Module II
Module II
जल शिक्त मंत्रालय
जल संसाधन, नदी िवकास और गंगा संरक्षण िवभाग
के द्रीय जल आयोग
रा ट्रीय जल अकादमी
िडजाइन और अनुसंधान
Module II : Analysis and Design Aspects of Embankment Dams
पुणे
नवंबर 2019
Government of India
Central Water Commission
National Water Academy
िडजाइन और अनुसंधान
Module-II
Module Co‐ordinator
Shri S N Pande, Director (Designs)
Pune
November 2019
Module – II
INDEX
2. Design of Core and Earth Filter in Earth and Rockfill dam 43-55
Embankment Dams
1. Introduction
• Water conservation and development of water resources for irrigation have attracted human
ingenuity since time immemorial.
• The oldest known works dates from 504 B.C. in Ceylon (now Sri Lanka).
• In India, the Grand Anicut across the Cauvery River, built more than 1600 years ago is still in service,
providing irrigation to 0.4 million hectares of land in the Cauvery delta.
• In the past, design of the earthen embankments was mainly carried by the rule of thumb and
judgment of the designer.
• The heights adopted were modest. Most of the embankments constructed earlier to 1900 AD were
of homogeneous type using locally available soils compacted by animal force.
• Puddle filled trenches and lime concrete or masonry core walls were usually provided.
• In the post-independence period there has been a great stride in water conservation and
development resulting in development of technology and design and construction of earthen
embankments.
• Dams have been built across rivers by mankind right from the dawn of civilization for storing the
water during rainy season and releasing it afterwards for other purposes: e.g. domestic, irrigation,
flood control and generation of hydro power.
• With the growth of population all these functions of dams and storages have assumed greater
significance.
• Dams constitute perhaps the largest and the most complex kind of structures being built by civil
engineers.
• Are built to last from 100 to 300 years depending upon merits of each case.
• Designed to withstand all the possible destabilizing forces with a certain factor of safety which has
been an indicator of a factor of ignorance or lack of knowledge of various response processes of
materials used in construction, the stresses caused, the strains experienced and finally the failure
mechanism.
• Large dams store very large volumes of water, therefore, has to be extra safe so that there is a
minimum probability of their failure and consequent rapid or sudden release of storage which can
cause havoc on the downstream.
• Homogeneous Embankment
• Zoned Embankment
• Rock-fill Dams with clay cores
• Rock-fill Dams with u/s Face Membranes
a) HOMOGENEOUS EMBANKMENT:
• In this type of embankment, the dam section entirely consists of almost one type of material.
• It is adopted due to compulsions of material availability within a reasonable distance.
Page 1
• A zoned section is always preferable, if materials in the two broad categories of ‘impervious or
semi-pervious’ and ‘pervious’ are available.
• Usually this type of section is made of low permeability material and requires flatter slopes
than a zoned section.
b) ZONED EMBANKMENT:
• This type of embankment uses two or more types of materials, depending on their availability,
utility and costs.
• There is an impervious zone called the ‘core’ inside the dam section.
• The outer zones on both sides, called ‘shells’, should preferably be of pervious materials.
• If different grades of pervious material are available, the coarser or more pervious materials
are placed on the outer faces.
• The different zones are separated by filters and even if the material in the shell is not pervious
enough, it may still be necessary to provide internal drainage.
• Any dam which relies on fragmented rock material, either obtained by blasting or available as
natural boulder deposits, as a major structural element is called a rock fill dam.
• Rock fill dams with earth cores usually have substantial rock fill zones on both sides, with an
impervious zone in the middle, and transition zones and /or filters in-between.
• There may be further zoning by material type gradation or degrees of compaction within each
category also.
• Good quality rock fill provides free drainage and high shear strength and most of the highest
embankment dams are of this type.
• This type is basically similar to zoned earth embankment.
3. Embankment Dams:
• Embankment dams are defined as those constructed primarily of the natural materials of the
earth, namely soil and rock.
• The principal vulnerability of an embankment dam is that it may be damaged or even
destroyed if insufficient height or spillway capacity allows overtopping and erosion of the dam,
or if uncontrolled seepage results in internal erosion of the embankment and its foundation.
Page 2
4. TERMINOLOGY :EMBANKMENT DAMS
• BORROW AREA – Source of construction materials for earth & rock fill dam.
• CASING – Zones except core in a zoned earthen dam, also called shell or shoulder.
• CORE – A zone of impervious earth within a zoned earth or rock fill dam.
• CUT-OFF – A barrier to reduce seepage of water through foundation and abutments.
• POSITIVE CUT-OFF – A cut-off taken to an impervious stratum. A full cut-off in the form of an
open excavated trench and back filled with compacted impervious material, also provided in the
form of sheet piles, plastic diaphragm, concrete diaphragm, grouted cut-off, cut-off wall, etc.
• PARTIAL CUT-OFF – A cut-off, which does not go down to impervious stratum.
• FULL RESERVOIR LEVEL (FRL) – The highest reservoir level that can be maintained without
spillway discharge or without passing water through sluiceways. It dose not include any depth
of surcharge.
• MINIMUM DRAW DOWN LEVEL (MDDL) – The lowest level to which a reservoir may be lowered
keeping in view the requirements for hydro-power generation or irrigation and other
requirements.
• FREEBOARD – The vertical distance between the crest of the embankment (without camber) and
the maximum reservoir water level.
• HORIZONTAL FILTER – A layer of uniform or graded previous materials placed horizontally.
• INCLINED/VERTICAL FILTER – A layer of uniform or graded pervious materials, placed inclined or
vertical.
• IMPERVIOUS BLANKET – An upstream impervious soil layer laid over a relatively pervious
stratum and connected to the core.
• RELIEF WELL – Relief Wells are generally provided downstream of partial cut-off to relieve excess
hydrostatic pressure.
• RIPRAP – It is the protection to the embankment material against erosion due to wave action,
velocity of flow, rain-wash, wind action, etc. provided by placing a protection layer of rock
fragments or manufactured material.
• TURFING – It is a cover of grass grown over an area to prevent erosion of soil particles by rain
wash.
• TOE DRAIN – A trench filled with filter material along the down-stream toe of an earthen dam
to collect seepage from horizontal filter and lead it to natural drain.
• PARAPET WALL– A wall provided along the edge of the embankment.
• PORE PRESSURE – The pressure developed in the fluid within the voids of the soil under external
force when drainage is prevented.
• ROCK TOE – A zone of free draining material provided at the toe of the dam.
Page 3
Earthen Dam with Central Core & Partial Cutoff
Page 4
6. FUNCTIONS AND DESIGN REQUIREMENTS OF COMPONENTS
Page 5
The core may be located either centrally or inclined upstream.
The locations will depend mainly on the availability of materials, topography of site,
foundation conditions, diversion consideration, etc.
The main advantage of a central core is that it provides higher pressure at the contact
between the core and foundation reducing the possibility of leakage and piping.
Inclined core reduces the pore pressure in the downstream part of the dam and
thereby increases the safety.
Also permits the construction of down -stream casing ahead of the core.
The following practical considerations governs the thickness of the core:
Availability of suitable impervious material
Resistance to piping
Permissible seepage through dam
Availability of other materials for casing, filter, etc.
Minimum width that will permit proper construction
The minimum top width of core should be 3 m with thickness at any height not less
than 30 percent (preferably not less than 50%) of maximum water head at that height.
The top level of the core generally should be fixed at 0.5 m above MWL.
Page 6
• The slopes of the embankment shall be stable under all loading conditions and flat
enough so as not to impose excessive stress on foundation.
• Slopes shall be designed as per the provisions contained in IS: 7894-1975.
• The u/s slope shall be protected against erosion by wave action and the crest and d/s
slope shall be protected against erosion due to wind and rain.
• The seepage through the embankment and foundation should be such as to control
piping, erosion and sloughing and excessive loss of water.
• Seepage control measures are required to control seepage through dam and foundation.
• Design for control of seepage through foundation may be made in accordance with
provisions contained in IS : 8414-1977.
• The phreatic / seepage line should be with in the d/s face of the dam section.
• If the dam section is homogeneous and no drainage arrangements are made, any
seepage is going to emerge on the d/s face.
• This results in “sloughing” or softening of the d/s face and may lead to local toe failure,
which may progressively develop upwards.
• This can be safeguarded against by providing a free draining zone on the d/s face or by
intercepting the seepage inside the dam section by internal drainage.
Overtopping 30%
Page 7
Seepage effect, Piping and Sloughing 25%
Slope Slides 15%
Conduit Leakage 13%
Damage to slope Paving 5%
Miscellaneous 7%
Unknown 5%
Especially in Embankment Dams the overtopping causes an instant failure of the dam.
Therefore sufficient margin is provided between the crest of embankment and the still
reservoir water surface to prevent this overtopping .
Free Board Provides safety against many contingencies such as :
1. Occurrence of a flood somewhat larger than the design flood.
2. Malfunctioning of the gates of the spillway & outlets.
3. Settlement of the Dam greater than the anticipated etc.
FREEBOARD
Page 8
It is the vertical distance between the crest of embankment (excluding camber) and the still
reservoir water surface. Freeboard mainly can be classified in two categories:
1. Normal Freeboard
2. Minimum Freeboard
NORMAL FREEBOARD
It is the freeboard above the full reservoir level (FRL).
MINIMUM FREEBOARD
It is the freeboard above the maximum water level (MWL) worked out for designed
inflow flood (DIF).
Page 9
14. Factors Considered For Freeboard Estimation.
Important Note
Freeboard requirement does not account for effect of
Earthquake
Settlement of dam
Dam foundation
Earthquake Seiches
Out of the available methods for freeboard computations/ assistance has been derived from “T.
Saville’s” method, which is widely used for free-board computation of embankment dams. The
details of the procedure to be followed for computation for freeboard are discussed later .
• Normal Freeboard
While calculating normal freeboard at FRL, full wind velocity should be adopted . The
design wave height (Ho) be taken as 1.67 times the significant wave height (Hs). Normal
freeboard should not be less 2.0m.
• Minimum Freeboard
While calculating minimum freeboard at MWL half to two third wind velocity should be
adopted . The lower values may be adopted in regions where maximum wind velocities
occur during the period when water level in the reservoir is at or below FRL. This
freeboard should be subject to a minimum of 1.5m . The design wave height (Ho) be
taken as 1.27 times the significant wave height (Hs).
• The freeboard which gives the highest requirement of TBL (Top Bund Level) should
finally be adopted.
• 1.0m high parapet wall may be provided in all embankment dams but the same is not to
be considered as a part of freeboard. The freeboard which gives the highest requirement
of TBL (Top Bund Level) should finally be adopted.
Page 10
16. Procedure for Computation of Freeboard for Embankment Dams
1. Normal Freeboard
Select a line “A-B” , with “A” on Dam axis and “B” on FRL contour.
So as to cover the maximum reservoir water spread area within 45 degrees on either
side of line AB (fetch length).
Draw seven radials at six degrees interval on each side of line “A-B” and compute
effective fetch (Fe) for FRL by the following formula :
ΣX1cos α (cos α)
Fe = ----------------------------
Σcosα
Where X1 denotes the length of any radial which is at an angle the central radial.
If felt necessary more trials may be done so that maximum effective fetch may be
computed. Enter effective fetch (Fe) as step (1) .
From Fig. 1 of IS 875 (Part3):1987 read basic wind speed on land for 50years return
period (U) for region in which proposed dam falls. Enter wind velocity on land (U) as step
(2).
Compute wind velocity on water surface (V) , by multiplying coefficient Q from Table
(Wind Velocity Relationship Land to Water)
Page 11
1 1.10
2 1.16
4 1.24
6 1.27
8 1.30
10 and above 1.31
Corresponding to effective fetch to the wind velocity on land (U) . Enter Q and wind
velocity on water surface as steps (3) and (4) respectively.
Enter Ts as Step 6.
Page 12
2 Flexible brick pitching 0.8
3 Hand placed rip rap 0.75
(a) Laid flat 0.60
(b) Laid with projection
4 Dumped rip rap 0.50
Calculate average water depth (D) along fetch length (F). Enter average reservoir depth
(D) as Step 13.
Compute wind set–up (S) from the formula:
s = V2 . F/ 62000 D.
If wind set–up as calculated above is higher than the average depth of water , the value
of wind set-up should be limited to average depth of water. Enter wind set–up (S) as
Step 14
Compute Freeboard as step (12) + step (14). Enter as Step 15.
If freeboard calculated in step (15) is less then 2.0 meters , if so provide at least 2.0
meters freeboard. Enter required freeboard as Step 16.
Minimum Freeboard at MWL
For obtaining minimum freeboard at MWL repeat above procedure by calculating fetch
length (F) and effective fetch (Fe) at MWL. Half to two –third wind velocity on land and
effective fetch at MWL may be adopted for different calculations using above steps.
Check, if minimum freeboard is less than 1.5 m and if so, provide at least 1.5 m
freeboard.
Fixing of TBL:- Calculate the TBL required for the following conditions and enter as step
(17).
FRL+ Normal freeboard (not less than 2.0 m )
MWL + Minimum freeboard ( not less than 1.5 m ).
Adopt the highest of the above two values as TBL.
Page 13
Relative Homogeneous Zoned Earth Dam Impervious
Suitability Dykes Blanket
Imperious Pervious
GC SW, GC
Very suitable GC
GW
Suitable CL, CI CL, CI GM CL, CI
GM, GC, SM, SC, SP, GP CH, SM, SC, GC
Fairly suitable SP, SM, CH
CH
Very well graded coarse mixtures of sand, gravel and clayey fines, D85
Very
1. coarser than 50mm, D50 coarser than 6mm. If fines are cohesion less, not
Good
more than 20 % finer than 75 micron IS Sieve.
a) Well graded mixture of sand, gravel and clayey fines, D85 coarser than
25mm. Fines consisting of inorganic clay (CL with plasticity index greater
2. Good
than 12).
b) Highly plastic tough clay (CH with plasticity index greater than 20).
a) Fairly well graded, gravelly, medium to coarse sand with cohesion less
fines. D85 coarser than 19mm, D50 between 0.5mm and 3.0mm. Not more
3. Fair
than 25% finer than 75 micron IS Sieve.
b) Clay of medium plasticity (CL with plasticity index greater than 12).
a) Clay of low plasticity (CL and ML) with little coarse fraction. Plasticity
index between 5 and 8. Liquid limit greater than 25.
