGRESS REPORT- 31.08.2021 To 06.09.

2021

Name of Work: Construction of Jetty for Indian Coast Guard at OOT Vadinar.

Client : Deendayal Port Trust

Contractor : Paresh Constructions and Foundation Pvt. Ltd.

PMC : Prof. R. SUNDARAVADIVELU, FNAE


Institute chair professor,
Member BOG IIT Madras (2018-2019),
Department of Ocean Engineering, IIT Madras

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
1
IIT Madras.
Weekly Progress Report

31/08/21 to 06/09/21

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
2
IIT Madras.
Project Details
Project Name Construction of Jetty for Indian Coast Guard at OOT Vadinar

Client Deendayal Port Trust

Contractor Paresh Construction and Foundation Pvt. Ltd.

Project Start Date 26.03.2021

Project End Date 26.09.2022

PMC Start Date 26.03.2021

PMC End Date 26.09.2022 (Construction period 18 months)

No of staff as per
4 Project Engineer, 1 Senior Project Officer
contract
No of staff present at
2 Project Engineer, 1 Senior Project Officer
site
Rs.70,00,000.00 plus applicable GST.
Consultancy Charges
(For 18 Months @ Rs.3,88,888.00 per month)

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
3
IIT Madras.
Project Layout

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
4
IIT Madras.
DAILY PROGRESS FOR THE WEEK

31.08.21 Gantry fabrication work in progress.

01.09.21 No Work progress at site due to rain.

02.09.21 Sea bed level marked for MBH-6 & MBH-7 and Pontoon shifted at MBH-6.

03.09.21 No work progress at site due to rain.

04.09.21 No work progress at site due to rain.

05.09.21 No Work Progress.

06.09.21 No work progress.

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
5
IIT Madras.
PROJECT PROGRESS

WORK TOTAL WORK PROGRESS TILL CURRENT WORK


NAME PERCENTAGE LAST WEEK PROGRESS
Soil Investigation 10% 7.50% 7.50%
Reclamation Area 30% 0% 0%
Approach Jetty 30% 0% 0%
Landing Jetty 30% 0% 0%
TOTAL PROGRESS 100% 7.50% 7.50%

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
6
IIT Madras.
Current Work Progress

▪ The Survey for EGL at Reclamation Area has been completed on 14.08.2021.
▪ Soil investigation is on halt due to bad weather conditions since 30.07.2021,
expected to start by this week.
▪ Gantry Fabrication work in progress.

Borehole Starting R.L.(m) Termination R.L.(m) Total Depth(m) Rock Level R.L.(m) Completion Date
LBH1 7.009 -22.490 29.50 -12.991 22.05.2021
MBH1 1.699 -23.301 25.00 -13.691 08.06.2021
MBH2 0.273 -21.277 21.55 -14.847 17.06.2021
MBH3 -1.300 -27.300 26.00 -18.300 29.06.2021
MBH4 -3.750 -26.750 23.00 -21.150 12.07.2021
MBH5 -7.362 -28.862 21.50 -22.862 30.07.2021
MBH6 Yet to be completed
MBH7 Yet to be completed

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
7
IIT Madras.
SITE PHOTOS

8
SITE PHOTOS

9
SITE PHOTOS

10
SITE PHOTOS

11
THANK YOU

Vadinar PMC team


V. Esakkimuthu
Nikhil Dadmi

Deendayal Port Trust Prof. R. SUNDARAVADIVELU. F.N.A.E


Department of Ocean Engineering
12
IIT Madras.