Simplified Cost Accounting Part Ii: Solutions Manual
Simplified Cost Accounting Part Ii: Solutions Manual
CHAPTER 1
Exercise 1-1 (TRUE OR FALSE)
1. X 6. √ 11. X 16. X
2. √ 7. X 12. √ 17. √
3. √ 8. √ 13.√ 18. √
4. X 9. X 14. X 19. X
5. X 10.X 15. √ 20. √
Exercise 1-3 (EP under FIFO versus EP under Weighted Average Method)
MAY JUNE
D) QS: M CC M CC
IPB -0- (30%M;80% CC) 15,000 ( 4,500) ( 12,000)
RP-I 75,000 90,000
F&T 60,000 60,000 60,000 75,000 75,000 75,000
IPE (30%M; 80% CC) 15,000 4,500 12,000 (30%M; 40% CC) 30,000 9,000 12,000
EP-FIFO 64,500 72,000 EP-FIFO 79,500 75,000
======= ====== ====== ======
Dept. 1 Dept. 1
QS: M CC
IPB (100%M; ¼ CC) 72,000 (72,000) (18,000)
SIP 36,000
F&T 80,000 80,000 80,000
FOH 28,000 28,000 28,000
IPE - - -___
EP-FIFO 36,000 90,000
====== ======
Dept. 2
QS: M CC
IPB (2/3 CC) 48,000 - (32,000)
RPD 80,000
F&T 80,000 80,000 80,000
FOH - - -
IPE (1/3 CC) 48,000 - 16,000
EP-FIFO 80,000 64,000
====== ======
Dept. 3
QS: M CC
IPB (40% CC) 20,000 - (8,000)
RPD 80,000
F&T 56,000 56,000 56,000
FOH 24,000 24,000 24,000
IPE (100%M;80%CC)20,000 20,000 16,000
EP-FIFO 100,000 88,000
Exercise 1-8 (Calculation of Weighted Average Unit Cost for each cost element)
E P________
QS: M L O UC:
RPD 25,000 M = P16,250 ÷ 25,000 = P 0.65
F&T 20,000 20,000 20,000 20,000 L = P10,350 ÷ 23,000 = P 0.45
IPE (100%M; 60%L; 40%O) 5,000 5,000 3,000 2,000 O = P 16,500 ÷ 22,000 = P 0.75
EP – WA 25,000 23,000 22,000
Exercise 1-9 (Determination of units in process, beginning and their percentage of completion)
Units in IPB = EP in IPB for Materials ÷ % applied for Materials
= 32,000 ÷ 100%
= 32,000
=====
Exercise 1-11 (Calculation of Material Costs and Conversion Costs for the Current Period)
M CC
F&T 40,000 40,000
+ IPE 3,000 1,800
EP under WA 43,000 41,800
- EP in IPB (6,000) (1,200)
EP under FIFO 37,000 40,600
x Unit Cost x P 0.10 x P0.20
Total Cost P 3,700 P 8,120
====== ======
Exercise 1-12 (Calculation of EP, Unit Cost, Cost of Goods Completed and WIP end Using
Weighted Average Method)
1. P134,400 ÷ 16,800 = P 8
5. B
Materials Conversion Total
Total cost........................................................ P73,950 P135,720
÷ Equivalent units.............................................. 5,800 5,200
= Cost per equivalent unit.................................. P12.75 P26.10
× Ending inventory
Materials: 800 units × P12.75...................... P10,200
Conversion costs: *200 units × P26.10....... P5,220 P15,420
6. C
Cost from beginning inventory.................................................................................
P 3,600
Cost to finish beginning inventory: (1 − 40%) = 60% × 2,000
= 1,200 EU × P8 cost per EU..............................................................................
9,600
Total cost of units from beginning inventory............................................................
P13,200
7. B
To complete beginning work in process (15,000 units × 40% complete).......... 6,000
Units started and completed during the period (? units started − 10,000 units
in ending inventory)...................................................................................... ?
Ending work in process (10,000 units × 75% complete)................................... 7,500
Equivalent units of production.......................................................................... 37,500
To solve for Units started and completed during the period, solve algebraically:
6,000 + ? + 7,500 = 37,500
? = 24,000
Next:
Units started & completed = units started – 10,000 units from ending inventory 24,000 = units
started – 10,000
= 34,000
8. B EP under WA 22,000
- EP in IPB 5,000 x 1/5 = 1,000
EP under FIFO 21,000
======
9. A M CC
F&T 43,900 43,900
+ EP in IPE (60%CC) 2,400 WIP end = 2,400 EP in IPE x P 7.40
EP under WA 43,900 46,300 = P 17,760
- EP in IPB (1,580) =======
EP under FIFO 43,900 44,720
====== =====
F & T:
Costs last month or WIP beg. P 11,850
Costs added to IPB:
CC = 7,900 u x 80% x P 7.40 = 46,768
Started & Completed this month (43,900 – 7,900) x P 7.40 = 266,400
P325,018
=======
10. C
Page |8
Quantity Schedule: M CC
IPB (100% M; 40% CC) 200 u (200 u) (80 u)
SIP 600 u
- IPE (100% M) 100 u 100 u
F&T 700 u 700 u 700 u
EP under FIFO 600 u 620 u
===== =====
UC:
