CIE 055 - CONSTRUCTION METHODS AND PROJECT MANAGEMENT

Project Name:Lifting Station


Name: QUIZ 2
Section:4BSCE-01
Schedule:
7:30AM - 10:30AM / Monday & Friday
GENERAL CONSTRUCTION WORKS:
Detailed Breakdown
Fixed Lump Sum SELLING PRICE
TOTAL
Item Description Unit Qty Rate Amount
A. PRELIMINARIES

a Preliminaries lot 1.00 183,709.31 183,709.31

Sub Total : DIVISION 02 - GENERAL REQUIREMENTS 183,709.31

B. SITE DEVELOPMENT

a. Site Survey and Layout m² 29.20 14.23 415.57


b. Clearing and Grubbing m² 29.20 33.29 972.05
c. Excavation m³ 67.85 733.20 49,747.89
e. Hauling and disposal m³ 67.85 191.88 13,019.05
f. Soil Trimming m² 78.72 157.44 12,393.67
g. 200mm thk Compacted G1 Gravel bedding m³ 2.71 1,131.60 3,066.64

Sub Total : SITE DEVELOPMENT 79,614.85

C. STRUCTURAL WORKS

a. Concrete (5000 psi) - assumed m³ 36.10 4,120.40 148,746.44


b. Formworks m² 221.08 997.77 220,585.99
c Rebars kg 3,371.69 10.13 34,150.50

Supply of Reinforcing Steel Bars


d Reinforcing Steel Bars - Grade 60/40 kg 3,540.28 64.15 227,101.17

Supply of Cement
e 5,000 PSI bags 338.00 225.08 76,077.04

f. Allowance on Actual Site Condition lot 1.00 21,199.70 21,199.70

Sub Total : STRUCTURAL 727,860.84

D. METAL WORKS

Supply and Installation of Roofing


a. Manhole Checkered Plates (600 x 1200) ea 1.00 26,172.95 26,172.95
b. Manhole Checkered Plates (600 x 600) ea 1.00 13,086.48 13,086.48
e. Accessories lot 1.00 291,233.10 291,233.10

Sub Total : METAL WORKS 330,492.52

E. MOISTURE & THERMAL CONTROLS

Supply and Application of Waterproofing


a. Polyethylene Sheeting (Vapor Barrier) m² 13.57 127.39 1,728.62
b. Waterproofing - Capillary Type m² 100.80 454.39 45,802.66
c. Bentonite Water Stop m² 2.81 871.63 2,449.27

E. FINISHES
Supply and Application of
a. Rubbed Concrete in slab soffit m² 29.60 147.13 4,355.17
b. Straight to Finish in all concrete surface m² 127.94 233.69 29,897.92

Allowance on Actual Site Condition lot 1.00 2,526.88 2,526.88

Sub Total : MOISTURE AND THERMAL CONTROLS 84,233.64

GRAND TOTAL 1,408,438.05

Qualifications
1.0 Assumed 5000 psi on concreting for all members.
2.0 Assume 1 manhole for every chamber.
3.0 Assumed waterproofing.