Diagnosis of Paper-Oil Power Transformer Insulation: Utility Consulting ABB Vadodara, India
Diagnosis of Paper-Oil Power Transformer Insulation: Utility Consulting ABB Vadodara, India
Diagnosis of Paper-Oil Power Transformer Insulation: Utility Consulting ABB Vadodara, India
V. R. Kulkarni
Utility Consulting ABB Vadodara, India
1.0 Introduction
Power transformer is the most critical
Td
and expensive component in the Discharging time
transmission and distribution of
electricity. The failure of transformer Figure 1
without any warning causes interruptions
in service, valuable customer minutes 3.0 Case studies for diagnosis of two
lost and loss of revenue. If incipient identical power transformers.
failure is recognized before it leads to an The diagnostic tests were carried out on
internal fault, then one can plan for the two identical power transformers of
transformer repair or replacement. This rating 75MVA, 132/34.5/6.9kV. The
will minimize a forced outage and the tests were carried out after 7 years of
scope of the repair. service. The diagnostic tests include
Capacitance and Tandelta, Recovery
2.0 The basic principle of Recovery voltage measurement, Furan content and
Voltage Measurement (RVM) Oil analysis.
The recovery voltage measurement is
based on the determination of 3.1 Measurement of Capacitance and
polarization spectrum by applying DC Tandelta
charging and discharging the insulation Capacitance and Tandelta measurement
and is shown in Figure 1. First, a sample was carried out on both the transformers
is charged for a time Tc. Then the i.e T1 and T2. The measurements were
sample is isolated from HV source and carried out at 10kV & 5kV to test the
short circuited for a time Td. At the end various insulation configuration as
Td the short circuit is removed and the shown in Table1.
recovery voltage appearing at the
electrodes is measured. The main
parameters derived from polarization
Table 1.
Test configuration T1 T2
Insulation between C=11.22nF C=12.15nF
HV & LV@ 10kV Tand=0.46 Tand=0.18
(UST mode)
Insulation between C=8.6nF C=8.169nF
HV & MV@ 10kV Tand=0.53 Tand=0.19
(UST mode)
Insulation between C=22.44nF C=22.8nF
HV & Earth @ Tand=0.5 Tand=0.29
10kV Fig. 2 Time constant =16.49sec
(GST ground mode)
Insulation between C=20.63nF C=21.96nF
MV & Earth @ 5kV Tand=0.56 Tand=0.32
(GST ground mode)
Insulation between C=13.35nF C=13.98nF
LV & Earth @ 5kV Tand=0.47 Tand=0.38
(GST ground mode)
Note:- UST- Ungrounded Specimen Test
GST:- Grounded Specimen Test
HV=132kV,MV=34.5kV,LV=6.9kV winding
4.0 Conclusion:
The results indicate that insulation of
transformer T1 has absorbed moisture
and needs reconditioning which includes
the drying of oil paper insulation.
Transformer T2 does not require any
reconditioning.