Module I
Module I
Module I
जल शिक्त मंत्रालय
जल संसाधन, नदी िवकास और गंगा संरक्षण िवभाग
के द्रीय जल आयोग
रा ट्रीय जल अकादमी
िडजाइन और अनुसंधान
Module I : Basic Sciences, Analysis and Design Aspects of Gravity Dams
पुणे
नवंबर 2019
Government of India
Central Water Commission
National Water Academy
िडजाइन और अनुसंधान
Module-I
Module Co‐ordinator
Shri S N Pande, Director (Designs)
Pune
November 2019
MODULE - I
Basic Sciences, Analysis and Design of Gravity Dams
INDEX
2. Application of Finite Element Method in Design of Gravity Dams under 34‐57
Earthquake Load Combinations ( Dynamic Analysis )
3. Overview of Dams 58‐74
4. Design of Concrete Gravity Dams 75‐89
5. Design of SpillWays 90‐107
6. Design of Energy Dissaptors 108‐127
7. Finite Element Analysis of Dams 128‐138
8. Design of Openings in Gravity Dams 139‐142
9. Investigations of Gravity Dams 143‐162
31 INDUCTION TRAINING PROGRAM
Mr.Karl Terzhaghi spent about 50 years (1913-1963) in doing pioneering research on soil
and published his first book titled Erdbaumechanik (means Soil Mechanics) in 1925. This
was the first attempt in the world to treat soil mechanics on the basis of the physical
properties of the soils, since prior to this, all the designs were used to be based on intuition,
experience and empirical formulas, which never provided full confidence about the safety
and economy of the design. No wonder then, Mr.Karl Terzhaghi is known as the father of the
Soil Mechanics. In 1922 Pavlovsky of Russia solved the complex problem of seepage below
the hydraulic structures and enunciated the electrical analogy method for seepage
computation.The important Darcy’s law relating to the flow of water through the soils, and
the Stokes’s law for the settlement of the solid particles in a liquid were enunciated in the
year 1856. These laws play very important role even today, in soil engineering.
Soil Mechanics is a discipline of Civil Engineering that concerns the application of the
principles of mechanics, hydraulics to engineering problems related to soil. The study of the
science of soil mechanics equips a civil engineer with the basic scientific tools needed to
understand soil behaviour and its application as an engineering material for construction of
earthen dams, bridges and dykes, etc.
Soil consists of a multiphase aggregation of solid particles, water, and air. This fundamental
composition gives rise to unique engineering properties, and the description of its mechanical
behaviour requires some of the most classic principles of engineering mechanics.
Engineers are concerned with soil's mechanical properties: permeability, seepage, stiffness,
and strength. These depend primarily on the nature of the soil grains, the current stress, the
water content and unit weight.
Field of Soil Mechanics is very vast. The civil engineer has many diverse and important
encounters with soil. Apart from the testing and classification of various types of soil in order
to determine its physical properties, the knowledge of soil mechanics is particularly helpful in
the following problems in civil engineering
Page 1
31 INDUCTION TRAINING PROGRAM
A soil mass consists of solid soil particles, containing void spaces between them. These voids
may be filled either with air, or water, or both. A schematic diagram of the three-phase
system is shown in terms of weight and volume symbols respectively for soil solids, water,
and air. The weight of air can be neglected. For the purpose of engineering analysis and
design, it is necessary to express relations between the weights and the volumes of the three
phases.
Page 2
31 INDUCTION TRAINING PROGRAM
Volume relation
1. Void ratio (e) is the ratio of the volume of voids (Vv) to the volume of soil solids (Vs), and
is expressed as a decimal.
2. Porosity (n) is the ratio of the volume of voids to the total volume of soil (V), and is
expressed as a percentage.
and
3. The volume of water (Vw) in a soil can vary between zero (i.e. a dry soil) and the volume
of voids. This can be expressed as the degree of saturation (S) in percentage.
For a dry soil, S = 0%, and for a fully saturated soil, S = 100%.
4. Air content (ac) is the ratio of the volume of air (Va) to the volume of voids.
5. Percentage air voids (na) is the ratio of the volume of air to the total volume.
Weight relation
1. The ratio of the mass of water present to the mass of solid particles is called the water
content (w), or sometimes the moisture content.
Page 3
31 INDUCTION TRAINING PROGRAM
Its value is 0% for dry soil and its magnitude can exceed 100%.
2. The mass of solid particles is usually expressed in terms of their particle unit weight
or specific gravity (Gs) of the soil grain solids .
3. Dry unit weight is a measure of the amount of solid particles per unit volume.
4. Bulk unit weight is a measure of the amount of solid particles plus water per unit
volume.
5. Saturated unit weight is equal to the bulk density when the total voids is filled up
with water.
6. Buoyant unit weight or submerged unit weight is the effective mass per unit volume
when the soil is submerged below standing water or below the ground water table.
Page 4
31 INDUCTION TRAINING PROGRAM
Moisture Content
Density
Porosity
Void ratio
Specific Gravity
Plasticity Characteristics
Liquid limit
Plastic limit
Plasticity index
Shrinkage limit
Shrinkage index
Liquidity index
Consistency index
Activity
Gradation Characteristics
Effective Diameter
Percent grain size
Uniformity coefficient
Coefficient of curvature
Page 5
31 INDUCTION TRAINING PROGRAM
Page 6
31 INDUCTION TRAINING PROGRAM
In accordance to IS two test methods are available in finding the distribution of grain
sizes Wet sieve analysis shall be applicable to all soils and dry sieve analysis shall be
applicable only to soils which do not have an appreciable amount of clay. For the
determination of distribution of grain sizes smaller than 75-microns the pipette method is
given as the standard method; the hydrometer method is given as a subsidiary method. This
method shall not applicable if less than 10 percent of the material passes the 75-micron IS
Sieve.
Test Procedure - Dry Sieve Analysis
1. The soil fractions retained on and passing 4’75-mm IS Sieve shall be taken separately
for the analysis. The portion of the soil sample retained on 4*75-mm IS Sieve shall be
weighed and the mass recorded.
2. The quantity of the soil sample taken shall depend on the maximum particle size
contained in the soil.
3. The sample shall be separated into various fractions by sieving through the set of
Indian Standard Sieves taken in descending order. While sieving through each sieve,
the sieve shall be agitated so that the sample rolls in irregular motion over the Sieve.
4. The material from the sieve may be rubbed, if necessary, with the rubber pestle in the
mortar taking care to see that individual soil particles are not broken and re-sieved to
make sure that only individual particles are retained.
5. The weight retained in each sieve is measured. The cumulative percentage quantities
finer than the sieve sizes (passing each given sieve size) are then determined.
6. The resulting data is presented as a distribution curve with grain size along x-axis
(log scale) and percentage passing along y-axis (arithmetic scale).
Test Procedure - Wet Sieve analysis
1. The portion of the soil passing 4.75mm IS Sieve shall be oven-dried at 105 to
110°C.
2. The oven-dried material shall then be riffled so that a fraction of convenient mass
is obtained. This shall be about 200 g if a substantial proportion of the material
only, just passes the 4.75-mm IS Sieve or less if the largest size is smaller.
3. The fraction shall be weighed to 0.1 percent of its total mass and the mass
recorded.
4. The riffled and weighed fraction shall be spread out in the large tray or bucket and
covered with water.
Page 7
31 INDUCTION TRAINING PROGRAM
Sedimentation analysis
Sedimentation analysis is used only for the soil fraction finer than 75 microns If the
passing from the 75 micron is more than 12 percentages then hydrometer analysis is widely
used to estimate the distribution of the particle size from 0.0075 mm to around 0.001 mm.
Soil particles are allowed to settle from a suspension. The decreasing density of the
suspension is measured at various time intervals. The procedure is based on the principle that
in a suspension, the terminal velocity of a spherical particle is governed by the diameter of
the particle and the properties of the suspension.The hydrometer used in this analysis is
shown below
Page 8
31 INDUCTION TRAINING PROGRAM
In this method, the soil is placed as a suspension in a jar filled with distilled water to
which a deflocculating agent is added. The analysis is based on Stokes’s law, according to
which the velocities of free fall of spherical, fine particles, through a liquid are different for
different sizes.
The soil particles are then allowed to settle down. The concentration of particles
remaining in the suspension at a particular level can be determined by using a hydrometer.
Specific gravity readings of the solution at that same level at different time intervals provide
information about the size of particles that have settled down and the mass of soil remaining
in solution.The results are then plotted between % finer (passing) and log size.
The diameter of the particle in suspension at any sampling time t shall be calculated
from the formula
G = specific gravity of the soil fraction used in the sedimentation analysis, in g/cm3;
Page 9
31 INDUCTION TRAINING PROGRAM
The sample form is shown below to record the results of grain size distribution for sieve
analysis and for hydrometer analysis
2. Uniformity coefficient,
3. Curvature coefficient,
Both Cuand Cc will be 1 for a single-sized soil.Cu > 5 indicates a well-graded soil,
i.e. a soil which has a distribution of particles over a wide size range.Cc between 1 and 3 also
Page 10
31 INDUCTION TRAINING PROGRAM
indicates a well-graded soil.Cu < 3 indicates a uniform soil, i.e. a soil which has a very
narrow particle size range.
Consistency of Soilisthe relative ease with which soil can be deformed. This term is mostly
used for fine – grained soils for which the consistency is related to a large extent to water
content. The liquid and plastic limits of soils are both dependent on the amount and type of
clay in a soil and form the basis for the soil classification system for cohesive soils based on
the plasticity tests. Besides their use for identification, the plasticity tests give information
concerning the cohesion properties of soil and the amount of capillary water which it can
hold. They are also used directly in specifications for controlling soil for use in fill. These
index properties of soil have also been related to various other properties of the soil.
A gradual increase in water content causes the soil to change from solid to semi-
solid to plastic to liquid states. The water contents at which the consistency changes from one
state to the other are called consistency limits (or Atterberg limits).The three limits are known
as the shrinkage limit (WS), plastic limit (WP), and liquid limit (WL)as shown. The values of
these limits can be obtained from laboratory tests with reference to IS 2720 (Part V) - 1985.
Sample result sheet for liquid and plastic limit is shown below.
Page 11
31 INDUCTION TRAINING PROGRAM
Result Summary:
The grain-size range is used as the basis for grouping soil particles into boulder,
cobble, gravel, sand, silt or clay. Gravel, sand, silt, and clay are represented by group symbols
G, S, M, and C respectively.
Page 12
31 INDUCTION TRAINING PROGRAM
The laboratory classification criteria for classifying the fine-grained soils are given in
the plasticity chart as shown below. The' A ' line has the following linear equation between
the liquid limit and the plasticity index:
1p= 0·73 (WL - 20)
where
Ip - plasticity index, and
WL -liquid limit.
Clay particles are flaky. Their thickness is very small relative to their length &
breadth, in some cases as thin as 1/100th of the length. They therefore have high specific
surface values. These surfaces carry negative electrical charge, which attracts positive ions
present in the pore water. Thus a lot of water may be held as adsorbed water within a clay
mass.
A tetrahedral unit consists of a central silicon atom that is surrounded by four oxygen atoms
located at the corners of a tetrahedron. A combination of tetrahedrons forms a silica sheet.
Page 13
31 INDUCTION TRAINING PROGRAM
1) Visual Examination
The visual examination of soil is done by naked eye with reference to size, shape
(angularity), touch and grading characteristics of soil grains.
To perform this test, take a small quantity of the soil in hand, moisten it if needed, and
work it with fingers and feel it. If the soil is clayey, a soapy touch would be felt; if the soil is
sandy, a feeling of roughness is experienced; and in case of silty soil, moisture will come out
if it is squeezed in between the fingers. Also, clay sticks to the fingers and dries slowly, but
silt dries fairly quickly, and can be wiped off the fingers easily. This test helps to distinguish
the major soil characteristics, that is , whether the soil is clayey, sandy or silty.
3) Thread test
To perform this test, take a small quantity of soil, moisten it if needed, and roll it in
between the palms of the hand or on a flat smooth surface into a thread of about 3mm
diameter. If crumbling does not occur, fold thee thread and re-roll as before. Repeat the
process until the moisture content of the soil has been reduced by drying during
manipulation, to the plastic limit, which is indicated by crumbling which occurs as the soil is
being rolled. The characteristic of the thread as it approached the plastic limit affords the
means of identification of the soil.
4) Dilatancy test - After removing particles retained on IS 425 micron sieve, prepare a pat of
moist soil of size of 2cm cube. Add enough water, if necessary to make the soil soft but not
sticky. Place the pat in the open palm on one hand and shake horizontally striking vigorously
Page 14
31 INDUCTION TRAINING PROGRAM
against the other hand several times. A positive reaction consists of the appearance of water
on the surface of the pat which changes to a consistency and becomes glossy. When the
sample is squeezed between the fingers, the water and the gloss disappear from the surface,
the pat stiffens and finally it cracks and crumbles. The rapidity of appearance of water during
shaking and its disappearance during squeezing result in identifying the fines in a soil. Very
fine clean sand gives quickest and most distinct reaction, whereas, plastic clay has no
reaction. Inorganic silt such as typical rock flour, show a moderately quick reaction.
After removing particles retained on IS 425 micron sieve, mould a pat of soil to the
consistency of putty, adding water if necessary. Allow the pat to dry completely by oven, sun
or air drying, and then test its strength by breaking and crumbling between the fingers. This
strength is a measure of the character and quantity of the colloidal fraction contained in the
soil. The dry strength is characteristicfor clays of the CH group. Atypical inorganic silt
possesses only very slight dry strength. Silty fine ands and silts have about the same slight
dry strength, but can be distinguished by the feel when powdering the dried specimen. Fine
sand feels gritty; whereas typical silt has the smooth feel of flour.
Permeability of soil
Pressure, Elevation and Total heads
In soils, the interconnected pores provide passage for water. A large number of such
flow paths act together, and the average rate of flow is termed the coefficient of permeability,
or just permeability. It is a measure of the ease that the soil provides to the flow of water
through its pores.
Page 15
31 INDUCTION TRAINING PROGRAM
At point A, the pore water pressure (u) can be measured from the height of water in a
standpipe located at that point.
The elevation head (hz) of any point is its height above the datum line. The height of water
level in the standpipe above the datum is the piezometric head (h).
h= hz + hw
Total head consists of three components: elevation head, pressure head, and velocity
head. As seepage velocity in soils is normally low, velocity head is ignored, and total head
becomes equal to the piezometric head. Due to the low seepage velocity and small size of
pores, the flow of water in the pores is steady and laminar in most cases. Water flow takes
place between two points in soil due to the difference in total heads.
Darcy’s law states that there is a linear relationship between flow velocity (v) and hydraulic
gradient (i) for any given saturated soil under steady laminar flow conditions.
If the rate of flow is q (volume/time) through cross-sectional area (A) of the soil mass,
Darcy's Law can be expressed as
v = q/A = k.i
Page 16
31 INDUCTION TRAINING PROGRAM
The flow velocity (v) is also called the Darcian velocity or the superficial velocity. It is
different from the actual velocity inside the soil pores, which is known as the seepage
velocity, vS. At the particulate level, the water follows a tortuous path through the pores.
Seepage velocity is always greater than the superficial velocity, and it is expressed as:
For different soil types as per grain size, the orders of magnitude for permeability are as
follows:
Soil k (cm/sec)
Gravel 100
Coarse sand 100 to 10-1
Medium sand 10-1 to 10-2
Fine sand 10-2 to 10-3
Silty sand 10-3 to 10-4
Silt 1 x 10-5
Clay 10-7 to 10-9
Page 17
31 INDUCTION TRAINING PROGRAM
In soils, the permeant or pore fluid is mostly water whose variation in property is generally
very less. Permeability of all soils is strongly influenced by the density of packing of the soil
particles, which can be represented by void ratio (e) or porosity (n).
For Sands
In sands, permeability can be empirically related to the square of some representative grain
size from its grain-size distribution. For filter sands, Allen Hazen in 1911 found that k = 100
(D10)2 cm/s where D10= effective grain size in cm.
Different relationships have been attempted relating void ratio and permeability, such
as k µ e3/(1+e), and k µ e2. They have been obtained from the Kozeny-Carman equation for
laminar flow in saturated soils.
where ko and kT are factors depending on the shape and tortuosity of the pores
respectively, SS is the surface area of the solid particles per unit volume of solid material,
and gw and h are unit weight and viscosity of the pore water. The equation can be reduced to
a simpler form as
Page 18
31 INDUCTION TRAINING PROGRAM
The coefficient of permeability depends on several factors, most of which are listed below.
4. Composition of soil particles. For sands and silts this is not important; however, for soils with
clay minerals this is one of the most important factors. Permeability depends on the thickness of
water held to the soil particles, which is a function of the cation exchange capacity, valence of the
cations, and so forth. Other factors remaining the same, the coefficient of permeability decreases
with increasing thickness of the diffuse double layer.
5. Soil structure. Fine-grained soils with a flocculated structure have a higher coefficient of
permeability than those with a dispersed structure.
Page 19
31 INDUCTION TRAINING PROGRAM
Total head h in standpipe of area a is allowed to fall. Hydraulic gradient varies with time.
Heads h1 and h2 are measured at times t1 and t2. At any time t, flow through the soil sample of cross-
sectional area A is
--------------------- (1)
= ----------------- (2)
or
Page 20
31 INDUCTION TRAINING PROGRAM
Field or in-situ measurement of permeability avoids the difficulties involved in obtaining and setting
up undisturbed samples in a permeameter. It also provides information about bulk permeability,
rather than merely the permeability of a small sample.
A field permeability test consists of pumping out water from a main well and observing the resulting
drawdown surface of the original horizontal water table from at least two observation wells. When a
steady state of flow is reached, the flow quantity and the levels in the observation wells are noted.
Two important field tests for determining permeability are: Unconfined flow pumping test, and
confined flow pumping test.
In this test, the pumping causes a drawdown in an unconfined (i.e. open surface) soil stratum, and
generates a radial flow of water towards the pumping well. The steady-state heads h1 and h2 in
Page 21
31 INDUCTION TRAINING PROGRAM
observation wells at radii r1 and r2 are monitored till the flow rate q becomes steady.
The rate of radial flow through any cylindrical surface around the pumping well is equal to the
amount of water pumped out. Consider such a surface having radius r, thickness dr and height h. The
hydraulic gradient is
Area of flow,
Seepage in soils
Page 22
31 INDUCTION TRAINING PROGRAM
A rectangular soil element is shown with dimensions dx and dz in the plane, and thickness dy perpendicular
to this plane. Consider planar flow into the rectangular soil element.
In the x-direction, the net amount of the water entering and leaving the element is
Similarly in the z-direction, the difference between the water inflow and outflow is
For a two-dimensional steady flow of pore water, any imbalance in flows into and out of an element in the
z-direction must be compensated by a corresponding opposite imbalance in the x-direction. Combining the
above, and dividing by dx.dy.dz , the continuity equation is expressed as
When the continuity equation is combined with Darcy's law, the equation for flow is expressed as:
For an isotropic material in which the permeability is the same in all directions (i.e. k x= k z), the flow
equation is
This is the Laplace equation governing two-dimensional steady state flow. It can be solved graphically,
analytically, numerically, or analogically.
Page 23
31 INDUCTION TRAINING PROGRAM
For the more general situation involving three-dimensional steady flow, Laplace equation
becomes:
The values of constants can be determined from the specific boundary conditions.
As shown, at x = 0, h = H , and at x = L, h = 0
c2 = H ,
Page 24
31 INDUCTION TRAINING PROGRAM
which states that head is dissipated in a linearly uniform manner over the entire length of the
permeameter.
At every point (x,z) where there is flow, there will be a value of head h(x,z). In order to represent these
values, contours of equal head are drawn.
A flow net is to be drawn by trial and error. For a given set of boundary conditions, the flow net will
remain the same even if the direction of flow is reversed. Flow nets are constructed such that the head
lost between successive equipotential lines is the same, say h. It is useful in visualising the flow in a soil
to plot the flow lines, as these are lines that are tangential to the flow at any given point. The steps of
construction are:
1. Mark all boundary conditions, and draw the flow cross section to some convenient scale.
2. Draw a coarse net which is consistent with the boundary conditions and which has orthogonal
equipotential and flow lines. As it is usually easier to visualise the pattern of flow, start by drawing the
flow lines first.
3. Modify the mesh such that it meets the conditions outlined above and the fields between adjacent flow
lines and equipotential lines are 'square'.
(a) A submerged permeable soil boundary is an equipotential line. This could have been determined by
considering imaginary standpipes placed at the soil boundary, as for every point the water level in the
standpipe would be the same as the water level. (Such a boundary is marked as CD and EF in the
following figure.)
(b) The boundary between permeable and impermeable soil materials is a flow line (This is marked as
AB in the same figure).
Page 25
31 INDUCTION TRAINING PROGRAM
The graphical properties of a flow net can be used in obtaining solutions for many seepage problems such
as:
1. Estimation of seepage losses from reservoirs: It is possible to use the flow net in the transformed
space to calculate the flow underneath the dam.
2. Determination of uplift pressures below dams: From the flow net, the pressure head at any point at
the base of the dam can be determined. The uplift pressure distribution along the base can be drawn and
then summed up.
3. Checking the possibility of piping beneath dams: At the toe of a dam when the upward exit hydraulic
gradient approaches unity, boiling condition can occur leading to erosion in soil and consequent piping.
Many dams on soil foundations have failed because of a sudden formation of a piped shaped discharge
channel. As the stored water rushes out, the channel widens and catastrophic failure results. This is also
often referred to as piping failure.
