Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

00 - MS - Electrical Identifications Installation

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

METHOD STATEMENT

FOR
ELECTRICAL IDENTIFICATIONS INSTALLATION

 TABLE OF CONTENTS

1. SCOPE

2. DEFINITIONS

3. HEALTH AND SAFETY

4. OPERATION

5. INSTALLATION AND FIXATION

6. RESPONSIBILITIES

7. MANPOWER REQUIRED

8. MATERIALS REQUIREMENTS

9. EQUIPMENTS REQUIREMENTS

10. WASTE MANAGEMENT

11. SPECIAL CONTROL MEASURES.

12. SUPPORTING DOCUMENTATION

13. DISTRIBUTION
1.SCOPE
 This procedure to clear the method of the supply, installations of
Electrical Identifications for the project.
 This document details Electrical Identifications Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.

2. DEFINITIONS
PQP : Project Quality Plan

PSP : Project Safety Plan

QCP : Quality Control Procedure

HSE : Health, Safety and Environment

MS : Method Statement

ITP : Inspection Test Plan

QA/QC : Quality Assurance / Quality Control Engineer.

WIR : Inspection and Test Request

MIR : Material Verification Record.

3. HEALTH AND SAFETY


 Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials.
 Ensure all involved personnel shall be aware of the same.
 Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.

4. OPERATION
 Material: 

 Material used will be as approved by the Engineer.


 The sizes and routes routing will be as per the approved Shop
Drawings.

 Storage and Protection: 


 Deliver components parts to site, completely identified in accordance
with shop and certified CAD Drawings prepared for this work.

 Store in accordance with the manufacturer’s instructions, above


ground, properly protected from the weather and construction activities.

5. INSTALLATION AND FIXATION


 Pre-Installation:
 All materials and documentation relevant to this particular section of
works will be checked and verified ensuring that these are correct
and approved type.

 Prior to the commencement of works, ensure that the areas for


permanent installation are ready, accessible and in suitable
condition.

 Installation:
 Install identification devices according to manufacturer's written
instructions.

 Install labels where indicated and at locations for best convenience


of viewing without interference with operation and maintenance of
equipment.

 Lettering, Colors, and Graphics: Coordinate names, abbreviations,


colors, and other designations used for electrical identification with
corresponding designations used in the Contract Documents or
required by codes and standards. Use consistent designations
throughout the Project.

 Sequence of Work: Where identification is to be applied to surfaces


that require finish, install identification after completion of finish
work.

 Self-Adhesive Identification Products: Clean surfaces of dust, loose


material, and oily films before applying.

 Install Circuit Identification Labels on Boxes: Label externally on


exposed boxes with pressure-sensitive, self-adhesive plastic label
on cover.

 Color-Code Conductors: Secondary service, feeder, and branch


circuit conductors throughout the secondary electrical system as
follows:
 Tri-phase System: As follows:
o Phase A : Red.
o Phase B : Yellow
o Phase C : Blue.
o Neutral : Grey or Black.
o Ground : Green / Yellow
 Factory-apply color the entire length of the conductors, except
the following field applied, color-coding methods may be used in
lieu of factory-coded wire.

 Apply Identification to conductors as follows:


 Conductors to Be Extended in the Future: Indicate source and circuit
numbers.
 Multiple Power or Lighting Circuits in the Same Enclosure: Identify
each conductor with source, voltage, circuit number, and phase. Use
color coding for voltage and phase indication of secondary circuit.
 Multiple Control and Communications Circuits in the Same Enclosure:
Identify each conductor by its system and circuit designation. Use a
consistent system of tags, color coding, or cable marking tape.

 General Identification as follows:


 Apply labels for each unit of the following categories of equipment.
a) Panel boards, electrical cabinets, and enclosures.
b) Electrical switchgear and switchboards.
c) Motor control centers.
 Apply designation labels for disconnect switches, breakers, push
buttons, pilot lights, motor control centers, and similar items for power
distribution and control components above.
 For panel boards, provide typed circuit schedules with explicit
description and identification of items controlled by each individual
breaker.

 Raise Request for Inspection of Electrical Identification Installation.

 Technical Assistance:
 The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
 This instruction shall be scheduled at the convenience of the
staff.
 All such instruction shall be properly recorded.
 WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.

6. RESPONSIBILITIES

 PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.

2. To ensure that the progressing of works is carried out according


to the planned program and as per the approved method of
statement.

3. To ensure that all the equipment and material required


executing the work are available according to the planned
construction program.

4. To co-ordinate with the Main contractor, MEP coordinator,


Safety Officer for a safe and proper execution of the works.

 SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.

2. To provide all necessary information and distribute


responsibilities to his construction.

3. To monitor the progress of work in relation with the work


program and to report to the Project Manager.

4. To co-ordinate with the safety officer and to ensure that the


works are carried out in safe practicing method.

 FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.

2. To ensure that his assistant foreman/ charge hand are aware of


the job requirements and they have enough information to carry
out their duties properly.

3. To ensure that the daily work is progressing as planned and


advice the site engineer of any requirement for additional
resources.
4. To ensure in consultation with the site engineer that the
manpower involved in the works are moving as agreed and
planned for the work.

5. To control disposal of waste materials according to the


instructions received from the site engineer.

6. To ensure full coordination with the safety officer to maintain


safe working and proper house keeping of the site, following the
proved safety measures and further ensure that all his working
team are aware of the same to prevent accident and losses.

7. To inform the site engineer regarding areas ready for inspection.

8. Foreman and the storekeeper are responsible for the distribution


and control of materials.

 SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.

2. Ensure all the implemented safety measures are adequate to


maintain safe working on the site.

3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.

 TECHNICIAN FROM SUPPILER


1. The carrying-out of work and the proper distribution of all the
available resources in coordination with the sub-contractor
Site Engineer on a daily basis.
2. Daily reports of the works are achieved and coordinated for
the future planning with the Site Engineer.
3. Complying with the sub-contractor basic design practices,
particularly those related to safety and engineering
4. Meeting with any type of unforeseen incident or requirement
and reporting the same to the Site Engineer immediately.

 STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.

7. MANPOWER REQUIRED
 Charge hand and Experienced Technicians

8. MATERIALS REQUIREMENTS
 Electrical Identifications Components and Accessories

9. EQUIPMENTS REQUIREMENTS
 The Equipment that will be engaged for Electrical Identifications
Installation will be as follows:

 Wire cutters

 Hacksaw

 Measuring tape

 Drill machine

 Wooden hammer

 Flat file

 Screw drivers

 Open and box spanners

 Base Cutter

10. WASTE MANAGEMENT

 The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
11. SPECIAL CONTROL MEASURES
 The following general control measures against Safety, Environment and
Quality shall be required for our scope of work and special control
measures are not applicable for us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made
available to site.
 All workers doing the work shall be briefed on this method statement
and risk assessment.

12. SUPPORTING DOCUMENTATION


 This method Statement should be read in conjunction with the below
referenced documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.

13. DISTRIBUTION
 Copy of this method statement shall be issued to the following for
information / action / comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer

5. Technician From Supplier

6. Store Keeper

You might also like