Testing and Commissioning Procedure For Earthing System Method Statement
Testing and Commissioning Procedure For Earthing System Method Statement
Webmaster
The purpose of this procedure is to define the step by step method to implement the
correct practices for the pre-commissioning & commissioning of Earthing
System through the guidelines contained herein so as to ensure that the job execution
complies with the project requirements and serves the intended function to satisfactory
level.
The earthing system consist of a dedicated earth bus bar for each floor in the electrical
room where all the earthing leads of the respecitve floor equipment are terminated. The
earth bus bars of individual floors shall be connected to the main bus bar in the ground
floor which shall drain into the earth pits.
1/2
Commissioning Procedure for Earthing System
1. Ensure that all the pre commissioning checks are carried out successfully.
2. Ensure the earth bars are in level using spirit level.
3. Check the continuity of the earth cables from the respective equipment to the floor
earth bar.
4. Check the continuity of the earth cables from the respective floor earth bars to the
main earth bar of the respective building.
5. Check the continuity of the earth cables from the respective main earth bar of the
building to the earth pits.
6. Check the earth resistance values at the earth pits individually & ensure that the
value is less than one ohm.