Consolidation of soil
Elastic settlement is on account of change in shape at constant volume, i.e. due to vertical compression
and lateral expansion. Primary consolidation (or simply consolidation) is on account of flow of water
from the voids, and is a function of the permeability and compressibility of soil. Secondary
compression is on account of creep-like behaviour.
Primary consolidation is the major component and it can be reasonably estimated. A general theory for
Page 26
31 INDUCTION TRAINING PROGRAM
consolidation, incorporating three-dimensional flow is complicated and only applicable to a very limited
range of problems in geotechnical engineering. For the vast majority of practical settlement problems, it is
sufficient to consider that both seepage and strain take place in one direction only, as one-dimensional
consolidation in the vertical direction.
Compaction of soils
Compaction is the application of mechanical energy to a soil so as to rearrange its particles and reduce
the void ratio.
It is applied to improve the properties of an existing soil or in the process of placing fill such as in the
construction of embankments, road bases, runways, earth dams, and reinforced earth walls. Compaction
is also used to prepare a level surface during construction of buildings. There is usually no change in the
water content and in the size of the individual soil particles.
Laboratory Compaction
The variation in compaction with water content and compactive effort is first determined in the
laboratory. There are several tests with standard procedures such as:
Page 27
31 INDUCTION TRAINING PROGRAM
in the field under heavier loading conditions, and this led to the development of the Heavy Compaction
Test (Modified Test). The equipment and procedure are essentially the same as that used for the
Standard Test except that the soil is compacted in 5 layers, each layer also receiving 25 blows. The same
mould is also used. To provide the increased compactive effort, a heavier rammer of 4.9 kg and a greater
drop height of 450 mm are used.
The water content of a compacted soil is expressed with reference to the OMC. Thus, soils are said to be
compacted dry of optimum or wet of optimum (i.e. on the dry side or wet side of OMC). The
structure of a compacted soil is not similar on both sides even when the dry density is the same, and this
difference has a strong influence on the engineering characteristics.
SoilStructure
For a given compactive effort, soils have a flocculated structure on the dry side (i.e. soil particles are
oriented randomly), whereas they have a dispersed structure on the wet side (i.e. particles are more
oriented in a parallel arrangement perpendicular to the direction of applied stress). This is due to the well-
developed adsorbed water layer (water film) surrounding each particle on the wet side.
Page 28
31 INDUCTION TRAINING PROGRAM
Swelling
Due to a higher water deficiency and partially developed water films in the dry side, when given access to
water, the soil will soak in much more water and then swell more.
Shrinkage
During drying, soils compacted in the wet side tend to show more shrinkage than those compacted in the
dry side. In the wet side, the more orderly orientation of particles allows them to pack more efficiently.
Permeability
The randomly oriented soil in the dry side exhibits the same permeability in all directions, whereas the
dispersed soil in the wet side is more permeable along particle orientation than across particle orientation.
Soil Stabilization
Stone columns – Top feeded and bottom feeded procedure are illustrated in the diagram
shown below
Page 29
31 INDUCTION TRAINING PROGRAM
Lime. Slaked lime is most often used in the stabilization of subgrades and road bases, particularly
in soil that is clay-like or highly plastic. ...
Cement
Bitumen
Chemical Compounds
Geotextiles
Mixing Materials
Grouting
Electrical Stabilization
Instrumentation is the use of special devices to obtain critical scientific measurements of engineered
behaviour. A typical instrument arrangement consists of one or more of three basic elements: a sensor;
a signal conducting media; and a readout/recorder. The data recording may be done by hand, chart
recorder, film recorder, digital printout, or magnetic recorder, and in some cases, may be transmitted
directly to computer storage. Structural displacements, deformations, settlements, seepages, the
piezometric pressure within the structure and its foundation are items that are the focus of a monitoring
system
Water Pressure
A certain amount of water seeps through, under, and around all dams. The water moves through the
Page 30
31 INDUCTION TRAINING PROGRAM
pores in the soil, and through the cracks and joints in the rock. The pressure of the water acts uniformly
in all directions; it is termed pore pressure. The upward component of pore pressure, called uplift
pressure, has the effect of reducing the effective downward weight of the dam and can decrease the
stability of the structure. Devices used to measure pressure include several types of piezometers and
total pressure cells.
The below figure illustrates the parameters to be measured at the major cross section of the embankment
dam
Piezometers are devices used to measure the water pressure at specific locations in dam bodies,
foundations, and abutments. The primary value of water pressure data is to warn of certain conditions or
problems that may exist or may be developing. Unusual water pressure data may show that
unanticipated movement or seepage is occurring.
There are two basic types of piezometers: (1) hydraulic piezometers in which the pressure is obtained
directly by measuring the water level or the pressure into the tube; and (2) electrical piezometers in
which the pressure is measured with electrical-acoustic or electric resistant pressure gauges
(manometers), or with pneumatic sensors.
Stress and Strain - Design stresses may not always occur as expected in a completed dam. For this
reason, special total pressure instruments are used to measure the actual stresses at selected locations,
such as between a dam and its abutments or foundation, or between certain components of the dam. The
purpose of total pressure monitoring is to measure the total pressure (total load) on a contact surface or
within the mass of the dam. Several types of devices (cells) are used to measure the static total pressure
Page 31
31 INDUCTION TRAINING PROGRAM
in a dam. The measured load can be caused by earth, water, or concrete. A dam’s principal stresses can
be evaluated based on data
Earth pressures within fill and against concrete structures are measured with earth pressure cells,
which are also known as total pressure cells. They consist of two flexible diaphragms sealed around the
periphery, with a fluid in the annular space between the diaphragms. Pressure is measured by the
increase in fluid pressure behind the diaphragm with pneumatic or vibrating wire sensors. Earth pressure
cells should have similar stiffness as the surrounding soil to avoid inaccurate measurements of in-situ
stress caused by arching.
A variety of mechanical and electrical strain gauges are used to measure strain in concrete structures.
Some of the instruments are designed to be embedded in the dam during construction, and others are
surface mounted following construction. Strain gages are often installed in groups so that the three-
dimensional state of strain can be evaluated
The figure below illustrates the overall instrumentation for the core dam.
Page 32
31 INDUCTION TRAINING PROGRAM
Temperature is also measured in concrete dams under construction to evaluate mix design, placement
rates, and block and lift sizes; to time grouting of block joints; and to assess thermal loads. Resistance
thermometers or thermocouples can measure the temperatures of a dam, its foundation, and other
instruments.
References:
8)https://nptel.ac.in/courses/105103097/
10) Guidelines for instrumentation for large dams – jan 2018 Dam safety rehabilitation
directorate
Page 33
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
INTRODUCTION
During 20th century, many large dams have been constructed in all parts of India. These
dams have been designed based on experience or simplified methods which often
resulted in either over safe design or unsafe design. Due to frequent occurrences of
strong earthquakes in northern parts (Himalayan region), eastern parts (Assam and
other north-eastern region), western parts ( Bhuj earthquake in Gujarat and Koyna and
Latur earthquakes in Maharashtra ) and central parts (Madhya Pradesh) of India,
safety of existing and proposed dams lying in these high seismic zones have become
of great concern to project authorities. Moreover, these dams have been designed
based on recommendations of old BIS codes and old classified seismic zones of India
with less magnitude of seismic coefficients. Since then, BIS codes have been revised
several times and seismic zones of India have also been reclassified with higher
magnitude of seismic coefficients. As per modern design practices, the dam should be
safe against earthquake forces under detailed dynamic response analysis using site-
specific seismic parameters. Dynamic analysis of dams is much more complicated
since interaction between dam and the foundation rock and hydrodynamic forces need
to be modeled in a realistic way. Prior to the invention of fast computers i.e., earlier to
1970, all the dams have been designed based on conventional approaches by
considering the dam as a vertical cantilever beam and normal stresses have been
evaluated at upstream and downstream faces. With the invent of fast computers, more
sophisticated structural analysis methods such as Finite Difference Method, Boundary
Integration Method and Finite Element Method have been evolved and state of the art
finite element softwares have been developed. At present, more rigorous analysis is
carried out generally by Finite Element Method by using these general purpose finite
element softwares with automesh generation and with facilities of animation of results
during post processing. The methods of analysis need to be applied suitably to get
correct estimation of the response, as the results are very sensitive to the
approximations and idealizations made. Two dimensional(2D) finite element analysis is
generally appropriate for concrete gravity dams. It should be understood that the actual
34
Page 34
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
response of the structure is three dimensional(3D) therefore the designer should review
the analysis and realistic results to assure that the 2D approximation is acceptable and
realistic. For spillway blocks, plane stress approach gives more realistic results as
compared to plane strain approach. For long conventional concrete dams, a 2D
analysis is reasonably correct. Dams located in narrow valleys between steep
abutments and dams with foundation of varying rock Modulii which vary across the
valley, dams with openings and weak foundation zones are conditions that necessitate
3D modeling and analysis. Further, the analysis results almost become identical from
separate 2D and 3D analysis, if ratio of length to height of the dam is greater than 4.
Dynamic analysis results need to be calibrated by monitoring the response to actual
earthquakes and forced vibration tests.
FEM Softwares
Many general purpose Finite Element Softwares have been developed and are in use
all over the world. A few popularly used, general purpose FEM softwares are as follows:
The basic principle of all the softwares is same. The main difference lies in mesh
generation capability and post processing of results. The main components of such
programs for structural analysis are as follows:
Input – Definition of physical model, geometry, material loading and
Boundary conditions.
Library of elements – Generation of mathematical models.
Solution – Assembly and solution of algebraic equations.
Output – Display of calculated displacements and stresses
REQUIREMENT OF DYNAMIC ANALYSIS
The dynamic analysis using site specific earthquake ground motions becomes
necessary if following conditions exist:
i. The dam is 100 feet (30m) or more in height and the peak ground
acceleration
(PGA) at the site is greater than 0.2 g for maximum credible earthquake i.e.
35
Page 35
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
Zone III.
ii. The dam is less than 100 feet high and the PGA at the site is greater than 0.4
g for the maximum credible earthquake i.e. Zone IV & V.
iii. There are gated spillway monoliths, wide roadways, intake structures, or
other
monoliths of unusual shape or geometry.
Site specific seismic response spectra and acceleration time history of ground motion is
generated by Earthquake experts. At CWPRS, Engineering Seismology division is
carrying out such type of studies. In brief, two general approaches for developing Site
Specific Response Spectra and Acceleration Time History of ground motion are the
deterministic and probabilistic approaches.
for ground motion exceedance. For example, ground motions could be estimated
for a 10 percent probability of exceedance in 100 years or for a return period of
950 years. A probabilistic ground motion assessment incorporates the frequency
of occurrence of earthquake of different magnitudes on the seismic sources, the
uncertainty of the earthquake locations on the sources and the ground motion
attenuation including its uncertainty.
Seismic coefficients based on IS: 1893 ( Part 1) : 2002 are calculated as follows:
where:
Ah= Horizontal seismic coefficient
Z = Zone factor,
I = Importance factor
R = Response reduction factor (I/R=1.0 )
Sa / g = Average response acceleration coefficient
The value of seismic coefficients in vertical direction is taken as 1/2 to 2/3 of horizontal
seismic coefficient Ah .The value of seismic coefficients is taken as 1.5 times of Ah at
top of the dam and reduced linearly to zero at base. Sometimes, site specific seismic
coefficients are given by project authority based on seismic studies.
PERMISSIBLE STRESSES
The maximum tensile and compressive stresses developed in the dam body should
always satisfy the stability criteria as per IS:6512-1984. The maximum permissible
tensile stress in concrete gravity dams under simplified approaches as per BIS is taken
as 4% of characteristic cube compressive strength. As per latest design practices in
India, the allowable tensile stress using modern rigorous methods of analysis under
static and pseudodynamic conditions is taken as 1/10 to 1/8 of characteristic cube
compressive strength.
As per International practices, the splitting tensile test or the modulus of rupture
test can be used to determine the tensile strength. For initial design investigations,
static, pseudostatic, pseudodynamic and linear dynamic analysis, permissible tensile
strength of concrete is calculated from the following equation (Raphael 1984):
37
Page 37
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
The static tensile strength determined by the splitting tensile test may be increased by
1.33 to be comparable to the standard modulus of rupture test. Modulus of rupture i.e.
bending tensile strength is obtained as follows:
DAMPING
The damping plays important role in dynamic analysis. Damping in a structure is due to
nonlinearities that cause loss of energy. The dynamic motion of any system is damping
dependent. The damping is defined as resistance to motion. Most nonlinear analysis
use Rayleigh damping which combines a mass damping equation with a stiffness
damping equation to arrive at a percent of critical damping.
C= α×M +β×K (6)
Where α and β are damping constants, M and K are mass and stiffness matrices. α
and β are calculated as follows:
38
Page 38
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
where:
LOAD COMBINATIONS
The analysis is generally carried out for the following load combinations based on IS:
6512 – 1984:
The effect of earthquake loads into two dimensional (2D) and three dimensional (3D)
analysis is taken into account by following approaches.
The dynamic analysis has been carried out for a proposed 62.5 m high non-overflow
concrete gravity dam with a base width of 60.4 m located in the highest seismic zone V
as per IS: 1893 (Part I)-2002 as shown in Fig.1. The analysis is based on the
assumptions that the material in the dam and the foundation is isotropic and
homogeneous and it behaves in linear elastic way, that the dam is in plane strain
condition, and that all the displacement components reduces to zero at base of
40
Page 40
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
foundation block. The properties of the dam and foundation material adopted in the
analysis are as given below:
Young’s Modulus of Dam Concrete: 2.20×105 kg/cm2
41
Page 41
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
topography, geology and past seismic record has been considered in the analysis. The
horizontal and vertical response spectra at different damping are shown in Fig.2.
To take into account the elastic behavior of the foundation rock strata, a section of the
foundation part up to a depth equal to more than 4 times the height of the dam and
width equal to 4 times of dam base have been included in the analysis. To allow free
field ground motion the mass of the foundation is neglected in the analysis. The total
202 numbers of 2-D isoparametric plane strain elements have been generated by
defining 891 nodes including generated nodes. The detailed idealization is shown in
Fig.3.
42
Page 42
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
Fig. 3: Finite Element Model of Non Overflow Section for Dynamic Analysis
The boundary conditions are modified under dynamic analysis as compared to other
analysis. In foundation, only horizontal movement is allowed at the ends of the
foundation block as per recommendation of ICOLD Bulletin 30-Jan 1978. The base of
the foundation is assumed fixed i.e. all displacement components are assumed as zero.
At the interface of dam body and foundation block, two sets of nodes are defined by
giving identical coordinates. The dam body is treated as attached to foundation in
vertical direction i.e. dam is not allowed to move horizontally independently and firmly
rested on foundation block. At the interface, only vertical movement is allowed in the
dam body. At all other places, horizontal and vertical movements are allowed. The
detailed boundary conditions are shown in Fig.3. The hydrodynamic effects are
modeled as an added mass of water moving with the dam using Westergaard’s formula
as mentioned above. First, natural frequencies of vibration and corresponding mode
shapes for specified modes are computed by applying all static loads as per load
combination E. The earthquake loading is computed from earthquake response spectra
for each mode of vibration induced by the horizontal and vertical components of
response spectra. These modal responses are combined to obtain an estimate of the
43
Page 43
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
maximum total response. Stresses are computed by a static analysis of the dam using
the earthquake loading as an equivalent static load. The results of static and response
analysis are combined by square root of the sum of the squares (SRSS) method for
getting complete response. Figs 4-6 show the three mode shapes and fig.7 shows the
total response under three modes.
44
Page 44
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
RESULTS
Results are obtained in the form of displacements and principal stresses including static
effects. Figs. 8 - 10 show the distribution of horizontal, vertical and resultant
displacements in the dam body.
The 2D dynamic analysis has been carried out by using same mathematical model as
used for response spectrum analysis shown in fig 3. The dynamic analysis has been
performed by taking static as well as dynamic material properties. The dynamic material
properties are determined by Resonance Column test (facility available at CWPRS) by
taking concrete and rock cores. The Young’s Modulus of Elasticity E for old concrete
say more than one year is almost same as Static Modulus. Site specific acceleration
time histories of horizontal and vertical components of motion generated at CWPRS by
46
Page 46
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
taking into account seismotectonics, geology and past earthquake history of the region
has been used to define the input excitation. These time-histories are shown plotted in
Fig. 14. After generation of mathematical modal based on prepared data as mentioned
above, dynamic analysis is performed in two steps. In first step only static analysis is
performed and results are saved and plotted for static analysis. In second stage the
damping factors are defined and added mass at upstream nodes is added and
acceleration time history is defined. The Finite element software considers the static
displacements as initial displacements and dynamic analysis by Newmaark method is
performed for predefined time steps at the interval of 0.020 seconds. The results are
generated at each time step in the form of displacements, direct stresses, principal
stresses and effective stresses.
500
400 Horizontal PGA=0.38g
Acceleration (cm/sec2)--->
300
200
100
0
-100
-200
-300
-400
-500
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45
300
Vertical PGA=0.24g
200
Acceleration (cm/sec2)--->
100
-100
-200
-300
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45
Time (s)--->
Fig. 14: Acceleration Time History along Horizontal and Vertical Directions
RESULTS
Results are plotted in the form of displacement time history in both directions at
selected nodes and element stress history in high stressed zones. The maximum and
minimum principal stress envelopes for dambody by taking the principal stresses at the
47
Page 47
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
centroid of each element are plotted to know the overall distribution of tensile and
compressive stresses. The results are presented for one Earthquake load combination
E. Node displacement histories under normal operating condition with earthquake is
plotted for node 1 at upstream top point of the dam in both horizontal and vertical
directions as shown in Fig.15. The maximum horizontal displacement nearly 2 cm and
vertical displacement 1.3 cm are found to have taken place at node 1.
The maximum and minimum principal stress time histories are plotted at the centroid of
selected elements to know the stress variation during earthquake. Figs.16-17 show the
variation of maximum and minimum principal stress at the centroid of elements
13- 15. The maximum principal stress (tensile) of the order of 40 kg/cm2 is found to be
developed at the centroid of element 15 and minimum principal stress (compression) of
the order of 64 kg/cm2 is also found to be developed at the centroid of element 15.
The envelope of maximum and minimum principal stresses is plotted by taking the
principal stresses at centroid of each element in the dambody. The pattern of the tensile
and compressive stress distribution is used in assessing the safety of the dam by
comparing the calculated stresses with allowable stresses under different loading
conditions.
48
Page 48
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
Fig.16: Variation of Maximum Principal Stress with time for selected elements
Fig.17: Variation of Minimum Principal Stress with time for selected elements
Fig.18 shows the envelope of maximum and minimum principal stresses. The maximum
principal stress (tension) of the order of 40 kg/cm2 is found to be developed near the
49
Page 49
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
slope starting point at downstream face near to top of the dam. The tensile stresses
almost cover 80% area of the dam under the complete acceleration time history. The
tensile stresses developed under Normal operating condition with earthquake are more
than the allowable limits. The maximum compression of the order of 64 kg/cm2 is also
found to develop at the same location. Also the compressive stresses developed almost
cover 100% area of the dam under the complete acceleration time history. The
maximum compressive stress developed is not excessive and remains within allowable
limit. The principal stresses are higher on upstream and downstream faces of the dam
body as compared to central region.
40
36 -2
32 -6
-10
28
-14
24 -18
-22
20
-26
16
-30
12 -34
-38
8
-42
4 -46
0 -50
-54
Fig. 18: Envelope of Max. and Min. Principal Stresses under Load combination E
50
Page 50
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
both direction by applying trapezoidal rule for the time integration of the modal
response. Modal damping varying from 5-10% has been adopted in the analysis for
three modes.
RESULTS
Results are plotted in the form of displacement time history in both directions at
selected nodes and element stress history in high stressed zones. The maximum and
minimum principal stress envelopes for dambody by taking the principal stresses at the
centroid of each element are plotted to know the overall distribution of tensile and
compressive stresses. The results are presented for one Earthquake load combination
E. Node displacement histories under normal operating condition with earthquake is
plotted for node 1 in both horizontal and vertical directions as shown in Fig.19. At node
1, the maximum horizontal displacement nearly 3.8 cm and vertical displacement 1.8
cm are found developed.
The maximum and minimum principal stress time histories are plotted at the centroid of
selected elements to know the stress variation during earthquake. Figs.20 shows the
variation of maximum principal stress at the centroid of elements 16- 18.
51
Page 51
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
Fig.20: Variation of Maximum Principal Stress with time for selected elements
Figs.21 shows the variation of minimum principal stress at the centroid of elements
22- 24.
Fig.21: Variation of Minimum Principal Stress with time for selected elements
52
Page 52
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
Fig. 22: Envelope of Max. and Min. Principal Stresses under Load combination E
dams by Dr. AK Chopra, USA and by adopting same mathematical model excluding
foundation part as used for earlier analysis and is shown in fig 23.
54
Page 54
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
39
-2
36
-6
33
-10
30
-14
27 -18
24 -22
21 -26
18 -30
-34
15
-38
12
-42
9
-46
6 -50
3 -54
For old dams, stability evaluation by static and pseudodynamic stress analysis
using in-situ material properties is carried out as per BIS criteria by finite element
method for small dams lying in seismic zone II and III.
The pseudodynamic approach is generally used for small height dam (less than
30m) and for seismic zone II & III. This approach is also applied at the initial
55
Page 55
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
stages of design to finalize the profile of dam section and in 3 Dimensional stress
analysis to economies the cost.
