Statement for Low Currrent
Statement for Low Currrent
Statement for Low Currrent
: 00
Method of Statement for low
current Date : 16-9-2021 Page: 2 of 3
00 Hytham El-Nouby
Rev.: 00
Method of Statement for low
current Date : 16-9-2021 Page: 2 of 3
05
04
03
02
01
00 - Original Issue
1. SCOPE
This procedure to clear the method of the supply, installations Telephone / Data
System for the project.
This document details the Telephone / Data System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
Specific safety measures have to follow as applicable, and all the safety measures are
covered separately in the project safety plan.
4. OPERATION
Material:
The sizes and routes routing will be as per the approved Shop Drawings.
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer recommendations,
Approved shop drawings and project specifications.
Installation:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out
according to the Contract Specification and with the approved drawings.
3. To ensure that all the equipment and material required executing the work
are available according to the planned construction program.
4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for
a safe and proper execution of the works.
SITE ENGINEER
1. To ensure that the works are carried out according to the Contract
Specification, approved method statement and the shop drawings.
3. To monitor the progress of work in relation with the work program and to
report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practicing method.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination
with the site engineer on daily basis, and ensure proper distribution of the
work force on the required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties
properly.
3. To ensure that the daily work is progressing as planned and advice the site
engineer of any requirement for additional resources.
4. To ensure in consultation with the site engineer that the manpower involved
in the works are moving as agreed and planned for the work.
6. To ensure full coordination with the safety officer to maintain safe working
and proper house keeping of the site, following the proved safety measures
and further ensure that all his working team are aware of the same to
prevent accident and losses.
8. Foreman and the storekeeper are responsible for the distribution and control
of materials.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with
the HSE plan and everybody aware of it for it’s proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe
working on the site.
3. Inspect all the site activities and train the person to prevent accidents and
it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to store the
material delivery to the site and keep it in suitable area that will keep the
material in safe from rusty and damage.
2. One who will acknowledge the receiving of materials at site in coordination
with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Telephone / Data System Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Telephone / Data System Installation will be
as follows:
Wire cutters
Hacksaw
Measuring tape
Drill machine
Wooden hammer
Flat file
Screw drivers
Base Cutter
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for information/ action/
comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper