Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
113 views12 pages

Buoyancy Control For Pipelines Buoyancy Control For Pipelines

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 12

BUOYANCY CONTROL

FOR PIPELINES
INTRODUCTION
Platipus® Anchors are market leaders in the design, manufacture and supply of
mechanical earth anchoring products. The company is renowned for providing some
of the most innovative and cost-effective anchoring solutions for the Civil
Engineering, Construction and Marine industries.

The percussion driven earth anchor (PDEA) is a unique, modern and versatile device that can be quickly
installed in most displaceable ground conditions. It offers a lightweight corrosion resistant anchor that can be
driven from ground level using conventional portable equipment. It creates minimal disturbance in the soil
during installation; can be stressed to an exact holding capacity and made fully operational immediately. As a
completely dry system it also has minimal impact on the environment.

KEY BENEFITS OF THE PLATIPUS® EARTH


ANCHORING SYSTEM
Proven design solutions for buoyancy control of small
& large pipelines
Significant time & cost savings over concrete coating /
set on / bolt on weights / bags
Minimal environmental damage
Proof testing of each anchor upon installation
Application designed webbing for fast installation with no
damage to pipes or their coating
Installation before or after the pipe is laid
No specialist installation equipment required
Flexible anchor selection for varying soil conditions
No Cathodic protection required
2
‘SIMPLY’ HOW A MECHANICAL ANCHOR WORKS
There are three steps to the installation of an anchor system:

DRIVING THE ANCHOR REMOVING THE RODS LOADLOCKING

STRESS DISTRIBUTION & BEARING CAPACITY


The stress distribution in front of a loaded anchor can be modelled using
foundation theory. The ultimate performance of an anchor within the soil is defined
by the load at which the stress concentration immediately in front of the anchor
exceeds the bearing capacity of the soil.

Factors that will affect the ultimate performance of the anchor include:-

· Shear angle of the soil · Depth of installation


Granular Soil · Size of the anchor · Submerged conditions
(Based on Terzaghi’s calculation)
®
Platipus anchors perform exceptionally well in a granular soil, displaying short
loadlock and extension characteristics, a broad frustum of soil immediately in front
of the anchor and extremely high loads.

Stiff cohesive soils, such as boulder clays, can also give outstanding results.
However, weaker cohesive soils, like soft alluvial clays, can result in long loadlock
and extension distances and a small frustum of soil in front of the anchor.
Consequently these conditions require a larger size of anchor and if possible a
deeper driven depth to achieve design loads.
Soft Cohesive Soil
(Based on Skempton’s calculation)

TYPICAL ANCHOR BEHAVIOUR

LOADLOCK COMPACTION MAXIMUM LOAD RANGE BEARING CAPACITY FAILURE


AND LOAD

3
STEALTH ANCHOR
The Stealth anchor is designed to cover a
wide range of lightweight anchoring solutions.
Its chisel point and streamline shape make
installation easy using simple hand tools.

We have designed three complete solutions


with our S4 / S6 / S8 anchors combining them
with our own tensioners and webbing.

Each set can be installed in a few minutes


using hand tools.

DIMENSIONS PROJECTED TYPICAL MINIMUM


ANCHOR EYE L x W x H (mm) SURFACE AREA LOAD DRIVEN
MATERIALS
TYPE VERSION SQUARE mm RANGE* DEPTH
(L x W x H - inches)
(SQUARE inch)

121 x 41 x 34 4,127 1 - 10 kN 0.6 - 0.75 m


S04E (4.8 x 1.6 x 1.3) (6.39)
Aluminium Alloy
(220 - 2200 lbs) (2' - 2.5')

171 x 58 x 50 8,200 Aluminium Alloy; 5 - 25 kN 0.8 - 1.2 m


S06E (6.7 x 2.2 x 1.9) (12.71)
SG Cast Iron;
(1100 - 5500 lbs) (2.5' - 3.5')
Bronze

263 x 90 x 76 19,555 SG Cast Iron; 10 - 40 kN 1.1 - 1.5 m


S08E (10.3 x 3.5 x 3) (30.31) Bronze (2200 - 8800 lbs) (3.5' - 5')

BAT ANCHOR
The Bat anchor is designed to achieve higher
loads and also enhanced anchoring in soft
cohesive soils. Its ability to accept the T-Loc
lower termination allows flexibility with regard
to on-site anchor assembly and choice.

The installation equipment requires more


powerful hand-held / machine mounted
breakers and hydraulic loadlocking equipment.

