MS Conduit Installation
MS Conduit Installation
MS Conduit Installation
ELECTRICAL
CONTENTS PAGE
1.0 OBJECTIVE 2
2.0 SCOPE OF WORK 2
3.0 REFERENCES 2
4.0 SITE ORGANISATION 3
5.0 CONSTRUCTION METHODS 4
6.0 INSPECTION AND TESTING 7
7.0 SAFETY 8
8.0 ENVIRONMENTAL 8
METHOD STATEMENT
ELECTRICAL
1.0 OBJECTIVE
This work method statement defined the preparation and installation of work
for conduit in all reinforced concrete slab, brick wall, columns, and where
ever applicable.
3.0 REFERENCES
4.1 General
The head office will provide, where necessary, technical support, personnel
resources and professional expertise and experience to the projects. IJMC
will have regular meetings on a monthly basis, and as required, to ensure
that the execution of the projects is proceeding at the rate required meeting
the contract completion dates.
4.2 Co-Ordination
Item Description
1. Electric grinder / diamond cutter
2. Electric drill
3. Screw driver
4. Styrofoam
5. Portable generator set
6. Hammer and chisel
Item Description
1. G.I conduit
2. Flexible conduit
3. Conduit circular boxes and accessories
Conduits
Conduit circular boxes
Flexible conduit
b) All materials are under the responsibility of the Material Controller and
the supervisor on duty
All materials will be handled in such a manner as not to damage the item and
hence its performance.
METHOD STATEMENT
ELECTRICAL
b) Mark on the soffit of the slab or wall surface, the conduit routing and
ensure there is no obstruction. If there is any obstruction, further co-
ordination will be done.
c) Once the route has been confirmed, install the saddle onto the wall or
soffit along the marked conduit route with an interval of 1200mm.
e) For jointing of one conduit to another (in straight line), bushes shall be
provided.
h) Conduit circular box cover will be installed at the end stage after
drawing of wires.
c) Once the first layer of reinforcement bars is laid, conduits are then laid
onto the slab re-bars and secured tightly with steel wires.
Visual Inspection shall be carried out before every casting of the floor slab,
column or plastering of brick wall, especially for conceal conduit installation:
6.1.1 Pre-installation
7.0 SAFETY
All work will be planned and undertaken in accordance with the Project Safety
Plan. All activities will be undertaken with safety in mind ensuring that
Personal Protective Equipment are being used at all times.
METHOD STATEMENT
ELECTRICAL
8.0 ENVIRONMENTAL
All work will be planned and undertaken in accordance with the Project
Environment Management Plan.