METHOD STATEMENT

ELECTRICAL

CONTENTS PAGE

1.0 OBJECTIVE 2
2.0 SCOPE OF WORK 2
3.0 REFERENCES 2
4.0 SITE ORGANISATION 3
5.0 CONSTRUCTION METHODS 4
6.0 INSPECTION AND TESTING 7
7.0 SAFETY 8
8.0 ENVIRONMENTAL 8
METHOD STATEMENT
ELECTRICAL

1.0 OBJECTIVE

This method statement provides information concerning the plant, equipment


and method of construction to ensure compliance with contract requirements,
drawings, technical specification and quality control.

2.0 SCOPE OF WORK

This work method statement defined the preparation and installation of work
for conduit in all reinforced concrete slab, brick wall, columns, and where
ever applicable.

The scope of work comprises the following: -


Installation of conduits
Installation of flexible conduits
Installation of conduit circular boxes and accessories

3.0 REFERENCES

This method statement shall be read in conjunction with the following


documents:

Regulations of JBE, TNB, JKKP etc.

4.0 SITE ORGANISATION

4.1 General

NY ENGINEERING has formed a management committee, which will oversee


and monitor the execution of the project.

The head office will provide, where necessary, technical support, personnel
resources and professional expertise and experience to the projects. IJMC
will have regular meetings on a monthly basis, and as required, to ensure
that the execution of the projects is proceeding at the rate required meeting
the contract completion dates.

The day-to-day management of the contract will be headed by the roject


Manager who will be assisted by senior personnel. If the Project Manager at
any time considers it necessary to increase the supervisory staff for the
projects, he will report directly to the management committee enabling
prompt actions to the site requirements.

The Project Manager is responsible for execution of the works.


METHOD STATEMENT
ELECTRICAL

4.2 Co-Ordination

Formal coordination meetings chaired by the Project Managers and attended


by all subcontractors.

4.3 Equipment And Tools

Item Description
1. Electric grinder / diamond cutter
2. Electric drill
3. Screw driver
4. Styrofoam
5. Portable generator set
6. Hammer and chisel

4.4 Material Proposed

Item Description
1. G.I conduit
2. Flexible conduit
3. Conduit circular boxes and accessories

5.0 CONSTRUCTION METHODS

5.1 Storage Of Material

a) All material must be properly segregated into the following category:

Conduits
Conduit circular boxes
Flexible conduit

b) All materials are under the responsibility of the Material Controller and
the supervisor on duty

c) All material must be collected and returned to the designated storage


area after working hours and properly secured and locked.
5.2 Handling Of Material

All materials will be handled in such a manner as not to damage the item and
hence its performance.
METHOD STATEMENT
ELECTRICAL

5.3 Sequence Of Work


In general, the sequence of works will be carried out in accordance to main
civil work schedule and / or Architectural work schedule.

5.4 Installation Procedure

5.4.1 Surface Conduit Installation

a) Prior to laying of conduits, check and determine the conduit routing


first. Consider the mounting height as well as the size of conduits as
per construction drawings.

b) Mark on the soffit of the slab or wall surface, the conduit routing and
ensure there is no obstruction. If there is any obstruction, further co-
ordination will be done.

c) Once the route has been confirmed, install the saddle onto the wall or
soffit along the marked conduit route with an interval of 1200mm.

d) Install conduits along the marked route and secure it to saddles.


Conduits shall be bent or cut on site to suit local conditions. Cut edge
shall be trim off by using reamer to avoid any damages on the cables
or wiring.

e) For jointing of one conduit to another (in straight line), bushes shall be
provided.

f) All free ends of conduits shall be fitted with appropriated bushes /


plugs / conduit circular boxes.

g) Conduits to all motors, withdraw able or removable items of


equipment, and all items of equipment where vibration may reasonably
be expected, shall be of flexible type.

h) Conduit circular box cover will be installed at the end stage after
drawing of wires.

5.4.2 Slab Concealed Conduit Installation

a) Prior to laying of conduits, check and determine the conduit routing


location as per construction drawings.

b) Mark conduit routing, position of lighting & power points, conduit


circular boxes, and etc. on the formwork.
METHOD STATEMENT
ELECTRICAL

c) Once the first layer of reinforcement bars is laid, conduits are then laid
onto the slab re-bars and secured tightly with steel wires.

d) Conduit circular boxes are to be secured tightly onto the formwork


with steel wires and nails. At the same time, the boxes shall be first
stuffed with paper / styrofoam to prevent seepage of slurry into the
boxes.

e) For jointing of one conduit to another, bushes shall be provided. At the


joint section shall be sealed with masking tape to prevent ingress of
slurry into the conduit.

f) All free ends of conduits shall be fitted with appropriated bushes /


plugs / conduit circular boxes.

6.0 INSPECTION AND TESTING

Visual Inspection shall be carried out before every casting of the floor slab,
column or plastering of brick wall, especially for conceal conduit installation:

6.1 Visual Inspection Procedure

6.1.1 Pre-installation

a) Check the conduit routing layout according to shop drawings.

b) Check correctness of brand, model and type of conduits and


conduit circular boxes.

6.1.2 During Installation

a) Check correctness of location and mounting.

b) Check secure of installation.

c) Check level of outlet boxes.

7.0 SAFETY

All work will be planned and undertaken in accordance with the Project Safety
Plan. All activities will be undertaken with safety in mind ensuring that
Personal Protective Equipment are being used at all times.
METHOD STATEMENT
ELECTRICAL

8.0 ENVIRONMENTAL

All work will be planned and undertaken in accordance with the Project
Environment Management Plan.