Module 8 - Setting Out HZ Alignment - 10
Module 8 - Setting Out HZ Alignment - 10
In order to relieve the surveyor from the onus of providing daily assistance to the
site, it is essential that the basic survey skills are available on site.
traight lines are set out by marking points every 50m to 100m with ranging rods.
Between these ranging rods, intermediate points are set out at every 10m.
Normally, sections of not more than 50 to 100m are set out at the time. In
mountainous terrain, sections of less than 50m may be chosen.
In hilly or rolling terrain, when the line of sight between two fixed points is
obscured, the following method can be used to set out the straight.
Conditions :
From point A, ranging rods set at
points B and C must be visible.
From point D, ranging rods set at
points C and B must be visible.
Proceed as follows:
! From A, set B and C in a straight line.
! Sight from D and move C to be in line D-B
! Sight form A and move B to be in line A-C
Repeat this procedure until A-B-C and D-C-B show a straight line without further
movements.
The centre line is normally described by means of a series of straight lines meeting
at points of intersection. Eventually, these straights will be joined by curves that
will be set out during the detailed setting out.
The distance between the intersection points can easily be measured and used as a
first estimate of the length of the road to be constructed.
There are various methods to set out curves. With rural roads designed for low
traffic volumes, it is usually sufficient to follow existing tracks and to improve
existing curves where necessary. Two simple methods to set out circular and
parabolic curves using only a tape measure, ranging rods, pegs and strings are
described on the following pages.
The intersection method is a simple and effective method to set out a parabolic
curve. It requires simple equipment and can be easily understood by the foremen.
Step 1: First place a peg at the point where the two straight lines meet (intersection point
PI). Then locate the tangent points, TP. The first tangent point is where your curve
begins, and the second is where it ends. Divide the tangent lines in equal lengths,
by setting out a number of ranging rods along the tangent lines, at say 5m intervals.
With longer tangents, you will achieve a longer curve with a larger radius.
Deciding the length of the tangents is best done by experience. You will gain
experience in how to select the best tangent length. First look at the intersection
angle between the two tangents:
A large intersection angle (i) will produce an easy curve with a large radius. The
tangent length can then be short (however, not shorter than 20m).
A smaller intersection angle will give a sharper curve with a short radius. In such
situations, the tangent lines should be made longer (30, 40, 50 or 60m) to increase
the radius of the curve.
Sometimes, you will want to adjust the tangent length to control where the centre
line of the curve goes (see below: Adjusting the Position of the Curve).
Step 2: Give each ranging rod a letter as shown in the figure below. Sight along line a - a
with an assistant holding a ranging rod in your sight line. A second assistant stands
at point b and sights along the line b - b. Move your assistant along line a - a until
he also stands on line b - b. Mark this spot with a ranging rod and a peg. This is
your first point defining the curve.
Step 3: Now repeat this exercise by sighting along b - b while an assistant is sighting along
c - c to find your next curve point.
Step 4: Complete the exercise for line c - c, d - d, etc. Finally, use these curve points to
set out intermediate points along the curve at 5 m intervals. Inspect the curve and
make sure that all the points provide a smooth curve.
Even numbers of ranging rods gives uneven numbers of curve points, then the
middle curve point will be opposite the intersection point, PI. Where the middle
two lines intersect is the middle point of the curve (as below with 3-3 & 4-4 and 2-2
& 3-3).
If we increase the length of the tangent lines, the curve moves further away from PI.
We can use this when we need to set out the centre line of the curve to avoid
obstacles such as trees, buildings, boulders, etc.
There will often be a need for stakes to be replaced due to carelessness, children
playing near the site, theft for fire wood, etc. When the road alignment follows a
straight line there is no problem. The missing stakes are replaced by sighting and
measuring 20 meters between stakes using those remaining as a reference. If stakes
around a curve are missing, this poses a slightly more difficult problem.
However, it is not necessary to wait for a survey as the supervisor should be able to
replace curve stakes by using the following method.
