Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Method Statement - Concealed Conduit

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

METHOD STATEMENT Ref. No.

HPEC/MS/CONDUIT/SFORM/2018

INSTALLATION OF CONCEALED PVC CONDUIT / PVC DUCT (SYSTEM FORMWORK)

Objective

1. To outline work method statement for installation of concealed conduit and


etc. under erection of wall / slab using system formwork.

Installation of concealed PVC conduit / duct complete with accessories in RC wall

1. This section is applicable to installation of lighting switches, switched socket


outlet points, TV points, telephone points, air cond points, recessed distribution
panel and etc.

2. Location and quantity of LV and ELV point shall be identified and determined
based on the approved shop drawing and coordination drawing.

3. Once the vertical BRC / steel mesh are erected, PVC conduit shall be laid in
between BRC layers and secured by tighten up with steel wire / cable tie.

4. Polyfoam are cut into suitable size matching base box dimension of various
switched socket outlet, telephone point, TV point, DB and etc. The cut
polyfoam are then wrapped up with masking tape and securely placed in
designated location which will form groove line or recessed on RC wall surface
after concreting.

5. The open end of conduits shall be wrapped and sealed off with masking tape
to prevent ingress of unnecessary debris during concreting.

6. After all PVC conduit and polyfoam are installed and fixed, inspection shall be
carried out together with client / consultant’s site representative.

7. The conduit work shall be redo or undergo necessary rectification, if fail to


meet the standard requirements.

8. Once the aforesaid inspection passed, the system formwork can be closed up
and ready for concreting.

Page 1 of 4
METHOD STATEMENT Ref. No. HPEC/MS/CONDUIT/SFORM/2018

Figure 1: Conceal conduit in vertical RC wall.

Figure 2: Sample of site working photo

Page 2 of 4
METHOD STATEMENT Ref. No. HPEC/MS/CONDUIT/SFORM/2018

Installation of concealed PVC conduit / duct complete with accessories in RC Slab

1. This section is applicable to installation of lighting points, fan points, under floor
duct and etc.

2. Location and quantity of LV and ELV point shall be identified and determined
based on the approved shop drawing and coordination drawing.

3. Once the bottom formwork are erected and BRC / steel mesh are laid, PVC
conduit / PVC duct complete with necessary accessories shall be laid in
between BRC layers and secured by tighten up with steel wire / cable tie.

4. Polyfoam are cut into suitable size to form recessed surface on slab soffit for
interconnection of under floor PVC duct.

5. After all PVC conduit, PVV duct and polyfoam are installed and fixed,
inspection shall be carried out together with client / consultant’s site
representative.

6. The conduit work shall be redo or undergo necessary rectification, if fail to


meet the standard requirements.

7. Once the aforesaid inspection passed, the floor slab is ready for concrete
casting.

Figure 3: Conceal conduit in RC slab.

Page 3 of 4
METHOD STATEMENT Ref. No. HPEC/MS/CONDUIT/SFORM/2018

Figure 4: Sample of site working photo

Page 4 of 4

You might also like