The detailed dynamic analysis should be carried out for dams lying in high
seismic zones IV and V irrespective of height.
Starting point
2 Pseudodynamic 19.065 -32.675 Toe
of U/S slope
56
Page 56
31 INDUCTION TRAINING PROGRAM
Induction Training Program (ITP) for the newly appointed officers of Central Water Engineering (Group 'A') Services.
REFERENCES
1. Burman A., Maity, D. and Sreedeep, S. (2010). ‘Iterative Analysis of Concrete
Gravity Dam-Nonlinear Foundation Iteration’, International Journal of Engineering
Science and Technology, 2(4), 85-99.
2. Clough R.W. and Joseph, P. (1975). ‘Dynamics of Structures’, Mc-Graw Hill Book
Company Inc, 336-338.
3. ICOLD (1978). ‘Finite Element Methods in Analysis and Design of Dams’, Bulletin
30, 20-23
4. IS 1893: 2002 Part-I, ‘Criteria for Earthquake Resistant Design of Structure’, Bureau
of Indian standards , New Delhi
8. USBR (2008). ‘State-of-Practice for the Nonlinear Analysis of Concrete Dams at the
Bureau of Reclamation, Reclamation’, Managing Water in the West, 11-19.
57
Page 57
31 INDUCTION TRAINING PROGRAM 30 ITP
Overview of Dams
Basic Concept
Types of Dams
• Gravity Dams
• Arch Dams
• Buttress Dams
• Earthen Dams
• Rock fill Dams
• Steel Dams
• Timber Dams
• Rubber Dams
• Arch Dams
77
• Buttress Dams
• Earthen Dams
78
• Steel Dams
Timber Dams
79
Rubber Dams
80
ROR Scheme
ROR stands for Run-of-River scheme
In ROR scheme, the water is stored during low power demand, which is utilized
during high power demand.
Run-of-River projects are constructed where no storage or a limited amount of
storage is available.
82
Rigid Dam
Made of stone, masonry, concrete, steel, or timber
Non-rigid Dam
Made of earth, rock fill etc.
Composite Dam
Earthen dams are provided with a stone masonry or concrete overflow (spillway)
section
Loads on Dams
Dead loads
Reservoir and Tail water loads
Uplift pressures
Earthquake forces
As per IS :1893 -1984
Inertial forces of dam body and hydrodynamic forces
Silt pressure
Ice pressure (for freezing conditions)
Wave loads
Thermal stresses
83
Dead Loads
Self weight
Weight of other structures on dam body
Spillway piers
Gates
Bridge, etc.
Unit weigths
Plain Concrete : 2400 kg/m3
Reinforced Concrete : 2500 kg/m3
Masonry : 2300 kg/m3
Uplift Loads
Act over 100% of the area
Uplift pressures are not affected by earthquakes
84
H FOUNDATION GALLERY
GROUT CURTAIN
L LINE OF DRAIN
Wh Wh
WH WH
W[h +1/3(H-h)]
Earthquake Loads
Determined as per IS :1893 -2002
Design Seismic Coefficient is worked out as per the above code based on the location
of the project on the seismic map of India
85
Load Combinations
Combination A (Construction condition)
Dam completed but no water in reservoir and no tail water
Combination B (Normal operating condition)
Full reservoir elevation, normal dry weather tail water, normal uplift and silt.
Combination C (Flood Discharge condition)
Reservoir at maximum flood pool elevation, all gates open, tail water at flood
elevation, normal uplift and silt
Combination D
Combination A with earthquake
Combination E
Combination B with earthquake
Combination F
Combination C but with extreme uplift (Drains inoperative)
Combination G
Combination E but with extreme uplift (Drains inoperative)
Stability Analysis
Stability analysis is done as per IS: 6512-1984 titled “Criteria for Design of Solid
Gravity Dam”
Dam shall be safe against sliding at any section
In the dam
At dam foundation interface
Within the foundation
Safe unit stresses in concrete/masonry shall not be exceeded
Dam shall be safe against overturning
Freeboard
Free Board is the vertical distance between the top of the dam and the still water level
Free Board calculations are carried out as per IS: 6512-1984 to fix the top of dam
Free board shall not be less than 1m above MWL
Galleries
Provided for various purposes like curtain grouting, drainage, inspection,
86
instrumentation etc.
Can run in longitudinal or transverse directions
Additional inspection / drainage galleries are generally provided after every 30 metre
height
General size 1.5m x 2.25m or 2.0m x 2.5m
Generally provided at a distance equal to 5% of the head or 3m whichever is more
from the u/s face of the dam
Minimum concrete cover between the foundation rock and the gallery is kept about 2
to 3 m
Sump well and pump chamber arrangements are provided for collecting and removal
of seepage water
Galleries
Contraction Joints
Longitudinal Contraction Joints – not preferred
Transverse Contraction Joints
Spacing 15 to 25 m
Grouted / Ungrouted
With / without keyways
87
Water stops are installed in the joints near the upstream face to prevent passage of
water through contraction joint
Types of water stops:
PVC Water Stops
Metal Water Stops
Rubber Water Stops
Thermal Studies
The heat generated due to hydration of cement raises the temperature of concrete far
above the placement temperature.
To restrict the rise in temperature measures like pre-cooling, post-cooling or a
combination of both techniques is adopted
For determining the placement temperature of concrete detailed temperature control
studies are carried out
Necessary guidelines are available in BIS 14591 – 1999 “Guidelines for temperature
control of mass concrete for dams”.
Use of ice or refrigerated water and pre-cooled aggregate for concrete preparation
Embedding copper pipes for flow of cool water after placing of concrete
Use of low heat cement, Pozzolana Portland cement, Portland slag cement, etc.
Controlling the amount of cement used
Use of shallow lifts (limiting lifts to 1.5m)
Keeping suitable time interval between successive lifts (normally 3 days)
Homogeneous Embankment
Dam section entirely consists of almost one type of material.
Section is made of low permeability material and requires flatter slopes than a
zoned section
Zoned Embankment
This type of embankment uses two or more types of materials, depending on their
availability, utility and costs
There is an impervious zone called the ‘core’ inside the dam section
88
The outer zones on both sides, called ‘shells’, should preferably be of pervious
materials
Rock-fill Dams with clay cores
Relies on fragmented rock material, either obtained by blasting or available as
natural boulder deposits, as a major structural element
Substantial rock fill zones on both sides, with an impervious zone in the middle,
and transition zones and /or filters in-between
Rock-fill Dams with u/s Face Membranes
Relies on fragmented rock material, either obtained by blasting or available as
natural boulder deposits, as a major structural element
Substantial rock fill zones on both sides, with an impervious membrane on
upstream and downstream face
89
Concrete/Masonry Dam
23 12966 Code of practice for galleries and other openings in dams: Part 1 General
requirements
24 12966 Code of practice for galleries and other openings in dams: Part 2 Structural
design
91
92
93
A.K. Nayak,
SE(HOC), CWC,
Bhubaneswar
1.0 Introduction
Conventional concrete dams are constructed by dividing the dam length into
blocks of 20-25m long. Concrete placement is done by cableways, cranes,
trestles etc. in lifts of 1.5-2m. The compaction of concrete is done by vibrators.
Roller compacted concrete dams are constructed using same
machinery/equipments as that used for embankment dams. Construction is
done from abutment to abutment in lifts of 300-600 mm. Compaction of
concrete is done with the help of vibratory rollers.
Masonry dams were preferred in our country earlier as they were labour
intensive, provided more employment opportunities, consumed less cement
and did not involve any temperature control measures. However the quality
of workmanship and workers are deteriorating now. There are problems of
heavy seepage through many of our existing masonry dams. For seepage
control, various remedial measures are being adopted these days, viz.
guniting on upstream face, upstream concrete membrane, sandwich concrete
membrane, prepacked masonry construction etc. Now-a-days, there is
therefore a shift in favour of concrete dams. Further, the construction of
concrete dams is faster vis-à-vis masonry dams.
2.0Gravity Dam
Gravity dams may be straight or curved in plan depending upon the axis
alignment. For uniformity, certain general dimensions and definitions have
been established and are defined as below:
The hydraulic height is the difference in elevation between the lowest point of
the original streambed at the axis of the dam and the maximum controllable
water surface.
The length of the dam is defined as the distance measured along the axis of the
dam at the level of the top of the main body of the dam from abutment
contact to abutment contact including the length of spillway if it lies wholly
within the dam. However, the length of the abutment spillway located in any
area especially excavated for the spillway is not included in the length of the
dam.
The volume of a concrete dam includes the main body of the dam and all mass
concrete appurtenances cot separated from the dam by construction or
contraction joints.
The axis of the dam is a vertical reference plane usually defined by the
upstream edge of the top of the dam.
Maps and photographs are of prime importance in the planning and design of
a concrete dam and its appurtenant works. From these data an evaluation of
alternative layouts can be made preparatory to determining the final location
of the dam, the type and location of its appurtenant works and the need for
restoration and/or development of the area.
i) A general map locating the area within the State, together with
district and township lines.
ii) Map showing existing towns, highways, roads, railways and
shipping points
iii) A vicinity map showing the following details:
iv) Site topography covering the area of dam, spillway, outlet works,
diversion works, construction access and other facilities
Dam designs and reservoir operating criteria are related to reservoir capacity
and anticipated reservoir operations. The loads and loading combinations to
be applied to the dam are derived from the several standard reservoir water
surface elevations. Reservoir capacity and reservoir operations are used to
properly size spillway and outlet works.
Reservoir design data required for the design of dam and its appurtenant
works are:
Climate conditions at a site affect the design and construction of the dam.
Measures to be employed during construction to prevent cracking of concrete
are related to ambient temperatures at site.
1) Sources of aggregate
2) Water for construction purposes
3) Results of sampling, testing and analysis of construction materials
4) Information on potential sources of soils, sand and gravel to be
used for backfill, road surface, protection of slope etc.
The following factors should be considered in selecting the best site out of
several alternatives:
Non-overflow section
Overflow section
Shear Tests
- Direct shear
- Triaxial Shear
- Sliding friction
Other Tests
- Solubility
- Petrographic Analysis
The following are the basic requirements of stability for a gravity dam:
4. Earthquake forces
5. Silt pressures
6. Ice pressure
7. Wave pressure
8. Thermal loads, if applicable
Dead Loads
Self weight of dam and weight of appurtenant works such as, spillway piers,
gates, hoists, spillway bridge etc. are considered for computing the dead
loads. The unit weights adopted in preliminary designs are 2.3 t/m3 for
masonry and 2.4 t/m3 for concrete.
Silt Pressures
The deposited silt may be taken as equivalent to a fluid exerting a force with a
unit weight 0.36 t/m3 in horizontal direction and 0.925 t/m3 in vertical
direction. Thus the horizontal silt and water pressure is determined as if silt
and water have a horizontal unit weight of 1.36 t/m3 and vertical silt and
water pressure is determined as if silt and water have a vertical unit weight of
1.925 t/m3.
Uplift Pressures
Water seeping through the pores, cracks and fissures of the foundation
material, and water seeping through the body of the dam exert an uplift
pressure on the base of the dam. It is assumed to act over 100% of the area of
base and assumed to vary linearly from upstream to downstream
corresponding to water heads. However, in case drainage galleries are
provided, there is a relief of uplift pressure at the line of drain equal to two-
thirds the difference of the hydrostatic heads at upstream and downstream. It
is assumed that uplift pressures are not affected by earthquakes.
αh = βIαo
where,
α h = β I FoSa/g
where,
The design vertical seismic coefficient is taken as half the design horizontal
seismic coefficient.
The basic work in this regard has been done by Westergaard. Subsequently
Zanger in 1952 presented formulas for computing hydrodynamic pressures
p = Csα h wh
where,
Cm y y y y
Cs = 2 − + 2 −
2 h h h h
where,
The approximate values of total horizontal shear and moment about the
center of gravity of a section due to hydrodynamic pressure are given by the
relations :
Vh = 0.726 py
Mh = 0.299 py²
where
Vh = hydroldynamic shear in kg/m at any depth, and
Mh = moment in kg.m/m due to hydrodynamic force at any depth y.
where,
The design horizontal seismic coefficient is calculated using the above time
period and for a damping of 5% from the average acceleration spectra given
in IS:1893.
The basic shear and moment due to the horizontal inertia forces is obtained by
the formulae given below:
The vertical inertia forces are calculated using the same distribution as
outlined in seismic coefficient method but using the seismic coefficient as
calculated above.
1. Concrete
2. Masonry
The partial factors of safety against sliding as per IS:6512 are given below:
Loading Fφ Fc
Condition
For dams and the For foundation
Contact plane with Thoroughly Others
Foundation investigated
A,B,C 1.5 3.6 4.0 4.5
D,E 1.2 2.4 2.7 3.0
F,G 1.0 1.2 1.35 1.5
The factor of safety against sliding shall be computed from the following
equation and it shall not be less than 1.0.
(W – U) tan φ + c.A
F= Fφ Fc
P
Where,
7.0 Freeboard
Free Board is the vertical distance between the top of the dam and the still
water level. Freeboard is computed from the following two considerations:
It is equal to wind set up plus 1 1/3 times the wave height above FRL or
above MWL (corresponding to design flood) whichever gives higher dam top
level. A minimum freeboard of 1m above MWL corresponding to design
flood shall be available. If design flood is not equal to PMF then the top of
dam should be at least equal to MWL corresponding to PMF. At least 1m high
solid parapet is to be provided, not withstanding the above requirements.
Operation considerations
IS:11223 specifies the following:
The freeboard as specified in IS: 6512 shall be available at FRL and MWL
corresponding to all bays operative condition. For gated spillways a
contingency of 10% of gates (min. one gate) being inoperative is considered as
an emergency. A reduced freeboard may be acceptable under the emergency
condition. The dam shall not be allowed to overtop in any case.
Design of Spillways
A.K. Nayak
SE(HOC), CWC,
Bhubaneswar
1.0 GENERAL
Spillway is a safety valve provided in the dam to dispose of surplus flood waters from a
reservoir after it has been filled to its maximum capacity i.e. Full Reservoir Level.
The importance of safe spillways needs no over-emphasis as many failures of dams have
been caused by improper design of spillways or spillways of insufficient capacity
especially in case of earth and rockfill dams which are susceptible to breaching, if
overtopped. Concrete/Masonry dams can withstand moderate overtopping but this
should be avoided.
Further, the spillway must be hydraulically and structurally adequate and must be so
located that the overflowing discharges do not erode or undermine the downstream toe
of the dam.
The spillway design flood is generally determined by transposing great storms which
have been known to occur in the region over the drainage area. The resulting flood
hydrographs are then determined by rational methods. In determining the discharge
capacity consideration should be given to all possible contingencies, e.g. one or more
gates being inoperative.
IS : 11223 – 1985 provides guidelines for fixing spillway capacity. Inflow design flood for
the safety of the dam is guided by the following criterion:
The dams may be classified according to size by using the hydraulic head and the gross
storage behind the dam as given below. The overall size classification for the dam
would be the greater of that indicated by either of the following two parameters:
The inflow design flood for safety of the dam would be as follows:
Floods of larger or smaller magnitude may be used if the hazard involved in the
eventuality of a failure is particularly high or low. The relevant parameters to be
considered in judging the hazard in addition to the size would be:
For more important projects dam break studies are done as an aid to the judgement in
deciding whether PMF needs to be used. Where the studies or judgement indicate an
imminent danger to present or future human settlements, the PMF should be used as
design flood.
It is the flood that may be expected from the most severe combination of hydrological
and meteorological factors that are considered reasonably characteristic of the region
and is computed by using the Standard Project Storm (SPS). While transposition of
storms from outside the basin is permissible, very rare storms which are not
characteristic of the region concerned are excluded in arriving at the SPS rainfall of the
basin.
It is the flood that may be expected from the most severe combination of critical
meteorological and hydrological condition that are reasonably possible in the region and
is computed by using the Probable Maximum Storm (PMS) which is an estimate of the
physical upper limit to maximum precipitation for the basin. This is obtained from the
transposition studies of the storms that have occurred over the region and maximizing
them for the most critical atmospheric conditions.
The process of computing the reservoir storage volumes and outflow rates
corresponding to a particular hydrograph of inflow is known as flood routing. It is used
for arriving at the MWL for the project. The relationship governing the computation is
essentially simple – over any interval of time the volume of inflow must equal the
volume of outflow plus the change in storage during the period. If the reservoir is rising,
there will be increase in storage and change in storage will be positive, if the reservoir is
falling, there will be decrease in storage and the change in storage will be negative.
For an interval of time ∆t, the relationship can be expressed by the following expression:
I .∆t − O.∆t = ∆S
Where,
I = Average rate of inflow during time equal to ∆t
O = Average rate of outflow during time equal to ∆t
∆S = Storage accumulated during time equal to ∆t
The following three curves are required for carrying out the computations:
c) The rating curve showing the total rate of outflow through outlets and over
the spillway against various reservoir elevations
Flood routing in gated spillways is generally carried out assuming the flood to impinge
at FRL assuming inflow equal outflow to at that level. For ungated spillways this would
correspond to the spillway crest or a little above this.
This method gives quite reliable results, provided the chosen time interval is sufficiently
small, so that the mean of the outflow rates at the start and the end of the interval may be
taken as the average throughout the interval.
This method arranges the basic routing equation as below so that the knowns are placed
on the left side and unknowns are placed on the right side of the equation.
I 1 + I 2 S1 O1 S 2 O2
+ − = +
2 ∆t 2 ∆t 2
Since this equation contains two unknowns it cannot be solved unless a second
independent function is available. In the modified Puls method, a storage-indication
curve viz. outflow O versus the quantity (S/∆t+O/2) is constructed for the purpose.
In the above equation, it may be noted that subtracting O2 from (S2/∆t+O2/2) gives
(S2/∆t-O2/2). This expression is identical to (S1/∆t-O1/2) on the left side of the equation
except for the subscripts. Since the subscript 1 denotes values at the beginning of a time
increment and subscript 2 denotes values at the end of a time increment, it is apparent
that (S2/∆t-O2/2) at the end of one time increment is numerically equal to (S1/∆t-O1/2)
for the beginning of the succeeding time increment.
i) Compute the numerical value of left side of the equation for given values of I1, I2,
S1 and O1 for the first time increment.
ii) With this numerical value, which equals (S2/∆t+O2/2), refer storage-indication
curve and read outflow O2 corresponding to this computed value of
(S2/∆t+O2/2). The O2 thus read is the instantaneous outflow at the end of the first
time increment.
iii) Subtract this value of O2 from (S2/∆t+O2/2), which gives the value for (S2/∆t-
O2/2). The value of (S1/∆t-O1/2) for the second time increment is equal to (S2/∆t-
O2/2) for the first time increment. Consequently the left side of the equation can
be computed for the second time increment and the entire procedure is repeated.
The overfall type is by far the most common and is adapted to masonry dams that have
sufficient crest length to provide the desired capacity.
This type comprises a control weir which is ogee or S-shaped. The ogee shape conforms
to the profile of aerated lower nappe from a sharp crested weir. The upper curve at the
crest may be made either broader or sharper than the nappe. A broader curve will
support the sheet and positive hydrostatic pressure will occur along the contact surface.
The support sheet thus creates a backwater effect and reduces the coefficient of
discharge. The sharper crest on the other hand creates negative pressures, increases the
effective head and thereby the discharge.
Low crested spillways with either breast wall or sluice type arrangements are now
increasingly being provided for flushing out the silt and controlling the silt entry in the
power intake which is kept above the spillway crest. These spillways are called orifice or
sluice spillways (See figures below).
The orifice spillways have the advantage of having high discharging capacity due to the
high water head. At sites where only a limited area and relatively short length of suitable
foundation material are available for the spillway structure, the orifice spillway offers
the most economic means of passing the design flood. However, the orifice spillways
result in high flow concentration, which increases the size and cost of energy dissipation
work below.
Orifice spillways are being provided in many of our diversion dams recently in rivers
carrying heavy silt load. The power intake is kept above the spillway crest and as close
to the spillway as possible. This kind of spillway arrangements thus performs the dual
function of passing the flood and managing the sediment in the reservoir.
Examples of spillways with breast wall type arrangements are in Ranganadi H.E. Project
(Arunachal Pradesh), Chamera H.E. Project Stage-I (Himachal Pradesh), Rangit H.E.
Project Stage-III (Sikkim) etc. and that of sluice spillways are in Tala H.E. Project
(Bhutan), Nathpa Jhakri H.E. Project (Himachal Pradesh), Myntdu H.E. Project Stage-I
(Meghalaya) etc.
A spillway where discharge is conveyed from the reservoir to the downstream river
through an open channel or chute along a dam abutment or through a saddle is called a
chute or trough spillway. The chute is the commonest type of water conductor used for
conveying flow between control structures and energy dissipators. Chute can be formed
on the downstream face of gravity dams, cut into rock abutments and either concrete-
lined or left unlined and built as free-standing structures on foundations of rock or soil.
These are mostly used with earth/rockfill dams and have the following main
advantages:
i) Simplicity of design
ii) Adaptability to all types of foundations and
iii) Overall economy by using large amount of spillway excavation in dam
construction
Examples of chute spillways are Beas Dam, Ram Ganga Dam, Kolar Dam, Tehri Dam etc.
The distinctive feature of side channel spillway which distinguishes it from chute
spillway is that whereas in the chute spillway the water flows at right angle to the axis of
the dam, in the side channel spillway, the flow is initially in a channel parallel to the axis
of the dam and thereafter it flows in a discharge channel at approximately right angle to
the dam axis.
This type of spillway is suited to narrow canyons with steep sides which rise to a
considerable height above the dam. This type of spillway is also provided at sites where
the overfall type is ruled out for some reason and where saddle of sufficient width is not
available to accommodate a trough (chute) type spillway. It is assumed that all the
energy of the overfalling water is dissipated in turbulence in the side channel. Example
of side channel spillway is Pancheshwar Project.
In this type of spillway water enters over the lip of a horizontal circular crest and drops
through a vertical or sloping shaft and then flows downstream through a horizontal
conduit or tunnel. The spillway is suitable to dam sites in narrow canyons where room
for a spillway restricted.
In some instances advantage of the existing diversion tunnel has been taken for
conversion into tunnel spillway. A disadvantage of this type is that the discharge beyond
a certain point increases only slightly with increased depth of overflow and therefore
does not give much factor of safety against underestimation flood discharge as
compared to the other types.
Examples of Tunnel/Shaft spillways are Tehri Dam, Itaipau Dam etc. A typical
Tunnel/Shaft Spillway is shown in figure below:
Siphon spillways are based on the principle of siphonic action in an inverted bent pipe.
If such pipe is once filled with water, it will continue to flow so long as the liquid surface
is higher than the lower leg of the pipe unless of course, the upper leg gets exposed
earlier.
Siphon spillways are often superior to other forms where the available space is limited
and the discharge is not extremely large. They are also useful in providing automatic
surface-level regulation within narrow limits. The siphon spillways prime rapidly and
bring into action their full capacity. Therefore, they are especially useful at the power
house end of long power channels with limited forebay capacity where a considerable
discharge capacity is necessary within a very short time in order to avoid overflow of the
channel banks.
However, siphon spillways are not very common mainly because of:
i) Possibility of clogging of the siphon passage way and siphon breaker vents
with debris, leaves etc.
ii) The occurrence of sudden surges and stoppages of outflow as a result of the
erratic make and break action of the siphon, thus causing fluctuations in the
downstream river stage.
iii) The release of outflows in excess of reservoir inflows whenever the siphon
operates, if a single siphon is used. Closer regulation which will more nearly
balance outflow and inflow can be obtained by providing a series of smaller
siphons with their siphon breaker vents set to prime at gradually increasing
reservoir heads.
iv) Vibration disturbances which are more pronounced than in other types of
spillways.
Overfall ogee spillway has its overflow profile conforming, as nearly as possible, to the
profile of the lower nappe of a ventilated jet of water over a sharp crested weir. These
spillways are classified as high and low depending on whether the ratio of height of the
spillway crest measured from the river bed to the design head is greater than or equal or
less than 1.33 respectively. In the case of high overflow spillways the velocity of
approach head may be considered negligible.
Upstream Quadrant
The upstream quadrant of the crest may conform to the ellipse:
2 2
X 1 Y1
+ = 1
1 B1
A
The magnitude of A1 and B1 are determined from the graph P/Hd vs A1/Hd and B1/Hd
respectively in fig.2 of IS:6934, where,
Hd = Design Head
Downstream Quadrant
The downstream profile of the crest may conform to the equation:
= K 2 .H d
1.85 0.85
X2 .Y2
The magnitude of K2 is determined from the graph P/Hd vs K2 in fig.2 of IS:6934.
In the case of sloping upstream face, the desired inclination of the face is fitted
tangentially to the elliptical profile described under (i) above, with the appropriate
tangent point worked out from the equation. The profile of the downstream quadrant
remains unchanged.
Figure 2 – IS:6934
Whenever structural requirements permit, removal of some mass from the upstream face
leading to offsets and risers as shown in fig.1 of IS:6934 results in economy. The ratio of
risers M to the design head Hd i.e. M/Hd should be at least 0.6 or larger, for the flow
condition to be stable. The shapes of u/s and d/s quadrants defined for spillways with
vertical upstream face are also applicable to overhanging crests, for the ratio M/Hd > 0.6.
The net length of overflow crest is reduced due to contraction caused by abutment and
crest piers. The effective length L of the crest may be calculated as follows:
L = L' − 2 H ( N .K p + K a )
where,
L’ = Overall length of the crest excluding piers
H = Head over crest
N = Number of piers
Kp = End contraction coefficient of piers
Ka = End contraction coefficient of abutment
The pier contraction coefficient, Kp is affected by the shape and location of the pier nose,
thickness of pier, the actual head in relation to the design head and the approach
velocity. The average pier contraction coefficients may be taken as follows:
Type Kp
The abutment contraction coefficient, Ka is affected by the shape of the abutment, the
angle between the upstream approach wall and the axis of flow, the actual head in
relation to the design head and the approach velocity. The average abutment coefficient
may be taken as follows:
Type Ka
Fig. 3 of IS:6934 gives the coefficient of discharge C for the design head as a function of
approach depth and inclination of upstream face of the spillway. These curves can be
used for preliminary design purposes.
Fig. 4 of IS:6934 gives the variation of coefficient of discharge as a function of ratio of the
actual head to the design head (i.e. H/Hd). This curve can be used to estimate C for
heads other than design head.
The coefficient of discharge is reduced due to submergence by the tail water. The
position of the downstream apron relative to the crest level also has an effect on the
discharge coefficient. Fig. 5A and 5B of IS:6934 give the variation of C with the above
parameters.
When the ogee crest is formed to a shape differing from the ideal shape or when the crest
has been shaped for a head larger or smaller than the one under consideration, the
coefficient of discharge will differ.
A design head grater than the actual head will push the crest surface into the theoretical
nappe and result in greater pressure along the curved surfaces and in lower discharge
capacities. Conversely, a design head lower than the actual head pulls the crest surface
below the theoretical nappe, resulting in sub-atmospheric pressures over some portion
of the crest curve. At the same time the discharge capacity of such a crest curve is
increased.
Designing the crest shape to fit the nappe for a head less than maximum head expected
often results in economies in construction. The resulting increase in unit discharge may
make possible a shortening of the crest length, or a reduction in freeboard allowance for
reservoir surcharge under extreme flood conditions.
Because the occurrence of design floods is usually so infrequent, the spillway crests are
fitted to the lower nappe of a head which is 75% of that resulting from the actual
discharge capacity. Tests have shown that the sub-atmospheric pressures on a nappe-
shaped crest do not exceed about half of the design head when the design head is not
less that about 75% of the maximum head. An approximate diagram of the sub-
atmospheric pressures, as determined from model tests, is shown by figure. The design
head is normally kept as 80% to 90% of the maximum head corresponding to MWL.
The minimum crest pressure must be greater than cavitation pressure. It is suggested
that the minimum pressure allowable for design purposes be 20ft of water below sea
level atmospheric pressure and that the altitude of the project site be taken into account
in making the calculation. For example, assume a site where the atmospheric pressure if
5ft of water less than sea level pressure, and in which the maximum head contemplated
is 60ft; then, only 15 additional feet of sub-atmospheric pressure is allowable.
The waters flowing down the spillway have very high energy. The same if not dissipated
can cause considerable erosion/scour downstream which can endanger the dam stability.
It is, therefore, necessary to provide adequate downstream protection work or energy
dissipation arrangements (EDA) for dissipating the energy downstream of the spillway
and minimize erosion of natural river bed.
As per IS : 11223 – 1985 “Guidelines for fixing spillway capacity”, the energy dissipation
works should be designed for a flood which may be lower than the inflow design flood
for the safety of the dam. The E.D.A. should be designed to work most efficiently for
dominant floods. The designs are invariably checked for lower discharges which would
correspond to various percentages of the dominant flood.
The problem of designing energy dissipators is one essentially of reducing the high
velocity of flow to a velocity low enough to minimize erosion of downstream river bed.
This reduction in velocity may be accomplished by any or a combination of the
following, depending upon the head, discharge intensity, tail water conditions and the
type of the bed rock or the bed material.
These are one of the most efficient and commonly adopted Energy Dissipation
Arrangements. In stilling basins, the energy is dissipated through the well known
phenomenon of hydraulic jump which is the most effective way of dissipating the energy
of flowing water. The simplest kind of protection could be used if a jump would form at
all stages on a horizontal floor, at the stream-bed level, extending from the dam to the
downstream end of the jump. The height of the tail water for each discharge seldom
corresponds to the height of a perfect jump. In some cases the sloping apron will permit a
hydraulic jump to form at proper depth within the limits of the apron throughout the
entire range of spillway discharges and corresponding tail water depths.
IS : 4997 – 1968 (reaffirmed 1995) gives the criteria for design of hydraulic jump type
stilling basins with horizontal and sloping aprons.
32
When the tail water rating curve approximately follows the hydraulic jump curve or is
slightly above or below it, then hydraulic jump type stilling basin with horizontal apron
provides the best solution for energy dissipation. In this case the requisite depth may be
obtained on an apron near or at the ground level which is quite economical. For spillways
on weak bed rock and weirs and barrages on sand or loose gravel, hydraulic jump type
stilling basins are recommended.
Hydraulic Jump type stilling basins with horizontal apron may be classified into the
following two categories:
a) Stilling basin in which the Froude number of the incoming flow is less than 4.5.
This case is generally encountered on weirs and barrages. The basin is called
Basin-I.
b) Stilling basins in which the Froude number of the incoming flow is greater than
4.5. This case is generally encountered in dams. This basin is called Basin-II.
Design Criteria
Factors involved in the design of stilling basins include the determination of the elevation
of the basin floor, the basin length and basin appurtenances.
Knowing HL and q; Dc, D1 and D2 can be determined from the following formulae or
from fig.7 of IS:4997:
(D2 − D1 ) 3 q2
1/ 3
HL = Dc =
4 D1 D2 g
2
D1 2q 2 D1
D2 = − + +
2 D1 g 4
where,
HL = Head Loss
33
D1 = Prejump depth
D2 = Post jump depth
q = Discharge per unit length
g = Acceleration due to gravity
Having obtained D1 & D2, the elevation of basin floor may be calculated.
Basin – I
Requirements of basin length, depth and appurtenances for basin-I are as under:
Basin Length and Depth: Length of basin may be determined from the curve in Fig. 8A
of IS:4997. The basin is provided with an end sill preferably dentated one. In the boulder
reach the sloping face of the end sill is generally kept on the upstream side. Generally the
basin floor should not be raised above the level required from sequent depth
consideration. If the raising of the floor becomes obligatory due to site conditions, the
same should not exceed 15% of D2 and the basin in that case should be further
supplemented by chute blocks and basin blocks. The basin blocks should not be used if
the velocity of flow at the location of basin blocks exceeds 15 m/s and in that case the
floor of the basin should be kept at a depth equal to D2 below the tail water level. The
tail water depth should not generally exceed 10% of D2.
34
Basin Appurtenances: Requirements for basin appurtenances, such as chute blocks, basin
blocks and end sill are as below:
a) Chute blocks: Height and top length of chute blocks should 2D1 while width should
be D1. The spacing of chute blocks should be kept as 2.5D1 and a space D1/2 should
be left along each side wall.
b) Basin blocks: Height of basin blocks in terms of D1 may be obtained from fig.9B of
IS:4997. Width and spacing should be equal to their height. A half space is
recommended adjacent to the walls. Upstream face of the basin blocks should be
vertical. The blocks should be set at a distance of 0.8D2 downstream from chute
blocks.
c) End sill: Height of the dentated end sill should be 0.2D2. Maximum width and spacing
should be 0.15D2. In the case of a narrow basin, the width and spacing can be reduced
but in the same proportion. A dent is recommended adjacent to each side wall.
Basin – II
Requirements for basin length, depth and appurtenances for Basin-II are as under:
Basin Length and Depth: Length of the basin will be determined from the curve in Fig.
9A of IS:4997. The basin should be provided with chute blocks and end sill. The
maximum raising of the basin floor shall not exceed 15% of D2 and basin in that case will
be further supplemented by basin blocks. However, when the velocity of flow at the
location of basin blocks exceeds 15 m/s, no basin blocks are recommended and in that
case the floor of the basin should be kept at a depth equal to D2 below the tail water level.
The tail water depth should not generally exceed 10% of D2.
35
Basin Appurtenances: Requirements for basin appurtenances, such as chute blocks, basin
blocks and end sill are as below:
a) Chute blocks: Height, width and spacing of chute blocks should be kept as D1. The
width and spacing may be varied to eliminate fractional blocks. A space D1/2 should
be left along each side wall.
b) Basin blocks: Height of basin blocks in terms of D1 may be obtained from fig.9B of
IS:4997. Width and spacing should be equal to three-fourth of the height. A half space
is recommended adjacent to the walls. Upstream face of the basin blocks should be
vertical. The blocks should be set at a distance of 0.8D2 downstream from chute
blocks.
When the tail water is too deep as compared to the sequent depth D2, the jet left at the
natural ground level would continue to go as a strong current near the bed forming a
drowned jump which is harmful to the river bed. In such a case, a hydraulic jump type
stilling basin with sloping apron should be preferred as it would allow an efficient jump
to be formed at suitable level on the sloping apron.
36
Hydraulic Jump type stilling basins with sloping apron may be classified into the
following two categories:
Basin – III: This is recommended for the case where tail water curve is higher than D2
curve at all discharges.
Basin – IV: This is recommended for the case where tail water depth at maximum
discharge exceeds D2 considerably but is equal to or slightly greater than D2 at lower
discharges.
Design Criteria
The slope and overall shape of the apron are determined from economic consideration,
the length being judged by the type and soundness of river bed downstream. The
following criteria should be used only as a guide in proportioning the sloping apron
designs.
Basin III
a) Assume a certain level at which the front of jump will form for the maximum tail
water depth and discharge.
b) Determine D1 from the known upstream total energy line by applying Burnoulli’s
theorem and calculate F1.
c) Assume a certain slope and determine the conjugate depth D’2 and length of jump
for the above Froude number from fig.5 and fig.3 of IS:6977 respectively. The
length of apron should be kept 60% of the jump length.
37
d) Compare the available tail water depth with D’2. If they do not match, change the
slope or the level of upstream end of the apron or both. Several trails may be
required for arriving at final figures.
e) The apron designed for maximum discharge may then be tested for lower
discharges, say 25%, 50% and 75% of maximum discharge. If the tail water depth
is sufficient or in excess of the conjugate depth for intermediate discharges, the
design is acceptable. If not, a flatter slope at the lower apron level should be tried
or Basin IV may be adopted.
f) The basin should be supplemented by a solid or dentate end sill of height 0.05 to
0.2D’2 with an upstream slope of 2:1 to 3:1.
38
Basin IV
a) Determine the discharge at which the tail water depth is most deficient.
b) For the above discharge, determine the level and length of horizontal portion of
apron by criteria for horizontal apron.
c) Assume a certain level at which the front of jump will form for the maximum tail
water depth and discharge.
d) Determine D1 from the known upstream total energy line by applying Burnoulli’s
theorem and calculate F1. Then find out the conjugate depth D2 from equation 3.3
of IS:4997.
e) Determine a suitable slope (by trial and error) so that the available tail water depth
matches the required conjugate depth D’2 determined from fig.6 of IS:4997.
39
f) Determine the length of jump for the above slope from fig.3 of IS:4997. If the
sum of the lengths of inclined and horizontal portion is equal to about 60% of the
jump length, the design is acceptable. If not, fresh trials may be done by changing
the level of upstream end of jump formation.
g) The basin should be supplemented by a solid or dentate end sill of height 0.05 to
0.2D2 with an upstream slope of 2:1 to 3:1.
An upturn solid roller bucket is used when the tail water depth is much in excess of the
sequent depth. The dissipation energy occurs as a result of formation of two
40
complementary elliptical rollers, one in bucket proper called the surface roller, which is
anti clockwise (if the flow is to the right) and the other downstream of the bucket called
the ground roller, which is clockwise.
Normally the invert level of a roller bucket is so fixed that the difference in the design
maximum tail water level and the invert level (d3) is between 1.1 to 1.4 times the sequent
depth (d2). It has been seen that a satisfactory energy dissipation is obtained when the
roller height (hb) is between 75 and 90 percent of the tail water depth (d3). If the
aforesaid two criteria are satisfied, then the surge height (hs) measured above the invert
level is 105 to 130 percent of the tail water d3, that is, hs/d3 = 1.05 to 1.3.
Charts at fig.4 and fig.5 of IS:7365 are used for determining the roller depth (hb) and the
surge height (hs) respectively.
41
The values given in fig.4 of IS:7365 shows the range of H1/R for which good roller
action can be expected. One formula which has been found to be widely applicable for a
bucket lip angle of 45o is as under:
R
= 8.26 X 10 − 2 + 2.07 X 10 −3 FD + 1.4 X 10 −5 FD
2
H1
where,
FD = Discharge parameter q
= X 10 3
3
H1 = Reservoir Pool Level – Bucket InvertgH
level
1
There are many other empirical formulae available for calculating the radius of bucket.
The bucket radius is chosen to fall within the recommended ranges (fig.4, IS:7365)
consistent with economical and structural considerations.
42
c) Bucket Lip
A flat topped lip tends to lower the jet after it leaves the lip and the size and strength of
the ground roller would reduce. This is not desirable from the point of view of prevention
of erosion near the lip. Therefore, a downstream slope of 1 in 10 or slightly steeper than
that may be given to the bucket lip. The width of the lip should not be more than one
tenth of the radius of bucket. However the minimum width may be kept as one metre.
A 45o bucket lip angle with the horizontal is generally found to be satisfactory for most
cases where the discharge parameter lies between 30 and 80.
This is an improvement over the solid roller bucket arrangement. In the slotted roller
bucket, a part of the flow passes through the slots, spread laterally and is lifted away from
the channel bottom by a short apron at the downstream end of the bucket. Thus the flow
is dispersed and distributed over a greater area resulting in a less violent flow
concentrations compared to those in a solid roller bucket. The height of boil is also
reduced in case of slotted roller bucket. The slotted roller bucket provides a self cleaning
action to reduce abrasion in the bucket.
Although a slotted roller bucket is an improvement over the solid roller bucket,
experience has shown that bucket teeth are vulnerable to damage on account of various
reasons like boulders rolling down the spillway, unsymmetric gate operation causing
heavy discharge intensities etc. Slotted roller buckets are not recommended in bouldery
stages of the river.
43
a) Bucket Radius
44
45
• Find the minimum tail water depth Tmin and maximum tail water depth Tmax from fig.9
and fig.10 respectively of IS:7365.
• Set such bucket invert elevation for which tail water elevations are between tail water
depth limits.
d) Tooth dimensions
• Width of tooth is kept as o.125R and spacing of tooth is kept as 0.05R, where R is the
radius of the bucket.
• Detailed tooth dimensions are given in fig.12A and fig.12B of IS:7365.
Model studies are desirable for confirming the design parameters. It shall be ensured that
the teeth perform cavitation free.
46
47
48
This bucket is used when the tail water depth is insufficient for the formation of hydraulic
jump and when the bed of the river channel downstream consists of sound rock capable of
withstanding the impact of high velocity jet. The flow coming down the spillway is
thrown away from the toe of the dam to a considerable distance downstream as a free
discharging upturned jet which falls on the channel bed downstream. There is no energy
dissipation within the bucket. The device is used mainly to increase the distance from the
structure to the place where the jet hits the channel bed. In the ski jump bucket, only part
of the energy is dissipated through interaction of the jet with the surrounding air. The
remaining energy is imparted to the channel bed below.
Design Criteria
The principal features of hydraulic design of trajectory bucket consist of the following:
a) Bucket shape
b) Bucket invert elevation
c) Bucket radius
d) Bucket lip elevation and exit angle
e) Trajectory length
f) Estimation of downstream scour
a) Bucket shape
The performance of the trajectory bucket is judged mainly by the trajectory height and
length of throw. Generally a circular shape is preferred from practical consideration.
This depends on the site and tail water condition. For a clear flip action, the lip should be
kept above the maximum tail water level. However this may not always be possible.
Some of the various considerations which are taken into account while fixing bucket
invert elevation are as under:
49
ii) A submergence of not more than 70% of the sequent depth over the lip of the
bucket
iii) A safe maximum submergence equal to critical depth over the bucket lip
elevation
An attempt is made to keep the bucket invert of the trajectory bucket as high as possible
consistent with economy. The hydraulic performance is normally verified in a model.
c) Bucket radius
The radius of bucket should not be less than 3 times the maximum depth of flow (d1)
entering the bucket to avoid separation tendency.
The formula generally used for determining the radius of bucket is as under:
R = 0.6to0.8 H .H 5
where,
H = Depth of overflow over the spillway crest
H5 = Reservoir Pool Elevation – Jet Surface
Elevation at bucket invert
The lip angle affects the horizontal throw distance. The factors affecting the horizontal
throw distance also include the initial velocity of the jet and the difference in elevation
between the lip and the tail water. Normally adopted lip angle is between 30o and 40o.
Greater the exit angle grater will be the distance of throw. However the jet impinges on
the tail water at a steeper angle which results in deeper scour. For submerged lips the
lower lip angle of 30o may be adopted to minimize sub-atmospheric pressures on the lip.
The lip shall be made flat in case tail water level is lower than the lip level. However, if
the tail water level is higher than the lip level, the lip shall slope downstream about 1 in
10. In some cases necessity of aeration may arise which may be finalized after model
studies.
e) Trajectory length
The following expression may be used for calculating the horizontal throw distance:
X Y
= Sin 2φ + 2Cosφ Sin 2φ +
Hv Hv
where,
X = Horizontal throw distance from bucket lip to the
centre – point of impact with tail water
Y = Difference between the lip level and tail water level,
50
sign taken as positive for tail water below the lip level
and negative for tail water level above the lip level
Hv= Velocity head of jet at bucket lip
Φ = Bucket lip angle with the horizontal in degrees
For the conditions when Y is negative, model studies may be carried out to confirm the
value of horizontal throw distance (X) and vertical distance of throw (a).