4. Poor b) Silts of medium to high plasticity (ML or MH) with little coarse fraction.
Plasticity index greater than 10
c) Medium sand with cohesion less fines.
Page 14
a) Fine, uniform, cohesion less silty sand, D85 finer than 0.3mm.
5. Very Poor b) Silt from medium plasticity to cohesion less (ML). Plasticity index less
than 10.
M - IMPERVIOUS P - PERVIOUS
SP - SEMI-PERVIOUS SM - SEMI-
IMPERVIOUS
R - RANDOM, INCLUDING SP OR SM
Page 15
M - IMPERVIOUS P - PERVIOUS
SP - SEMI-PERVIOUS SM - SEMI-
IMPERVIOUS
R - RANDOM, INCLUDING SP OR SM
Page 16
M - IMPERVIOUS P - PERVIOUS
SP - SEMI-PERVIOUS SM - SEMI-IMPERVIOUS
R - RANDOM, INCLUDING SP OR SM
M - IMPERVIOUS P - PERVIOUS
SP - SEMI-PERVIOUS SM - SEMI-IMPERVIOUS
R - RANDOM, INCLUDING SP OR SM
M - IMPERVIOUS P - PERVIOUS
SP - SEMI-PERVIOUS SM - SEMI-IMPERVIOUS
R - RANDOM, INCLUDING SP OR SM
Page 18
• Advantages of Central Core
Provides higher pressure on the contact surface between the core and the foundation,
thus reducing the possibility of hydraulic fracturing.
For a given quantity of soil, the central core provides slightly greater thickness.
Provides better facility for grouting of foundation or contact zone or any cracks in the
core if required afterwards, as this can be done through vertical rather than inclined
holes.
Foundation area is independent of depth of foundation and hence can be marked and
treated in advance.
• Disadvantages of Central Core
The advantages listed for a vertical core are not obtainable. Also, a moderately thick
central core with pervious shells will result in a slightly flatter downstream slope of the
dam.
The problem of differential settlement between the core and the shell zone may result
in cracking parallel to the dam axis.
• Advantages of Slanting Core
D/S rockfill can be placed in advance and laying of filter, core and U/S zone can be taken
up later. Ensures rapid progress, especially in conditions wherein core placement is
possible only during part of the year.
Foundation grouting of the core can be carried out while the downstream shell is being
placed and thus better progress achieved.
Since a very small part of the slip surface intersects the slanting core, the section is
practically free from the steady seepage pore pressures and is thus more stable under a
steady-state condition. This results in a steeper slope of the downstream shell and
corresponding economy.
Since the flow lines are essentially vertical and equipotential lines are almost horizontal
under sudden drawdown, the drawdown pore pressures are very much reduced.
However, a larger part of the slip surface for the upstream slope passes through the core
material than would be the case with a central core.
In the case of cracking of the core, the inclined core will leave a large mass of stable
rockfill on the downstream side and is likely to be safer.
Filter layers can be made thinner and placed more conveniently.
Contact area treatment becomes difficult : The depth of excavation of the foundation at
the contact surface of the core is determined by the nature of the formations and cannot
be predetermined in advance. Thus advance treatment of the contact area may present
a problem in the case of a slanting core because if the depth of excavation increases, the
contact area moves upstream.
Upstream slope becomes flat: By slanting the core upstream, although the downstream
slope can be made steeper, nevertheless, the upstream slope will generally become
Page 19
flatter as the shear strength of the core material will be less than that of the pervious
shell material; the advantage of reduced drawdown pore pressures may not
compensate this factor. Thus any economy in total quantity of materials by adjustment
of core position would depend on the relative strength of the two materials.
EXPANSIVE SOIL
Expansive soils exhibit heaving with the increase in moisture content, exert swelling
pressures on the structures restraining the heave.
During summer, wide, deep and map type cracking is normally observed.
Structure constructed using conventional methods exhibit heaving of floors, cracking of
walls and jamming of doors during rainy season. Restraining structures get tilted and
roads get rutted.
Bed heaving and side slips and sloughing are noticed in canals.
DISPERSIVE SOIL
Dispersive clays refer to clays in which physico-chemical state of the clay fraction of the
soil is such as to cause individual clay particles to disperse and repel each other in the
presence of relatively pure water.
Highly erodible by water flow with low hydraulic gradients and tractive stresses.
Non-cohesive silt, rock flour, and very fine sands also disperse in water and may be
highly erodible.
CASING : The function of casing is to impart stability and protect the core. Relatively pervious
materials, which does not crack on direct exposure to the atmosphere, are suitable for casing.
INTERNAL DRAINAGE SYSTEM: Comprises of inclined or vertical filter, a horizontal filter, a rock
toe, a toe drain, etc.
The design of filter consists of applying the conventional filter criteria, which take into
account the grain size distribution and the shape of the grains.
However, in addition to the grain size, the stability of the base soil adjacent to a given
filter depends on its resistance to drag forces.
Inclined or vertical filter together with the base filter, if required, is desirable to be
provided especially to protect the core material from migration.
Also filters help in controlling the leak through cracks in the core and subsequent repair
by it self of the crack.
However, the inclined or vertical filter may be avoided in zoned sections having pervious
d/s shell and clayey cores but a transition filter between the core and the d/s shell would
be necessary in case of dams where rock fill is used as shell material. Adequate toe
protection shall, however, be provided.
Page 20
Internal Drainage System
SLOPE PROTECTION:
U/S Slope
The upstream slope protection is ensured by providing riprap.
The riprap can be placed on the slope either by hand or it may be simply dumped.
For design of the riprap, IS: 8237-1985 may be referred.
The thickness of riprap in no case is less than 300mm.
Downstream Slope:
Page 21
The downstream slope protection is ensured by providing riprap or turfing.
If the average annual rainfall (AAF) is less than 200cm, it is usual practice to protect the
downstream slope from rain cuts by providing suitable turfing on the entire slope.
In case if AAF is more than 200cm, 300mm thick riprap is provided.
For details of d/s slope protection such as prevention from erosion by Rain-wash,
prevention from erosion by tail water IS: 8237-1985 may be referred.
IMPERVIOUS BLANKET
The horizontal u/s impervious blanket is provided to increase the path of seepage when
full cut-off is not practicable on pervious foundations.
The impervious blanket may be provided either with or without partial cut-off.
Impervious blanket shall be connected to core of the dam.
The material used for impervious blanket should have far less permeability than the
foundation soil.
To avoid formation of cracks, the material should not be highly plastic.
300 mm thick layer of random material over blanket is recommended to prevent
cracking due to exposure to atmosphere.
As a general guideline, impervious blanket with a minimum thickness of 1.0 m and a
minimum length of 5 times the maximum water head measured from upstream toe of
the core may be provided.
The impervious blanket may be designed in accordance with IS: 8414.
Reference may be made to IS: 1498 for suitability of soils for blanket.
RELIEF WELLS
Consists of a pipe (10 to 15 cm dia) having narrow slots placed in the centre, surrounded
by graded filter media (45 to 90 cm dia) sunk near d/s toe of earth dam.
Permit the ingress of seepage water into the well allowing it to rise to the outfall (relief)
level where the pressure gets relieved.
Ensures safety of the earth dam when the cut-off is partial or reliance is placed on
upstream blanket for controlling seepage,
Controls the pressure developed below the d/s toe of the dam, especially when
impervious layer of the soil at the top overlays a pervious layer.
A system of relief wells suitably spaced reduces the intensity of the under seepage
pressure and render it practically harmless.
Page 22
Page 23
18. ROCK FILL DAMS WITH EARTH CORES
Any dam which relies on fragmented rock material, either obtained by blasting or available
as natural boulder deposits, as a major structural element is called a rock fill dam.
Rock fill dams with earth cores usually have substantial rock fill zones on both sides, with an
impervious zone in the middle, and transition zones and /or filters in-between.
There may be further zoning by material type gradation or degrees of compaction within
each category also.
Good quality rock fill provides free drainage and high shear strength and most of the highest
embankment dams are of this type.
This type is basically similar to zoned earth embankment.
The rock for main rock fill should be hard, sound and durable so as to resist excessive
breakdown during handling and placing operations.
In general, un-weathered igneous and metamorphic rocks are suitable for rock fill, while
sedimentary rocks are not desirable.
Shale’s (a type of rock) which slake in the presence of air and rocks which shatter into very
small pieces or have high percentage of chips or dust are not suitable. The chips and dust
should not be more than 10%.
The angular bulky rocks are preferred as against flat elongated rocks or rounded boulders.
If rounded cobbles or boulders are used, they should be scattered through out the rock fill
and not concentrated in pockets.
Page 24
20. CHOICE OF TYPE OF DAM
TYPE OF DAM
• Rigid
• Flexible
• Foundation Geology
• Construction Materials aspect
• Valley shape
• Construction Equipment
• Cost
• Safety
21. SELECTION OF DAM SECTION
No single type of cross-section of embankment dam is suited for all site conditions. The
adoption of the particular type of embankment section depends upon the following
factors:
• The designs of all dams in general and embankment dams in particular are site specific
and cannot be generalized.
• The design has to be suited to valley shape and foundation geology, available materials
and methodology of construction.
Page 25
• As an important dam project involves a heavy investment, the designer is bound to study
several feasible alternatives of dam height and reservoir capacity, layout of dam and
ancillary works, and the dam section to meet the objective of optimum benefits.
• In the context of benefits, it is necessary to optimize the benefits for the river basin as a
whole rather than for an individual project.
The adoption of the particular type of embankment section depends upon the following factors:
Availability of the suitable local material in sufficient quantity within reasonable range.
Foundation conditions and cut-off requirements.
Types of construction, earth moving compaction machinery.
Diversion consideration and construction schedule.
Climatic conditions in relation to placement, moisture content control etc.
Safety with respect to stability and seepage.
In addition to basic design requirements, the following special design requirements, should also
be satisfied for both earth and rock fill dams:
Control of cracking
Stability in earthquake regions
Stability at junctions
Cracking of impervious zone results into a failure of an earth dam by erosion, piping,
breaching, etc. Due consideration to cracking phenomenon shall, therefore, be given in
the design of earth dam.
Cracking in the core of earth or rockfill dam occurs due to foundation settlement and/or
differential movements within the embankment.
Differential movements in the embankment take place due to the following reasons:
Unsuitable and/or poorly compacted fill materials
Different compressibility and stress-strain characteristics of the various fill
material
Variation in thickness of fill over irregularly shaped or steeply inclined abutments
24. MEASURES ARE RECOMMENDED FOR CONTROL OF CRACKING :
Use of plastic clay core and rolling the core material at slightly more than optimum
moisture content. In case of less plastic clay, 2 to 5 percent bentonite of 200 to 300 liquid
limits may be mixed to increase the plasticity.
Use of wider core to reduce the possibility of transverse or horizontal cracks extending
through it.
Careful selection of fill materials to reduce the differential movement. To restrict the
rockfill in lightly loaded outer casings and to use well graded materials in the inner
casings on either side of the core.
Wide transition zones of properly graded filters of adequate width for handling drainage,
if cracks develop.
Page 26
Special treatment, such as preloading, pre-saturation, removal of weak material, etc. to
the foundation and abutment, if warranted.
Delaying placement of core material in the crack region till most of the settlement takes
place.
Arching the dam horizontally between steep abutments.
Flattening the downstream slope to increase slope stability in the event of saturation
from crack leakage.
Cutting back of steep abutment slopes
Dams situated in earthquake zones are likely to be subjected to additional stresses and
deformation on account of earth acceleration. This needs a special treatment.
Following are the additional factors to be considered while designing an earth dam in
earthquake zones:
The stability of the slopes of the embankment under the extra forces set up by
the lateral and vertical accelerations.
The settlement of loose or poorly compacted fill or foundation material leading
to loss of freeboard and thereby possible overtopping.
The cracking of the impervious fill leading to possible failure by piping.
Liquefaction of deposits of loose sand in the foundation of the dam, causing
cracking, sliding or actual horizontal movement of the dam.
The stability analysis of slopes with earthquake consideration shall be carried out in
accordance with the provisions contained in IS: 7894-1975.
Additional freeboard shall be provided to avoid possible overtopping due to settlement
of embankment or foundation or both during an earthquake.
The provisions shall be made for discharging the maximum anticipated leakage rapidly.
For this purpose, downstream zones of large quarried rock or screened gravels and
cobbles are recommended.
The impervious core shall be made thicker for resisting the piping action.
The top of the dam should be made thicker by increasing the crest width or by using
flatter slopes at the top than would be required in non-seismic regions, so as to increase
the path of seepage through cracks.
The foundation should be as compact as possible. All loose and soft material should be
excavated and removed, if possible, or re-compacted.
27. STABILITY AT JUNCTIONS
Page 27
Junctions or earthwork with foundation, abutments, masonry structures like overflow and non
overflow dams and outlets need special attention with reference to one or all of the following
criteria:
Good bond between earthwork and foundation
Adequate creep length at the contact plane
Protection of earth dam slope against scouring action
Easy movement of traffic
Foundations on soils or non-rocky strata, vegetation like bushes, grass roots, trees, etc.
should be completely removed.
