DB, SMDB Method Statement
DB, SMDB Method Statement
DB, SMDB Method Statement
3. Location of Activity
Low Voltage Room and Electrical Rooms
5. Operation
1.
Materials: Materials used will be as per the material submittal approved by the
engineer and will be as per the approved drawings in coordination with other services.
2.
Storage / Protection: DB, SMDB, and MDB and Accessories shall be unloaded
with care to avoid any damages. If they are shipped in packs or pallets, each pack of
pallet shall be lifted individually with suitable lifting equipment. Every precaution
shall be taken to preserve their cleanliness before installation. Store in accordance
with manufacturers instructions, Properly protected from construction activities and
weather conditions.
3.
Installation:
a.
To make sure that the entire installation is in conformance and in
accordance with the design intent of the project for the Electrical and Low Voltage
System in addition to the specification and as per approved shop drawings and
comply.
b.
with local and International Standards.
c.
All the switchboards shall be fabricated at the manufacturers works.
d.
Before beginning installation in any area, examine all parts of the
adjoining works into which applicable work is to be placed. Should any condition be
found which will prevent the proper execution of the work, installation shall not
proceed in that area until such conditions are corrected by the contractor.
e.
Fix all equipment independently of wiring system. Use cadmium of zinc
electroplated bolts, nuts, washers and screw.
f.
Mount single DB at 1800mm from finish floor level to top of equipment,
unless shown otherwise on drawing / schedules.
g.
6. Responsibilities
1.
Project Manager
a.
To ensure that all the preparation and application works are carried out
according to the Contract Specification.
b.
To ensure that the progressing of works is carried out according to the
planned program and as per the approved method statement.
c.
To ensure that all equipment and material required executing the work are
available according to the planned Construction Programme.
d.
To co-ordinate with the Main Contractor, MEP co-coordinator, and Safety
Officer for a safe and proper execution of the works.
2.
Site Engineer
a.
To ensure that the works are carried out according to the Contract
Specifications approved method statement.
b.
To provide all necessary information and distribute responsibilities to his
construction team.
c.
To monitor the progress of work in relation with the work program and to
report to the Project Manager.
d.
To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practicing methods.
3.
a.
Foreman
The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure proper distribution of
the workforce in the required and planned locations.
b.
c.
d.
e.
f.
g.
h.
4.
To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties properly.
To ensure in consultation with the site engineer that the manpower
involved in the works are moving as agreed and planned for the work.
To ensure that the daily work is progressing as planned and advise the Site
Engineer for any requirement of the additional resources.
To control disposal of waste materials to the instructions received from the
site engineer.
To ensure full coordination with the safety officer to maintain safe working
and proper house keeping of the site, following the approved safety measures and
further ensure that all his working team are aware of the same to prevent accident
and losses.
After completion of works, Foreman shall inform the site engineer for
inspection of works.
Distribution and the control of materials shall be monitored by foreman
and storekeeper.
Safety Engineer
a.
7. Manpower Required
Charge hand and Experienced Technicians
8. Materials Requirements
DB, SMDB, MDB and accessories
9. Equipments Requirement
The equipment that will be engaged for Installation of DB, SMDB and MDB works will
be as follows:
1.
2.
Wire cutters
Measuring tape
3.
4.
5.
6.
7.
8.
Drill machine
Wooden hammer
Flat file
Screw drivers
Open and box spanners
Crimping tool
12. Distribution
Copy of this method statement shall be issued to the following for information/ action/
comments:
1.
2.
3.
Project Manager
Site Engineer
Foremen
Inspection
Description
Type of
Inspection
Design and
Drawings
Review of
Documents
Reference
Document
Testing Requirement/
Acceptance Criteria
Verifying / C
Data Forms
Design
Drawings
Design draw
Authorities
Departments
Requirement
Approved
Submittals
Documents
Drawing and
Specification
Documents
Check Switchgear
installation and
cable
terminations.
Visual, Insulation
Approved
Resistance and
Method
Continuity
Statement
TestReport
Properlocation installation,
termination etc Material
Approved Dr
should have minimum status
Method State
of NO Objection with
comments
Request for
inspection of
works
Visual, Insulation
Resistance and
Approved
Continuity Test
Drawing
report.