Vertical distance of throw above the lip level may be calculated from the following
formula:
v a Sin 2φ
2
a=
2g
where,
a = Vertical distance from the lip level to the highest
point of the centre of jet
Va = Actual velocity of flow entering the bucket
Φ = Bucket lip angle
g = Acceleration due to gravity
The factors governing scour below trajectory buckets are the discharge intensity, height
of fall, water level, lip angle, mode of operation of spillway, degree of homogeneity of
rock, type of rock, time factor etc. However, restricting the analysis of correlating the
scour depth with two dominant factors, namely discharge intensity (q) and the total head
(H4), the scour depth can be worked out by the following equation:
d s = m(qH 4 )
0.5
where,
ds = depth of scour
m = constant (0.36 for minimum scour, 0.54 probable
scour under sustained operation, 0.65 for ultimate
scour)
q = discharge intensity
H4 = reservoir pool elevation – bucket endsill elevation
Experience has shown that erosion upto the ultimate scour level will take place
irrespective of the type of rock etc. The process is merely a function of time. In case of
mega projects, pre-formed plunge pool upto the scour level is being invariably
considered.
51
In India there are more then 5000 large dams and numerous medium and small dams
constructed for various purposes like flood forecasting, irrigation, hydropower, water
supply etc. Construction of dams for water resources development and management is
an on-going process and many more projects are at present in planning stage. Design
and analysis of dam is a vital aspect, not only for new dams but also for the old dams
requiring rehabilitation and strengthening. Dams are classified as; Gravity Dams, Arch
dam, Buttress dam and Embankment (Earth &Rockfill)dams. The type of dam
depends on construction materials used, method of construction, etc. The design
procedure and criteria used for different type of dams is specified in relevant design
codes.
The Gravity Dams are designed with a consideration that all forces coming upon the
body of the dam are resisted by its weight alone. Whereas, in the Arch Dam forces
are transmitted to the thrust pads and to the abutments. Earth and Rockfill Dams are
built using locally available soils, rock masses. Earth and Rockfill dams are also
Gravity Structures as they resist all the forces coming upon them by virtue of their
weight alone. However, their design is quite complex as compared to the concrete
dam, due the heterogeneous nature of the material used, complexity in the material
properties and difficulties in predicting soil-foundation interaction .
Normally, for the design of gravity dams, conventional approach which is based on the
laws of Statics is widely used. This approach is simple in conception and calculations.
Gravity dam is designed against overturning and sliding. It is analysedfor tensile
stress, shear stress and maximum comprehensive stress induced in the body and
foundation of the dam. However, the conventional approach of the analysis does not
fully take into account the elastic properties of the foundation and dam material. The
variation in the material properties of the foundationis complex and missed out by this
method. The results obtained by this approachare very conservative. It does not give
the complete picture of the distribution of stresses, strains and displacements
developed throughout the body of the dam and the foundation. The conventional
analysis gives quite acceptable design foroverturning and sliding. However,
calculation of stresses by conventional methods are highly approximate, moreover
effects of openings like inspection galleries, drainagesetcand heterogeneous nature
Page 188
Page 128
31 INDUCTION TRAINING PROGRAM
30 ITP
&non-linear behavior of the material cannot be accounted for the analysis. The
deficiencies of the conventional methods can be overcome by using numerical
methods. The numerical methods combined with computational power of the
computers make it possible to do the complete stress analysis of any type of dam with
a desired accuracy.
The problems involved in the analysis of continuous structure such as dams and their
foundation are generally analyzed by differential equation or integral statement for
which closed solution is possible. Analytical / Mathematical solutions are available or
possible only for Simplified situations. The Finite Element analysis of discretizing and
approximating the continuum is one of the most general and useful numerical method
for such analysis.FEM gives approximate but acceptable solution for the unknown
quantities at the discrete number of Points in the continuum.
Finite Element models are used for linear elastic static and dynamic analyses and for
nonlinear analyses that account for interaction of the dam and foundation. The
advantage of Finite Element Analysis is the capability of modeling complex geometries
including discontinuities, corners, openings, galleries and wide variations in material
properties.It can also model thermal behavior and couple thermal stresses with other
loads. An important advantage of this method is that complicated foundations involving
various materials, weak joints,fractures and faults can also be readily modeled.
The Finite Element (FE) Analysis in theory involves the following steps:
Page 189
Page 129
31 INDUCTION TRAINING PROGRAM
30 ITP
element stiffness matrices can be stored in the program as element library. A standard
program can be written for assembly of n number of elements. The only input that is
required is the co-ordinates of the nodes, element connectivity and material properties.
Once the boundary conditions are implemented in the form of nodal loads and nodal
restraints/constraints, the problem finally takes a form of solving n number of
simultaneous equations. A simple algorithm based on Gauss Elimination Method can
easily take care of solving these equations. The commercially available software has
made the complex looking FEM very easy and simple for the user. The typical steps
for FEM using any standard software are as follows
Page 190
Page 130
31 INDUCTION TRAINING PROGRAM
30 ITP
In the Figure 2 shown above, material properties given in Zone1, 2 and 3 pertains to
the rock occurring in the respective zone, whereas, material properties given in Zone 4
and 5 represent M20 and M15 concrete respectively. Though it is advised to do
Page 191
Page 131
31 INDUCTION TRAINING PROGRAM
30 ITP
analysis for each block separately as 3 dimensional analysis, however, in case there is
not much variation in the cross section along the length and the length is considerable
with respective to the cross section, then it is possible to do simple 2 dimensional
analysis for each block. However, it may result in a bit approximate solution.
The earth dam is most economical as it uses locally available soils, rocks for its
construction, but the design and analysis is more involved, as it involves materials with
complex properties. Typically,an earthen dam is designed against overtopping,
internalerosion and piping, cracking in the embankment and against seepage.
Basically, the Earth Dam is a gravity dam and all aspects of designing of gravity dam
are also applicable to earth dam. However, the earth dam posses more specific
problems which are not faced by gravity dam like seepage, internal cracks and dam-
foundation interaction. Finite Element analysis can be used in analysis of earth dam
for following phenomena:
3. Seepage analysis
Page 192
Page 132
31 INDUCTION TRAINING PROGRAM
30 ITP
uniform throughout the length. This continuous structure do not have joints in
between. So a 2 dimensional approach give good result for earth dam. The two
dimensional plain strain elements are appropriate. The 3nodedlinear elements or
6noded second order elementsgives the acceptable results, though 4 noded linear
element or 8 noded second order element are preferable.
When the valley is narrow and the abutments are stable & strong, an economical
section of the dam in the form of horizontal arch can be provided . In such type of
construction, the hydrostatic load is transmitted to the abutments through the arch
dam. Typically, thickness of the arch is small as compared to the other dimensions.
There are simple conventional methods of analyzing the arch dam considering it as
apart of thin or thick cylinder. In the conventional analysis, the dam is considered to
be made up of number of sectors (part of a ring) one over the above and each sector
is analysed separately. Depending upon the type of construction, the dam can be
analysed as constant angle arch dam and constant radius arch dam. However the
results are highly approximate and counter productive to the economy being offered by
the arch dam. Moreover such conventional analysis does not throw any light on the
stress distribution across the dam body, foundation and abutments. The only
appropriate method of analysis and design of arch dam is finite element analysis.
For designing an arch dam using FEM , the analysis has to be 3 dimensional with full
details of the dam body, foundation and abutment. The geometry of the dam is also
required to be reproduced accurately in the model.
Page 193
Page 133
31 INDUCTION TRAINING PROGRAM
30 ITP
The 3 dimensional analysis used for analysis of arch dam have be with parabolic or
cubic element so as to conform to the profile of the dam. Use of linear element may
be avoided. Though, FEM makes it possible to incorporate the exact geometrical
features for the foundation as well as abutments, it may lead to quite a complex
geometric model, which can pose difficulty in discretisation. The tetrahedral element
offers ease in meshing using the automatic meshing feature of the software.
However, this element is not considered to be a good element for structural analysis as
it is a stiffer element. If inevitable, only a parabolic tetrahedral should be used.
However, the results should be interpreted in the light of the stiffer element.Parabolic
or cubic brick elements are always preferred.
i. Geometry of the dam foundation, abutments etc.: To the extent possible the
smaller dimensions and intricate features can be neglected. However, bigger openings
like inspection galleries, foundation galleries, sluices should taken into account in
geometric modeling as they have profound effect on the stress concentrations.
ii. Material properties: Structural analysis of the dam requires material properties for
each type of the concrete used and for different zones of the rock encountered in the
foundation and abutment. The properties required are Poisson’s ration, Young’s
modulus, shear modulus, coefficient of thermal expansion, density etc. In a model
Page 194
Page 134
31 INDUCTION TRAINING PROGRAM
30 ITP
where the thermal loads are to be taken into account, the analysis requires ambient
temperature, temperature within the dam body, tail water temperature etc.
iii. Loads: The various significant loads acting on the dam body and required for analysis
are as below:
a. Dead load of the dam: This load is generally calculated automatically by the FEM
Software using the geometric properties of the dam section and density defined for
various elements.
b. Uplift pressure: The uplift pressure is considered to be acting along with the base
width of the dam with maximum intensity at the heel and minimum intensity at toe.
Profile of the uplift pressure is determined based the drainage facilities provided and
the uplift intensity factor considered. The pressure with this profile is applied on the
base of the dam acting in upward direction.
c. Hydrostatic load. The main purpose of dam is to hold water, the hydrostatic
pressure acts on the dam body on its upstream face with maximum intensity at the
base and with zero intensity at the free surface. The uniformly varying hydrostatic
load is applied on the upstream face of the dam and also at the bottom of the reservoir.
There are simple ways of applying hydrostatic loads in the standard FEM software.
e. Silt Pressure. The silt deposited in the vicinity of the upstream faces of the reservoir
exerts lateral pressure on the dam face. This pressure depends on the depth of the silt
deposited, specific gravity of the silt soil and porosity of the silt deposited.
f. Ice pressure : Big sheets of ice floating on the reservoir can exert large thrust on the
dam body. This force depends upon the thickness of the ice sheets and intensity of
the ice pressure.
Page 195
Page 135
31 INDUCTION TRAINING PROGRAM
30 ITP
Typically, the dam is analysed for various load combination of the above forces as
given in the design codes. FEM analysis makes it possible to combine any load in
given proportion and create a load combination. All the anticipated forces acting on
the dam are created as individual loads and they are combined in various load sets for
analysis.
In dam analysis the bottom face of the foundation of the foundation are restrained in
translation as well as rotation i.e. the X, Y, Z translation and rotation for nodes on this
plane are made zero where as the side faces are allowed displacements only in
vertical direction.
It is possible to use symmetry in arch dams to economize on the model if the arch dam
is fairly symmetrical about the vertical plan. In such a situation instead of doing
analysis for whole dam, FEM model is prepared only for ½ portion of the dam and
appropriate constraint are given on the plane of the symmetry. This results in ½
number of elements in the model, thus saving on the time required for solution.
An important aspect of any finite element analysis is that of selecting and presenting
essential information from the extensive results produced. It is extremely helpful to
Page 196
Page 136
31 INDUCTION TRAINING PROGRAM
30 ITP
have the results presented in graphical form, both for checking and evaluation
purposes. The results should contain information for the complete structure to make a
judgment regarding the dam safety, as well as to determine whether the boundary
conditions given were appropriate or whether there are inconsistencies in the stress
distribution.
The basic results of a typical static analysis of a dam consist of nodal displacements
and element stresses computed at various element locations. Nodal displacements are
computed in most computer analyses and are directly available. They are simply
presented as deflected shapes across selected group of elements. The stress
quantities usually are plotted as stress contours ( principal, von-mises, axial etc. ) on
the dam body. Fig 6 shows a sample result for stress distribution depicted graphically.
Application of FEM in Dam analysis is not only restricted to stress analysis, in fact any
problems handled by modern digital computers connected with static and dynamic
analysis of complicated machines or structures are generally of the form
Page 197
Page 137
31 INDUCTION TRAINING PROGRAM
30 ITP
i. Equilibrium or steady state Problems, where the entities given in above equation
are not function of time. i.e. the problem is in the form of [K] [U] =[F] e.g.
ii. Eigen value Problems or natural frequency Analysis where the first term of the
above equation is zeroand problem is in the form of [C]{Ù} + [K]{U} = {F(t)} e.g.
iii. Propagation Problems or Dynamic Analysis where all the terms of the above
equation are significant. E.g.
7. Sediment transport
8. Wave propagation
9. Seismic analysis of W.R. structures
10. Transient seepage in soil and rock
11. Dynamic soil-Structure Interaction
Though this lecture notes deals only with stress analysis (steady state) analysis of
dams, the Finite Element Method can be used for all of the above analysis problems
effectively.
----------------
Page 198
Page 138
31 INDUCTION TRAINING PROGRAM 30 ITP
2.0 Galleries
1
Page 199 Page 139
31 INDUCTION TRAINING PROGRAM 30 ITP
The general size of the gallery varies from 1.5 m x 2.25m to 2.0 mx2.5 m
Galleries are generally provided at a distance equal to 5% of the head or 3m
whichever is more from the u/s of the dam. Minimum concrete cover between
the foundation rock and the gallery is kept about 2 to 3 m.
Wherever possible seepage water collected is drained by gravity through adits
provided in the dam above maximum tail water level.
Grouting and drainage gallery normally extends the full length of the dam.
The gallery is located near the upstream face as close to the foundation surface
as feasible but with a minimum of 2m of concrete between the floor of the
gallery and the foundation. A minimum of 3m clear distanced is usually
provided between the upstream face and the gallery.
In high gravity dams, a second drainage gallery is sometimes provided at about
two-third of the base width downstream of the grouting and drainage gallery.
The sizes of gate chambers, located directly over service and emergency sluice
gates are determined by the sizes of gates and hoists.
(Ref: 12966:1992 Code of practice for galleries and other openings in dams)
Structural Design of openings:
i. Therory of elasticity
ii. Stress Coefficients
iii. Photo elastic Methods
iv. Finite Element Method
C. Computation of total tension (Ft) there from
D. Computation of reinforcement for critical loading
Ast = Ft/ σst
Stress calculations:
For concrete/masonry Gravity dams with plane transverse joints which are
either keyed or grouted, the Gravity method of stability analysis is used. IS
6512 is used for carrying out stability analysis and finding out the stresses in
dam sections.
Reinforcement:
For calculating reinforcement around galleries and other openings tensile area
is normally calculated using the relation
Tensile area=0.149 A σn
Where,
A = size of opening
σn = Maximum normal stress at the location of opening due to critical
loads
IS code 12966-1990 part II describes in detail the basis of design of galleries
and other openings in dams.
List of BIS:
5
Page 203 Page 143
31 INDUCTION TRAINING PROGRAM 30 ITP
1.0 INTRODUCTION:
Besides, these DPRs need to get clearance from the Central Soil and Material
Research Station (CSMRS) from construction material aspects, the Geological
Survey of India (GSI) from geological aspects and Seismic aspects from NCSDP.
Presently, the Survey and Investigation (S&I) and preparation of detailed project
report of hydro projects are required to be carried out as per “ Guidelines for
preparation of Detailed Project Reports (DPRs) of irrigation and multipurpose
projects” issued by Ministry of Water Resources. These guidelines were
reviewed, updated and finalised in April 2000, by a working group was
constituted by Ministry of Water Resources.
2.1 The following activities are carried out for the various alternatives considered
to justify the final choice of the location of different components of the
project:
a) River surveys
b) Reservoir surveys
c) Head works surveys (dams, barrage, weir, etc)
d) Plant sites and colonies
e) Canal, branch canals, and water conductor system
f) Major canal structures
g) Power house, switch yard, surge shaft, tail race tunnel(s), adits,
penstocks etc.
i) Surveys for command area including Ground Confirmation Survey
j) Soil surveys
1
Page 204 Page 144
31 INDUCTION TRAINING PROGRAM 30 ITP
k) Soil conservation
l) Construction material surveys.
2.2 The different activities of survey and investigations which are carried out
before preparing a Detailed Project Report are given in Sub-para 2.2.1 to
2.2.4.
The Survey of India (SOI) has published topographical maps covering the
whole country in 1:2,50,000 and 1:50,000 scale. Besides SOI has also
published topographical maps of many parts of the country in1:25,000
scale and they are already on the job of producing maps in 1:25,000 scale
for the whole country.
(i) General
The following inputs are of overriding importance since they have significant
bearing on cost, safety and useful life of surface and underground structures :
a. Geology and structural / tectonic features
b. Rock mass and intact rock properties
c. Permeability of rock mass and Hydrogeological data
d. In-situ stresses
e. Design details
f. Construction methodology
g. Stabilization measures
h. Instrumentation (monitoring) data
a) Surface investigations
After ascertaining the regional geology of the area the site specific
geological mapping is taken up by intensive surface traverses of the
project area and also with the aid of aerial photographs & satellite
3
Page 206 Page 146
31 INDUCTION TRAINING PROGRAM 30 ITP
The direct tools include exploratory pits, trenches, drill holes, drifts,
which provide a detailed information of the ground under survey.
Test pits and trenches are best suited for shallow exploration on
moderately steep slopes. Rotary drilling is the most extensive and
common technique employed for detailed exploration to know the 11
condition of soil and rock. Water tightness of the bed rock is
determined by conducting water pressure tests. These tests are
normally carried out at proposed dam sites, powerhouse, other
caverns and reservoir locations etc. Drifts are generally made to
explore dam abutments, adit / tunnel alignments.
Details of seismological events are collected from IMD, New Delhi and
site specific design earthquake parameters are evaluated either by the
institutes such as IIT, Roorkee or CWPRS, Pune, for working out the site
specific design earthquake parameters. These parameters are further put up
to National Committee on Seismic Design Parameter (NCSDP) for final
approval before adopting the same in detailed design of the project. Micro
Earthquake studies are also conducted for the assessment of seismicity of
the area and demarcation of the active faults in and around the project area,
depending upon the sensitivity & magnitude of the project.
(vi) Rock & Soil Mechanic Testing and Construction Material Survey
a) Laboratory Testing
It is conducted to evaluate the engineering properties. Some of the
laboratory tests are
i) Determination of deformability of rock materials in uniaxial
compression
ii) Triaxial compression tests
iii) Determination of tensile strength
iv) Determination of Direct Shear Strength
v) Rheologic properties of rocks
b) Field Testing
These include the following:
a. Rock stress determination using flat jack, over coring and hydro
fracturing
b. Determination of modulus of deformation by Goodman Jack test
and cyclic plate load test
Preference should be given to identify quarry sites in area of submergence
(reservoir) keeping in view the environmental aspects and other related
complexity of forest clearance / land acquisition, etc.
v. Water quality
vi. Evaporation
vii. Availability of water for the benefits envisaged
viii. Design flood for various structures
The different stages of project for which investigations are carried out are:
a. Pre-Feasibility Stage
b. Feasibility Stage
c. Detailed Investigation (DPR) Stage
d. Construction Stage
It is more of a desk study with limited field checks. Based on the 1:50000 or
1:25000 scale Survey of India toposheets, possible hydroelectric sites are marked.
These sites are examined by preliminary field traverses wherein topography,
broad geological aspects in terms of locating the project components are looked
into. If required, broad assessment of the terrain at the likely site is also carried
out by geophysical survey to understand the sub surface condition of the rocks.
Reconnaissance of the Area: This stage of investigation forms the basis for
taking up preliminary stage investigations. The reconnaissance must be carried
out by experienced and competent engineering geologists to study the merits and
demerits of the various sites proposed by the sponsoring agency. Later on based
on the techno-economic feasibility, one site may be taken up for further
evaluation by geological investigation.
The identification and feasibility of the water resources projects, whether storage
or run of the river schemes, depends on location, geology, gradient of river,
hydrology and seismicity.
6
Page 209 Page 149
31 INDUCTION TRAINING PROGRAM 30 ITP
For example in the higher Himalaya (1000-6000 m asl ), which lies in the north
of the Main Central Thrust (MCT), the terrain is characterized by high river
gradient (> 10m/km), less river discharge, high river velocity, steep hill slopes,
high seismicity, very thick overburden of fluvio-glacical deposits over hard rocks
of Central Crystalline Group. This sector is best suited for small diversion dams
and run of the river schemes because of deeper rock foundation level and
availability of more head for power generation due to steep river gradient, which
otherwise will have less storage capacity if high dams are proposed instead.
On the other hand, high storage dams are feasible in the Lesser Himalayan
Terrain (400m – 1000 m asl) which is bounded by MCT in the north and MBF
(Main Boundary Fault) in the south and is characterised by high river
discharge, less river gradient (2-10m/km, average 5m/km) with adequate storage
capacity, rock foundation level at shallow depths (as river bed deposits ate 7 to
10 m thick).
After selecting the site during Pre-feasibility stage, intensive field traverses are
under taken. Detailed survey like contour plans and sections in 1: 1000 to 1:5000
scale are prepared for various important structures such as dam, tunnels,
7
Page 210 Page 150
31 INDUCTION TRAINING PROGRAM 30 ITP
powerhouse, etc. One or two alternate axis are probed by detailed geophysical
survey and a few drill holes to ascertain depth and quality of bed rock besides
carrying out broad geological mapping & collection of regional geological
information. The hydrometeorological data collection is also started during this
stage. Based on this data, lay-out of the project is prepared and its techno-
economic viability is established.
The first consideration of the selection of a dam site is whether the topography of
the river valley provides a feasible dam and reservoir site with adequate storage
capacity and is in conformity with the geology and structure of foundation rocks.
8
Page 211 Page 151
31 INDUCTION TRAINING PROGRAM 30 ITP
• Study of regional geology and tectonics using existing geological maps and
also latest satellite imageries of high resolution. Lineament pattern picked
up from satellite images and ground validation.
• Identification and delineation of neotectonic features -active faults/thrust.
Time-lapse measurements by geodetic surveys to record movements along
active faults.
• Categorization of tectonic features/dislocation identified in the area in
different orders based on their strike continuity and seismic status.
• Seismotectonic evaluation of the area to find the linkage between tectonic
features and a seismic events in the area.
• Landslide zonation in reservoir area and study of slope stability around
reservoir rim.
• Identification and detailed investigations of areas rich in construction
materials. The investigations include geological mapping, geophysical
profiling, pitting, sampling and testing.
• Long-term siltation studies in the reservoir area.
• Micro seismic investigations by establishing a net work of
seismographs/accelerographs in and around project site.
b. Geomorphological Studies
c. Sub-surface Explorations
In order to unravel the depth of bed rock below the thick apron of overburden
mass/slide mass, to decipher the limits of weathering/destressing of rock mass, to
prove or disprove the interpreted structural features like faults.
10
Page 213 Page 153
31 INDUCTION TRAINING PROGRAM 30 ITP
d. Geophysical Exploration
• These are indirect methods of exploration for getting useful information
related to subsurface geology of a larger area.
• The geophysical surveys include seismic (refraction/reflection) profiling,
seismic tomography by ground penetrating radar (GPR), electric resistivity
sounding and ultrasonic logging.
• The seismic and resistivity surveys are used for determining depth to bed
rock, disposition of fault of shear zone and for assessing modulus values
(modulus of deformation) of rock mass.
• Modulus value of rock mass can also be obtained by ultrasonic logging of
drill cores. The geophysical interpretation should be substantiated by
drilling and drifting.
11
Page 214 Page 154
31 INDUCTION TRAINING PROGRAM 30 ITP
Exploratory drill holes are planned at project sites with the objective of
exploring quality of rock mass likely to be encountered, depth of
overburden, depth of weathering / destressing, existence of shear zone /
weak zone, rock cover above the proposed underground structures.
It may be mentioned that drilling gives very limited information about the
sub-surface geological conditions at required depths. It is a point
information.
Drilling is a time consuming operation and mostly the delay is due to poor
and less drilling rate/day.
12
Page 215 Page 155
31 INDUCTION TRAINING PROGRAM 30 ITP
f. Exploratory Drifting
g. Laboratory Tests:
• The drill core samples should be tested for determining the physical and
mechanical properties of intact rocks by different methods in the
geotechnical laboratory.
• The core samples should be tested for determining specific gravity,
modulus of elasticity, poisson’s ratio, unconfined compressive strength (in
dry/wet state) tensile strength, swelling index and hardness.
h. In-situ Tests :
At project sites, the in-situ tests are done to determine the key
parameters:
13
Page 216 Page 156
31 INDUCTION TRAINING PROGRAM 30 ITP
• In-situ stresses
• Modulus of deformation
• Shear parameters
• Permeability
Both the abutments are probed further by two or three level exploration drifts
with cross cuts. The number and length vary depending upon the size of the dam.
Nowadays, the dam base is scanned by seismic tomography depending upon the
site conditions/requirements. All other tests like grouting, shear tests are also
carried out. Insitu test for ascertaining bearing capacity of the foundation may be
required. In some cases SPT tests may also be necessary depending on geological
conditions.
At least one drill hole shall be placed specifically for energy dissipation
arrangement immediately after the spillway. A provision of at least three drill
holes is generally kept separately for spillway in case it is a side channel spillway,
away from the main body of the dam. The location of coffer dam in the river bed
portions especially for the upstream one is required to be probed by a drillhole to
understand nature of overburden material and bedrock depth. Similarly, for
diversion tunnel also, a provision of minimum three drill holes is kept with one
each at the inlet & outlet portals and the third one suitably placed on the tunnel
alignment, depending on the geological set-up and topographic considerations.
holes down to tunnel grade is a difficult task. Hence, majority of the tunnel
forecast is based on detailed geological map & projections. However, certain
major weak zones such as faults or thrusts etc should be probed by advance core
drilling during the tunneling activity to identify the exact condition and to
minimize geological uncertainties.
Tunnel Portals are mapped using 1: 500 scale with 2m contour interval instead of
1: 1 000. For Adits / Access Roads, Borrow Areas / Quarry Sites all construction
as well as access adits are mapped on 1 :2000 scale with 4m contour interval.
Vulnerable areas on access roads are also mapped on the above scale. As such, all
geological maps are updated in this stage. If there have been certain changes in
the layout, additional areas are covered.
Permeability tests should be conducted in all the drill holes selective pits &
trenches. Geological logging of Drill Holes, Drifts, Trenches & Pits is carried out
using 1:100 scale.
Groutability tests to assess the grout intake and reduction in permeability values
are generally done in this stage of investigation. Generally the rock mechanic or
soil tests are carried out in the DPR stage for detailed design. Moreover, some of
the detailed & expensive tests like mortar bar test for construction material survey
and insitu rock stress measurements for design input are done at this stage. The
seismotectonic studies are pursued in detailed manner during this stage for getting
site specific earthquake parameters.
In case of underground works especially for tunnels, major identified grey ares
are probed by advance drilling or drifting to minimize geological uncertainities.
15
Page 218 Page 158
31 INDUCTION TRAINING PROGRAM 30 ITP
Aerial photographs and satellite imagery are used for rapid interpretation of
geomorphology, lithology, structure and preparation of land use thematic maps
which are widely used in environmental impact assessment of the project.
Geographical Information System (GIS) is used for mapping and analyzing things
that exist and events that happen on earth. GIS technology integrates common
database operations and statistical analysis. The process of making maps by GIS
is much more flexible than traditional manual or automated cartography
approaches. Existing maps are digitized and computer compatible information are
translated into GIS. Remote sensing using sensors such as cameras carried on
aeroplanes, GPS receivers, or other devices collect data in the form of images and
provide specialized capabilities for manipulating, analyzing, and visualizing these
images.
The cost and feasibility of the project is dominated by geology and geological
complexities – which are generally inadequately explored. Hence, critical
attention must be given to the prospective use of state-of-the-art techniques of
geological / structural data collection, geophysical surveys, exploration by
drilling, and in- situ / laboratory testing followed by numerical modeling. These
are required to avoid the cost and time overruns.
The investigation programme, planned in different stages, must provide
adequate geological and geotechnical data required for assesment of rock mass
condition and also to identify potential geo-hazards that may exist at the project
site. Information obtained from geological mapping, sub-surface explorations
and rock mechanics investigation is of great help in finalization of project
layout, design and construction methods; and thus in cost saving.
16
Page 219 Page 159
31 INDUCTION TRAINING PROGRAM 30 ITP
ANNEXURE-I
17
Page 220 Page 160
31 INDUCTION TRAINING PROGRAM 30 ITP
ANNEXURE-II
(ii) 2-3 drill holes down stream of 10m deep in fresh rock or equal to
spillway. maximum height of dam in
absence of rock.
18
Page 221 Page 161
31 INDUCTION TRAINING PROGRAM 30 ITP
(c)Tunnels
(i) Drill holes at each of the portal Drill holes 5-10 m below the tunnel
and adit sites and additional at- grade of maximum possible depth.
least one every 1-5 km interval Wherever it is not possible to drill
depending on the length of along the central line of the tunnel
tunnel. the holes can be shifted.
19
Page 222 Page 162
31 INDUCTION TRAINING PROGRAM 30 ITP
INTRODUCTION:
Any water resources development project involves interaction between the super
structure and its foundation. The stability of the structure is hugely influenced by
characteristics of foundation medium. The foundation strata may vary from loose
sandy soils to dispersive, expansive soils to hard rock. The characteristics of
foundation need to be evaluated for safe and economic design of the proposed
structure. Numerous direct and indirect techniques are available for determining
the material properties.
A gravity dam is keyed into the foundation so that the foundation will normally
be adequate if it has enough bearing capacity to resist the loads from the dam. If,
however, weak planes or zones of inferior rock are present within the foundation,
the stability of the dam will be governed by the sliding resistance of the
foundation. The following strength parameters for use in stability and stress
analyses:
a. Bearing capacity (compressive strength).
b. Shear strengths along any discontinuities and the intact rock.
c. Deformation Modulus of the rock mass.
d. Hydrostatic pressure in rock joints.
1
Page 223 Page 163
31 INDUCTION TRAINING PROGRAM 30 ITP
foundations. Associated with stability are problems of local over stressing in the
dam due to foundation deficiencies.
2
Page 224 Page 164
31 INDUCTION TRAINING PROGRAM 30 ITP
In situ stresses- In situ stresses play an important role in safe and economic
design of structure created inside of rock mass. In situ stresses are rarely uniform
in a rockmass. Underground works require knowledge of in-situ stresses. Many
methods are available for determination of magnitude of principal stresses.
Empirical correlations for assessing the rock mass quality: In the absence of
test data, some empirical correlations developed from time to time are also used
for assessing the rock mass quality.
Intact Rock and Rock Mass: When studying the subject of rock mechanics, the
terms Rock Mass and Intact Rock are generally used. It's important to distinguish
between rock mass and intact rock.
a. Intact Rock: The term intact rock refers to rock which has no through
going fractures significantly reducing its tensile strength. It is usually
characterized by density, deformability Young's modulus and Poisson's
ratio) and strength (unconfined compressive strength, cohesion and angle
of friction).
b. Rock Mass: The term discontinuity is used in rock engineering for all such
types of fractures to indicate that the rock is not continuous unlike the
intact rock described above which is mechanically continuous. Clearly the
nature, location and orientation of discontinuities profoundly affect most of
the rock properties (deformability, strength, permeability, etc.) and,
therefore, the rock engineering application. The rock mass means in-situ
material, which consists of intact rock, joints and other discontinuities. The
3
Page 225 Page 165
31 INDUCTION TRAINING PROGRAM 30 ITP
greater the strength of intact rock, the more important is the discontinuities
in determining the behaviour of rock mass.
The rock mass is characterised by conducting in-situ testing along with testing in
the laboratory. The objective of both the tests is to classify the rock for
engineering design purposes. The characterization of rock and rock mass is
essential to study the behavior of foundation materials on which the structure has
to rest or which has to support the rock loads in case of underground caverns and
tunnels.
The following tests are being conducted frequently on the rock cores.
4
Page 226 Page 166
31 INDUCTION TRAINING PROGRAM 30 ITP
Where,
σc = Compressive Strength of Specimen (MPa)
F = Applied force at failure (N) and
A = Initial x-sectional area of the specimen transverse to direction of force
(mm2)
There is an arrangement for applying constant lateral fluid (oil) pressure to the
specimen in the triaxial cell. After enclosing the specimen in the triaxial cell, the
cell is placed in a compression-testing machine, and the specimen, under constant
lateral hydraulic pressure, is loaded axially to failure. The specimens are tested
under different lateral/confining pressures.
The normal stress at failure versus confining pressure (i.e., Strength Envelop),
comprising all the tested specimens, is plotted. The modified failure envelope,
which is the ‘best-fit’ of the tested data, is drawn to estimate shear strength
parameters. In the sense of Coulomb’s failure theory, the apparent cohesion (C)
and the internal friction angle (Ф) are computed using the following formulae:
Ф = arc sin [(m-1) / (m+1)]
C = b [(1- sin Ф) / 2 cos Ф]
where,
m = slope of the modified failure envelop, and
b = intercept of the failure envelop on the axial stress axis
The Point Load Strength Test is intended as an index test for strength
classification of rock materials. It may also be used to predict other strength
parameters with which it is correlated, for example uniaxial tensile and
compressive strength.
2.2.1 Shear Strength Parameters: Shear strength parameters are required for
design of any structure on rock. Shear strength parameters involve two
components viz. cohesion (c) and friction angle (Ф). The shear failure may occur
in two ways i.e. either in concrete/rock interface or within rock mass.
For testing purpose, a set of minimum five blocks each of rock over rock and
concrete over rock has to be prepared. Each block is sheared at constant but
different normal load. Vertical and horizontal shear loads are applied by
hydraulic jacks of respective adequate capacity. From the side reaction pad, the
horizontal shear load is applied at an angle of 150 with the horizontal so that the
resultant force passes through the center of the test block.
7
Page 229 Page 169
31 INDUCTION TRAINING PROGRAM 30 ITP
During the test, the shear force and the corresponding vertical, horizontal and
lateral displacements of the block are measured by dial-gauges of 0.01 mm least-
count. The observations are recorded even after the failure to the extent possible
to get the information regarding residual frictional resistance.
Each test block is sheared till failure and beyond for establishing the peak and
residual shear strength parameters as per IS 7746:1991. After completion of the
test, block is overturned to measure the actual area under shear and to know the
failure pattern.
The peak shear stress and residual shear stress both are plotted against the normal
stress and using linear regression analysis ‘best fit envelope’ are drawn. From the
equation of straight line obtained, the intercept on the Y- axis gives cohesion ‘c’
of the rock mass and the slope of the line gives the friction angle ‘Ф’ of the rock
mass.
Deformation characterisation of rock mass is required for load transfer from the
proposed structure, be it foundation of any water retaining structure or any other
civil engineering structure or heavy machinery or an underground tunnel/cavern.
The response of the foundation strata due to cyclic pressure needs to be studied.
The deformation viz. elastic or plastic needs to be analysed for better
understanding of the rock mass behaviour. A number of methods exist for the
determination of modulus of deformation of rock mass. The following in situ
tests are conducted for determination of modulus of deformation:
• Plate loading test,
• Plate jacking test,
• Goodman Borehole jack test,
• Flat jack test,
• Cable jacking test,
• Radial jack test, and
• Dilatometer test.
8
Page 230 Page 170
31 INDUCTION TRAINING PROGRAM 30 ITP
9
Page 231 Page 171
31 INDUCTION TRAINING PROGRAM 30 ITP
Introduction:
2. River diversion trough tunnel: The river diversion through tunnel has great
applicability in embankment dams but it has the highest cost.
3. River diversion trough conduits: Alternative to tunnel diversion when
surrounding rock has no enough quality to make a tunnel.
4. River diversion trough channel: When it’s not economically unfeasible to carry
out a tunnel- this solution can use where the topography is characterized by
flattened valleys.
5. Opening left in the dam body: This method use in concrete dams, more
especially arch dam.
Scheme of Diversion varies from project to project depending on various factors.
Cost and economics of the scheme mainly decides over the available choice. A
good & reliable diversion scheme is a pre-requirement for successful completion
of the Project.
11
Page 233 Page 173
31 INDUCTION TRAINING PROGRAM 30 ITP
12
Page 234 Page 174
31 INDUCTION TRAINING PROGRAM 30 ITP
13
Page 235 Page 175
31 INDUCTION TRAINING PROGRAM 30 ITP
14
Page 236 Page 176
31 INDUCTION TRAINING PROGRAM 30 ITP
15
Page 237 Page 177
31 INDUCTION TRAINING PROGRAM 30 ITP
Diversion Flood:
The diversion structures work process need to guarantee that the river can bypass the
dam site during construction. Design of this river diversion needs study of
hydrological characteristic of the water course and morphological characteristic of the
site.
The efficient scheme of diverting the river flow away from the work area should aim
at limiting the seepage into the work area to minimum. The proper planning and
design of such temporary diversion work would be greatly influenced by design flood
in addition to other factors.
Flood routing and hydraulic model studies for evolving suitable arrangement of the
diversion through open channel help in:
a. Discharging capacity ( Numbers and size) of the diversion outlets/conduits.
b. Height of the upstream and downstream coffer dams. ( MWL is known from
flood routing, Height= MWL+Free Board)
c. Deciding the most efficient alignment of the diversion channel
d. Protection measures for the coffer dams if they are to be overtopped
e. Flow conditions in the diversion channel depending on its utility during
diversion as well as during permanent stage.
Selection of Diversion Arrangement:
A concrete or masonry dams could be allowed to get overtopped during floods when
construction activity is not in progress. Generally the largest observed non-monsoon
flood or non-monsoon flood of 25 year return period is adopted as a diversion flood.
Advantage is also taken of passing the floods over partly completed dam or spillway
blocks, thereby keeping the diversion channel of relatively smaller size than that is
required for embankment dam. In such a case a small excavated channel either in the
available width of the river or one of the banks of the river proves to be adequate.
Construction sluices are located in such excavated channels which allow passage of
non-monsoon flows without hindrance to the construction activity.
Such sluices are subsequently plugged when the dam has been raised to adequate
height. If the diversion channel is excavated on one of the river banks, it is possible to
use the same for locating an irrigation outlet, a power house or a spillway depending
upon the magnitude and purpose of the project
16
Page 238 Page 178
31 INDUCTION TRAINING PROGRAM 30 ITP
Design criteria of masonry Coffer Dam: The dead load, upstream and downstream
water loads, uplift, etc. considered in the design of coffer dam calculate according to
IS:6512-1972. Forces considered in Design concrete coffer dam:
i. Dead load
ii. Hydrostatic pressure, including velocity head
iii. Uplift pressure
iv. Earth and Silt pressures
v. Reaction of foundation
Requirement of stability:
i. The coffer dam shall be safe against overturning
ii. The coffer dam shall be safe against sliding
iii. The unit stresses developed in the masonry or concrete of the coffer dam or In
the foundation material shall not exceed the permissible values
iv. Resistance against Overturning: following criteria must be satisfied
a. The resultant of all forces shall normally fall within the middle third of the
base.
b. The maximum compressive stresses at any point shall be within
permissible limit.
For minimizing seepage through the dam body an impervious central earth core and/or
an impervious upstream membrane is usually provided. Adequate provision for passage
of diverted river discharge should be made. Design and analysis of earthen coffer dam
is carried out in accordance with IS:7894 & IS:8826
Diversion Tunnel:
Diversion Tunnel carries water from the mainstream to other channels or across the
construction site. These can be permanent or temporary structures. The size of a tunnel
depends upon magnitude of diversion flood and height of u/s coffer dam ( higher the
head smaller the size of the tunnel), Economics of height versus diameter of tunnel shall
17
Page 239 Page 179
31 INDUCTION TRAINING PROGRAM 30 ITP
be worked out. A tunnel can be pressure or free flow type. Permanent closure of the
tunnel is done by placing concrete plug in the tunnel.
Channel are designed on the basis of manning’s formula. The velocity in the unlined
section should ot exceed 5m/s. in lined channels velocity may go up to 15m/s. For the
diversion channel excavated in overburden, it is also necessary to ensure that the banks
are not eroded due to flood flows.
18
Page 240 Page 180
31 INDUCTION TRAINING PROGRAM 30 ITP
1 INTRODUCTION
The RCC is a material composed by the same components that made a conventional
concrete (cement, admixtures, sand, grave, water and Additives) but is transported,
extended and compacted with the own technology of the earth’s movement.
Generally, shear strength along the horizontal joints between the layers is more
critical because of the “layered” method that is used in the construction of RCC
dams. In addition, because of the construction technique, temperature distributions
and the corresponding thermal stresses in the dam are very different from those of a
traditional concrete dam. This is one of the major design considerations and is often
investigated using finite-element method (FEM) analysis
The interest in RCC dams is driven by economic considerations and also where
speed of construction is an important element. Given an adequate foundation, RCC
dams commonly have a lower cost than the equivalent fill dams when the savings in
cost of diversions and spillways are taken into account.
Although well-designed RCC dams are frequently the least-cost solution when
compared to other forms of dam, there are conditions that can make RCC dams
more expensive. Situations where RCC may not be appropriate include those where
aggregate material is not reasonably available, the foundation rock is of poor quality
or not close to the surface, where foundation conditions could lead to excessive
differential settlement, or where the valley is very narrow and steep-sided leaving
limited room in which to manoeuvre the equipment.
318
Requirements for galleries, instrumentation, and appurtenance for RCC dams are
similar to those of traditional concrete dams. Nevertheless these features can impact
on the construction programme. To ensure that RCC construction can proceed
rapidly, thereby ensuring that low unit prices for the RCC are obtained, the design of
the inserts in the dam in particular should be such that they have the minimum
possible effect on rates of concrete placement.
2 DESIGN CONCEPTS
The lean (low-cementitious material content) RCC dam, with a low cementitious (i.e.
Portland cement and mineral admixtures) content (< 100 kg/m3) The low-
cementitious RCC dam uses an upstream watertight membrane to protect the low-
cementitious roller-compacted interior concrete that is usually fairly permeable,
particularly at the joints between the layers. This membrane can either be an
immersion-vibrated concrete facing (up to 500 mm wide) placed at the same time as
the interior concrete and cast against conventional formwork, or pre-cast concrete
panels with or without an attached geo-membrane. Bedding mixes (concretes or
mortars with a higher cementitious content) are frequently placed between each lift
near the upstream face to improve the bond and reduce seepage between the layers
of RCC.
The design philosophy of the high-cementitious content RCC dam is that the roller-
compacted interior concrete should be the watertight barrier. Thus the RCC has to be
designed to bond layer to layer and to have an in-situ permeability equivalent to that
of a traditional concrete dam. Contraction joints are formed through the dam. If
immersion-vibrated concrete is used on the faces of the dam, it is provided to give an
improved finish and to contain the water stops at the upstream end of induced
contraction joints.
3 ENGINEERING PROPERTIES
The most important properties of RCC when used in dam construction are density,
permeability, compressive strength, shear strength and tensile strain capacity.
Density:
The in situ density of RCC is depends largely on specific gravity of the aggregates to
be used. It also depends on void ratio of fine aggregate and the paste-mortar ratio. A
lean Paste RCC has about 95% to 98% of Theoretical Air Free (TAF) density while in
high paste ration it varies from 98% to 99.5%.
319
Unit weight of RCC is typically equal or slightly higher than for conventional non air
entrained concrete.
Permeability:
Permeability value of RCC are generally lower than for conventional concrete due to
presence of high cementatious material. Usual values of permeability in low paste
RCC varies from 10-4 to 10-9 m/sec while same varies from 10-10 to 10-13 m/sec in
high paste RCC.
Compressive Strength:
In general compressive strength of RCC mixes is higher at later ages than for a
conventional concrete mix with the same cemntatitious content.
Tensile Strength:
Shear Strength:
The cohesion value (C) of RCC typically varies from 0.5 MPa to 4 MPa. Friction angle
at bonded joint is usually more than 45 degree. For preliminary design typical value
of Angle of Friction (φ) is 45 degree and Cohesion as 10 % of compressive strength of
RCC.
Strain is induced in concrete when a change in its volume is restrained. When the
volume change results in, tensile strain that exceeds the capability of the material to
absorb the strain, a crack occurs. The threshold strain value just prior to cracking is
tensile strain capacity of material. It is influenced by rate of loading, type and shape
of aggregates and cement content
RCC tensile strain capacity is lower because of less cement content.
Elastic properties:
A low value is desired to decrease the crack potential. Typical values are 15 to 25
GPa.
Poisson Ratio:
It is usually similar to conventional concrete and its values varies from 0.2 to 0.3.
320
4 DESIGN CONSIDERATIONS
The use of vibratory rollers to compact concrete instead of immersion vibrators does
not change the basic design concepts for dams; nevertheless, it does affect
construction procedures. Therefore, during construction planning, the structural
design and layout of appurtenant structures and inserts and the methods that are to
be used for the treatment of the joints between the layers must all be considered so
that the advantages of the rapid method of construction that is possible with roller
compacted concrete are not lost.
Important considerations that must be addressed before proceeding with the design
of an RCC dam include the basic purpose of the dam and the owner’s requirements
for cost, programme, appearance, water-tightness, operation and maintenance. A
review of these considerations should help to determine the optimum RCC mixture
proportions, the type of layer surface treatment, the method of forming the face of
the dam and the basic configuration of the structures. The overall design should be
kept as simple as possible in order to fully utilise the advantage of the rapid method
of construction using RCC. The Designer, in taking advantage of the flexibility
afforded by RCC, must balance the potential cost savings against the technical
requirements of the structure.
RCC gravity dams are designed to the same criteria as a traditional concrete gravity
dams with respect to stability and allowable stresses in the concrete. Given the
layered form of construction of RCC, the strength of lift joints and the potential for
sliding on lift joints must be considered carefully. With high cementitious content
RCC, good cohesion is achievable, but low-cementitious RCC and RCCs that
segregate can have low cohesion. Low cohesion values also tend to lead to high
permeability. The shear properties and permeability at lift surfaces are dependent on
a number of factors that include material properties, mixture proportions, joint
preparations, construction operations, and exposure conditions. Actual values used
in final designs should be based on tests of the materials to be used or careful
extrapolation from tests on RCC mixtures from other projects with similar
aggregates, cementitious material contents, and aggregate gradings.
As with any dam design, the Designer of RCC structures must be sure that design
assumptions are realistically achievable with the construction conditions anticipated
and the materials available.
321
critical section for stability evaluation. However, because of the potentially weaker
horizontal joints between the layers, in addition to the dam-foundation interface, it is
also necessary to perform stability analyses for other critical sections through the
body of the RCC dam.
Seismic aspects:
The analysis of RCC dams for seismic loading conditions is identical to that for
traditional concrete dams. In seismic design of concrete dams, there are certain
“good practices”, such as eliminating or minimising geometrical discontinuity in the
dams and reducing dead load at the top of the dam. These practices are equally
applicable to RCC dams. The tensile and shear strength of the horizontal lift joints
required for seismic loading may be higher than those under static loading. Proper
measures have to be taken during construction to accommodate these requirements.
Galleries
Galleries and adits serve the same purposes in RCC dams as they do in traditional
concrete dams. For example, a foundation gallery can serve as access to the interior
of the dam for inspection, as a collector of seepage, as access for instrumentation and
other equipment, and as a terminal point for drain holes drilled from the crest or a
gallery at a higher elevation. Design requirements for RCC galleries and adits are
commensurate with those of traditional concrete dams. The paradox is that the
inclusion of galleries in RCC dams interferes with clean, efficient placement and
compaction of RCC. For that reason, some Designers of RCC dams would like to
reduce the number of galleries and adits to a minimum, especially in low dams
where the need for them may be questionable [24]. However galleries provide the
only immediate interior access during operation for inspection, for safety, and to
clean or re-drill drains to maintain stability as designed. Costs associated with
failure or for additional stability can far outweigh the costs of construction. RCC
productivity may drop 10 to 15 percent for those layers that cross a gallery.
Spillways:
322
Spillway designs used for traditional concrete dams are also suitable for RCC dams.
However, in RCC dams when gated spillways are provided, they are constructed in
conventional concrete.
Appurtenant structures and inserts can provide obstacles to RCC placement. The
preferred practice for RCC dams is to locate any insert that has to pass through the
dam in or along the rock foundation to minimise delays to RCC placement.
6 INSTRUMENTATION
7 CONSTRUCTION
The layout, planning and logistics for construction of RCC dams are somewhat
different from those of traditional mass concrete dams. Instead of vertical
construction with independent monoliths, RCC construction involves placing
relatively thin lifts over a large area, essentially placing a series of roads one on top
of the other in rapid succession. If a problem develops on a given layer, it has to be
resolved before any subsequent layers can be placed. There are no alternate
monoliths on which to work while a problem is being studied. It is therefore
important that all related activities such as foundation clean-up, access and delivery
of materials and embedded parts be planned and programmed well ahead of time.
When problems of an engineering nature develop, responsibility and authority to act
on those problems should ideally be at site level.
Thickness of layers:
323
A number of factors effect the thickness of layer. Modern vibratory rollers have more
than sufficient energy to obtain good densities with a well-designed workable RCC
in layer thicknesses certainly up to 1000 mm. The more important factor is the need
to have sufficient compactive energy at the bottom of the layer to obtain good bond
between the new layer and that previously compacted. A further factor that
influences lift thickness is the maximum allowed exposure time before covering one
layer with the subsequent layer. Each project should be studied to optimise the
benefits of various layer thicknesses. Thicker layers mean longer exposure times but
fewer joints between those layers and thus a reduction in the number of potential
weaknesses in the structure. Thinner layers result in more potential joints but allow
those joints to be covered sooner, resulting in improved bond. The compacted
thickness of any RCC lift should be at least three times the diameter of the maximum
size of aggregate The majority of layers have been 300 mm thick.
.
Compaction:
The freshly-spread RCC surface should be smooth so that the roller drum produces a
consistent compactive pressure under the entire width of the drum. If the spread
surface of less workable RCCs is not smooth, the drum may over-compact high spots
and under-compact low spots.
Generally four to eight passes of a 10-ton vibratory roller will achieve the desired
density for RCC in 300-mm thick layers. This assumes compaction in a timely
manner with appropriate equipment. Over-compaction or excessive rolling should
be avoided as it may reduce the density in the upper portion of the layer.
324
The performance of an RCC dam will almost entirely be dictated by the performance
of the horizontal joints between the layers. If there is no segregation when the RCC is
placed and spread, if there is intimate contact between the two layers and if there is
sufficient energy from the vibratory roller to turn that contact into good bond, the
RCC will perform as a monolithic structure with a performance at least to that of a
traditional concrete dam. In addition the joint surfaces must be scrupulously clean;
this is generally accomplished by a vacuum truck or by air blowing. However, if any
of these factors are not present, the performance of the joint may be less satisfactory.
1. Fresh (or “hot”) joint – this is a joint that occurs when the RCC layers are being
placed in rapid succession and the RCC is still workable when the next layer is
placed.
2. Intermediate (or “warm” or “prepared”) joint – this is the condition that occurs
between a fresh joint and a true “cold” joint.
325
3. Cold joint – at this stage the surface of the previously-placed layer is judged to be
such that little or no penetration of the aggregate from the new layer will be
possible into the previously-compacted layer.
Bedding mixes used on the surface of the layer will improve the shear and tensile
strength of the joint for a given set of conditions. However, with a well designed
workable RCC with an excess of paste an equivalent performance can be achieved.
Indeed, the joints with the best performance found during the testing of cores have
all been in RCC dams without bedding mixes.
There are two forms of bedding mix, mortar and bedding concrete (with a maximum
size of aggregate greater than 5 mm). The mortar is generally 10 to 20 mm thick. The
thickness of the bedding concrete has varied considerably and has been up to 75 mm
thick.
After the RCC has been placed and compacted, the surface of the layers should be
kept continuously moist 24 hours a day and protected from drying or freezing prior
to placement of the next layer as would concrete placed by traditional methods. The
surface should be clean and at, or near, a saturated-surface-dry (SSD) condition just
prior to placement of the next layer. The surface should also be protected from
freezing by insulating with plastic thermal blankets (or some other means) until it
gains sufficient maturity.
The final layer of RCC should be cured for an appropriate time, generally in excess
of 14 days. Curing compound is generally considered unsuitable because of the
difficulty in achieving 100 % coverage on the relatively rough surface, the probable
damage from construction activity, the low initial moisture in the mixture, and the
loss of beneficiary surface temperature control that is associated with moist curing
when there is low relative humidity. An effective cure is covering with a layer of
damp sand which will also provide beneficial thermal protection.
10 PERFORMANCE
Cores have been extracted from a significant number of RCC dams for testing to
ascertain the performance of the dam. The diameter of the cores should be at least
two and a half times that of the maximum size of aggregate and preferably three
times. These results giving the in-situ performance are far more important that those
obtained from testing of manufactured specimens as they give a representation of
the concrete in the dam. In addition it is the performance at the horizontal joints
between the layers that is of more importance than the performance of the parent
(unjointed) material.
Results of various constructed RCC dams have shown that RCC dams can be
designed for any reasonable impermeability and there are examples of dams in
326
which the in-situ permeability has been measured at 1 X10–12 m/s which is at least as
good as, if not rather better than, the in-situ permeability of traditional concrete
dams
It is also apparent that the performance at the joints increases significantly as the
cementitious content increases, for example with low-cementitious RCC dams the
average cohesion is approximately 6 % of the compressive strength, while with high-
cementitious content RCC dams it is over 9 %.
• More rapid construction (2.5 to 3 m vertical progress per week can be achieved in
large dams – greater rates have been achieved in smaller dams);
• Effective use of conventional equipment (trucks, dozers, vibratory rollers, etc.);
• A reduced cost of construction as a consequence of the above
327
V. C. SHELKE,
ABSTRACT: Ghatghar Pumped Storage Scheme is conceived for enhancing hydropower capacity of
Government of Maharashtra and thereby achieving balance of hydro-thermal ratio in the state. Ghatghar
Pumped Storage Scheme is first ever largest scheme (250 MW) consists two units of 125 MW each.
Ghatghar Pumped Storage Scheme comprises underground powerhouse complex. The construction of
machine hall, transformer hall of powerhouse complex are in advanced stage. In order needs commission
powerhouse, the construction of upper and lower dam needs to be completed prior to or concurrently to
powerhouse. Upper dam is 15 m high while lower dam is 84 m high. Conventional masonry or concrete
dam would require 5 to 10 years for construction. This has lead to search for latest technology to build
dam fastest. The answer to this is Roller Compacted Concrete (RCC). Roller Compacted Concrete (RCC)
dam is a key solution for number of hydro projects world over. India has also gone for its first ever RCC
dam for Ghatghar Hydroelectric project. This project is unique of its kind because of use of reversible
turbine pumps and adoption of RCC technology for three dams. Out of three dams Saddle dam (40000
m3) has been completed and in next two seasons, it is planned to complete the Lower dam (600000 m3).
On successful completion of Lower dam the new trend will be set for adopting RCC technology in
upcoming new dams for hydroelectric projects in the country.
This paper describes preliminary trials like Test sections, full scale trial and the construction
methodology. Use of fly ash is also an attractive eco-friendly feature of the dam.
Introduction
Ghatghar Pumped Storage Scheme in Maharashtra state of India is on river Pravara, 15 km upstream of
existing Bhandardara dam on same river, provider for an installation of two reversible pump turbines,
each of 125 MW in an underground powerhouse.
Power will be generated during peak hours of demand using potential energy by releasing water from
upper dam to lower dam and water will be pumped back from lower dam to upper dam during night hours
utilizing surplus power.
The scheme envisages construction of two reservoirs, i.e., (i) Upper reservoir near village Ghatghar
District Ahmednagar (ii) the lower reservoir near village Chondhe (Bk.) District Thane (iii) and a water
conductor system with powerhouse in between the two dams. The scheme involves transferring of water
alternately between the upper reservoir and the lower reservoir with a vertical distance of more than 400
m between them. The scheme is intended to be operated on a weekly cycle with generation for six hours
daily except Sunday and pumping for seven hours during of peak hours from Monday to Saturday and the
balance on Sunday.
To have a speedy construction of this hydroelectric project, the upper dam and lower dam are proposed to
be constructed in Roller Compacted Concrete. The features of upper and lower dam are as given below:
Table No.1: The features of upper and lower dam
Dam Height Length Qty. of RCC
Upper dam 14.5 m 451 m 42000 m3
Saddle dam No.1 11.5 m 250 m 13000 m3
203
RCC Dams
Three RCC dams namely saddle dam, (11.5 m) 13000 m3 upper dam (14.5 m) 42000 m3 and the lower
dam (84.0 m) 600,000 m3 will be built in the same order for Ghatghar pumped Storage Scheme. The
saddle and upper dam is located near the origin of river Pravara at Ghatghar close to the westerly natural
slope of Sahyadri ranges at MSL 750 m. It provides storage of 5.87 m3 of water required for the operation
of pumped storage scheme. Tow saddles on right fringe of upper reservoir, open out on the westerly
slope, out of which one saddle is already build in colgrout masonry. The Saddle.250 m, along with
maximum height of 11.5 m, above the deepest foundation was proposed to be constructed in RCC and is
completed in April 2003. The upper dam is gravity dam 451 m long with 14.5 m maximum height above
the deepest foundation the dam has a vertical upstream face and a stepped downstream face with a slope
0.8:1 (H.:V.) beyond 10 m vertical from the top. Top width is 8 m. Central spillway in the river portion
with 5 radial gates each of 12 m3 m in size. River sluice located in one of piers of the non-overflow
portion. The overflow portion is in conventional concrete while the non-overflow portion of the dam is
being constructed in RCC.
The lower dam is located down the continental divide across Shahi river, near Village Chonde at MSL
350 m which is at the foot hill of Sahyadri ranges. It provides storage 3.80 Mm3 of water. The lower dam
is a gravity dam 415 m long with maximum height 84 m above deepest foundation. The dam has
upstream batter of 0.14:1 (H: V), and downstream batter of 0.782:1 (H: V) and beyond 11 meter height, it
is vertical and the top width of 8 m. An ungated stepped spillway 84 m long with height and width of
each step at 0.6 m and 0.47 respectively is proposed in the gorge portion with 8 m wide bridge on the top.
The discharge over the stepped spillway is 2 m3/m which is quite low. The lower dam including overflow
portion is proposed to be constructed in RCC.
Design of Dams
All the three dams are designed basically as gravity dam. The lower main dam having maximum height of
84 m is provided with foundation gallery, and foundation drainage holes, inspection gallery, ventilation
shaft, lift shaft etc., as per the conventional gravity dam. The other two dams with low height are not
provided with such openings.
All the three dams are proposed to be constructed using high paste RCC withl layer thickness of 300 mm.
Further to make the dam impermeable 0.5 m-1 m wide facing both upstream and downstream is proposed
to be formed in grout enriched vibrated RCC (GEVR). All the three dams are being constructed by one
and the same contractor, Patel Engineering Ltd (India) in association with ASI ( USA ).The work of
powerhouse complex is also with the same contractor. Thus coordination between two works has become
204
easier. The design of the dam is done by Tata Consulting Engineers (India) as an Indian counter part of
EDPC (Japan) who is the prime consultant. Malcolm Dustan and Associates (UK) is the consulting
engineer for RCC dam.
Test Section 1
Based on MERI mix (Table2) Test Section 1 was carried out in March 2002. Test section 1 was
successful in understanding methodology and sequence of operation and training the staff. Also new
procedure for GEVR was decided in Test Section 1. However the results of test section were not up to the
mark for impermeability and requirement for strength due to lapses in quality control aspects like lack of
uniform gradation of aggregate, no temperature control etc. due to these discrepancies it was decided to
place additional test section 2. It was realized from test section 1 that extensive laboratory work is
required to finalize the mix proportion. The results of test section 1 were analyses in light of mix design
parameter. Accordingly a detailed mix design exercise at field laboratory was carried out. The
cementations material was kept same as per MERI design and changing other parameters like gradation of
aggregate sand / aggregate ratio. The corrections for specific gravity and water absorption, were applied.
The different mixes were evolved based on 28 days strength result.
Test Section 2
Test section 2 was carried out in October 2002 based on mix by field lab (Table3), though there was
increase in strength of specimen as well as in-situ core strength. The test section 2 was not successful in
getting a continuous core, due to segregation observed at lift joints. At this juncture, Malcolm Dunstan
and Associate (MD&A) were invited for guidance. The objective of the trial mix programme carried out
by MD&A was to optimize the gradation and workability of the RCC so that cohesive RCC could be
obtained with little potential for segregation and one that could be used for GEVR. At this stage actual
strength of RCC was considered to be less important because it was to be used initially in the Saddle dam
in which the stresses required are less stringent than the upper dam and much less stringent than lower
dam. Two main changes were made to the specified mixture proportion, first the gradation was changed
and second mix was made much workable. The actual optimize gradation is compared to the suggested
limit. This mix was designated as G-85.
A small trial of the proposed RCC was undertaken with the mix suggested by MD&A. A number of load
of RCC were dump from truck on to the surface of test section 2. The RCC was spread in layer and
compacted by 4 passes of the double drum vibratory roller ( 1 static and 3 vibratory ). All the nuclear
205
densitometer readings were in excess of 2500 kg/m3. Although the trial was only small it was sufficient
to show that RCC with the gradation proposed and with the workability proposed could easily be handle
and could be roller compacted to a high density. The surface of RCC after roller compaction was
satisfactory. The same mix was decided to be adopted for placement of saddle dam as a full scale trail.
The full-scale trial was done for layer 1-2-3 with mix proposed by MD&A as shown in Table 4for saddle
dam in December 2002. it was found that both the cylinder density and in-situ densities are very much
higher than those found during the first two test section. This was because the water contents of the mix
was higher and thus theoretical air free density was lower than that of mixes used in two test sections.
The reasons for higher density were that the RCC was much more compactable and thus there were lower
air voids.
The objective of the full scale trial was to investigate all the construction procedure in particular the
joint treatment between the layer and the training of personnel who were suppose to work at the
Upper dam and lower dam. The first trial was constructed between 9 to 27 March 2003 and consisted of
19 layers of 300 mm compacted thickness with a total volume of 6780 m3 in left hand side (LHS)
portion of saddle dam. Similarly the second half of saddle right hand side (RHS) portion was started on
22nd April 2003 and completed on 9th May 2003. The RCC volume of 7431 m3 was placed in RHS. Thus
this full scale trial of RCC placement for complete saddle dam for the placement of RCC volume of
14200 m3 gave good learning curve to all the supervisors of department and the contractor and the
designer. During this learning, following activities were learned:
. Calibration of nuclear densitometers and measuring the in-situ densities
. Optimization of dosages of set-retarder
. The optimization of the exposure time between layers
. The insertion of joint crack inducers
. The use of interface against abutment: Upstream and downstream GEVR
. The optimization of water contents in different hours of day and night.
. The optimization of number of passes of vibratory rollers
206
The specifications required that placement temperature of RCC shall not more than 27o C. To achieve this
aggregate were covered by weather sheds and were chilled by water to 10o C. But during summer, hottest
day, chilling plant had difficulties and the work of upper dam was to be stopped for few hours and to be
taken during cooler hours.
Transportation of RCC
The batching plant is installed at upper dam location which is at a distance of 2 km from the saddle. The
transportation of fresh RCC was done by the dump trucks with capacity of 4 m3. A special arrangement
was done to the rear of the trucks to reduce the potential for segregation when the concrete was dumped.
The trucks were covered to avoid dust and to protect from solar radiation.
A stacker-conveyor was installed at the center of saddle to convey the RCC from specially raised
platform to saddle.
A hopper was installed at a fixed point from where the RCC was again discharge into intra-dump
trucks in the body of a dam. Pair intra dump trucks were used for conveying the RCC to the point the
placement.
RCC Placement
The RCC discharged at the point of placement by the intra dump trucks was spread the required thickness
(340 mm un-compacted, to achieve 300 mm after compaction) the thickness of layer was assured by
automatic laser guided system connected to blades of dozers.