The soil containing organic material or dissoluble salt should also be completely
removed. After removal of these materials, the foundation surface should be moistened
to the required extent and adequately rolled before placing embankment material.
For rocky foundation, the surface should be cleaned of all loose fragments including
semi-detached and over-hanging surface blocks of rock. Proper bond should be
established between the embankment and the rock surface so prepared.
The rocky abutments should be suitably shaped and prepared in order to get good
contact between the impervious core of the embankment and the rock. Overhangs, if
any, should be removed.
Vertical surfaces should be excavated to form moderate slopes, not less than 1 in 4 to 1
in 5. A wider impervious zone and thicker transitions are also provided sometimes at
the abutment contacts to increase the length of path of seepage and to protect against
erosion.
Sufficient creep length should be provided between impervious section of the dam and
the abutment, so as to provide safety against piping. The creep length should be not
less than 4 times the hydraulic head.
Junction of non-overflow masonry/concrete dam with earth dam shall be established by
proper compaction of contact layers.
Proper bond should be provided between the earthwork and the outlet walls.
Page 28
28. CHOICE OF CONSTRUCTION MATERIALS FOR EARTHEN DAMS
• Because of huge quantities of material involved in construction of earth dam, the material
must come from borrow areas and quarries close to the site.
• The earth dam may be designed as a homogeneous one or zoned type depending upon the
qualities and quantities of the various materials available from the borrow areas and
foundations.
• To economize the design, even erratic material that cannot be relied upon to have the
consistent minimum properties needed for any zone can be utilized in random zones.
• It is general practice to utilize the materials available in their natural state rather than to
improve the properties of the materials by blending, mixing, screening, washing, etc.
• The designer should aim at maximum utilization of the material available from compulsory
excavation.
• The soils available from the borrow areas and excavation shell be identified and classified in
accordance with IS: 1498 – 1970.
29. DESIGN CONDITIONS OF SLOPE STABILITY ANALYSIS
• An earth dam shall be safe and stable during all phases of construction and operation of the
reservoir.
• Hence, the analysis shall be done for the most critical combination of external forces which
are likely to occur in practice.
The following conditions are usually critical for the stability of an earth dam:
Page 29
Case I – Construction condition with or without partial pool (for upstream and
downstream slopes).
Case II – Reservoir partial pool (for upstream slope),
Case III – Sudden drawdown (for upstream slope),
Case IV – Steady seepage (for downstream slope),
Case V – Steady seepage with sustained rainfall (for down stream slope) where
annual rainfall is 200 cm or more,
Case VI – Earthquake condition (for upstream and down-stream slopes)
30. METHOD OF SLOPE STABILITY ANALYSIS
The methods of analyzing the slope stability depending upon the profile of failure surface are:
Circular arc method
Sliding wedge method
CIRCULAR ARC METHOD
In this method of analysis the surface of rupture is assumed as cylindrical or in the cross
section by an arc of the circle.
This method, also known as Swedish or Slip Circle method, is generally applicable for
analyzing slope of earth dams and dams resting on thick deposits of fine grained
materials.
SLIDING WEDGE METHOD
The sliding wedge method of analysis is generally applicable in the circumstances
where it appears that the failure surface may be best approximated by series of
planes rather than a smooth continuous curve as for the method of circular arc.
This method is predominantly not much used.
For details refer BIS code IS: 7894-1975 code of practice for stability analysis of
Earth Dam.
31. MINIMUM DESIRED VALUE OF FACTOR OF SAFETY AS PER B.I.S. FOR THE VARIOUS
LOADING CONDITIONS
Page 30
• In regions of seismic activity stability calculation of the slope of a dam should also include
seismic forces because they reduce the margin of safety or may even bring about the
collapse of the structure.
• General design approach for earthquake forces is given in IS: 1893-1984. Where the
analysis is carried out by the circular arc or sliding wedge method, total weight of the
sliding mass considered for working out horizontal seismic force shall be based on
saturated unit weight of the zones below the phreatic line and moist weight above it.
• If the zone above the phreatic line is freely draining, drained weight shall be considered
for that zone.
• The critical condition of analysis of upstream slope for operating condition is the sudden
drawdown.
• When the reservoir is full the seepage pressure acting toward the downstream side
increases the resistance of upstream slope toward the sliding and as such, such a
condition is not considered most critical. However this condition combined with
earthquake force is considered critical as the stability of upstream slope get reduced and
may lead to the failure of dam when the reservoir is full.
• Similarly, the down stream slope of the dam shall be analyzed for a condition of steady
seepage combined with earthquake forces.
• After deciding upon the tentative cross section of the proposed earth dam a possible circular
failure surface through the dam and foundation is assumed.
• Theoretically it is necessary to try an infinite number of possible failure circles with different
centers and radii before the most critical one giving lowest accepted factor of safety may be
located.
• In practice, however, a limited number of slip circles, about 12 to 15, selected on the basis of
past experience are considered sufficient for each condition of analysis.
• After trying about 12 to 15 failure circles, if the lowest value of factor of safety is acceptable the
profile of the section needs no changes and the assumed profile shall be considered adequate
from consideration of stability.
• The circle which yields the minimum value of factor of safety is the most critical.
• The circle which yields the minimum value of factor of safety is the most critical.
• However, if the value of the factor of safety obtained for the critical failure arc is more than
required, the section shall be modified by reducing the berm widths and steeping the slopes.
Page 31
• The above process shall be repeated till the profile of the section gives the required factor of
safety. If, on the other hand, the value of the factor of safety obtained during the process of
calculation for the failure surface is less than the minimum acceptable, the same shall be
increased to the required value by trials after carrying out necessary changes in the profile.
• For the sake of simplicity and reducing the calculations, the various materials, namely, riprap,
internal filters, rock-toe, etc. falling within the sliding mass shall be considered to have the same
properties as those of the respective zones within which they are located.
• This will not materially affect the value of factor of safety as these materials usually cover only
a small area as compared to the area of the zones in which they are located.
• However, if such materials cover appreciable cross- sectional area, they shall be considered
separately.
• Stability analysis of the slope shall be done for sections of dam for different heights, the entire
length being divided into suitable reaches.
• In deciding the reaches, variations in foundations conditions shall also be taken into account.
• The trial sliding mass is divided into a number of vertical slices. The number of slices depends
upon the width and mass of the sliding mass, number of various zones included in the sliding
mass and the accuracy desired.
• For zoned embankment and stratified foundations with different properties, where an arc of the
potential failure surface passes through more than one type of material, the vertical ordinates
of the slices for each zone or part of the foundation shall be obtained by locating the slice at
each such dividing point.
• The slices (for convenience) may be of equal width though it is not rigidly necessary to do so.
The failure surface is shown in Figure.
• The driving forces and resisting forces are computed to calculate the factor of safety.
• The total weight W of the slice of width b is equal to the areas of the various zones included in
the slice multiplied by their respective appropriate units weights (soil plus water).
• This acts vertically downwards through the center of the gravity of the slice.
• The two components of this weight W, namely the force normal to the arc of the slice, N= W cos
and the force tangential to the arc of the slice, T= W sin are determined after resolving weight
W in the radial and tangential direction, being the angle made by the radius of failure surface
with the vertical at the center of the slice.
• In the total stress method of analysis the test results include the influence of pore water pressure
and hence they need not be accounted for separately in the analysis.
• However in the analysis by the effective stress method allowance for pore pressure shall be
made separately. The pore water pressure U acting on the arc of the slice results in an uplift
force which reduces the normal component of the weight of the slice.
• The net or effective downward force acting on the curved bottom boundary of the slice is the
total weight minus the upward force due to pore water pressure.
Page 32
• The effect of the pore pressure on resisting forces is accounted for by assuming buoyant weight
of the material lying below the phreatic line.
• Component of shearing resistance due to internal friction is therefore (N-U) tan, where is the
angle of shearing resistance of the material at the base of the slice and (N-U) is the effective
normal load N.
• Another force acting at the bottom of the slice and which opposes the movement of sliding mass
is the shearing resistance offered by the material due to its cohesion, C and is equal to the unit
cohesion, C multiplied by the length of the bottom of the slice and is approximately equal to c x
b / cos.
• In practice the length of the arc may be measured accurately as the expression b / cos shall not
give the length of arc of the slice when b is infinitely small.
• The total resisting or stabilizing force S developed at the bottom of the slice is equal to (c x
b/cos ) + (N-U) tan.
• The driving or the actuating force T due to the weight of the slice is equal to W sin.
• Similar forces are worked out for all the slices considered for a potential failure surface.
• The results of these components shall be tabulated and sums of the resisting and driving forces
shall be obtained.
Page 33
The factor of safety against sliding for the assumed failure surface is computed by the equation:
Where,
FS = Factor of safety
S = Resisting or stabilizing Force.
T = Driving or actuating force.
b
C = c1 X ------
Cos
N = Force normal to the arc or slice.
U = Pore water pressure.
= Angle of shearing resistance.
W = Weight of the slice.
= Angle made by the radius of the
failure surface with the vertical
at the centre of slice.
c1 = Unit cohesion, and
b = Width of the slice.
34. ADVANTAGES OF EMBANKMENT DAMS
Embankment dams have many advantages compared to gravity dams. Some of the main
advantages are:
Embankment dams can be constructed on any given foundation condition and the excavation
for foundation need not be up to rock level, where the bed rock is deep seated.
Use of costly manufactured items like cement and steel is eliminated and thus saving in cost.
Embankment dam is more resistant to seismic forces and are preferred in areas of high
seismicity.
Embankment dam can be constructed in stages and the dam height can be increased later on
easily, if needed.
With modern earth moving machineries, the dam can be completed in less time compared to a
rigid dam.
Page 34
• Overtopping and external erosion during flood discharge because of inadequate spillway
capacity or non-functioning flood gate
• Internal erosion along the dam-foundation interface or along embankment with adjoining or
embedded appurtenants structures or concentrated piping in the embankment itself because
of inadequate or non-existent filter zones.
• liquefaction
Occurs when the reservoir water level exceeds the height of dam and flows over the crest.
Overtopping failure takes place because of the external erosion of the dam and
may result from
Uncontrolled flow of water over the dam, around the dam, and adjacent to the
dam plus the erosive action of water on the dam.
It may be caused by a number of factors or a combination of factors including:
Inadequate inflow flood calculations,
Inadequate spillway design, and / or,
Poor spillway maintenance.
Occur in the abutments, foundation and embankment slopes e.g. failure due to overturning,
sliding, build up of pore pressure.
Reasons:
Poor foundation conditions
Poor construction practices
Page 35
Poor fill materials
Inadequate slopes
Poor design of the dam and its appurtenances
Can be observed in early stages by:
Presence of longitudinal or transverse cracks on the crest or slopes
Excessive settlement
Misalignment of the crest.
Development of a slope failure from transverse cracking
Also occurs in appurtenant works, spillway, outlets and gates.
Occurs both through the dam and under and around the dam in the foundation and
abutment materials and allowed in controlled manner.
If uncontrolled, can erode material starting at d/s slope or foundation back toward u/s
slope to form a “pipe” which often leads to a complete failure. This phenomenon is
known as “Piping”.
Another type of seepage problem is sloughing i.e. miniature slide on u/s or d/s slope of
the embankment.
Clear seepage is not a serious problem if adequate drains and filters are provided to
prevent the transport of fill material and if the seepage water is not allowed to pond at
the downstream toe.
Seepage can emerge on the d/s slopes, below the toe of the dam or on the d/s
abutments.
The presence of seepage may be identified by a change in vegetation seepage areas on
d/s slope.
Dirty seepage is indicative of erosion of the fill material and may lead to failure by
progressive erosion (piping) if remedial action is not taken.
Page 36
Longitudinal Crack in dam
Page 37
Transverse cracks in Dams
Page 38
Inspection, Monitoring & Maintenance of dams as well as data analysis and interpretation has
a critical role in the field of dam safety
Page 39
42. TEHRI ROCKFILL DAM
LIQUEFACTION
The material for clay core and the shell were extensively tested for possibility of
liquefaction under shaking and were found to be safe.
However, the shell is being compacted to concrete like density of 2.36 to achieve
maximum seismic resistance against liquefaction.
Such high density could be achieved because of gradation of fill material available at
Tehri, which was a mixture of sand, gravels and cobbles.
FILTERS
Two tiers of filters (5m thick each), are provided both on u/s and d/s sides.
The d/s filter can prevent failure of the dam even if there are concentrated leaks after a
seismic event, by preventing migration of particles and can help in eventually plugging
the leaks.
The u/s filter has been designed so that in the event of cracking of core it would get
washed into cracks and seal them by choking the water passages.
INSPECTION GALLERIES
An Inspection galley about 100 m below the FRL is provided for the first time in India.
The gallery has been designed with special deformation joints so that it can easily
undergo the settlement pattern of the clay over which it is seated.
Through this, it is possible to observe the behavior of dam through its settlements, gaps
in the joints etc., at various stages of construction, operation and seismic events.
One more Inspection Gallery on the top of the core has also been proposed to observe
the cracks in the core, if any due to differential settlements.
Page 40
Page 41
Page 42
43. Rock-fill Dams with u/s Face Membranes
Type of facings or membranes
• Cement Concrete Membranes
• Asphaltic Concrete Membrane
• Steel or Timber Membranes
44. Dam with Cement Concrete membranes
Page 43
Design of Core and Filter in Earth and Rockfill Dams
Dams have been built across rivers by mankind right from the dawn of civilization for
storing the river flow during rainy season and releasing it during the remaining part of
year for either domestic use or for irrigation. Flood control has been another important
function of these dams. While releasing water from the storages, hydroelectric energy is
also generated. With the growth of population all these functions of dams and storages
have assumed great significance and hence every civilization has tried to keep pace with
the needs of the society for food, energy, fibre and well being through this activity of
water resources development.