M = P1,000,000 ÷ 600 u = P 1,666.67
CC = P 1,250,000 ÷ 620 u = 2,016.13
P 3,682.80
========
11. C refer to #11 for the quantity schedule
12. C M CC
EP under FIFO 600 u 620 u
+ EP in IPB 200 u 80 u
EP under WA 800 u 700 u
13. D F&T 80,000 chairs – 15,000 chairs in IPB = 65,000 chairs started and completed in Feb.
16. A 11,000 u - 2,000 u = 9,000 u completed – 3,000 units started last month
= 6,000 u started & completed this month
18. B Dept. 2
M CC CC
F&T 42,803 42,803 EP for CC under WA 49,562
IPE (100% M; 50% CC) 13,517 6,759 EP for CC under FIFO 46,362
EP under WA 56,320 49,562 Difference 3,200
EP in IPB (100% M;40% CC) 8,000 3,200 =====
EP under FIFO 48,320 46,362
19. B Dept. 1
M
F&T 42,120
IPE (100% M; 50% CC) 16,380
EP under WA 58,500
EP in IPB (100% M;60% CC) 3,500
EP under FIFO 55,000
======
20. D
COMPREHENSIVE PROBLEMS
Page |9
Quantity Schedule: M CC
IPB (100% M; 25% CC) 20,000 u
SIP 80,000 u
F&T 84,000 u 84,000 84,000
IPE (100% M; 80% CC) 16,000 u 16,000 12,800
EP under WA 100,000 96,800
====== =====
Costs Charged to the Department: TCUC
WIP beginning or Costs last month (250,000+489,000) = P739,000
-
Costs added this month:
M …………………………………………………………….. 725,000 P 9.75
(250,000+725,000)/100,000
CC ………………………………………………………….. 600,000 11.25 (489,000+600,000)/96,800
Total Costs to be accounted for ………………………………..P2,064,000 P 21.00
======== ======
Cost Assignment:
F & T 84,000 u x P 21 ……………………………………………………. P1,764,000
IPE:
M = 16,000 x 100% x P 9.75 ……………………………….P 156,000
CC = 16,000 x 80% x P 11.25 …………………………… 144,000 300,000
P a g e | 10
Problem 1 – C (Preparation of CPR in one production department; FIFO vs. Weighted Average)
a)
Dico Phil Inc.
Cost of Production Report – Weighted Average
For the month ended June 30, 2013
Quantity Schedule: M L O
IPB (100% M; 30%L; 60% O) 42,000 u
SIP 60,000 u
F&T 72,000 u 72,000 72,000 72,000
IPE (100% M; 40%L; 80% O) 30,000 u 30,000 12,000 24,000
EP under WA 102,000 84,000 96,000
====== ===== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (32,400+14,070+35,580)= P82,050 -
Costs added this month:
M …………………………………………………………….. 90,000 P 1.20 (32,400+90,000)/102,000
L …………………………………………………………….. 32,130 0.55 (14,070+32,130)/84,000
O ……………………………………………………………. 46,020 0.85 (35,580+46,020)/96,000
Total Costs to be accounted for ………………………………..P 250,200 P 2.60
======== ======
Cost Assignment:
F & T 72,000 u x P 2.60 ……………………………………………………. P 187,200
IPE:
M = 30,000 x 100% x P 1.20 ……………………………….P 36,000
L = 30,000 x 40% x P 0.55 ………………………………. 6,600
O = 30,000 x 80% x P 0.85 ………………………………. 20,400 63,000
Total Costs as accounted for ………………………………….. P 250,200
========
b) Dico Phil Inc.
Cost of Production Report – FIFO
For the month ended June 30, 2013
Quantity Schedule: M L O
IPB (100% M; 30%L; 60% O) 42,000 u (42,000) (12,600) (25,200)
SIP 60,000 u
F&T 72,000 u 72,000 72,000 72,000
IPE (100% M; 40%L; 80% O) 30,000 u 30,000 12,000 24,000
EP under FIFO 60,000 71,400 70,800
====== ===== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (32,400+14,070+35,580)= P82,050 -
Costs added this month:
M …………………………………………………………….. 90,000 P 1.50 (90,000/60,000)
L …………………………………………………………….. 32,130 0.45 (32,130/71,400)
O ……………………………………………………………. 46,020 0.65 (46,020/70,800)
Total Costs to be accounted for ………………………………..P 250,200 P 2.60
======== ======
Cost Assignment:
F & T:
WIP beginning or Costs last month ………………………..P 82,050
Costs added to IPB:
L = 42,000 u x 70% x P .45 = 13,230
P a g e | 11
Dept 1 MAT CC
Complete 20,000 20,000 20,000
Eq-End WIP 5,000 0 2,000
- Eq-Begin (2,000) 0 (1,200)
EP-FIFO 23,000 20,000 20,800
Quantity Schedule: M CC
IPB (100% M; 70% CC) 16,000 kg (16,000) (11,200)
SIP 405,000 kg
F&T 393,000 kg. 393,000 393,000
IPE (100% M; 25% CC) 28,000 kg. 28,000 7,000
EP under FIFO 405,000 388,800
====== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (244,100+56,800) = P300,900 -
Costs added this month:
M …………………………………………………………….. 850,500 P 2.10 (850,500/405,000)
CC (344,000 + 239,200)………………………………….. 583,200 1.50 (583,200/388,800)
Total Costs to be accounted for ………………………………..P1,734,600 P 3.60
======== ======
Cost Assignment:
F & T:
WIP beginning or Costs last month ………………………… P 300,900
Costs added to IPB:
CC = 16,000 kg. x 30% x P1.50 = 7,200
Started & Completed = 377,000 kg. x P3.60 = 1,357,200 1,665,300
IPE:
M = 28,000 kg. x P2.10 = 58,800
CC = 28,000 kg. x 25% x P1.50 = 10,500 69,300
Total Costs as accounted for …………………………….. P1,734,600
========
Quantity Schedule: M CC
IPB (100% M; 70% CC) 16,000 kg
SIP 405,000 kg
F&T 393,000 kg. 393,000 393,000
IPE (100% M; 25% CC) 28,000 kg. 28,000 7,000
EP under WA 421,000 400,000
====== ======
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (244,100+56,800) = P300,900 -
Costs added this month:
M …………………………………………………………….. 850,500 P 2.60
(244,100+850,500)/421,000
CC (344,000 + 239,200)………………………………….. 583,200 1.60 (56,800+583,200)/400,000
P a g e | 13
Cutting Department
Quantity Schedule: M L O
IPB (80% M; 50%L; 30% O) 10,000 u ( 8,000) (5,000) (3,000)
SIP 30,000 u
F&T 25,000 u 25,000 25,000 25,000
IPE (100% M; 80%L; 60% O) 15,000 u 15,000 12,000 9,000
EP under FIFO 32,000 32,000 31,000
====== ===== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (80,100+17,500+7,900)= P105,500 -
Costs added this month:
M …………………………………………………………….. 288,000 P 9.00 (288,000/32,000)
L …………………………………………………………….. 64,000 2.00 (64,000/32,000)
O ……………………………………………………………. 124,000 4.00 (124,000/31,000)
Total Costs to be accounted for ………………………………..P 581,500 P15.00
======== ======
Cost Assignment:
F & T:
WIP beginning or Costs last month ………………………..P105,500
Costs added to IPB:
M = 10,000 u x 20% x P 9 = P 18,000
L = 10,000 u x 50% x P 2 = 10,000
O = 10,000 u x 70% x P 4 = 28,000
Started & Completed = 15,000 u x P15 = 225,000 P386,500
IPE:
M = 15,000 x 100% x P 9 ………………………………. P 135,000
L = 15,000 x 80% x P 2 ………………………………. 24,000
O = 15,000 x 60% x P 4 ………………………………. 36,000 195,000
Total Costs as accounted for ………………………………….. P 581,500
P a g e | 14
========
Assembly Department
Quantity Schedule: M L&O
IPB (60% M; 30% L&O) 5,000 u ( 3,000) (1,500)
RPD 25,000 u
F&T 18,000 u 18,000 18,000
IPE (80% M; 40% L&O) 12,000 u 9,600 4,800
EP under FIFO 24,600 21,300
====== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (10,000+1,000+2,000+4,000)= P17,000 -
Costs from Previous Dept. or Costs transferred-in 386,500 15.46 (386,500/25,000)
Costs added this month:
M …………………………………………………………….. 98,400 P4.00 (98,400/24,600)
L …………………………………………………………….. 42,600 2.00 (42,600/21,300)
O ……………………………………………………………. 75,402 3.54 (75,402/21,300)
Total Costs to be accounted for ……………………………….. P619,902 P25.00
======== =====
Cost Assignment:
F & T:
WIP beginning or Costs last month ……………………….. P17,000
Costs added to IPB:
M = 5,000 u x 40% x P 4 = P 8,000
L&O = 5,000 u x 70% x P 5.54 = 19,390
Started & Completed = 13,000 u x P25 = 325,000 P369,390
IPE:
CPD 12,000 u x P 15.46 P185,520
M = 12,000 u x 80% x P 4 ………………………………. 38,400
L&O = 12,000 u x 40% x P 5.54 …………………… 26,592 250,512
Total Costs as accounted for ………………………………….. P 619,902
========
IPB (100% M; 25% L&O) 24,000 u (24,000) (6,000) (100%M;30% L&O) 30,000 u (30,000) (9,000)
SIP/RPD 1,200,000 u 1,224,000 u
F&T 1,224,000 u 1,224,000 1,224,000 1,214,000 u 1,214,000 1,214,000
IPE -0- ________ ________(100%M;80% L&O) 40,000 u 40,000 32,000
EP under FIFO 1,200,000 1,218,000 1,224,000 1,237,000
======= ======= ======= ========
Costs Charged to the Department: TC UC TC UC
WIP beginning or Costs last month P 2,700 - P 5,370 -
Costs from Previous Dept. or Costs Transferred-In 120,000 P 0.10 183,600 P 0.15
Costs added this month:
M …………………………………………………………… 24,480 .02
L&O…………………………………………………………… 60,900 0.05 37,110 .03
Total Costs to be accounted for ………………………………..P 183,600 P 0.15 P 250,560 P 0.20
======== ====== ========= =====
Cost Assignment:
F & T:
WIP beginning or Costs last month ……………………….. P 2,700 5,370
Costs added to IPB:
L&O = 24,000 u x 75% x P.05 = 900 (30,000x70%x.03) 630
Started & Completed = 1,200,000 u x P0.15 = 180,000 180,900 1,184,000 x .20 = 236,800 242,800
IPE:
Costs from Previous Dept.= 40,000 x .15 = 6,000
M 40,000 x .02 = 800
L&O _________ 32,000 x .03 = 960 7,760
Total Costs as accounted for …………………………….. P 183,600 P250,560
======== =======
CHAPTER 2
Exercise 2-1 (CPR with Production Shrinkage Using Weighted Average Method):
Mio Chemical Inc.