The options in this case cover four anchor head configurations and two different tensioner solutions combined
with a low impact webbing strap to remove both the need for cathodic protection and damage to the pipe
coating.
DIMENSIONS PROJECTED
TYPICAL MINIMUM
ANCHOR T-LOC SURFACE AREA
L x W x H (mm) MATERIALS LOAD DRIVEN
TYPE VERSION SQUARE mm
(L x W x H - inches) RANGE* DEPTH
(SQUARE inch)

310 x 110 x 93 28,600 SG Cast Iron; 20 - 60+ kN 1.5 - 2.5 m


B04T (12.2 x 4.3 x 3.6) (44.33) Bronze (4400 - 13200 lbs) (5' - 8')

336 x 206 x 91 45,500 SG Cast Iron; 30 - 100+ kN 2-3m


B06T (13.2 x 8.1 x 3.6) (70.52) Bronze (6600 - 22000 lbs) (6' - 10')

423 x 259 x 105 71,500 SG Cast Iron; 50 - 150+ kN 3-4m


B08T (16.6 x 10.2 x 4.1) (110.82) Bronze (11000 - 33000 lbs) (10' - 13')

541 x 335 x 110 115,800 SG Cast Iron; 75 - 200+ kN 4-5m


B10T (21.3 x 13.2 x 4.3) (179.49) Bronze (16500 - 44000 lbs) (13' - 16')

*The typical load range of an anchor is dependant on the engineering properties of the soil, from soft clays to compacted granular material.
4
INSTALLATION
Anchor systems can be installed using a range of light, medium or heavy installation equipment. As the
requirement for anchor size and placement depth increases it may be necessary to utilise more powerful
equipment.
Light Installation
Drive the
Drive the anchor
anchor Remove the rods Loadlock the anchor

Medium Installation
Drive the anchor Remove the rods Loadlock the anchor

Heavy Installation
Drive the anchor Remove the rods Loadlock the anchor

5
Case Study
GAZ DE FRANCE, CALAIS

Client: Gaz de France


Consultant: Typicon
Main Contractor & Anchor Installer: Denys
PROJECT SPECIFICATION
A 14km high pressure gas pipeline needed to be laid through the northern part of Calais. High water
levels meant that buoyancy control measures were required to hold the pipeline in position.
Conventional methods were considered too expensive so an alternative solution, with minimal
environmental impact, was required.
SOLUTION
Extensive site tests were carried out, which determined three anchor sizes were needed to achieve
the required load of 75kN. At calculated distances, anchors were installed either side of the 1m Ø
pipeline, proof loaded and connected together using a specifically engineered tensioning system.
Finally, the excavated soil was backfilled concealing all evidence of the pipeline.

Anchor System: B04TB, B06TB & B08TB aluminium bronze anchors c/w 5m & 8m of
high strength polyaramid strap & stainless steel tensioning buckle.

Quantity: 3000 Anchor Design Life: 60yrs Soil Type: Wet sand

6
Case Study
OUTFALL PIPELINE - ISLE OF LEWIS

Client: Scottish Water


Consultant: Allen Gordon, Inverness
Contractor & Anchor Installer: Bardon Hebrides Ltd - Aggregate
Industries UK Ltd
PROJECT SPECIFICATION
Due to localised shallow slip failures and ground movement along this stretch of the coastline the existing
outfall pipeline had in places fractured and broken causing leakage of the pipe contents. This leakage
into the surrounding ground promoted further erosion and movement and increased the damage to the
pipe and the surrounding area.
SOLUTION
Complete replacement of this 700m long section of pipeline using a 280mm diameter HPPE product was
deemed the most cost effective long term solution. To prevent the same fate affecting this new pipeline it was
securely anchored into the bottom of a new trench at a depth below any future expected slope failure.
Working with limited access the anchors provided a quick and easy way of securing the pipeline. The solution
removed the requirement for concrete anchor blocks and minimised the need for machine traffic on site,
reducing the damage to the surrounding machair grassland. Once the trench was backfilled S2Geo System
anchors were used to secure a MacMatR geosynthetic to minimise any surface erosion and to quickly aid
vegetation regeneration.

Anchor System: Pipeline - S06EB aluminium bronze anchor c/w 2m of 6mm Ø stainless steel wire
tendon, 25mm wide polypropylene webbing strap and stainless steel ratchet fixing.
Erosion Control - S2 Geo System c/w 0.6m of 3mm Ø stainless steel wire tendon, 90mm Ø
polyethylene plate & copper swage.
Quantity: Pipeline: 90 sets, Erosion Control: 100 Design Life: 120 yrs Soil Type: Sandy/Clay

7
Case Study
REYNOLDSWOOD DRIVE DRAINAGE
IMPROVEMENTS – TAMPA, FL.
Client: Hillsborough County
Main Contractor: Pospiech Contracting – Inverness, FL.

PROJECT SPECIFICATION
The county of Hillsborough improved the outfall from the Reynoldswood subdivision pond through a
conveyance system along Ehrlich Road to the tributary of Sweetwater Creek. By constructing a new swale and
installing 1,300 linear feet of 24” diameter high-density polyethylene (HDPE) pipe, the excess water from the
pond could be transported to the creek. The pipe was backfilled with 2 feet of compacted sandy material, but
high ground water caused the pipe to become buoyant.

RETROFIT SOLUTION
To prevent a redesign of the pipeline, a quick and easy way to counteract buoyancy was through the use of a
Platipus 2 Ton Pipe Kit. The cost effective solution removed the need to re-excavate the trench and backfill with
stone or concrete. Within one week, all 1,300 linear feet of pipe was secured every ten feet by driving an anchor
on either side of the pipe and installed with a specifically designed tensioning system.

Anchor System: Pipeline - S06EA aluminum alloy anchor c/w 1.5m of 6mm Ø stainless
steel wire tendon, 35mm wide polypropylene webbing strap, delta link & strap tensioner.
Quantity: 130 Anchor Design Life: 40 yrs Soil Type: Silty Sand

8
INSTALLATION INSTRUCTIONS FOR LARGE PIPELINE SOLUTIONS

1 Using the Platipus Power Drive Rod (PDR) drive the 2 Remove the Drive Rod by hand or by using the Rod
anchors to the required / engineered depth using suitable Removers (RR1) which are useful if the rod is jammed in the
installation equipment. hole.

3 Using the Strap Setting Tool wrap the strap as depicted in 4 Thread the strap into both buckles as shown below. Place
the photograph and then loadlock and proof test the anchor the Tensioning Tool under the strap on the pipe on one side
using a suitable lifting device. and secure by engaging the lever / knurled cylinder against the
strap. Thread the loose end into the Tensioning Bar as shown.

5 Tighten by hand until the strap is 6 Place the Socket and Torque Wrench on the nut and continue to tension until
tight around the drum. tight or to the engineered torque / load setting. Remove the tool by releasing both
straps, cut off strap as required. Repeat on the other buckle if required.

9
INSTALLATION INSTRUCTIONS FOR SMALL PIPELINE SOLUTIONS

1 Using the suitable Platipus® Hand Drive Rod (HDR) or 2 You can invert the postrammer to complete the hand
Power Drive Rod (PDR) drive the Anchors into the ground to driving, then remove the rod by hand or by using the Rod
the required installation depth or so that the D-Ring is just Removers (RR1) which are useful if the Drive Rods become
above the surface. stuck.

3 Using the Platipus ® Plati-Hook (PH1) loadlock the 4 Thread the strap over the pipe and through each D-Ring
Anchor into its full working position by applying a load to and bring both ends to the top of the pipe. Place the
the wire tendon. You can also apply an additional load by passing tensioner on the top of the pipe and thread each strap
the drive rod through the handle with an extra person. through the frame body locators and then pass through the
centre of the wheel body. Cut the excess strap off ensuring all
the play is removed in the system first.

5 Leave about 5cm / 2 inches 6 Place the Tension Lever (TL1S / TL2S) on the tensioner and tighten until satisfied, ensuring
each side, then rotate the that the locking pin is fully located after the final adjustment, cut any surplus material away.
wheel by hand until the straps
tighten together.

10 11
PRELIMINARY DESIGN INFORMATION
Please find below the basic information that we require to be able to understand your
project and produce a specification and costing for you.

Name: Date:
Company:
Address:

Tel no.: Fax no.:


Web: E-Mail:

Project title:

Location of scheme:

New Remedial work to existing Timescale

Details of location:
Ground water level: or Water depth (if offshore):
Minimum depth of soil cover:

Soil details:
Shear angle: Density: Moisture content: %
Please give further details of soils present at the site including Borehole information,
SPT / Triaxial data.

Pipe uplift data:


Uplift / working load (specify each anchor or per set): kN
Anchor spacing: M
Factor of safety:
Life Expectancy:
Any other useful info:

11
110213

You might also like