Dams constitute perhaps the largest and the most complex of structures being built by
civil engineers. Basic input of water is dependent on nature, so also the river course, its
history, its underlying strata and its stability. Assessment of the variability of these
natural phenomenon and providing for it in the design of a dam, has been an important
challenge for the dam builders. The dams are built to last from 100 to 300 years
depending upon merits of each case. During their service life, they are designed to
withstand all the possible destabilizing forces with a certain factor of safety which has
been an indicator of a factor of ignorance or lack of knowledge of various response
processes of materials used in construction, the stresses caused, the stains experienced
and finally the failure mechanism.
Large dams store very large volumes of water. Design of such dams, therefore, has to
be extra safe so that there is a minimum probability of their failure and consequent rapid
or sudden release of storage which can cause disproportionate flooding and losses to the
human habitats in the downstream. Very stringent codes are laid down for this purpose.
In case of inflow into a reservoir, for instance, a conceptual Probable Maximum Flood
(PMF) is determined by following special analytical procedures. If the reservoir and the
Page 43
spillway caters to a properly determined outflow on the basis of such inflow, the dam
would be hydrologically safe. In similar manner, geotechnical properties of foundation
material or construction material can be determined and design constants worked out so
that structural design based on them yields a safe structural construction. Statistically
speaking, the design constants should cover the probability of occurrence of forces
expected during the lifetime of the structure under design.
The codes of practice invariably lag the strata or knowledge or state of Research &
Development (R&D). In fact codification follows verification of generated knowledge
and its global acceptance. Codes, therefore, tend to remain conservative and normally
incorporate a higher factor of safety and hence perhaps yield structures with larger
dimension and/or with higher costs. There is yet another aspect of design philosophy
which is not very explicitly understood nor adequately explained. It pertain to the various
stages of design for complex structures like dams viz. conceptualization, pre-feasibility,
feasibility, detailed project report (DPR), pre-construction, early construction and
advanced construction stages.
A designer starts with broad concept of design parameters in the beginning and goes
on refining his data base and hence the designs, as he proceeds through the various stages.
He assumes for the sake of his inadequate data base, simplifications or generalizations
which obviously incorporates a large factor safety in initial stages. As the passes through
successive stages, his data base proves, better and more accurate data base emerges; the
range of design constants narrows down and factor of safety reduces.
Generally, the outer dimensions of a structure do not necessarily get modified; but
components, zones or internal arrangements of a structure do undergo modification. The
structure’s response to the destabilizing forces is worked out with greater detail and is
refined while moving from one stage to the next stage. Engineers call this a process
which is loosely described as ‘Design as you build’ or ‘Refine the design as you build’
mode. It certainly does not mean inadequacy of design or does not reflect on ignorance
or incompetence of project or design engineers. However, an inadequate understanding
of this very philosophy is one major factor responsible for much public criticism of many
of our water resources projects.
Page 44
- Provide ample drainage zones to allow for possible flow of water
through cracks.
- Stabilize slopes around the reservoir rim to prevent slides into the
reservoir.
This list should not by any means be considered as all-inclusive. However, defensive
measures, specially the use of wide filters and transition zones, provide a major contribution
to earthquake-resistant design and should be the first consideration by the prudent engineer in
arriving at a solution to problems posed by the possibility of earthquake effects.
(i) There should lie no possibility of dam being overtopped by flood water.
(ii) The seepage line should be well within the downstream face.
(iii) The u/s and d/s slopes should be stable under worst condition.
(v) There should be no opportunity of free flow of water from u/s to d/s face.
(vii) The U/s face should be properly protected against wave action and the d/s
face against the action of rain
4.1 Core
4.2 The core provides impermeable barrier within the body of the dam. Impervious soils
are generally suitable for core. However, soils having high compressibility and liquid
limit are not suitable as they are prone to swelling and formation of cracks. Soils
Page 45
having organic content are also not suitable. IS:1498-1970 may be referred for
suitability of soils for core. Appendix A gives recommendations based on IS:1498-
1970. Recommendations regarding suitability of soils for construction of core for
earth dams in earthquake zones are given in Appendix B.
4.3 Core may be located either centrally or inclined upstream. The location will depend
mainly on the availability of materials, topography of site, foundation conditions,
diversions considerations, etc. The main advantage of a central core is that it
provides higher pressures at the contact between the core and the foundation educing
the possibility of leakage and piping. On the other hand inclined core reduced the
pore pressures in the downstream part of the dam and thereby increases its safety. It
also permits construction of downstream casing ahead of the core. The section with
inclined core allows the use of relatively large volume of random material on the
downstream.
4.4. The following practical considerations govern the thickness of the core:
4.5 The top level of the core should be fixed at least 1 metre above the maximum
water level to prevent seepage by capillary siphoning.
5.0 Casing
5.1 The function of casing is to impart stability and protect the core. The relatively
pervious materials, which are not subject to cracking on direct exposure to
atmosphere are suitable for casing. IS:1498-1970 may be referred for suitability of
soils for casing. Appendix A gives recommendations based on IS:1498-1970.
6.1 In addition to basic design requirements given at 5, the following special design
requirements, should also be satisfied for both earth and rock fill dams:
a) Control of cracking.
b) Stability in earthquake regions, and
c) Stability at junctions.
6.2 Control of Cracking - Cracking of impervious zone results into a failure of an earth
dam by erosion, breaching, etc. Due consideration to cracking phenomenon shall,
therefore, be given in the design of earth dam.
6.3 Reasons of Cracking - Cracking in the core of earth or rockfill dam occurs due to
foundation settlement and/or differential movements within the embankment.
Differential movements in the embankment take place due to the following reasons:
Page 46
a) Unsuitable and/or poorly compacted fill materials,
b) Different compressibility and stress-strain characteristics of the various fill
materials, and
c) Variation in thickness of fill over irregularly shaped or steeply inclined
abutments.
6.4 .Cracking also develops by tensile strains caused by various loads, such as dead load
of the structure, filling of the reservoir and seismic forces. Hydraulic fracturing of the
core may also occur when the hydrostatic pressure at a section in the core exceeds the
total minor principal stress at that section.
6.5 Types of Cracks - Cracks may be classified based on the following factors:
6.6 Tensile stresses produce cracks on flat surface by capillary action in the moisture
range just below saturation. Tensile stress steep slope category cracks are associated
with slumping in poorly consolidated materials.
6.7 Shrinkage cracks are produced by wetting and drying action in the moisture
range of plasticity index.
6.9 Cracking associated with shearing is commonly associated with steep slopes.
There are two conditions in this category. One is differential settlement which
involves a limited range of motion and the other is a slide failure which may involve
any amount of motion. The differential settlement condition commonly involves a
structure extending over two or more kinds of foundation with differing compressive
characteristics or a differential loading condition on a single kind of foundation
material.
6.10 Slide failures may be associated with loading ,unloading or moisture change, the
distinguishing characteristics is the potential for continued movement.
6.11.1 Where permeability and possible erosion are of primary concern, the tension
group is potentially the most serous. In this group, the cracks are open and although
usually only superficial, those associated with steep slopes may extend to depths
comparable to the size of structure involved. Though the development of this type of
Page 47
cracking is from the surface, it may persist, although deeply buried, where eventually
it may contribute to unsatisfactory seepage action.
6.11.3 Shearing cracks are identified primarily by displacement between the two sides
and a tearing configuration. Unlike tension or compression cracking, shearing cracks
commonly occur early in the failure action and further movement can be expected
after the first cracking shows up.
6.12 Measures for Control of Cracking - Following measures are recommended for
control of cracking:
a) Use of plastic clay core and rolling the core material at slightly more than
optimum moisture content. In case of less plastic clay, 2 to 5 percent
bentonite of 200 to 300 liquid limit may be mixed to increase the plasticity.
b) Use of wider core to reduce the possibility of transverse or horizontal cracks
extending through it.
c) Careful selection of fill materials to reduce the differential movement. To
restrict the rockfill in lightly loaded outer casings and to use well graded
materials in the inner casings on either side of the core.
d) Wide transition zones of properly graded filters of adequate width for handling
drainage, if cracks develop.
e) Special treatment, such as preloading, pre-saturation, removal of weak
material etc., to the foundation and abutment, if warranted.
f) Delaying placement of core material in the crack region till most of the
settlement takes place.
g) Arching the dam horizontally between steep abutments.
h) Flattening the downstream slope or increase slope stability in the event of
saturation from crack leakage.
i) Cutting back of steep abutment slopes.
The core contact area includes the foundation contact for the entire base width of the
impervious core, the upstream and the downstream filter zones, transitions and the
downstream drain. This area is the most important and critical in the foundation treatment of
earth-core rockfill dams. The controlling factors are:
1. The rock under the core, including the infilling material in faults and joints,
must be non-erodible and must be protected from erosion under seepage
gradients that will develop under the core.
2. Materials of the core must be prevented from moving down into the
foundations.
3. The contact between the core and the foundation rock surface must remain
intact despite distortions that might occur in the dam due to its weight and
reservoir loading.
Page 48
The primary hazards to a high embankment dam are cracking within the corecaused by
unequal settlement and the development of seepage channels along the contact of the
impervious core with the foundation and abutment rock. Either of these defects could lead to
failure of the dam. It must therefore be ensured that the foundation in the core-contact area
consists of sound and hard rock reasonablyfree from joints and fissures which could be the
cause of internal erosion.
These objectives are achieved by excavation of the uppermost weathered rock zones to the
level of sound rock and by consolidation grouting to reduce the permeability of the rock
under the excavated surface. Jointed rock is an acceptable foundation, provided the joints do
not contain soft materials or clays to an extent that could endanger the stability of the rock.
Impervious Pervious
Core Casting
9.0 Suitability of Soils for Construction of Core of Earth Dam in Earthquake Zones
Page 49
index greater than 12).
The core can be located in one of the following three positions: (1) central, (2) moderately
slanting or (3) slanting. The central location need not be exactly symmetrical: cores with a
steeper downstream slope and flatter upstream slope, or even with a slight slant in the
upstream direction would still have characteristics of central cores. When the downstream
face of the core has an upstream slant of 0.5 H : 1 V or more, the core may be considered
as moderately slanting. A truly slanting core would be such that the downstream zone
has a self-supporting slope, i.e., 1.25 H:1 V or more, the core may be considered as
moderately slanting. A truly slanting core would be such that the downstream zone has
a self-supporting slope, i.e. 1.25 H:1 V or so; such a core is almost always associated
with a rockfill dam in which the main mass of rockfill downstream of the core can be placed
independently by dumping or in thick layers and the placement of filter zones, core and
upstream pervious zone taken up later. Even with a moderately slanting core, if the
downstream rockfill zone is substantial, it is possible to carry out a portion of the work ahead
of core placement.
The relative advantages and disadvantages of vertical and sloping cores are discussed below:
Advantages
j) Downstream rockfill can be placed in advance and laying of filter, core and
upstream zone can be taken up later. This ensures rapid progress as
placement of bulk rockfill in the downstream portion is accelerated,
especially in conditions wherein core placement is possible only during
part of the year.
ii) Foundation grouting of the core can be carried out while the downstream shell
is being placed and thus better progress achieved.
iii) Since a very small part of the slip surface intersects the slanting core, the
section is practically free from the steady seepage pore pressures and is thus
more stable under a steady-state condition. This results in a steeper slope of
the downstream shell and corresponding economy.
Page 50
iv) Since the flow lines are essentially vertical and equipotential lines are almost
horizontal under sudden drawdown, the drawdown pore pressures are very
much reduced. However, a larger part of the slip surface for the upstream
slope passes through the core material than would be the case with a central
core.
v) In the case of cracking of the core, the inclined core will leave a large mass of
stable rockfill on the downstream side and is likely to be safer.
vi) Filter layers can be made thinner and placed more conveniently.
Disadvantages
i) The depth of excavation of the foundation at the contact surface of the core is
determined by the nature of the formations and cannot be predetermined in
advance. Thus advance treatment of the contact area may present a problem in
the case of a slanting core because if the depth of excavation increases, the
contact area moves upstream.
ii) By slanting the core upstream, although the downstream slope can be made
steeper, nevertheless, the upstream slope will generally become flatter as the
shear strength of the core material will be less than that of the pervious shell
material; the advantage of reduced drawdown pore pressures may not
compensate this factor. Thus any economy in total quantity of materials by
adjustment of core position would depend on the relative strength of the two
materials.
Advantages
i) Provides higher pressure on the contact surface between the core and the
foundation, thus reducing the possibility of hydraulic fracturing.
ii) For a given quantity of soil, the central core provides slightly greater
thickness.
iii) Provides better facility for grouting of foundation or contact zone or any
cracks in the core if required afterwards, as this can be done through vertical
rather than inclined holes.
iv) Foundation area is independent of depth of foundation and hence can be
marked and treated in advance.
Disadvantages
i) The advantages listed for a slanting are not obtainable. Also, a moderately
thick central core with pervious shells will result in a slightly flatter
downstream slope of the dam.
ii) The problem of differential settlement between the core and the shell zone
may result in cracking parallel to the dam axis.
Page 51
11.0 Design of Filters for Earth/Rockfill Dams
11.1 Introduction
Water conservation and development of water resources for irrigation have attracted
human ingenuity since time immemorial. A number of ancient tanks and earthen
embankments stand testimony to the skill of our ancestors. The Grand Anicut across
Cauvery River, built more than 1600 years ago and providing irrigation to 0.4 million
hectares of land, is a typical example of the ancient earth dams in the country, still in service
today. In the past, design of earthen dams was mainly carried by the rule of thumb and
judgment of the designer, and the heights adopted were moderate. Advances in the field of
soils mechanics and construction equipment over the years have made it possible to design
and construct earth/rockfill dams to heights which would have been considered impossible in
the past The Beas Dam (115m) Ram Ganga Dam (125m) and Salal Dam (128m) are
examples of such high dams successfully completed. Considering these achievements within
the country and the satisfactory performance of embankment dams of greater heights
elsewhere, a number of high embankment dams in the Himalayan region have been taken up
and are in different stages of development. The Tehri Dam (260m) now under completion on
Bhagirathi river in Uttaranchal is the first of the kind, and several other dams of similar
height are in the pipeline. The future mega dams like Tipaimukh, Subansiri, Dehang, Bursar,
Kishau, Kotli Behl and Utyasee within the country, as well as the Karnali, Pancheswar,
Wangchu and Kurichu dams across the border will need many engineering skills.