The RCC was placed in 8 m wide strip parallel to the axis of the dam. As width was less there was
not possibility of a joint either parallel or perpendicular of dam axis. The placement was carried out
continuously 7 days a week and 24 hrs a day.
Curing
The RCC was cured continuously by using sprinkling the water into in order to keep the surface of a layer
always in moist condition. A saturated surface dry (SSD) condition was maintained till the placement of
next layer. After completion of RCC placement of Saddle continuous curing was done for 40 days.
Contraction Joints
The contraction joints are vertical joint perpendicular to axis of a dam. These joints have been specified at
50 m for upper and saddle dam. Central Water Power Research Station, Pune (CWPRS) has
recommended placement temperature as 17oC. However in these thermal studies joints spacing and
cooling effect due to gallery have not been considered. In order to negotiate this contraction joints are
further decided to be at closer spacing of 25 m, accordingly they have been provided. Considering higher
ambient temperature at lower dam 15 m joints spacing is proposed. In saddle dam and upper dam at each
207
layer, galvanized steel crack inducer was inserted at the location of each contraction joints. The crack
inducers were 500 mm long and 200 mm high. These plates were inserted in a freshly laid layer with the
help of jack hammer very easily.
Quality Control
The quality control was exercised effectively through well equipped Quality Control Laboratory installed
at upper dam site. The personnel involved in this were trained and the supervisor had responsibility for
evaluating and controlling the following on a daily basis:
. Proper aggregate gradation
. Quality of cement and fly ash
. Mixture proportion and variability at the mixing plant
. Temperature and water content of fresh concrete both at mixing plant and placement points
. Fresh density and workability of the RCC (in terms of the Ve-Be time) insitue density
. Compressive and direct tensile strength
Conclusions
The in-situ properties of RCC for saddle dam are now available based on this; suitable optimized RCC
mix proportion would be adopted for the lower dam. The lower dam RCC placement will be started only
after analysis of the results of full scale trial on saddle as well as of upper dam. At the moment micro
planning for execution of lower dam is being done on the basis of experience gained during this long
learning curve. In general, the successful completion of Saddle and upper dam has boosted the level of
confidence for everyone who has participated in this process with a view to achieve an excellent RCC
dam. This step by step approach will facilitate in building the confidence level and heading towards
perfection. The lessons learnt from each earlier dam regarding the mix design, construction methodology,
adequacy of plant and equipment, results of strength obtained will be useful for construction of 84 m high
lower dam which is the main target.
The daily rate of placement of LHS of upper dam with the batch plant of 120 m3/hr was 900 m3. The two
batch plants of 120 m3/hr, are installed at lower dam and suitable augmentation in batch plant capacity
will be done. So that about 600000 m3 of RCC will be placed with average monthly rate of placement
40000 m3 in 15 months. Due to mon soon, the placement will be done in two seasons. This will be fastest
dam building activity in order to commensurate the commissioning of 250 MW powerhouses. This is
possible only because of decision of going for RCC. Thus, on the successful completion of the three dams
in general and lower dam in particular the new trend will be set for adopting RCC technology in
upcoming new dams for hydroelectric projects in the country.
x.x.x.x.x.x.x
References
Dunstan, Malcolm – November 99 ‘Report on construction methodology for upper and lower dam. MERI
Nashik – December 2000. ‘Report on RCC mix design for Ghatghar Project’.
Dunstan, Malcolm – December 2002 and February 2003 Report on Value- Engineering proposal for the
upper and lower dam.
208
Page 197
31 INDUCTION TRAINING PROGRAM
N.S
.L
N.S.L
River valley
• The hard rock foundation below the normal
river overburden
• Sand, loose rocks and boulders
Page 198
31 INDUCTION TRAINING PROGRAM
Page 199
31 INDUCTION TRAINING PROGRAM
Fault line
Paleolithic landslide
Page 200
31 INDUCTION TRAINING PROGRAM
Page 201
31 INDUCTION TRAINING PROGRAM
Page 202
31 INDUCTION TRAINING PROGRAM
Foundation Preparation
Foundation Preparation
Foundation Preparation
• The foundation surface should be shaped by excavation and
filling
• Foundations such as shale, chalk, mudstone, and siltstone
may require protection against air and water slaking.
• These excavations may be protected by leaving a temporary
cover of unexcavated material, immediately applying a
minimum of 12 inches of cement mortar to the exposed
surfaces.
Page 203
31 INDUCTION TRAINING PROGRAM
Foundation Problems
Most of the dams have to be built on complex foundations
requiring special treatments. Various types of geological
features encountered are:
1. Faults
2. Shear Zones
3. Shear Seams
4. Shattered/Highly jointed rock
5. Foundations with more than one type of rock with
different properties
6. Folds
7. Buried Channels
8. Jointing pattern of the rock mass
9. Caverns/Cavities
10. Springs etc.
Page 204
31 INDUCTION TRAINING PROGRAM
Page 205
31 INDUCTION TRAINING PROGRAM
Grouting
• Grouting is the process of injecting liquids,
mixed suspensions, or semi-solid mixtures
under pressure to achieve one or more
desirable end results in terms of improving
engineering properties.
• Permeation grouting is the injection of high-
mobility grouts (HMGs) into small voids or
low-( mobility grout (LMG) for effective filling
of large voids.
Page 206
31 INDUCTION TRAINING PROGRAM
Purpose of Grouting
Permeability Reduction:
• Necessary for reducing rates of seepage or
leakage through or into structures and
foundations
• Reducing hydrostatic forces acting on structures,
• Inhibiting internal erosion of foundation and
embankment materials
• In any critical hydraulic application, grouting is
normally one of several lines of defense.
Purpose of Grouting
Improvement of Mechanical Properties
• Enhancement of bearing capacity
• Improvement in settlement-related
properties such as elastic modulus and void
ratio
• Improvement in shear strength, and
elimination of voids that might adversely
affect either loading conditions or the
response to loads.
Page 207
31 INDUCTION TRAINING PROGRAM
Page 208
31 INDUCTION TRAINING PROGRAM
Page 209
31 INDUCTION TRAINING PROGRAM
Types of Grouting
• Suspension-type grouts:- The suspension-type
grouts include clay, cement and lime
• Emulsion-type grouts:- The emulsion-type
grouts include bitumen
• Solution type grouts:- The solution-type
grouts include a wide variety of chemicals
Page 210
31 INDUCTION TRAINING PROGRAM
Page 211
31 INDUCTION TRAINING PROGRAM
Foundation Grouting
In concrete dam foundation, two kinds of
grouting programme are usually identified:-
• Consolidation grouting
• Curtain grouting
Consolidation Grouting
• The intent is to fill open fractures to improve the structural
properties of the rock mass.
• To reduce deformations associated with closing of fractures
under applied loads,
• To treat locally fractured zones and thereby homogenize
the foundation,
• To fill fractures for the purpose of reducing movement of
rock blocks that might otherwise loosen during excavation
and/or tunneling operations.
• For foundations in karst areas to increase the level of
assurance of adequate foundation support.
• The enhancement value of consolidation grouting depends
on the rock mass conditions. Greatest benefit will occur in
highly fractured rock masses with a predominant number
of open joints.
Page 212
31 INDUCTION TRAINING PROGRAM
Consolidation Grouting
Consolidation Grouting
• Drilling and grouting is usually done from
excavated surface
• Holes drilled normal to the foundation
• For the dams more than 30 m in height, it is
usual to drill holes to a depth of 6 to 15 m.
• Spacing of 3 to 8 m.
Page 213
31 INDUCTION TRAINING PROGRAM
Consolidation Grouting
• Grout pressure is governed by rock condition.
• These pressure could be as low as 0.06 MPa to
a high range of 0.5 to 0.7 MPa.
• Consolidation grouting is usually done
through a 76 mm to 150 mm holes.
• Ascending Method
• Descending Method
• IS : 4999
Consolidation Grouting
Page 214
31 INDUCTION TRAINING PROGRAM
Grout Mix
• The grout mixes used for consolidation grouting are normally either
balanced stable grouts or neat cement grouts.
• Neat cement grouts generally develop a higher compressive
strength and have a shorter set time, either type of mix would
normally suffice, and the choice of one versus the other is
predominantly based on the project size and type rather than on
specific property differences.
• For example, on a dam project where balanced stable grouts are
being used extensively in a hydraulic barrier application, it would be
logical to use the same grouts for consolidation grouting. On a
foundation improvement project where the only activity is
consolidation grouting, it might be more logical to use neat cement
grouts to limit execution complexity.
• Where neat cement grouts are used, the starting mix should not be
thinner than a 2:1 water-cement ratio (by volume). If it is found that
thickening is routinely required during the grouting, the starting mix
should be changed to a 1:1 water-cement ratio
Refusal criteria
• Reaching a certain rate of grout take or reaching
zero measurable take.
• Sometimes the definitions incorporate rates of
take that vary with the applied pressure.
• Refusal be defined as the point at which there
has been no measurable take (3-4 l/minute) at
the desired pressure within a 15-minute period.
• It varied project to project based on various
factors.
Page 215
31 INDUCTION TRAINING PROGRAM
Curtain Grouting
• Grout curtain is provided near the heel of dam to
impede the flow of water under or around the
dam.
• Usually a single line of grout holes is provided
below concrete dams
• High grout pressures without causing
displacement in the rock or loss of grout through
surface cracks, curtain grouting is carried out
subsequent to consolidation grouting and after
some of the concrete has been placed.
Curtain Grouting
Page 216
31 INDUCTION TRAINING PROGRAM
Curtain Grouting
Curtain Grouting
• The grout holes are angled in the upstream
direction or parallel to dam axis. The
alignment of grout holes should be such that
the base of the grout curtain will be located
on the vertical projection of the heel of the
dam.
• When the holes are drilled from upstream
fillet, they are usually vertical or inclined
downstream.
Page 217
31 INDUCTION TRAINING PROGRAM
Curtain Grouting
• The depth of the grout curtain holes depends upon the
nature of the rock in foundation and in general, it may
range from 30 to 40 percent of the head of the water
on good foundation and to 70 percent of head on poor
foundations.
• According to IS: 11293 (Part2)-1993 “Guidelines for the
design of grout curtains”, the following empirical
criteria may be used as a guide:
• D= (2/3) H + 8
Where D is the depth of the grout curtain in meters
and H is the height of the reservoir water in meters.
Curtain Grouting
• Grout pressures are set to maximum permissible
values for each segment and depth zone of the
grout curtain on the basis of experience and
geological evaluation supported by test grouting.
• Thumb rule for determining the maximum
allowable pressure at the collar of the hole is that
grout pressure should not exceed 0.23 Kg/sqcm
per meter depth of the rock for average to weak
rock.
• For sound rock with tightly interlocked joints,
grout pressure several times of this value could
be achieved.
Page 218
31 INDUCTION TRAINING PROGRAM
Curtain Grouting
• Lugeon tests will determine the groutability of the rock mass and the
type of grout to be used. Refer the following table for details
• The hydraulic conductivity is expressed in terms of the Lugeon value,
which is empirically defined as the hydraulic conductivity required to
achieve a flow rate of 1 litre/minute per meter of test interval under a
reference water pressure equal to 1 MPa
1–3 No grouting
Page 219
31 INDUCTION TRAINING PROGRAM
Grouting
• Grouting for ground engineering is a process
for filling the voids, fissures or cavities existing
in the soil and rock to improve water-tightness
or mechanical characteristics
• The most important aim of the ground
investigation for grouting is to identify if or not
the ground is suitable for the intended
grouting technique i.e. groutability of the
ground.
Grouting Techniques
• Rock Fissure Grouting,
• TAM Grouting,
• Compaction Grouting,
• Compensation Grouting and
• Jet Grouting
Page 220
31 INDUCTION TRAINING PROGRAM
Page 221
31 INDUCTION TRAINING PROGRAM
Page 222
31 INDUCTION TRAINING PROGRAM
Page 223
31 INDUCTION TRAINING PROGRAM
Page 224
31 INDUCTION TRAINING PROGRAM
Axis
EL-1187.00
M:20
Colcrete
River Flow
Colcrete
Compacted Clay
ROCK LINE
ROCK
Jet Grouting
Page 225
31 INDUCTION TRAINING PROGRAM
Jet Grouting
• Mono-fluid system: Cement grout is used as desegregating and
consolidation fluid. In this the erosion and soil cementation are
achieved with the same fluid (Cement gout) forming a jet stream
when directed at the ground.
Jet Grouting
Page 226
31 INDUCTION TRAINING PROGRAM
Page 227
31 INDUCTION TRAINING PROGRAM
Jet Grouting
Jet Grouting
Page 228
31 INDUCTION TRAINING PROGRAM
Jet Grouting
Jet Grouting
• A jet grouted element corresponds to the volume of soil
eroded and cemented from a single borehole. When
rotating and simultaneously translating the erosive jet
stream in the borehole with constant speeds, a column is
formed having the shape of a cylinder in homogenous soil.
In heterogeneous ground, with obstacles, the jet grouted
column obtained has an irregular shape. The column
diameter varies all along the borehole as a function of the
resistance opposed by the soil to the jet erosion and as a
function of the parameters of execution.
• The jet grouted materials is the soil- cement mixture left in
the ground by the process, and constituting the body of a
jet grouted element after setting. When jetting in sandy
soils, the jet grouted material is like a cement mortar.
Page 229
31 INDUCTION TRAINING PROGRAM
Jet Grouting
Grouting Scheme Design Considerations
• When the SPT N value is greater than 50, the
soil mass is normally classified as not suitable
for jet grouting.
• Presence of cobble / boulder will cause
‘Shadowing ‘ effect on cutting and mixing .
• The final strength of the mixed soil mass
relates to the purpose of the grouting
Jet Grouting
• Pure cement grout is used for jet grouting to
strengthen the ground.
• Compressive strength of soil cement mix
ranges from 2 MPa to 25 MPa
• For water sealing purpose, bentonite is usually
added to the cement grout
• The longer the cutting time is, the more the
original soil mass be displaced and the larger
the grout column diameter
Page 230
31 INDUCTION TRAINING PROGRAM
Jet Grouting
• Mixing time dictates the extent of mixing of
the grout and the soil mass.
• Prolonged mixing will eventually displace all
the soil mass and replace it with the grout.
• it is very important to monitor the verticality
of the jet columns
Jet Grouting
MAIN ADVANTAGES:
• Wide range of soils that can be successfully
treated
• Capability to obtain columns of consolidating soil
with diameter ranging from 60 to more than
200cm by using small diameter drilled holes, in
general not larger than 100 to 140 cm
• Capability to overpass pre-existing foundations
boulders, rocky layers
• Use of light weighing and small sized drilling rigs
in small working areas
Page 231
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
• A concrete cutoff wall is used as a remedial
measure for seepage control.
• Positive cutoff is created by excavating the soil
beneath the dam in form of a trench and the
resulting void backfilled with a barrier material of
well defined properties.
• Plastic concrete consists of aggregate, cement,
water, and bentonite clay mixed at a high water
cement ratio to produce a ductile material
Diaphragm Walls
Axis
EL-1187.00
M:20
Colcrete
River Flow
Colcrete
Compacted Clay
ROCK LINE
ROCK
Page 232
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
The diaphragm wall is constructed as a series
of alternate panels:
• Primary panels
• Secondary panels
Diaphragm Walls
Page 233
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
Diaphragm Walls
Cut-Off Wall Construction
Page 234
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
Diaphragm Walls
Page 235
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
Diaphragm Walls
Pl a stic Concrete: Cement, Bentonite ( 1 to 2%), Sa nd and 10 mm s ize Aggregates
Page 236
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
Diaphragm Walls
Page 237
31 INDUCTION TRAINING PROGRAM
Diaphragm Walls
Dental Treatment
• Process of remove the weak material and
reinforcing and stabilizing the weak zone by
backfilling with concrete is known as dental
treatment.
Page 238
31 INDUCTION TRAINING PROGRAM
Dental Treatment
• Final excavation uncovers the faults, seams or
inferior rock extending to such depths that it is
impracticable to clear such areas.
• It requires to excavate such areas to certain
depths and backfill with concrete.
• This procedure of reinforcing and backfilling
with concrete is called “Dental Treatment”.
Dental Treatment
Shasta and Friant dams Formula
Page 239
31 INDUCTION TRAINING PROGRAM
Abutment
Abutment
Page 240
31 INDUCTION TRAINING PROGRAM
Circular Failure
• Circular failure occurs in waste rock heavily
fractured rock and weak rock with no
identifiable structural pattern. The failure
surface is free to find a line of least resistance
through the slope. The slide is controlled by
shear strength i.e. cohesion and friction angle
Circular Failure
Page 241
31 INDUCTION TRAINING PROGRAM
Plane Failure
Occurs in rocks with plane discontinuities, e.g., bedding planes .
Wedge Failure
Occurs in rocks with intersecting discontinuities
forming wedges
Page 242
31 INDUCTION TRAINING PROGRAM
Toppling Failure
• Occurs in rocks with columnar or block
structures separated by steeply dipping joints.
In such failures rock block width and height
ratio is less than the gradient of the toppling
plane
Toppling Failure
Page 243
31 INDUCTION TRAINING PROGRAM
Analysis
• Stability analysis of abutments is usually
carried out limit equilibrium methods or by
FEM analysis
• PHASE-2’, ‘ABACUS’ and ‘SLIDE’, GEO SLOPES.
Page 244
31 INDUCTION TRAINING PROGRAM
Reservoir Rim
Following aspects of the reservoirs have to be properly
investigated:-
(a) water tightness of the basins
(b) stability of the reservoir rim
(c) availability of construction material in the reservoir area
(d) silting
(e) direct and indirect submergence of economic mineral
wealth and
(f) Seismo-techtonics.
Page 245
31 INDUCTION TRAINING PROGRAM
Investigation Stage
A topographical index map on 1:50 000 scale
should be used at this stage to delineate the
areas which would require detailed study,
subsequently.
Investigation Stage
To prevent an undesirable amount of leakage
from the reservoir, the likely zones of such
leakage, such as:-
• Major dislocations and
• Previous or cavernous formations running
across the divide of the reservoir should be
identified
Page 246
31 INDUCTION TRAINING PROGRAM 30 ITP
Examples:
• Dam
• Raft Foundation
• Pile Cap.
• Thick Wall.
• Thick column.
• Deep Slap.
•Section Thickness.
• Ambient Temperature.
Thermal Cracking
Thermal cracks occur when:
• The tensile stress due to thermal stress is
greater than the tensile strength of concrete
OR
Thermal cracks occur when:
• The thermal strain is greater than the tensile
strain capacity of the concrete
External Restraint
• Caused by the foundation rock (or the
hardened surface of already cooled concrete)
beneath the freshly placed concrete.
• The external restraint is of concern during
temperature drop in concrete from the
maximum temperature.
• Ratio of the height H to the length L of the
concrete block
Internal Restraint
• When different areas of concrete have
different temperature change and therefore
volume change
• The thermal stress due to internal restraint is
induced by differential temperature changes
when the surface is cooled by ambient air
temperature
Internal Restraint
• Internal restraint is the main cause of
transverse vertical cracks on the upstream and
downstream faces of dam due to severe
ambient conditions. Provision of the
transverse joints at suitable spacing serves to
control or mitigate this tendency.
Important definitions
• Adiabatic condition: adiabatic environment is
the environment perfectly thermally insulated
• Heat is Energy, Heat Quantity is measured by
(Kj/Kg), it is Quantity dependent variable
• Heat Flow: Heat flows in the direction of
decreasing temperature. (for concrete,
generally from the interior to exterior, since
the interior tend to be hotter
IQ-Drum
• IQ-Drum is a semi-Adiabatic Calorimeter, a
plastic cylinder 150×300mm filled by concrete
then place in its place in IQ-drum then
connected to thermo-sensor attached to the
IQ-drum by a thermocouple.
• IQ-drum measures: (every 15 minutes):
Sample temperature (measured in °C) and the
rate of heat loss from the calorimeter
(measured in millivolt) .
IQ Drum
Precooling
• Keep temperature of the mix water to
approximately 0oC
• Replacing a portion of mix water with ice
• Cooling the Aggregates
• These treatments resulted in a drop not over
10oC when concrete is placed.
• A drop less than 10oC have been obtained in
colder months only
Mix Design
• Heat generated within mass concrete is
directly proportional to the amount of cement
• Mix selected is that which will provide the
required strength and durability with the
lowest cement content
• Heat of hydration requirements at ages 7 and
28 days are 70 and 80 calories per gram
respectively for OPC
Mix Design
• Pozzolana are used in concrete along with
cement.
• In place of OPC, PPC is used for production of
mass concrete.
• Fly Ash is the most common Pozzolona used in
concrete.
• About 40 to 50 percent cement is replaced by
fly ash.
Placement Temperature
• The thermal study is carried as per the Indian
Standard, “ Temperature Control of Concrete
for Dams – Guidelines”, IS:14591-1999.
• The loss of heat is calculated separately for
the following three idealized conditions and
then the total loss is obtained by summation
phase losses
Placement Temperature
• The first idealized condition assumes that the
placement temperature of the concrete and
the atmospheric temperature are the same
that is 0°C and the lift is cast upon an inert lift
initially at 0°C. The loss of heat as it is
generated as given by the equation
T3 = η T0
η = Ratio of heat lost to the total heat
generated.
Placement Temperature
• Under the second idealized condition, the
heat loss due to the difference between the
placement temperature and atmospheric
temperature θo
• T2= calculated as equation given in code