Cost of Production Report – Weighted Average
For the month ended May 31, 2013
Cooking Department
Quantity Schedule: M CC
IPB (100% M; 60% CC) 10,000 u
SIP 45,000 u
F&T 40,000 u 40,000 40,000
IPE (100% M; 40% CC) 9,000 u 9,000 3,600
Normal Shrinkage or Normal Lost Units 6,000 u ___-___ __-____
EP under WA 49,000 43,600
====== =====
Costs Charged to the Department: TC UC
P a g e | 16
Sure-Na Company
Production Cost Report – Weighted Average
For the month ended July 31, 20_
Finishing Department
Quantity Schedule: M CC
IPB (100% M; 60% CC) 2,000 u
RPD 20,000 u
F&T 15,000 u 15,000 15,000
IPE (100% M; 20% CC) 4,000 u 4,000 800
Normal Discrete Spoilage (100% M; 80%CC) 3,000 u 3,000 2,400
EP under WA 22,000 18,200
====== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (6,050+3,410+1,638+2,184)=P 13,282 -
Costs transferred-in or CPD 54,450 P 2.75 (6,050 +
54,450)/22,000
Costs added this month:
M …………………………………………………………….. 30,690 P 1.55 (3,410+30,690)/22,000
CC ………………………14,742 + 19,656 =……..………….. 34,398 2.10
(3,822+34,398)/18,200
Total Costs to be accounted for …………………………………… P132,820 P 6.40
======== ======
Cost Assignment:
F & T 15,000 u x P 6.40 ……………………………………. P96,000
Cost of Normal Discrete Spoilage:
CPD or Costs transferred-in 3,000 x P 2.75 8,250
M = 3,000 x P 1.55 = 4,650
CC = 2,400 x P 2.10 = 5,040 P 113,940
IPE:
CPD = 4,000 x P 2.75 …………………………………….. P11,000
M = 4,000 x 100% x P 1.55 ………………………………. 6,200
CC = 4,000 x 20% x P 2.10 …………………………… 1,680 18,880
Exercise 2-3 (CPR with Normal and Abnormal Discrete Spoilage using FIFO method):
Endless Company
Cost of Production Report – FIFO
For the month ended May 31, 2013
Cost Assignment:
F & T:
WIP beginning or Costs last month ………………………..P 7,632
Costs added to IPB:
L&O = 5,600 u x 50% x P .44 = 1,232
Started & Completed = 64,400 u x P 1.44 = 92,736 P101,600
Cost of Normal Discrete Spoilage 2,100 x P 1.44 = 3,024
Adjusted Cost of F & T ………………………………………….. P 104,624
IPE:
M = 7,500 x 100% x P 1.00 ………………………………. P 7,500
L&O = 7,500 x 1/3 x P 0.44 …………………………… 1,100 8,600
Cost of Abnormal Discrete Spoilage 400 x P 1.44 =………. 576
Total Costs as accounted for ………………………………….. P 113,800
========
Exercise 2-4 (CPR with accretion; using Weighted Average method)
AUPIP stands for Additional Units Put Into Process w/c resulted from accretion.
Barley Company
Cost of Production Report – Weighted Average
For the month ended October 31, 20_
Mixing Dept.
Quantity Schedule: M CC
IPB 1,000 u
RPD 2,000 u
AUPIP 6,000 u
F&T 7,800 u 7,800 7,800
IPE (100% M;25% CC) 1,200 u 1,200 300
EP – WA 9,000 8,100
==== =====
Costs Charged to the Dept.: TC UC
WIP beg. or CLM (1,120+190+60+120) P 1,490 -
CPD or Costs transferred-in 9,680 P 1.20 (1,120 + 9,680) ÷ (1,000 u + 2,000 u +
6,000 u)
P a g e | 18
Blending Department
Quantity Schedule: M L O
IPB (100% M; 20% L; 40% O) 2,000 u (2,000) (400) (800)
RPD 5,000 u
AUPIP 5,000 u
F&T 10,500 u 10,500 10,500 10,500
IPE (100% M; 60% L; 80% O) 1,500 u 1,500 900 1,200
EP – FIFO 10,000 11,000 10,900
===== ===== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (2,460+500+150+ 600)= P 3,710 -
CPD or Costs transferred-in 12,500 P 1.25 (12,500 ÷ 5,000 urpd
+5,000 u)
Costs added this month:
M …………………………………………………………….. 2,500 P 0.25 (2,500/10,000)
L …………………………………………………………….. 3,300 0.30 (3,300/11,000)
O ……………………………………………………………. 7,630 0.70 (7,630/10,900)
Total Costs to be accounted for ……………………………….. P 29,640 P 2.50
======== ======
Cost Assignment:
F & T:
WIP beginning or Costs last month ………………………..P 3,710
Costs added to IPB:
L = 2,000 u x 80% x P0.30 = 480
O = 2,000 u x 60% x P0.70 = 840
Started & Completed = 8,500 u x P2.50 = 21,250 P26,280
IPE:
CPD = 1,500 x P 1.25 …………………………………… P 1,875
M = 1,500 x P0.25 ………………………..…………. 375
L = 900 x P0.30 …. ………………………………. 270
O = 1,200 x P0.70 ….………………………………. 840 3,360
Total Costs as accounted for ………………………………….. P 29,640
========
Exercise 2-6 (CPR involving spoiled units with salvage value; using FIFO method)
Petrophil Company
Cost of Production Report – FIFO
For the month ended September 30, 2013
P a g e | 19
Blending Department
Quantity Schedule: M L&O
IPB (60% M; 30% L&O) 2,800 u (1,680) (840)
RPD 8,400 u
F&T 7,600 u 7,600 7,600
IPE (100% M; 50% L&O) 2,500 u 2,500 1,250
Normal Discrete Spoilage (100%) 1,100 u 1,100 1,100
EP – FIFO 9,520 9,110
===== =====
Costs Charged to the Department: TC UC
WIP beginning or Costs last month (17,889+2,733+7,278+12,350)= P 40,250 -
CPD or Costs transferred-in 68,040 P 8.10 (68,040 ÷ 8,400 urpd)
Costs added this month:
M …………………………………………………………….. 11,900 P 1.25 (11,900/9,520)
L&O 30,063 + 51,016 …………………………………… 81,079 8.90 (81,079/9,110)
Total Costs to be accounted for ……………………………….. P 201,269 P18.25
======== ======
Cost Assignment:
F & T:
WIP beginning or Costs last month ………………………..P 40,250
Costs added to IPB:
M = 2,800 u x 40% x P1.25 = 1, 400
L&O = 2,800 u x 70% x P8.90 = 17,444
Started & Completed = 4,800 u x P18.25 = 87,600
Costs of Normal Discrete Spoilage 1,100 x P 18.25 = 20,075
Adjusted Cost of F&T ………………………………………….. P 166,769
IPE:
CPD = 2,500 x P 8.10 …………………………………… P 20,250
M = 2,500 x P1.25 ………………………..…………. 3,125
L&O = 1,250 x P8.90 …. ………………………………. 11,125 34,500
Total Costs as accounted for ………………………………….. P 201,269
========
P 4,645
=======
Exercise 2-8 (Calculation of Unit Production Cost and Total Production Cost with journal entries):
1. SIZE
Medium Large
DM:
Job # 401 P 200,000 ÷ 5,000 P 40.00
Job # 402 P 500,000 ÷ 10,000 P 50.00
CC:
Cutting Dept. P 450,000 ÷ 15,000 30.00 30.00
Assembling Dept. P 225,000 ÷ 15,000 15.00 15.00
Finishing Dept. P 150,000 ÷ 15,000 10.00 10.00
Unit Production Cost P 95.00 P105.00
X Quantity produced ……………………….. x 5,000 x 10,000
Total Production Cost ………………………P 475,000 + P 1,050,000 = P 1,525,000
======== ========= =========
2.
WIP – Cutting Department ……………………………..P 1,150,000
Materials 200,000 + 500,000 ……………….. P 700,000
Applied Conversion Costs ……………………… 450,000
Exercise 2-9(Using Hybrid Costing in Calculating Unit Production Cost and Total Production
Cost):
a. Extrusion Form Trim Finish
Material Costs P 192,000 P 44,000 P 15,000 P 12,000
÷ Quantity produced ÷ 16,000 u ÷ 11,000 u ÷ 5,000 u ÷ 2,000 u
Unit Cost of M P 12 P4 P3 P6
SIP ……………………….….130
F & T ……………………..….105
IPE (100% M; 60% CC) 25
1. T 6. F 11. T
2. T 7. T 12. T
3. F 8. T 13. T
P a g e | 22
4. T 9. T 14. T
5. T 10. T 15. T
1. D 6. B 11. B 16. B
2. B 7. D 12. B 17. A
3. B 8. D 13. B 18. A
4. D 9. B 14. C 19. C
a. c.
Materials Conversion Costs Transferred In Mat CC
46,500 46,500 44,500 44,500 44,500
9,000 3,000 12,000 0 2,400
(8,000) (6,000) (10,000) 0 (3,000)
47,500 43,500 46,500 44,500 43,900
b. Since the material in the second department goes in at the 50 percent point and
the ending WIP inventory is only at the 20 percent point, units complete is the
same as the equivalents of material 44,500, given that units started plus units in
beginning WIP are equal to units complete plus ending WIP 10,000 + 46,500 -
44,500 = 12,000 units in ending WIP.
a.
TI Mat CC
Complete 33,600 33,600 33,600
+ Equiv Ending 10,500 10,500 4,200
WIP
+ Normal Sp 1,680 1,680 1,680
+ Abnor Sp 420 420 420
46,200 46,200 39,900
c. 10,500 x P5 P52,500
10,500 x P1 10,500
P a g e | 23
4,200 x P3 12,600
P75,600
C. Operation costing is a hybrid system because it contains features that are present in both a
job-costing system and a process-costing system. Direct materials are assigned directly to
the batches of goods produced; in contrast, conversion costs are accumulated by
department and are then assigned to manufactured goods by using an averaging technique.
Chapter 3
Exercise 3-1 (True/False)
3-1
1 F 6 T 11 T
2 T 7 F 12 T
3 F 8 F 13 F
4 T 9 T
5 T 10 T
3-2
1 B 11 C 21 D
2 D 12 D 22 B
Approximated NRV/
3 B 13 B 23 Hypothetical NRV
4 D 14 A 24 C
P a g e | 24
5 D 15 B 25 C
6 A 16 B 26 C
7 D 17 D 27 C
8 C 18 A 28 D
9 C 19 B 29 A
10 A 20 B 30 D
Refined
3-3 Sugar Wine Total
Production Cost P600, 000 P700, 000 P1, 300, 000
Replacement (60,0
Cost 00) 60,000
540,0 760,0 1,300,0
Production Cost 00 00 00
after Cost Transer
3-5
a. (1,000/5,150) * P9,000 = P1,748
r b. (1,400/5,150) * P9,000 = P2,447
c. (750/5,150) * P9,000 = P1,311
d. (2,000/5,150) * P9,000 = P3,495
3-7
50,0
Joint Cost 00
1,7
Less: NRV of BP 00
48,3
Allocable Cost 00
P a g e | 25
48,3
2x4 lumber 00 x 200,000/300,000 32,200
3-8
a. Product Pounds
250,0
A 2000/3500 X 00 142,857
250,0
B 900/3500 X 00 64,286
250,0
C 600/3500 X 00 42,857
250,000
P250,000/ 1, 000 units=
b. P250/unit
Product
125,0
A 00
75,0
B 00
50,0
C 00
250,0
00
c.
Product Total Points
5,0
A 00 x 250000 148,810
2,4
B 00 x 250000 71,429
1,0
C 00 x 250000 29,762
8,4
00 250,000
3-9
P a g e | 26
Disposal NRV
Sales Price Costs at
Split-
Yards Split-off Split-Off Off Total
A 800 P6.50 P3.00 P3.50 2,800
B 1,100 P8.25 P4.20 P4.05 4,455
C 1,500 P8.00 P4.00 P4.00 6,000
P13,255
c. P(2,800/13,255) * P2,100 = P444
d. P(6,000/13,255) x P2,100 = P951
3-10
a. P26,000 =(4,000xP9)-P10,000
b.
Product
4,628.
A 57
13,371.
B 43
18,000.
00
Comprehensive Problems
Cocoa
Beans
Processing
Milk
Processing
Milk-Chocolate Chocolate
$26,250
Liquor Base
SPLITOFF
POINT
1b.
Physical-measure method:
Physical measure of total production
(15,000 1,500) ´ 60; 90 600 gallons 900 gallons 1,500 gallons
Weighting, 600; 900 1,500 0.40 0.60
Joint costs allocated,
0.40; 0.60 ´ $30,000 $12,000 $18,000 $30,000
P a g e | 28
Step 1:
Final sales value of total production, (6,000 ´ $4) + (10,200 ´ $5) $75,000
Deduct joint and separable costs, ($30,000 + $12,750 + $26,250) 69,000
Gross margin $ 6,000
Gross-margin percentage ($6,000 ÷ $75,000) 8%
Step 2:
Chocolate- Milk-
Powder Chocolate Total
Final sales value of total production,
6,000 ´ $4; 10,200 ´ $5 $24,000 $51,000 $75,000
Deduct gross margin, using overall
gross-margin percentage of sales (8%) 1,920 4,080 6,000
Total production costs 22,080 46,920 69,000
Step 3:
2. Chocolate- Milk-
Powder Chocolate Total
a. Revenues $24,000 $51,000 $75,000
Joint costs 10,500 19,500 30,000
Separable costs 12,750 26,250 39,000
Total cost of goods sold 23,250 45,750 69,000
Gross margin $ 750 $ 5,250 $ 6,000
Gross-margin percentage 8% 8% 8%
Chocolate Factory could increase operating income by $1,350 (to $7,350) if chocolate-powder
liquor base is sold at the splitoff point and if milk-chocolate liquor base is further processed into
milk chocolate.
COST (4,000)
NRV P2,000
NRV:
P400,000
ALLOCATION:
A (P300,000/P400,000 x P200,000 = P150,000
B (P100,000/P400,000 x P200,000 = 50,000
UNIT COST:
A (P150,000 + P50,000)/800,000 = P .25
B (P50,000 + P30,000)/200,000 = P .40
GROSS PROFIT:
A (P .4375 - P.25) x 640,000 = P120,000
B (P .65 - P.40) x 180,000 = 45,000
P165,000
SALES VALUE
A 10,000 P10 = P100,000/P200,000 x P70,000 = P35,000
B 20,000 P 5 = 100,000/P200,000 x P70,000 = P35,000
P200,000
UNIT COST
P a g e | 31
b. ENDING INVENTORY
B 5,000 x P2.15 = P10,750
C 1,000 x P2.00 = 2,000
P12,750
c. NRV
A P100,000 - P10,000 = P 90,000/P182,000 x P70,000 = P34,615
B P100,000 - P8,000 = 92,000/P182,000 x P70,000 = 35,385
P182,000 P70,000
UNIT COST
A (P34,615 + P10,000)/10,000 = P4.46
B (P35,385 + P8,000)/20,000 = P2.17
ENDING INVENTORY
B 5,000 x P2.17 = P10,850
C 1,000 x P2.00 = 2,000
P12,850
Answer:
Cost reduction Revenue
when produced when sold
Sales: Lumber P480,000 P480,000
Shavings 4,080
Total Sales: P480,000 484,080
Cost of Good Sold:
Total manufacturing costs P332,000 P332,000
Byproduct 4,080 0
Total COGS 327,920 332,000
Gross Margin P152,080 P152,080
CHAPTER 4
E 4-1 E4-2
1 T 11 F 21 T 1 C 11 D
2 T 12 F 22 T 2 C 12 B
3 T 13 F 23 T 3 C 13 B
4 F 14 F 24 T 4 D 14 D
5 T 15 T 25 F 5 A 15 B
6 T 16 F 26 T 6 A 16 B
7 F 17 F 27 T 7 A 17 A
8 T 18 T 28 F 8 A 18 D
9 T 19 T 29 T 9 B 19 D
10 T 20 F 30 T 10 D
E4-3
1. C
2. D
3. A
4. D
5. D
6. B
7. B
8. B
9. D
10. C
= P64,250.00 - P54,462.50
= P9,687.50U
11. A
= P(64,250 - P58,437.50)
= P5,812.50 U
12. B
= P(58,437.50 - 54,562.50)
= P3,875.00 U
13. C
= P(64,250 - 56,250)
= P8,000.00 U
14. B
= P(56,250.00 - 58,437.50)
= P2,187.50 F
15. C
Volume Variance = Budget Based on Standard Quantity - Overhead Applied
= P(58,437.50 - 54,562.00)
= P3,875.00 U
16. C
= P(26,250.00 - 17,500.00)
= P8,750.00 U
17. C
VOH Efficiency Variance = Budgeted VOH based on Actual - Budgeted VOH/Standard Qty
= P(17,500.00 - 19,687.50)
= P2,187.50 F
18. D
= P(38,000 - 38,750)
= P750 F
19. D
= P(58,437.50 - 54,562.00)
= P3,875.00 U
Summary:
Actual hours 5,000 hours
Standard hours allowed 50,000 hours
Denominator hours 53,000 hours
Spending variance P 5,500 U
Efficiency variance P15,000 U
Budget variance P 7,200 U
Volume variance P 4,800 U
d. Total standard labor cost of actual hours = (450 x 3 x P8) + P400 = P11,200
Actual hours = P11,200/P8 = 1,400
E4-8
a. Direct materials' unfavorable price variance may have been caused by: (1) paying a higher price
than the standard for the period, (2) changing to a new vendor, or (3) buying higher-quality
materials.
Direct manufacturing labor's favorable price variance may have been caused by: (1) changing
the work force by hiring lower-paid employees, (2) changing the mix of skilled and unskilled
workers, or (3) not giving pay raises as high as anticipated when the standards were set for the
year.
b. Direct materials' favorable efficiency variance may have been caused by: (1)
employees/machinery working more efficiency and having less scrap and waste materials, (2)
buying better-quality materials, or (3) changing the production process.
Direct manufacturing labor's unfavorable efficiency variance may have been caused by: (1) poor
working conditions, (2) changes in the production process (learning something new initially
takes longer), (3) different types of direct materials to work with, or (4) poor attitudes on behalf
of the workers.
PROBLEMS
(a.)
8,200*P16.40= 8,200*P15.60= (1,640*5.2)*P15.60=
P134,480 P127,920 P133,036.80
(b.)
8,500*P15.60= 8,200*P15.60=
P139,400 P132,600 P127,920
Halibut: (P.70 per oz. - P.60 per oz.) x 5,500 oz.......................................................................... P 550 unfav.
Asparagus: (P.20 per oz. - P.25 per oz.) x 3,800 oz..................................................................... (190) fav.
Rice: (P.12 per oz. - P.10 per oz.) x 4,900 oz............................................................................... 98 unfav.
Yogurt: (P.22 per oz. - P.20 per oz.) x 3,150 oz........................................................................... 63 unfav.
a. Labor rate variance = (AH x AR) - (AH x SR) = P59,470 - (3,800 x P15.50) = P570 U
*SH = Standard hours per unit x Actual output = 3.0 x 520 = 1,560
Variable OH Variances:
3,700*P3.00= (7,600*0.50hrs)*P3.00=
P10,730 P11,100 P11,400
P370 F P300 F
VOH VOH
Spending Variance Efficiency Variance
Fixed OH Variances:
4,000*P8= (7,600*0.50hrs)*P8.00=
P29,950 P32,000 P30,400
P2,050 F P1,600 U
FOH FOH
Spending Variance Volume Variance
(b-d)
P10,730+29,950= P11,100+32,000= P11,400+32,000= P11,400+30,400=
P40,680 P43,100 P43,400 P41,800
P1,120 F
Total Overhead Variance ONE WAY
Variable expenses:
overhead rate:
P30,000
10,000 DLH
P30,000 + P12,000
1
Beeswax............................................................ 4,100 lbs. @ P1 per lb............................................. P 4,100
2
Weighted average standard materials costs:
$400
Standard materials cost = = $.381 per lb .
1,050 lbs .
3
Standard materials costs $400
= = $.40 per lb . cost per unit of output
Standard output 1,000 lbs .
P 4-13 (Journal Entry Preparation)
SOLUTION
Materials....................................................................................................................... 90,000
Materials................................................................................................................ 77,000
Payroll.................................................................................................................... 144,000
or
SOLUTION
Materials................................................................................................................ 23,600
1
P250,000 - P30 (4,000) = P130,000 fixed overhead
2
Budget allowance based on actual hours..................................................... P 256,000
3
Budget allowance based on standard hours allowed................................... P 250,000
SOLUTION
Page | 49
Work in Process (P40 F.O. rate x 4,600 SH).................................................................... 184,000
SOLUTION
(1)
P150,000
P1,000,000
P50,000
P1,000,000
P800,000
P1,000,000
P150,000
P1,000,000
Page | 50
P50,000
P1,000,000
P800,000
P1,000,000
P250,000
P2,500,000
P2,000,000
P2,500,000
1
Labor rate variance - Labor efficiency variance = Net labor variance
P150,000
P1,500,000
P150,000
Page | 51
P1,500,000
P1,200,000
P1,500,000
(2)
Materials.................................................................................................................................... P 800,000
Labor.......................................................................................................................................... 2,000,000
Overhead................................................................................................................................... 1,200,000
P 4,000,000
Overhead................................................................................................................................... 25,200
Labor.......................................................................................................................................... (3,200)
1. The materials mix variance equals the actual total quantity used times the difference between the budgeted
weighted-average standard unit cost for the budgeted mix and the budgeted weighted average standard unit
cost for the actual mix. This variance is favorable if the standard weighted average cost for the actual mix is less
than the standard weighted-average cost for the budgeted mix. The standard mix weighted-average standard
unit cost id P225 per liter (P135 standard total cost / 600 liters).