Assuming the worst possible case, that is all stakes along the curve are missing,
including the tangent-point reference stakes.
It is necessary to know the length of the tangents BD and DC (ref. figure below).
These are usually the same, but can be different if necessitated by site conditions.
In this case, the curve is not a simple one but a compound of two curves. The
tangent length can be calculated from Radius R x Tangent A/2 where A is the
intersection angle in degrees.
The intersection D can be located simply by sighting back along both tangent lines
until the intersection is found. With the tangent length calculated from the above
formula, the distance can be measured back in both directions (along the centre line)
and the tangent points B and C located and staked. The curve can then be reset by
tape measure or as shown in the above figure.
Once the centre line survey has been established, it is desirable to establish
permanent references off-set from the centre line as the centre line pegs may be lost
during construction. These off-set pegs become the permanent markers for setting
out works, and provides an efficient reference for checking completed works. In
other words, these off-set pegs are used for planning, organising and measuring the
work.
After the road works have been completed, those pegs will be retained to serve as
useful references for the maintenance supervisors.
Of crucial importance is that off-set pegs are located at right angles to the design
centre line. The following method illustrates a simple way of ensuring this using a
piece of string about 5 m long.
In flat and rolling terrain, the off-set distance is usually half the width of formation
plus the width of the side drains. This would apply to the off-set distance on both
sides of the road alignment as shown in the figure below.
Where the road passes through sloping ground, and side cuts are required, it is
necessary to locate a toe and a back-slope peg in order to fully define the road
alignment. Normally, the toe peg defines the outside shoulder edge on the low side
and the back-slope peg is that which defines the top of the back slope - the point of
incidence between the natural surface and the beginning of the back slope cut.
The location of the toe peg is the distance from the centre line to the outside
shoulder edge as defined by the cross-section.
The location of the back-slope peg involves understanding the relationship between
cross slope, back slope and formation width of the road. This relationship involves
the following calculations:
Y
tan Q o ' (1)
X % Fw
Thus (1) and (2) can be combined to determine one unknown, i.e,
X
tan Q o ' 1.5
X % Fw
Here, the only unknown is X, the additional horizontal distance from the centre line
peg to the back-slope peg. In other words, the off-set distance, from the centre line
peg to the back-slope peg is Fw/2 + X. The distance may be obtained using the
straight edge or using two profile boards and a line level as described in Section 8.2.
Once the off-set pegs have been located in the horizontal plane forming a
"plan" of the road alignment on the surface of the ground, the shape of the
road in the vertical plane must now be defined by placing levels on the
off-set pegs. These levels define the distance down (-) or up (+) from
the top of the off-set pegs to finished formation level of the road.
During the initial survey of the road, centre line pegs are located and levelled. Thus
on every centre line peg is a level up (+) or down (-) from the top of the peg to the
finished formation level of the road. To transfer this centre line peg, level to the
off-set pegs, use the straight edge or a line level to determine the cross-slope of the
hillside and calculate "X".
From the figure below it can be seen that one end of the beam is placed on top of the
centre line peg. The spirit level is used to ensure horizontality of the beam and
obtain a measurement to the ground. This process may be continued until the toe
off-set is reached. Thus the summation of these measurements will provide the
exact excavation and fill levels of the centre line and the toe of the fill.
Equally, the same exercise is carried out to establish the difference between the top
of the back-slope and centre line pegs. It is essential that as level differences are
measured, a calculation is made using the centre line level data to complete the
levels up/down to the finished road formation level from the top of the toe and back-
slope pegs. A simple example follows to illustrate these points.
Example:
At chainage 0 + 950, the level on the centre line peg reads (- 0.75) which means
that the finished formation level of the road is 75 cm (0.75 meters) below the top
of the peg.
Using the straight edge, a spirit level and a tape measure, the difference in levels
between the top of the back-slope peg and the top of the centre line peg is
found to be 1.35 meters. Using the same method, the difference in level
between the top of the centre line peg and the top of the toe peg is found to
be 1.05 metres.
Thus the off-set pegs now have a full set of information defining: