ESTIMATE OF PROPOSED HOUSE FOR MR. S. N. H. M. KASUN CHAMIKA. AT, NO.
1673/1/2, KOTTAWA, PANNIPITIYA.
SUMMARY
D REINFORCEMENT 415,454.23
J PLUMBING 344,325.00
A EARTH WORKS
01. Earth excavation
a Earth excavation in wall foundation m3 12.52 1,268.00 15,874.36
b Earth excavation in Column foundation m3 13.75 1,268.00 17,439.82
c Earth excavation in Stair case foundation m3 0.76 1,268.00 968.88
B CONCRETE WORK
Ground floor
2" Thick 1:3:6 ( 1")lean concrete under specified
01.
for curing compacting.
a Column Footings m2 15.07 750.00 11,302.33
b Stair case base m 2
0.84 750.00 627.91
bars & 6 mm mild steel stirrups at 6" c/c in Ground floor Lm 17.73 1,450.00 25,715.40
C FORM WORK.
Rate included, fixing and removing both;
01. Columns.
Column Footings m2 15.07 2,163.00 32,595.91
Column up to DPC Level. m2 22.60 1,800.00 40,688.37
Columns upto slab level m2 41.30 1,800.00 74,344.19
Page 4 of 9
ESTIMATE OF PROPOSED HOUSE FOR Mr. S. N. H. M. KASUN CHAMIKA AT, NO. 1673/1/2, KOTTAWA,
PANNIPITIYA
D REINFORCEMENT
All reinforcement quantities were calculated according to
the structural detail drawings; but some quantities were
calculated on assumed details, where specific details were
not given.
01. Columns
a 12mm (1/2" dia) kg 545.80 197.00 107,521.64
b 6mm (1/4" dia) kg 31.68 197.00 6,240.10
02. Beam
a 12mm (1/2" dia) kg 263.97 197.00 52,002.93
b 6mm (1/4" dia) kg 32.35 197.00 6,373.43
03. Slab
a 10mm (1/2" dia) kg 1066.85 197.00 210,168.97
E MASONRY WORK
Unless otherwise specified, cement motar in masonry is
1:5 mixture;
01. Rubble work in wall foundations. m3 31.46 9,800.00 308,291.14
02. Brick work in Superstructure
a 225 mm m2 140.08 3,000.00 420,232.88
b 112.5 mm m2 29.97 1,750.00 52,453.47
F WATER PROOFING
Note:
a) For the description of materials and workmanship refer
Page 5 of 9
ESTIMATE OF PROPOSED HOUSE FOR Mr. S. N. H. M. KASUN CHAMIKA AT, NO. 1673/1/2, KOTTAWA,
PANNIPITIYA
two coats of hot tar and blinded with sand. m2 20.68 1,200.00 24,817.12
01. DOORS
In ground floor
a D m2 2.23 18,500.00 41,302.33
b D1 m2 2.23 5,650.00 12,613.95
c D2 m 2
1.95 5,650.00 11,037.21
d D3 m2 1.63 5,650.00 9,197.67
e DW m 2
2.23 10,500.00 23,441.86
f DW1 m2 3.72 10,500.00 39,069.77
g DW2 m2 5.58 10,500.00 58,604.65
02. WINDOWS.
In ground floor
a W m2 4.47 10,250.00 45,767.44
b W1 m2 1.86 10,250.00 19,069.77
c FL m 2
0.87 10,250.00 8,917.50
Page 6 of 9
ESTIMATE OF PROPOSED HOUSE FOR Mr. S. N. H. M. KASUN CHAMIKA AT, NO. 1673/1/2, KOTTAWA,
PANNIPITIYA
d Supply & fix bidet sprayer to working order. Nr.s 1.00 2,860.00 2,860.00
h Supply & fixing of PVC Floor Gully Nr.s 1.00 860.00 860.00
J PLUMBING
04. Supplying and fixing 1000 ltr water tank Nos. 1.00 14,500.00 14,500.00
05. Supplying and fixing water pump Nos. 1.00 17,200.00 17,200.00
07. Valves
a supply and fixing 1/2" dia stop valves Nos. 2.00 1,575.00 3,150.00
b supply and fixing 1" dia stop valves Nos. 2.00 3,252.00 6,504.00
c supply and fixing 1 1/2 " dia stop valves Nos. 3.00 6,240.00 18,720.00
Page 7 of 9
ESTIMATE OF PROPOSED HOUSE FOR Mr. S. N. H. M. KASUN CHAMIKA AT, NO. 1673/1/2, KOTTAWA,
PANNIPITIYA
Page 8 of 9
ESTIMATE OF PROPOSED HOUSE FOR Mr. S. N. H. M. KASUN CHAMIKA AT, NO. 1673/1/2, KOTTAWA,
PANNIPITIYA
L PAINTING.
(Rate included applying 1 filler coat and 2 coats of paint
on walls)
CIC paint -Colour to be decide by architect)