The standard cost of the actual quantity used was P18,606 (see below). Thus the actual mix weighted-average
standard unit cost was P0.220398 (P18,606/84,420 liters used), and the mix variance was P388.50 favorable.
[(0.220398 – P.225) x 84,420 liters].
Page | 52
2. The materials yield variance equals the difference between the actual input and the standard input allowed for
the actual output, times the budgeted weighted average standard cost per input unit at the standard mix. The
standard input for the actual output was 84,000 liters (140 batches x 600 liters per batch). The standard mix
budgeted weighted – average standard unit cost is P225 per liter (135 total cost / 600 liters). Thus, the yield
variance is P94.50 unfavorable [(84,420 liters used – 84,000 liters allowed) x P.225].
1. The fixed overhead spending (budget) variance is the difference between actual and budgeted fixed factory
overhead. Actual fixed overhead was P540,000. Budgeted fixed overhead was P5 per hour based on a capacity of
100,000 direct labor hour per month, or P500,000. Because these costs are fixed, the budgeted fixed overhead is
the same at any level of production. Hence, the variance is P40,000 unfavorable (P540,000 – P500,000).
2. The variable overhead spending variance is the difference between the actual variable overhead and the
variable overhead based on the standard rate and the activity level. Thus, the variable overhead spending
variance were P12,000 favorable [P740,000 actual cost – (P8 standard rate x 94,000 actual hours)]. Because
actual is less than standard, the variance was favorable.
3. The variable overhead efficiency variance equals the standard price (P8 an hour) times the difference between
the actual hours and the standard hours allowed for the actual output. Thus the variance is P48,000 [8 x (94,000
actual hours – (4 standard hours per unit x 22,000 units produced)]. The variance is unfavourable because actual
hours exceeded standard hours.
4. The direct labor price variance equals actual labor hours times the difference between standard and actual labor
rates. The actual labor cost was P940,000 for 94,000 or P10 per hour. The standard rate was P9 per hour. Thus
the variance is P94,000 (94,000 hours x (10-9)). Since actual is greater than the standard, unfavourable.
5. The direct labor rate efficiency variance equals the standard rate times the difference between actual and
standard hours. Hence, the variance is P54,000[9 x (94,000 hours – (4 std hrs per unit x 22,000 units)). The
variance is unfavourable because the actual exceeded the standard.
a. & b.
Raw Materials:
Price variance = AQ(AP − SP) (based on quantity purchased)
= 21,000 (P17 − P16) = P21,000 U
Page | 53
* SQ = 22,400 units at 1.5 grams per unit = 33,600
c. & d.
Direct labor:
Rate variance = AH(AR − SR) = 16,750(P8 − P8) = 0
e. & f.
Variable overhead:
Spending variance = AH(AR − SR) = 16,750(*P2.90 − P3) = P1,675 F
Chapter 5
Exercise 5-1 (True or False)
1. F 6. T
2. F 7. F
3. T 8. T
4. F 9. F
5. T 10. T
2. Backflushed: All raw materials purchased were requisitioned for production P 900,000
There are no RIP beginning and ending
RIP, beginning P0
RM purchased 540,000
Applied Conversion Cost 990,000
RIP, ending ___-___
Backflushed from RIP to FG P1530,000
Applied conversion costs transaction was entered into RIP account as mentioned in the problem
Page | 54
Amount backflushed P1,050,000
Divide: Units completed 18,000
Unit Cost P58.33
Multiply: Ending inventory
(18,000 – 17,800) 200
Finished Goods ending balance P11,666
3. Correction:
Standard price of DM should be P30 and conversion cost at P10.
Trigger points are the purchase of materials and when the products are sold.
Delivery cycle time per unit = (23,000 + 80,000) / 2,000 units = 51.5
Page | 55
Move time 12
Inspection time 17
Wait time 10
Queue time 14
Non-value added time 53
Process time 25
Move time 12
Inspection time 17
Queue time 14
Throughput time 68
MCE = 25 / 68 = 37%
Given the capacity of the company, it could not provide the additional order of 30 chairs to be delivered in 3 days
5. Current Productivity ratio = 2500 square yards = 357.14 square yards per hour
7 hours
New productivity ratio = 2700 square yards = 385.71 square yards per hour
7 hours
Percentage change = 385.71 – 357.14 = 8%
357.14
Chapter 6
Exercise 6-1 (Quality)
1. NVA 6. NVA 11. NVA 16. NVA
2. NVA 7. VA 12. VA 17. VA
3. NVA 8. VA 13. NVA 18. VA
4. VA 9. NVA 14. VA 19. VA
5. VA 10. VA 15. NVA 20. NVA
Page | 56
4. C 19. D
5. C 20. C
6. B
7. A
8. B
9. D
10. C
11. D
12. D
13. A
14. A
15. C
Exercise 6-4 (Cost of Quality)
1. IF 6. EF
2. IF 7. PC
3. IF 8. IF
4. AC 9. IF
5. EF 10. AC
1. B (4,616+3,144) 6. D
2. C 7. B
3. D 8. B
4. A 9. A
5. B 10.B
Page | 57
(b.) Target Costing = P10,864,000
Estimated Production:
Variable Cost (0.85+0.20+0.25) x 6,450,000= P8,385,000
Total Fixed Cost (100,000x8products) = 800,000 P9,185,000
Yes, Fast foods should begin the production of the new product, estimated production is lower than
the target cost.
Page | 58