Design and construction practice for embankment dams have undergone a number of
changes over the years. One of the important features that could be noticed is recognition of
the useful role of ‘protective filters’. Analysis of the performance of embankment dams in
the world showed that there are almost no cases of damage or failure by piping, when filters
had been provided as per accepted design practices, and most of the failures had occurred in
dams without chimney filter or which had excessively coarse filters. Well planned filter
drainage has become obligatory in the design of modern dams. Filters are provided to safely
carry the seepage water which may pass through the body of dam, through the foundations, or
along their contact, thus protecting the structure against the undesirable and harmful effects
of seepage. Generally seepage is expected to occur through the pores of the base soil. But
there could be a more severe condition of water leaking through cracks which may develop in
the dam body foundation system. Enough evidence already exists from the observed
behaviour of dams, supported by theoretical calculations, that such concentrated leaks can
develop due to various reasons. Fortunately, recent studies have shown that the filters, if
adequately designed can also be effective in controlling erosion through such concentrated
leaks. The embankment dam designer should therefore pay adequate attention in arriving at a
proper design of these filters.
The filter criteria contained in the IS code is based on the criteria recommended by Terzaghi
and studies carried out with non-cohesive soils. There is scope to improve the provisions in
the code to cater all soil types. Recent studies, which included controlled laboratory tests
performed by various agencies and individuals ha e brought out some new findings on the
evolution of criteria for conservative/critical filters, capable of preventing erosion and sealing
off concentrated leaks. Particulars of this modified criteria and details of its adoption in
rehabilitating a dam are briefly described. Some other situations where protective filters
could be advantageously used, are also discussed.
Page 52
12.0 Conservative Filter Criteria
As per the Indian Standard Code (IS: 9429-1980) a properly designed filter should
satisfy the following requirements:
iv) The gradation curve of the filter material should be nearly parallel to the
gradation curve of the base material.
(D15) filter
-------------- < 4 to 5 (Piping criteria)
(D85) protected soil
(D15) filter
-------------- > 4to 5 (Permeability criteria)
(D15) protected soil
(D50) filter
R 50 = -------------- = 9 to 30
(D 50) base material
(D15) filter
Page 53
R15 = -------------- = 6 to 18
(D15) base material
(D50) filter
R50 = -------------- = 12 to 58
(D50) base material
(D15) filter
R15 = ---------------- = 12 to 40
(D15) base material
(D50) filter
R50 = --------------- = 5 to 10
(D50) base material
The above criteria takes into account only the grain size of base material, and is based on
studies made with non-cohesive soils.
Even though the filters are provided generally to take care of the seepage through the pores of
the embankment soils, they should also be capable of preventing erosion of soils through
concentrated leaks that may occur in the dam body or at the foundation contact.
Certain improvements and modifications to the above criteria have been brought recently on
the basis of controlled laboratory tests performed by various organizations and individuals.
Contributions by the US Department of Agriculture, Soil Conservation Service is worth
making a special mention. Filter tests have been conducted using compacted impervious soil
specimens with an artificial slot or hole and subjected o water flow discharging into the filters
of varying coarseness. These studies confirmed that a conservative filter would be
remarkably effective in preventing erosion and sealing off concentrated leaks, even with
relatively high water pressures, velocities and gradients. Such filters are required on the
downstream face of impervious core of a zoned embankment dam, and in the chimney filter
of a homogeneous dam section. Because of the important role of these filters they are also
known as ‘critical filters’. Some of the useful conclusions drawn from the studies are :
i) The gradation curve of a filter need not have to be parallel or similar in shape
to the gradation curve of the base material.
ii) A filter should be uniformly graded to provide permeability and prevent
segregation. Particles finer than 0.075 mm in the filter should not exceed 5
per cent to ensure adequate permeability. The permeability of a filter should
be at least 25 times that of the base material (D15F should be more than
5xD15B).
iii) Coarse broadly graded soils need finer filters than believed to be necessary.
The filter should be designed to protect the fine matrix of the base material
Page 54
rather than the total range of particle sizes. Filters designed based on minus
4.75mm are found to be satisfactory.
iv) Sands and gravelly sands with average D15 size of 0.5 mm or smaller are
conservative filters for most of the fine-grained clays (including dispersive
clays) in nature with D85 size of 0.03 mm or larger.
v) Sand filters with average D15 size of 0.1 mm or smaller are conservative for
the finest dispersive clays.
Based on the above findings, the US Interior Bureau of Reclamation (USBR)
has developed a new set of filter criteria (2). The filter gradation limits are
determined through steps A to B as described below:
A. Select the gradation curve of the base soil that requires the smallest D15F size.
B. Proceed to step D if the base soil does not contain gravel (4.75 mm and above).
C. Prepare adjusted gradation curves for soils with particles larger than 4.75 mm.
Use the adjusted curve in working step D.
D. Determine the category of the soil from Table-1.
E. Determine the maximum D15F size in accordance with Table-2.
F. To ensure sufficient permeability set the minimum D15F size greater than or
equal to 5xD15B, but not less than 0.1 mm.
G. Set the maximum particle size at 75 mm and the maximum passing 0.074 mm
must have a plasticity index of zero.
H. Design the filter limits within the maximum and minimum values determined
in steps E, F and G. Plot the limit values and connect all the maximum and
minimum points by straight lines.
Typical filter gradation limits arrived for a category 2 type of base soil is shown below:
TABLE - 1
1. > 85
2. 40 - 85
3. 15 - 39
4. < 15
TABLE - 2
Page 55
Foundation Treatment of Dams
1. Foundation Treatment ?
To Foundation treatment is the controlled alteration of the state, nature or mass behaviour of
ground materials in order to achieve an intended satisfactory response to existing or projected
environmental and engineering actions.
Temporary
o e.g. dewatering or ground freezing, where the improvement is only during the
application.
Short-term
o e.g. some forms of grouting, or use of diaphragm walls for ease of construction
with longer term benefits.
Long-term
o e.g. soil nailing, vibro-replacement, curtain grouting of a dam, where the
treatment is integral to the permanent works.
Change of state;
o i.e. the same ground but made stronger, stiffer, denser, more durable.
Change of nature;
o i.e. the ground becomes a different material by inclusion of other materials.
Change of response;
o i.e. through the incorporation of other materials, the ground becomes a
composite material with enhanced load-carrying or deformation
characteristics.
Page 56
5. Foundation Treatment Techniques
9. Purpose of Grouting
The limiting Lugeon value given in the table, are recommended for deciding the necessity or
otherwise of grouting. Lugeon values in excess of those given in the table would indicate that
grouting is desirable.
Page 58
10. Function of Grouting
Page 59
11. Possibilities of infilling of grout in Rock joints / Void space
Curtain grouting is designed to create a thin barrier (or curtain) through an area of
high permeability.
Page 60
15. Consolidation grouting
Under the plinth for a concrete face rock fill dam It is usually restricted to the upper
5 to 15 m While carried out in sequence, consolidation grouting is commonly applied
to a predetermined hole spacing.
According to IS: 11293 (Part 1)-1985 “Guidelines for the design of grout curtains”, the
following empirical criteria may be used as a guide:
D= H/3 to H
Where D is the depth of the grout curtain in meters and H is the height of the
reservoir water in meters.
Page 61
17. Orientation of Grout holes
The orientation, plan and inclination of grout holes depend upon the type of joints and
the other discontinuities in the foundation rock.
The most common practice is to drill holes inclined towards the upstream at 5 to 10
degrees to the vertical.
Apart from the gallery at the foundation level, there could be other galleries also.
The holes are drilled and grouted in sequence to allow testing of the permeability before
grouting and allow a check on effectiveness of the grout take by the foundation.
Primary holes are drilled first, followed by secondary and then tertiary.
The final hole spacing will commonly be 1.5 or 3, but may be as close as 0.5 m. This
staged approach allows control over grouting operations.
Page 62
19. Staging of grouting
Upstage
Full Depth
Reduces the risk of leakage of grout to the top stage, allowing progressive assessment as
to whether the hole has reached the desired closure requirement.
Allows higher pressures to be used for lower stages, giving better penetration.
22. Upstage
Full depth is drilled in one go and grouting is done in stages using packers.
Does not allow progressive assessment of the depth of grout hole needed to reach
closure.
Cheaper, as the drilling rig is set only once, but savings may be offset by the need for
more conservative total depths.
Page 64
23. Full Depth
Does not allow proper assessment of where grout take is occurring or reduction in
Lugeon value is taking place.
Page 65
24. Lugeon Test
Tests not in harmony with grout takes, small quantity of water, large cement take
Impossible to reduce permeability even though originally permeable & large takes
Very little seepage though originally high permeability but grout takes were low
Page 66
26.
Different Conditions
Page 67
28. Pattern of WPT
Page 68
29. Interpretation
Page 69
Flow vs. Orientation Contd.
Page 70
31. Geologic Structures
Page 71
32. Conclusions
Page 72
The alignment of the cut-off should be fixed in such a way that it’s central line should
be within the base of the impervious core.
The partial cut-off is specially suited for horizontally stratified foundations with
relatively more pervious layer near top.
The depth of the partial cut-off in deep pervious alluvium will be governed by:
Permeability of substrata
The horizontal upstream impervious blanket is provided to increase the path of seepage
when full cut-off is not practicable on pervious foundations.
The material used for impervious blanket should have far less permeability than the
foundation soil.
Reference may be made to IS: 1498 for suitability of soils for blanket.
To ensure safety of the earth dam in cases where the cut-off is partial or reliance is
placed on an upstream blanket for controlling under seepage.
Page 73
This may be effectively done by installing a system of relief wells suitably spaced
which will reduce the intensity of the under seepage pressure and render the
seepage water practically.
A relief well is a small drainage well (45 to 90 cm in dia) near about the downstream
toe, with a pipe having narrow slots, placed in the centre and surrounded by graded
filter.
Page 74
36. METHODS OF TREATMENT OF DIFFERENT FOUNDATION MATERIAL-OVERBURDEN &
ROCK (IS 4999 :1991 & IS 6066 :1994)
Page 75
37. DEEP PERVIOUS FOUNDATIONS WITH IMPERVIOUS TOP STRATUM
Page 76
Page 77
Page 78
38. INVESTIGATION REQUIRED
To explore the local variation in the grain size distribution and permeability in order
to ascertain the groutability of the various strata and the extent of ungroutable
layers.
To investigate salt content of the soil as well as ground water to identify presence of
salts which may inhibit gellation.
The in-situ permeability is governed by the size, extent and spacing of layers of high
permeability zone.
Page 79
The average permeability of pervious deposits may be determined by pumping out
test in accordance with IS 5529 (Part-I):1985.
These are applicable where the primary purpose of grouting is to reduce the
permeability of the soil. In such cases consolidation of the soil is the primary
objective.
It is judge not merely in terms of the grain sige distribution of each individual layer or
lense but in terms of its contribution to the over permeability.
41. GROUTING METHODS & THEIR SELECTION
Pervious soils are generally heterogeneous, and the grain size distribution may
change abruptly over a short distance.
The grout flow generally concentrates along layers or pockets of coarser and
relatively pervious soils.
Hence, it is necessary to treat short lengths of grout holes at a time and repeat injections to
ensure that the least pervious and fine grained soils are treated thoroughly.
The following methods are generally followed for grouting of overburden soils:
Rising Tube
In this method, grouting is done through the casing which is driven to the bottom of
the hole.
The tube is withdrawn a short distance and grout is injected through the open end
into the cavity left by the tube as it is raised.
Page 80
In this manner the tube is lifted progressively until the entire depth required to be
grouted is treated.
Descending Stage
In this method, grouting is done through the lower open end of the grout pipe
in short stages of 1 to 2 metres starting with the top of the grouted zone.
Page 81
Grouting Through Tubes with Sleeves
Particle size ( in suspension ) should be small enough, so that the grout can penetrate
the soil easily.
The viscosity of the grout mix should be sufficiently low so that the mix canStravel
sufficient distance in the soil to achieve an economical and practicable spacing of
holes.
After penetration into the soil, the grout should form a deposit which will not be
eroded by the pressure gradient imposed on the curtain over the entire serviceable
life of the structure.
The normal practice of splitting the spacing starting with an initial spacing of 6 to
12.0 m for each of the rows.
Page 82
Final spacing depends upon the joints pattern, normally 3.0 m is provided.
Grout Mixture
Rock grouting is usually performed with a mixture of cement and water with or
without additives.
The cement generally used are.
Ordinary Portland IS 269:1989
IS 8112:1989
IS 12269:1987
Portland Slag IS 455:1989
Sulphate Resisting Portland IS6909:1990
Supersusulphated Cement IS 6909:1990
Portland Pozzolana IS 1489
(Part 1&2) 1991
Other solid materials may be used as additives to the grout mixture are:
Pozzolanas such as flyash (IS 3812:1981) and calcined shale (IS 1344:1981).
As early strength is important on most grouting jobs, the pozzolana may behave only
as inert non-cementing fillers.
Fine sands (IS 383:1970) are economical additives widely used in grouting.
Grout Mixture- Admixture
Use in small quantities the following admixtures impart certain desirable characteristics:
Retards to delay setting time.
Accelerator to hasten setting time.
Lubricants for increasing workability.
Protective colloids to minimize segregation.
Expansion materials to minimize shrinkage.
Page 83
For determining the mix proportions the viscosity& bleeding of grout, strength and
economy shall be the main consideration:
Mix proportion should be exercised according to the following guidelines (IS-
6066:1994)
The choice of grouting mixtures is based on results of percolation tests
conducted prior to grouting.
Ranging from 5:1 to 0.8:1 are recommended.
The grouting should be continued till refusal stage is achieved i.e the rate of
intake becomes almost negligible say 1.0 litre/min averaged over a period of
10 minutes at desired limiting pressure up to 3 kg/ cm2 and 1.5 lirte/min for
pressure between 3 and 10 kg/cm2.
It is desirable to carry out the grouting with the mixture of cement and water
only. However if the intake is more, the grout may be thickened by using inert
materials like.
Pozzolan as or fine sand, rock powder, clay bentonite etc.
Page 84
The grout pressure should be such that it should travel through the cavities to the
maximum possible distance at the same time, it shall not be so excessive that it may
cause upheaval.
Review the Acceptance criterion.
Consider chemical grouting in special cases
Page 85
Liquefaction and Testing
1. Soil liquefaction
Page 86
3. Liquefaction Potential of Foundation
Page 87
4. Total and Effective stress
Page 88
Simple Shear Test
b. IN SITU TESTS
Page 89
7. Types of liquefaction
Occurs when shear stress required for Occurs when the static shear stress is less
equilibrium of a soil mass (the static shear than the shear strength of the liquefied
stress) is greater than the shear strength soil.
(residual strength) of the soil in its Deformations are driven by both cyclic
liquefied state. and static shear stresses.
If the soil is loose and is being shaken, the particles will settle due to gravity.
When the soil is saturated, the pore-water is unable to move out of the way quickly
enough (because the soil permeability is relatively low), and more and more particles start
to partially float in the water (this leads to excess pore- pressure build up).
Eventually as shaking continues, the particles float in the water temporarily as they settle
downwards and reach a new densified and consolidated state.
susceptibility.
Page 90
10. Notes
Objectionable deformations might still occur if ru values are high, even if liquefaction does not occur).
Looser soils are more vulnerable.
As pore pressure builds-up, stratified soil profiles (particularly with permeability contrasts) may cause
water to be temporarily trapped under a relatively impervious layer or seam (e.g., due to alluvial or
hydraulic fill construction, or presence of an upper clay stratum), generating a low friction interface
and possibly leading to major lateral deformations. This mechanism actually is a driver of what we
commonly observe as sand boils where this water escapes upwards through any available high
permeability locale (e.g., taking advantage of a crack in the ground, or similar imperfection, …).
• Settlements
Page 91
Geologic criteria
Depositional environment - Saturated loose fluvial, colluvial, and aeolian deposits are more
susceptible to liquefaction.
Age - Newer soils are more susceptible to liquefaction than older soils.
Human-made soil strata - Uncompacted soils (e.g., hydraulic fill) are more susceptible to
liquefaction than compacted soils.
Compositional criteria
Grain size and plasticity characteristics - Sands, non-plastic silts, and gravelly soils, under
conditions of low permeability, are susceptible to liquefaction.
Gradation - Well graded soils are less susceptible to liquefaction than poorly graded soils.
Particle shape - Soils with rounded particles are more susceptible to liquefaction than soils
with angular particles
The measured SPT resistance and results of sieve analysis for a site in Zone IV are given in Table
1.1. Determine the extent to which liquefaction is expected for a 7.5 magnitude earthquake. The
site is level, the total unit weight of the soil layers is 18.5 kN/m3, the embankment height is 10
m and the water table is at the ground surface. Estimate the liquefaction potential immediately
downstream of the toe of the embankment.
Page 92
14. Liquefaction Analysis using SPT data :Solution
Page 93
Page 94
Page 95
III. If liquefaction is triggered, how much lateral deformation occurs?
Residual Strength (see Fig. 2). In addition, for the residual shear strength Sr, Olson and Stark (2002)
proposed:
Sr/ ’vo = 0.03 + 0.0075 (N1)60 plus or minus 0.03 for (N1)60 less or equal to 12
and
Sr/ ’vo = 0.03 + 0.0143 (qc1) plus or minus 0.03 for qc1 less than or equal to 6.5 Mpa
Earlier, Baziar and Dobry (1995) proposed for loose silty sands:
Page 96
Seepage through Body of the Dam and Slope Protection
1. What is a Dam?
A dam is a barrier built across a stream, river or estuary to hold and control the flow of water for
such uses as drinking water supplies, irrigation, flood control and hydropower generation etc.
Page 97
Page 98
New dam – first filling
Failed with small amount of water stored in the reservoir
Foundation and embankment cracks suspected
Dispersive clay soils were involved
Seepage through dam body creates the following two problems, apart from causing excessive
water loss
Page 99
• It is a Convectional practice to provide Impervious cores within the body of embankment
dam as a water barrier.
• In rockfill dams, instead of providing impervious core, an impervious membrane on the
upstream face is adopted.
The convectional types of seepage control and drainage features generally adopted for the
Embankment Dam are:
• Impervious Core,
• Inclined/Vertical filter with Horizontal filter,
• Network of inner Longitudinal and cross drains,
• Horizontal filter,
• Transition zones/transition filters,
• Intermediate filters,
• Rock toe, and
• Toe drain.
The most common drainage features adopted in earth dam are inclined filter, horizontal filter,
rock toe and toe drain.
In case of a Homogeneous section of earth dam either only horizontal filter or a combination
of vertical/inclined filter and horizontal filter shall be provided.
For rockfill dam with central impervious core upstream inclined filter shall be provided.
When the shell material is relatively impervious intermediate filters may be provided in the
upstream and down stream shell.
Toe drain located on the D/S toe of the embankment dam is necessary to collect seepage. The
collected water in the toe drain should be taken away from the toe of the dam by providing
outfalls at suitable locations along the toe drain.
In Rockfill dams, transition zones/transition filters may be required between the impervious
core and rockfill and between the overburden in dam seat and rockfill.
Where a single single zone of graded filter is costly, progressive zoning consisting of one or
more transition zones may be considered as an alternative.
Page 100
Seepage Analysis
Page 101
• If a sand boil continuously removes material due to an excessive hydraulic
gradient, they may eventually lead to piping, collapse or failure of the structure.
• Piezometers can be used to monitor downstream foundation uplift pressure and
detect unsafe conditions before failure occurs.
• A key indicator of a potential problem developing is fine soil carried in water
draining from a boil.
Type A is indicative of a
static condition for the
current hydraulic
gradient and is not
necessarily indicative of
an immediate problem
developing.
Type B is a boil that is
carrying material, but
the material is
originating from near
surface soils rather
than deeper zones.
Type C is indicative of a
critical condition,
where the present
hydraulic gradient is
removing subsurface
soils.
Page 102
6. Five Conditions must exist for piping to occur
• There must be a flow path/source of water.
• The hydraulic gradient must exceed a certain threshold value that is dependent
on the type of soil through which the flow path travels.
• There must be an unprotected exit (open, unfiltered) from which material can
escape.
• Soils that are susceptible to piping must occur within the flow path near the
discharge point of the seepage.
• The material being piped or the soil directly above it must be able to form and
support a “roof” to keep the pipe open.
Page 103
• Highly susceptible are silts and sands with low-plasticity fines (Plasticity Index
less than 6), as well as loose, well graded sand and gravel mixtures that are very
broadly graded and have low-plasticity fines.
• Clay soils with significant plasticity (Plasticity Index greater than 15) are less
susceptible to piping.
• A failure resulting from internal erosion may appear similar to a piping failure. In
the case of piping, the tractive forces result from the intergranular flow of water
between soil particles. Internal erosion, occurs when water flows:
• Along cracks or other defects in the soil or bedrock in the C/S.
• Along boundaries between soil and bedrock.
• Between soil and concrete or metal appurtenances.
Page 104
• Operation and maintenance records.
• Monitoring instrumentation records.
• Any special reports prepared for the project.
Page 105
15. Important indicators of seepage-related problems
• A progressive increase in volume of flow.
• Evidence of piping (sand boils), internal erosion, solutioning of solids, or increased
turbidity of seepage.
• Increase/decrease in hydrostatic pressures.
• A changing pattern of seepage.
• Seepage appearing at a critical location, such as adjacent to a conduit.
• A progressive increase in volume of flow.
• Evidence of slope instability as a result of seepage (sloughing).
• Appearance of sinkholes.
• Soft, unstable areas downstream.
• Unusual vegetative growth (green grass in an arid environment).
Page 106
• What happens in the area following rain, both with and without a reservoir level
increase.
• Whether the seepage water is ever turbid.
• Whether the seepage water carries particles.
• Whether accumulations of particles occur in the area of seepage.
• Whether seepage changes with climatic conditions.
• Whether seepage always exits at the same location.
• If the seepage changes on a cyclic annual, seasonal or daily pattern.
• If seepage is related to operation of the gates or other control structures.
• If the area was wet before the dam was built.
Page 107
20. Darcy’s Law
• Henri Darcy, a formula governing flow through porous media, now known as Darcy’s
law, was based on the study of water flow through vertical filters in laboratory
experiments.The experiments indicated that the quantity of flow is expressed by the
equation:
i = hydraulic gradient equals the head loss (cm) divided by the length over which
head loss occurs (cm)
• The discharge velocity Vd is an average fluid velocity and is defined as the gross
quantity of fluid that flows through a unit cross-sectional area of soil in a unit of
time.
• Since flow only occurs through the interconnected soil voids, the real velocity of flow
or seepage velocity (Vs) for a single molecule of water traveling a unique path in the
soil voids is greater than the discharge velocity.
• The seepage velocity is roughly equal to discharge velocity divided by the porosity of
the soil.
• Darcy's law is applicable only to laminar flow (adjacent flow lines are parallel and
straight and Vd is directly proportional to i).
Page 108
• This law is reasonable for most soils, but flow through coarse gravels and rock
openings may become turbulent and Vd is proportional to approximately the
square root of i.
• Darcy's law is limited to flow through saturated materials. Flow through
unsaturated materials is in a transient state and is time dependent.
• Darcy’s law is not useful in studying flow through cracks or fractures and similar
features in rocks or soil.
Darcy's law has many applications in seepage analysis, including:
• Determining permeability, both in the field and laboratory.
• Predicting quantity of laminar flow.
• With approximate modifications, Darcy's law can be applied to problems of
turbulent, transient (time-dependent), and partially saturated flow.
• Darcy's law is also used in solving many seepage and drainage problems
associated with dams.
Page 109
21. LAPLACE EQUATION
• The flow of water through a porous medium (soil) is only one of several forms of
streamline flow that obey similar fundamental relationships, which can be
represented by the Laplace equation.
• In two dimensions, the Laplace equation can be solved by drawing two families
of curves that intersect at right angles to form a pattern of "square" figures,
commonly known as a flownet.
• The Laplace equation for three-dimensional flow is:
• Developing the Laplace equation for flow of water through porous media
requires the following assumptions:
The porous media (soil) is homogeneous.
The voids are completely filled with water (i.e.,saturated).
The soil and water are incompressible
Flow is laminar and Darcy's law is valid.
Page 110
• be applied for approximating flow through a uniformly fractured rock mass if the
volume of rock under consideration is uniformly fractured and can be assumed
isotropic.
• The methods used to solve the Laplace equation & the Darcy permeability used
in the Darcy equation are prone to scale effects when considering fracture flow.
• Fracture flow varies from highly anisotropic to a relatively isotropic
phenomenon, depending on the size or scale of the rock volume under
consideration and the spacing of interconnected fractures.
• Fracture flow can be approximated as flow through two parallel plates.
• Experiments with flow through parallel plates led to the development of an
equation for determining the hydraulic conductivity (kf) of a fracture.
where a is the size of the fracture aperture and μ is the fluid viscosity, f is a
fracture roughness factor that accounts for friction, ρ is the density of the fluid
and g is the acceleration of gravity.
The quantity of flow through a fracture (Q) is dependent on the hydraulic
gradient, the hydraulic conductivity of the fracture, and the cross sectional area
perpendicular to flow and may be expressed as:
The validity and quality of any seepage analysis depend upon the information
available for input into the analysis.
• The location of various boundaries and flow paths.
• The type of flow.
• The permeability of the various materials through which the seepage flows.
Seepage problems are common because information available during the design
and construction phase of a dam is often insufficient for accurately predicting
seepage.
Therefore, post-construction field observations are required and can supply
much additional information needed to analyze and rectify any seepage
problems once they develop.
• Boundaries define the limits and conditions of flow in the cross-section being
analyzed.
• Boundaries include an impervious layer in the foundation below which no seepage is
expected
Page 111
• to occur, the entrance face for seepage, and the exit face. One must also define
whether boundaries are fixed or transient.
• The nature and location of various boundaries are determined by:
• • Field exploration and knowledge of site geology.
• • Assumptions based on engineering judgment.
• • Conditions imposed by design and type of structure.
• • Geometry of the dam and its zoning.
• In most cases, simplifying assumptions are required to establish boundaries that will
permit an analysis.
26. FlowNets
Page 112
27. NUMERICAL COMPUTER SOLUTIONS
• Computer models are used increasingly to make acceptable approximations for the
Laplace equation in complex flow conditions.
•
• The two primary methods of numerical solution are finite difference and finite
element.
• Both can be used for two-dimensional and three-dimensional problems and software
is available from several sources.
• Very simple problems can be solved by hand, but more difficult problems require a
computer.
• Both methods use a grid system to divide the flow region into discrete elements.
• Element intersections are called nodes.
• In either system, a series of linear algebraic equations are used to approximate the
Laplace equation.
• In the finite element method, if the grid consists of N elements, there will be N
equations in N unknowns to solve.
Page 113
30. FlowNets
To draw a flownet, several basic properties of the seepage problem must be known or assumed:
Page 114
32. General Guidelines for Seepage Analysis
Page 115
COMPOSITE DAMS AND INTERFACE DETAILS
1. Composite Dams and Interface Details
Made with Two or more types of materials having different behaviour especially
load transfer.
Page 116
3. Junction Of Embankment Dam With Gravity Dam
Page 117
5. Junction Of Embankment Dam With Gravity Dam
Page 118
8. OUTLET INTERFACE
Page 119
10. Latest Interface For Outlet
Page 120
14. Dams with Earth backing
Page 121
15. LOADS & MAIN PROPERTIES
16. ANALYSIS
Wc = Wt of concrete
U = uplift
C = cohesion concrete-foundation
P = Hydrostatic force
Page 122
18. Problem appreciation :- Punatsangchhu-I H.E. Project (1200 MW), Bhutan
PLASTIC CONCRETE
CUT- OFF-WALL
ROCK LINE
2. BASIC ISSUES
Alignment
Conduit Elevation
Shape
Spacing
3. DESIGN CONSIDERATIONS
Sill Level Close To Mddl
Pressure Conduit Upto Gate
Free Flow After Gate. 75% Full
Energy Desipation At The End Of Conduit
To Join With D/S Canal With Smooth Transtion Slopes
Page 126
4. Design Data
Discharge
MDDL
Canal Bed Level at the downstream
Canal FSL
Dam Section
5. Geological and other Data
Not very high loads are expected to come.
The foundation shall be hard compacted.
Can be constructed on any type of soil/rock.
Seismology and Hydrology not required.
6. Components of Outlet
Trash rack
Entrance shape Bell Mouth
Outlet conduit
Pressure flow
Free flow
Control Shaft
Energy Dissipation arrangement
Joining with downstream canal
7. Control gate/shaft position
Upstream
Intermediate point
Outside control
Underground control
Downstream
8. Issues
Ungated
Length of pressure flow
Accessibility
Design Loading
Page 127
9. Design Assumptions
Trash rack bars area = 20 % of total trash rack area.
Trash rack is designed for a velocity of 0.6 m/sec with 50 % clogging.
Value of Manning's Coefficient ‘n’ is 0.018.
Depth of flow in free flow portion shall not be more than 75% of total depth.
The flow is supercritical in the free flow portion and Frouds number slightly more
than 1.0
Page 128
10. Design Criteria/ Conditions of Analysis
Intake is designed
o Minimum hydraulic losses
o Provide smooth entry to outlet
o Prevent trash entering the outlet
Bell Mouth Entrance for smooth entry of flow to avoid cavitation pressure
develop.
An elliptical curved shape to minimize negative pressure
X2/D2 + Y2/(0.33D)2 = 1 where D = height of outlet
The piers of trash rack shall be sharp nosed and stream lined with the structure.
Sill Level close to or Lower than MDDL
11. Design
Size of outlet.
Single or Multi barrel outlet.
Length of pressure and free flow conduit.
Depth of free flow.
Losses (maximum & minimum)
Minimum operating head.
Full discharge with Maximum head loss (check).
Water profile in free flow portion.
Design of energy Dissipation.
Transition details between conduit and stilling basin.
Transition between stilling basin and canal
Shape of bell mouth.
Size and dimensions of trash rack piers etc.
Structural design
o Conduit
o Control Shaft
o Stilling Basin
12. Losses
Trash rack loss
Entrance loss
Stop log and Valve loss
Friction loss
Transition loss due contraction
Loss due to Gate grove
Transition loss due to Expansion
Exit Loss
Page 129
13. Structural design
Design parameters
o Angle of internal friction
o Saturated, Submerged & Moist unit wt. of Soil.
Design Assumptions
o Foundation is placed on firm foundation with uniform upward reaction
o There is no differential settlement
o Full earth and water load above the outlet are acting on the top and side
walls.
Page 130
Page 131
General Characteristics of Rock fill Dams
Rock fill dams are basically embankment dams. High inherent stability
and high perviousness are their special characteristics. The impervious
element in a rock fill dam is provided either by an impervious membrane of
manufactured material or by an earth core. Even in the case of concrete-faced
rock fill dams, the requirement of cement and other manufactured materials is
much less than for concrete dams, while in earth core dams, it is similar to
earth dams.
As in other embankment dams, in rock fill dams also the spillway and
outlets have normally to be provided separate and away from the dam section.
However, by placing heavier rock pieces near the downstream toe and tying
them to the main rock fill by anchor bars, they can withstand limited
overtopping. This can be taken advantage of in the determination of diversion
flood during construction and freeboard for highest flood.
Due to free drain ability and high frictional strength, rock fill dams have a
high inherent stability. In fact, there is no recorded case of failure of a rock fill
dam due to slope sliding. Their high damping capacity and flexibility also give
them a high level of protection against earthquake damage.
Rock fill dams require foundations intermediate in strength between
concrete gravity dams and earth dams.
The selection of the dam is mainly governed by the site conditions. This
equally applies to the choice between membrane and earth core for rock fill
dams. The circumstances in which the membrane type is likely to prove
advantageous are:
When suitable soil for an earth core is not available within a reasonable
distance, as for example in high rocky areas.
When foundations of hard rock with little overburden are available. In this
situation there is no possibility of failure through the foundations and the
dam slopes can be designed solely on the basis of shear strength of rock
fill. The slopes can be kept somewhat steeper than those for the earth
core section.
Continuously rainy weather. In continuously rainy whether, it is difficult to
maintain proper moisture control for compaction of earth cores. There is
no such problem in the placement of rock fill. The placement of the
membrane would require fair weather but it can be completed in a
relatively short time after placement of the rock fill.
Page 132
In sand-gravel dams and at locations where large-size stones for wave
protection are not available, a membrane can serve for wave protection
as well as water tightness.
Greater Stability: It provides greater safety against shear failure than any
other type of embankment dam. The high stability is obtained due to
total absence of adverse seepage forces and the availability of the entire
rock fill mass to resist the water pressure acting on the upstream face.
Greater tolerance for leakage: If ordinary leakage develops through the
membrane, it drains out through the rock fill and does not endanger the
dam. In fact, rock fills can withstand considerable flows before sliding
occurs [4, 5, 6] and, unlike earth cores, the membrane itself is not
subject to progressive erosion by leaks. If the membrane and the
underlying drainage layer are bulk headed into sections and a drainage
gallery is provided, the leaks can be easily located and treated. In the
case of earth cores, location as well as treatment of leaks is difficult.
Accessibility of membrane for inspection and repairs: This is normally
feasible up to the lowest drawdown level. But even below this modern
techniques enable underwater inspection, photographing or video
recording and effective repairs.
Speed of construction: For earth cores, the speed of construction is
limited by the necessity of compaction of the soil in relatively thin layers
and placement of graded filters on either side of the core. With a
membrane, the placement of rock fill can be done faster and can
continue without interruption.
Stage construction facility: It is often advantageous to limit investment by
building the dam to a lower height in the first instance and raising it later
when utilization increases or the reservoir silts up. The upstream
membrane type of dam is the simplest to raise in height. More rock fill
can be placed on the downstream side and the membrane extended in
continuation.
Limited life: Earth cores can last indefinitely as they are not subject to
deterioration. They can only be damaged by leaks. Most membranes
deteriorate with time due to weathering, chemical action or other causes,
and may require heavy repairs during the lifespan of the dam.
Page 133
Higher cost: At a location where suitable soil material for an earth core is
available within a reasonable distance, a membrane would generally be
more expensive.
Limitation on height: The highest existing membrane-type dam is 160m
while earth core dams have reached up to and beyond 300m. Larger
heights are being contemplated for both. Cooke [2] has expressed the
opinion that membrane-type dams could well be built to heights of 250m.
Nevertheless, in the range of very large heights, there is less existing
experience and consequent concern about cracking of the membrane
due to rock deformation under immense water pressures.
Possibility of Leakage: Leakage on initial filling has occurred in several
dams through cracks in membranes. Another vulnerable location is the
joint between the membrane and the cut-off. This latter problem has
been resolved by provision of a horizontal toe slab and grout curtain in
place of a vertical cut-off. Though leakage through the membrane does
not usually endanger the dam, it may require lowering of the reservoir
and expensive repairs. Again, better compaction of rock fill, resulting in
lesser deformations, and use of thinner, more flexible membranes are
proving to be effective measures against membrane cracking and
consequent leakage.
Page 134
General Characteristics of Rock fill Dams
Rock fill dams are basically embankment dams. High inherent stability
and high perviousness are their special characteristics. The impervious
element in a rock fill dam is provided either by an impervious membrane of
manufactured material or by an earth core. Even in the case of concrete-faced
rock fill dams, the requirement of cement and other manufactured materials is
much less than for concrete dams, while in earth core dams, it is similar to
earth dams.
Due to free drain ability and high frictional strength, rock fill dams have a
high inherent stability. In fact, there is no recorded case of failure of a rock fill
dam due to slope sliding. Their high damping capacity and flexibility also give
them a high level of protection against earthquake damage.
Rock fill dams require foundations intermediate in strength between
concrete gravity dams and earth dams.
The selection of the dam is mainly governed by the site conditions. This
equally applies to the choice between membrane and earth core for rock fill
dams. The circumstances in which the membrane type is likely to prove
advantageous are:
When suitable soil for an earth core is not available within a reasonable
distance, as for example in high rocky areas.
When foundations of hard rock with little overburden are available. In this
situation there is no possibility of failure through the foundations and the
dam slopes can be designed solely on the basis of shear strength of rock
fill. The slopes can be kept somewhat steeper than those for the earth
core section.
Continuously rainy weather. In continuously rainy whether, it is difficult to
maintain proper moisture control for compaction of earth cores. There is
no such problem in the placement of rock fill. The placement of the
membrane would require fair weather but it can be completed in a
relatively short time after placement of the rock fill.
In sand-gravel dams and at locations where large-size stones for wave
protection are not available, a membrane can serve for wave protection
as well as water tightness.
Page 135
Greater Stability: It provides greater safety against shear failure than any
other type of embankment dam. The high stability is obtained due to total
absence of adverse seepage forces and the availability of the entire rock
fill mass to resist the water pressure acting on the upstream face.
Greater tolerance for leakage: If ordinary leakage develops through the
membrane, it drains out through the rock fill and does not endanger the
dam. In fact, rock fills can withstand considerable flows before sliding
occurs and, unlike earth cores, the membrane itself is not subject to
progressive erosion by leaks. If the membrane and the underlying
drainage layer are bulkheaded into sections and a drainage gallery is
provided, the leaks can be easily located and treated. In the case of
earth cores, location as well as treatment of leaks is difficult.
Accessibility of membrane for inspection and repairs: This is normally
feasible up to the lowest drawdown level. But even below this modern
techniques enable underwater inspection, photographing or video
recording and effective repairs.
Speed of construction: For earth cores, the speed of construction is
limited by the necessity of compaction of the soil in relatively thin layers
and placement of graded filters on either side of the core. With a
membrane, the placement of rock fill can be done faster and can
continue without interruption.
Stage construction facility: It is often advantageous to limit investment by
building the dam to a lower height in the first instance and raising it later
when utilization increases or the reservoir silts up. The upstream
membrane type of dam is the simplest to raise in height. More rock fill
can be placed on the downstream side and the membrane extended in
continuation.
Limited life: Earth cores can last indefinitely as they are not subject to
deterioration. They can only be damaged by leaks. Most membranes
deteriorate with time due to weathering, chemical action or other causes,
and may require heavy repairs during the lifespan of the dam.
Higher cost: At a location where suitable soil material for an earth core is
available within a reasonable distance, a membrane would generally be
more expensive.
Limitation on height: The highest existing membrane-type dam is 160m
while earth core dams have reached up to and beyond 300m. Larger
heights are being contemplated for both. Cooke [2] has expressed the
opinion that membrane-type dams could well be built to heights of 250m.
Nevertheless, in the range of very large heights, there is less existing
Page 136
experience and consequent concern about cracking of the membrane
due to rock deformation under immense water pressures.
Possibility of Leakage: Leakage on initial filling has occurred in several
dams through cracks in membranes. Another vulnerable location is the
joint between the membrane and the cut-off. This latter problem has
been resolved by provision of a horizontal toe slab and grout curtain in
place of a vertical cut-off. Though leakage through the membrane does
not usually endanger the dam, it may require lowering of the reservoir
and expensive repairs. Again, better compaction of rockfill, resulting in
lesser deformations, and use of thinner, more flexible membranes are
proving to be effective measures against membrane cracking and
consequent leakage.
Page 137
GEOTECHNICAL INVESTIGATION
1. INTRODUCTION
Geotechnical investigations are performed to evaluate those geologic, seismologic, and soils
conditions that affect the safety, cost effectiveness, design, and execution of a proposed
engineering project. Insufficient geotechnical investigations, faulty interpretation of results, or
failure to portray results in a clearly understandable manner may contribute to inappropriate
designs, delays in construction schedules, costly construction modifications, use of
substandard borrow material, environmental damage to the site, post-construction remedial
work, and even failure of a structure and subsequent litigation. Investigations performed to
determine the geologic setting of the project include: the geologic, seismologic, and soil
conditions that influence selection of the project site; the characteristics of the foundation
soils and rocks; geotechnical conditions which influence project safety, design, and
construction; critical geomorphic processes; and sources of construction materials.
Geotechnical investigations are to be carried out by engineering geologists, geological
engineers, geotechnical engineers, and geologists and civil engineers with education and
experience in geotechnical investigations. Geologic conditions at a site are a major influence
on the environmental impact and impact mitigation design, and therefore, a primary portion
of geotechnical investigations is to observe and report potential conditions relating to
environmental impact.
2. SCOPE OF INVESTIGATION
From project conception through construction and throughout the operation and
maintenance phase, geotechnical investigations are designed to provide the level of
information appropriate to the particular project development stage. In most instances, initial
geotechnical investigations will be general and will cover broad geographic areas. As project
development continues, geotechnical investigations become more detailed and cover smaller,
more specific areas. For large, complex projects, the geotechnical investigation can involve
highly detailed geologic mapping such as a rock surface for a structure foundation.
It must be understood in the beginning itself that an unreasonably extensive, and hence,
expensive site investigation in an attempt to define in infinite detail every aspect of ground
conditions is not appropriate. A rational approach would be to carry out investigations to a
level, which will allow the design and construction of the project to proceed with an
acceptable level of confidence. Accordingly, Ministry of Water Resources, Govt. of India has
published a “Guidelines for preparation of Detailed Project Reports of Irrigation &
Multipurpose River Valley Projects”, which prescribes norms for carrying out the geotechnical
investigations systematically during preparation of Detailed Project Reports. A generalized
scope of the various increments of investigation is described in the following paragraphs, but
these may be modified depending up on particular project requirements and local conditions.
Reconnaissance studies are made to determine whether a problem has a solution acceptable
to local interests and is in accordance with administrative policy. If so, reconnaissance studies
Page 138 Page 135
provide information to determine whether planning should proceed to the feasibility phase.
Feasibility studies identify and evaluate the merits and shortcomings of environmental,
economic, and engineering aspects of the proposed project. Geotechnical investigations
during planning studies should be designed to provide information at a level such that critical
geotechnical features of candidate sites may be compared in the feasibility study report. These
investigations should be sufficiently complete to permit selection of the most favorable site
areas within the regional physical setting, determine the general type of structures best suited
to the site conditions, evaluate the influence of hydrogeology on site design and construction,
assess the geotechnical aspects of environmental impact, and to ascertain the costs of
developing the various project plans in sufficient detail to allow comparative cost estimates to
be developed.
The regional geology investigations are carried out during early stages of the study. A
schematic diagram for the development of regional geology is given in Fig. 1. Initial field
investigations begin after the regional studies are sufficiently detailed to identify areas
requiring geotechnical clarification. The schematic diagram for initial field investigations is
given in Fig. 2.
The feasibility report should contain summaries of the regional geology, soils, hydrogeology,
and seismological conditions plus brief summaries of the aerial and site geotechnical
conditions for each detailed plan. These summaries should include local topography,
geomorphic setting and history, thickness and engineering character of overburden soils,
description of rock types, geologic structure, degree of rock weathering, local ground water
conditions, possible reservoir rim problems, description of potential borrow areas and
quarries, accessibility to sources of construction materials, etc. In addition, special foundation
conditions such as excavation or dewatering problems, low strength foundations, and
cavernous foundation rock should be described. The summaries should conclude with a
discussion of the relative geotechnical merits and drawbacks of each plan.
Preconstruction engineering and design (PED) or Detailed Project Report (DPR) studies are
typically initiated after a feasibility study has been completed. PED / DPR studies are
developed to reaffirm the basic planning decisions made in the feasibility study, establish or
reformulate the scope of the project based on current criteria and costs, and formulate the
design memoranda which will provide the basis for the preparation of plans and specifications.
Fig. 3 schematically outlines the engineering tasks for the PED / DPR studies with the
requirements for geotechnical information. The provisions of Ministry of Water Resources,
Govt. of India “Guidelines for preparation of Detailed Project Reports of Irrigation &
Multipurpose River Valley Projects” is given in Annex A.
Construction Stage
Geotechnical activities in support of the construction phase of a project can be divided into
three phases: construction management, quality assurance, and compilation of summary
reports. Fig. 6 outlines the tasks for construction geotechnical activities.
Construction management
(a) Claims and modifications - Regardless of the intensity of geological investigations during
the preconstruction phase, differing site conditions, claims, and modifications are to be
expected on complex projects. Most common claim relates to overbreak due to geological
reasons. On a few occasions due to adverse geological conditions or geological surprises,
modifications in the project layout become necessary. Therefore, geotechnical engineers
should provide necessary support to investigate claims and provide design and cost-estimating
assistance for any claims and modifications.
(b) Site visits for verification of quality - On all projects, but especially those too small to
support a resident geologist or geotechnical engineer, site visits should be made regularly by
qualified personnel to verify that conditions match assumptions used in designing the project
features and to assist construction personnel on any issues affecting construction. All visits
should be well documented (including an extensive photographic and video record) and be
included in appropriate summary reports.
Quality assurance
The geotechnical engineer assigned to a particular project has the responsibility to monitor,
observe, and record all aspects of the construction effort relating to foundations,
embankments, cuts, tunnels, and natural construction materials. Fig.7. shows in tabulated
form some of the particular items requiring quality assurance particular to geo-technically
oriented features. An onsite laboratory should be required on major projects to perform all
soil and concrete testing. During construction, considerable data are assembled by the project
geotechnical quality assurance staff. These data consist generally of foundation mapping and
treatment features, embankment-backfill performance data, grouting records, material testing
The purpose of the construction geotechnical report is to ensure the preservation for future
use of complete records of foundation conditions encountered during construction and
methods used to adapt structures to these conditions. It is an important document for use in
evaluating construction claims, planning additional foundation treatment should the need
arise, evaluating the cause of foundation or structural feature distress and planning remedial
action to prevent failure or partial failure of a structure, planning and design of major
rehabilitation or modifications to the structure, providing guidance in planning foundation
explorations, and in anticipating foundation problems for future comparable construction
projects in similar geologic settings. Site geotechnical personnel responsible for the
foundation report must begin to formulate the report as soon as possible after construction
begins so that completion of the report can be accomplished by those who participated in the
construction effort. Fig. 8. presents the schematic diagram of construction geotechnical
investigations and documentation.
This report should include collaboration with design and construction personnel. Detailed
video recordings of foundation conditions should be an integral component of the foundation
report.
3. INVESTIGATION METHODS
There are several possible methods for geotechnical investigations. The major factors
influencing the selection of methods of investigation include:
Primarily, there are two types of geotechnical investigations, i.e., surface and sub-surface. The
detailed description of the various methods under these types are beyond the scope of this
lecture. However, they are briefly described below;
Surface investigations include the field operations that do not involve significant disturbance
of the ground at the time the investigation is conducted. This type of investigation typically
occurs at a preliminary stage of projects and supplies generalized information. However, these
investigations can involve mapping specific locations in great detail during construction. The
end product is commonly a pictorial rendering of conditions at the site. The degree of
accuracy and precision required in such a rendering varies with the application and purpose
for which the information is to be used.
Geologic and environmental features within the reservoir and adjacent areas that
should be studied and mapped include the following:
Site Mapping - Large-scale and detailed geologic maps should be prepared for specific
sites of interest within the project area and should include proposed structure areas
and borrow and quarry sites. Investigation of the geologic features of overburden and
rock materials is essential in site mapping and subsequent explorations. Determination
of the subsurface features should be derived from a coordinated, cooperative study of
information on origin, distribution, and manner of deposition of the overburden / rock
and the engineering properties of the site foundation and potential construction
Geophysical exploration consists of making indirect measurements from the earth's surface or
in boreholes to obtain subsurface information. Geologic information is obtained through
analysis or interpretation of these measurements. Boreholes or other subsurface explorations
are needed to calibrate or validate geophysical measurements. Geophysical explorations are
of greatest value when performed early in the field exploration program in combination with
limited subsurface exploration. They are appropriate for a rapid location and correlation of
geologic features such as stratigraphy, lithology, discontinuities, ground water, and the in situ
measurement of elastic moduli and densities. The cost of geophysical explorations is generally
low compared with the cost of core borings or test pits, and considerable savings may be
realized by judicious use of these methods.
The six major geophysical exploration methods are seismic, electrical resistivity, sonic,
magnetic, radar, and gravity. Of these, the seismic and electrical resistivity methods have
found the most practical application to the engineering problems.
SUB-SURFACE INVESTIGATIONS
Subsurface investigations require use of equipment to gain information below the ground
surface. The equipment is typically invasive and requires disturbance of the ground to varying
degrees. Most of these exploration techniques are relatively expensive, and therefore, should
be carefully planned and controlled to yield the maximum amount of information possible.
The major planning factors are;
Location of Investigations
An important piece of information for all geotechnical investigations that seems obvious but
commonly not given sufficient attention is the accurate determination of the location of
investigation. It is always preferable to select boring and test pit locations that fully
characterize geotechnical conditions. Although correlation of information from offsite may be
After the locations for field investigations work have been determined, routes of access to the
area and the specific sites for borings and excavations should be selected with care to
minimize damage to the environment.
Borings are classified broadly as disturbed, undisturbed, and core. Borings are frequently used
for more than one purpose, and it is not uncommon to use a boring for purposes not
contemplated when it was made. Thus, it is important to have a complete log of every boring,
even if there may not be an immediate use for some of the information. If there is doubt
regarding the range of borehole use or insufficient information to determine optimum
borehole size, then the hole should be drilled larger than currently thought needed. A slightly
larger than needed borehole is considerably less expensive than a second borehole.
Many methods are used to make borings and retrieve samples. Most common methods are
discussed in the following paragraphs. Some factors that affect the choice of methods are:
A major part of field investigations is the compilation of accurate borehole logs on which
subsequent geologic and geotechnical information and decisions are based. A field drilling log
for each borehole can provide an accurate and comprehensive record of the lithology and
stratigraphy of soils and rocks encountered in the borehole and other relevant information
obtained during drilling, sampling, and in situ testing.
Test pits and trenches can be constructed quickly and economically by bulldozers, backhoes,
pans, draglines, or ditching machines. Depths generally are less than 6 m (20 ft), and sides may
require shoring, if personnel must work in the excavations. Test pits, however, hand dug with
pneumatic jackhammers and shored with steel cribbing, can be dug to depths exceeding 18 m
(60 ft). Test pits and trenches generally are used only above the ground water level. Test pits
that extend below the water table can be kept open with air or electric powered dewatering
pumps. Exploratory trench excavations are often used in fault evaluation studies. An extension
of a rock fault into much younger overburden materials exposed by trenching is usually
considered proof of recent fault activity. Shallow test pits are commonly used for evaluating
potential borrow areas, determining the geomorphic history, and assessing cultural resource
potential.
Whenever the size and complexity of a project warrant, a large-scale, prototype test programs
can yield information unavailable by any other method. Because these investigations are
expensive and require the services of a construction contractor in most cases. For large
projects, it is desirable to perform these investigations during the PED / DPR phase, as they
provide a number of benefits that will result in an improved, more cost-effective design. These
benefits include: confirmation of assumptions for new or innovative design, improved
confidence level allowing reduced safety factors, proof of constructability, confirmation of
environmental compliance, and greater credibility in allaying public concerns.
Exploratory tunnels / adits / shafts permit detailed examination of the composition and
geometry of rock structures such as joints, fractures, faults, shear zones, other discontinuities,
range & extent of weathering and solution channels. They are commonly used to explore
conditions at the locations of large underground excavations and the foundations and
abutments for large dams. They are particularly appropriate in defining the extent of marginal
strength rock or adverse rock structure suspected from surface mapping and boring
information or when drilling is not possible due to inaccessibility / depths greater than 300 m
or so. For major projects where high-intensity loads will be transmitted to foundations or
abutments, tunnels afford the only practical means for testing in-situ rock at locations and in
directions corresponding to the structural loading. Although expensive, exploratory tunnels /
adits / shafts provide exceptionally good preconstruction information to perspective
contractors on major underground projects and can reduce bid contingencies and/or potential
for claims. Long horizontal exploratory drill holes can also be used in lieu of, or in combination
with, pilot tunnels to gather information about tunneling conditions prior to mining.
In the case of planned underground construction, an exploratory tunnel is often used to gain
access to crown and roof sections of future large underground excavations. The tunnel can
then be used during construction for equipment access and removal of excavated rock. A
small bore or exploratory “pilot” tunnel is sometimes driven along the entire length of a
proposed larger-diameter tunnel where difficult and often unpredictable ground conditions
are anticipated. A pilot tunnel may be the most feasible alternative for long deep tunnels
where deep exploratory drilling and access for in situ testing from the ground surface is
prohibitively expensive. The pilot tunnel can be positioned to allow installation of roof support
and/or consolidation grouting for critical areas of the full tunnel, or in some cases, to provide
relief or “burn cuts” to facilitate blasting. Exploratory tunnels, that are strategically located,
can be incorporated into the permanent structure. They can be used for drainage and post-
construction observations to determine seepage quantities and to confirm certain design
assumptions.
The purpose of laboratory tests is to investigate the physical and hydrological properties of
natural materials such as soil and rock, determine index values for identification and
correlation by means of classification tests, and define the engineering properties in
parameters usable for design of foundations. The engineering geologist and/or geotechnical
engineer, using the test data and calling upon experience, can then accomplish safe and
In-situ tests are often the best means for determining the engineering properties of
subsurface materials and, in some cases, may be the only way to obtain meaningful results.
Table, given below, lists in-situ tests and their purposes. In-situ tests are performed to
determine in-situ stresses and deformation properties of the jointed rock mass, shear strength
of jointed rock mass or critically weak seams within the rock mass, residual stresses within the
rock mass, anchor capacities, and rock mass permeability. Large-scaled in-situ tests tend to
average out the effect of complex interactions. In-situ tests are generally expensive and
should be reserved for projects with large, concentrated loads. Well-conducted tests may be
useful in reducing overly conservative assumptions. Such tests should be located in the same
general area as a proposed structure and test loading should be applied in the same direction
as the proposed structural loading.
Notes:
1. Primarily for clay shales, badly decomposed, or moderately soft rocks, and rock with soft seams.
2. Less frequently used.
3. Dynamic deformability.