Design of Steel Tied Arch Bridges
Design of Steel Tied Arch Bridges
Design of Steel Tied Arch Bridges
RRll71
7305
''l
I
I
I
I
I
I AN ALThRNATI VI:;
I
I
I Far American Institute Of Steel CalstructlOO
I
I
I
July '985
I
I
I
I , Bri<i3e SOftware Del/elopnent International Ltd.
Coo[ersl:urg, Pennsy ll/ania
I
I I':0
'~"
, -i-
'T)
I TABLE OF CINl'ENl'S
I Page
1 . 0 SlMlARY 1
I 1 .1 Introduction
1.2 Problem statement
I 1.3
1. 4
Objective
AWroach
1.5 Alternate ~thod
I 2 . 0 INTOOOOCl'IGl 5
I 2 . 1 Present Practice
2.2 Problems With Present Practice
2.3 Proposed Alternate ~thod
I 2 . 3 . 1 General
2.3.2 Erection of the Arch Ribs
2.3 . 3 Erection of Deck Units
I 2.3 .4 Jldvantages of Alternate ~thod
4.1 General
I 4.2 Floor Beam
4 . 3 Placement of Deck Units
4 . 3.1 Arch Rib
I 4 . 3 . 2 Hangers and Dead Wad Tie Cable
4. 3 . 3 Precast Deck Units
4 . 3 . 4 Bearings
I 4. 3.5 Procedure
4 . 4 Integrated Model
I 4 . 4. 1 General
4. 4. 2 Tie Beam
4.4.3 Deck
I 4.4.4 Floor Beams
4 . 4 . 5 Procedure
I
<:>
I~ -.J -ii-
I Page
5 . 0 RESULTS 38
I 5. 1 General
5 . 2 Floor Beam
I 5 . 3 Arch Ribs
5 . 3 . 1 General
5.3 . 2 Deck Unit Staging
I 5 . 3 . 3 Superimposed Dead Load
5 . 3 . 4 Temperature
5 . 3. 5 Live Load
I 5 . 4 HarY:Jers
5 . 4. 1 General
I 5 . 4 . 2 Deck Unit staging
5. 4. 3 Superimposed Dead Load
5 . 4. 4 Temperature
I 5 . 4. 5 Live Load
I 5. 6 Tie Beams
5 . 6 . 1 General
5 . 6 . 2 Deck Unit Staging
I 5 . 6 . 3 Superimposed Dead Load
5 . 6 . 4 Temperature
5 . 6 . 5 Live Load
I 5 . 7 Deck
5. 7. 1 General
I 5. 7 . 2
5. 7. 3
Deck Unit Staging
Superimposed Dead Load
5. 7. 4 Temperature
I 5. 7. 5 Live Load
I 5 . 8 Post Tensioning
5 . 8 . 1 General
5 . 8 . 2 Deck
5.8 . 3 Tie Beam
I 6 . 0 CIN:llJSlOOS 86
I 7 . 0~ 88
8 . 0 BIBLI(X;RAPHY 89
I
I ,~
'p
'n -iii-
I LIST OF FIQJRES
I FIGURE TITLE
I
- iv-
I FIGURE TITLE
I '~'.(1
.", -v-
~
I LIST CF TABUS
I TABLE TITLE
I TITLE
I
I
I
I
I
I
I
I
I
I
I
I •
I
I']).J)
'" 1
.....
1 1. 0 Stmnary
I 1 . 1 Introduction
I 200 arrl 1000 feet for this type of brici:Je . They are used where
single spans are required . If cootinuity fran adjacent spans
is available , tied arches are at a disadvantage canpared to cooti-
I
I
I
2
I
1 .2 Problan Statement I
Tied arch bridJes have becane less p::lpular because the tie
beams are cx:nsidered n::lI'l-redurrlant. AASID'O BridJe Specifications
define a n::lI'l-redundant member as a tension member which, if it
I
fails, is likely to lead to collapse of the structure. Although
few, if any, tied arch bridJes have actually failed, the tie
girders have suffered cracks in one or two instances (Ref,2).
I
It is clear that failure of such a member could be catastrophic.
Further, the cost of tied arch bridJes is high when canpared
to more modem bridges such as the cable stayed bridge and the
I
segmental cx:ncrete box girder bridJe.
1 . 4 Approach
I An alternate scheme for the oonstruction of a tied arch bridge
has been developed . A design study was then perforrred which
I was based <Xl an existiN3 design and the resulting design cxxnpared
to the original. The analysis was perforrred using a series of
canputer programs called the BR.IIX;E-SYSTElo1sm developed by Bridge
I Software Developroent International , Ltd . '!he canputer generated
rrodel of the tied arch had to be nodified by harxl .
After the arch ribs are erected , permanent cables are placed
I between the ems of arch ribs to carry dead load thrust. '!he
cables must be supported by the haN3ers to prevent sagging am
reductioo of the effective m:xfulus .
I The deck and tie beam are precast ooncrete units . Each unit
of the deck exterxls full width of the bridge . 'lhe deck is cast
I
I
4
I
I
When the units are in place and cast-in-place ooncrete c::att>letes
the closure in the center, the units are post tensiooed. Finally,
the ends of the deck are cast-in-place and the deck is post tensioned
I
to the ends of the arch ribs.
'Ihe concrete tie beams resist cnly thrust fran the applied
I
live loads and superimposed dead loads while the thrust fran
the dead load of the arch and deck system is resisted by the
dead load tie cable. Thus the tie beam is ncn-reduroant.
I
'!he deck is an integral unit after post tensioniD:} and the
joints within the span have been eliminated. nus permits the
I
deck to carry lateral loads tD the ahJtments. '!here is no need
for lateral bracing in cases where the deck is wide enough tD
resist these loads.
I
'Ihe entire structure may be erected without falsework. 'Ibis
should speed constructicn and greatly simplify scheduling ccnstruc-
I
tion and obtainiD:} permits to obstruct channels'-
.p
I :~ 5
I 2.0 INl'RCUJcrICN
steel tied arch bridges are used for ll'Oderate spans ranging
fran 200 to 1000 feet. Figure 2.1, which was produced try cx:rnp.1ter
graphics, shows a typical tied arch bridge. 'nle tied arch is
roost often used when a single span is needed or where the adjacent
I spans are so short that they would provide little benefit fran
exntinuity. They are oonsidered try many to be aesthetically
pleasirJj because functional lines are evident to even the roost
I casual observer. The tied arch also provides maximum clearance,
therefore, awroaches may be reduced to a minimum.
I
Hanoer
I
I Tie Beam
I
I
I TYPICAL TIED ARCH BRID<lE
I
I· Fi 0 2.1
6
I
'llu:ust in the arch is resisted by a tie beam connecting the
I
eros of the arch ribs. 'nle tie beam is also erected in secticns
by field I::x:lltir¥3 and can either be an I- or I::x:lx-shaped member.
'llle two tie beam !IlE!I1tlers are oonnect.ed with a full rrarent axmection
I
to the arch rib and they are subjected to I::x:lth tensile and flexural
loads. I
Hanger cables are used to suspend the tie beams fran the
arch ribs. It is through these han:Jers that the arch receives
vertical loads. 'nle hangers are CCIlIlDnly spaced at aI::olt 40
I
feet. 'llle shape of the arch rib has been develcped for uniform
vertical loadirv:J; and a parabola can be shown to be the IlOSt
efficient shape.
I
Tie beams connecting the eros of the arch ribs support a
series of transverse flcor beams. Floor beams are spaced so
I
they fall at hanger locations to minimize herDing in the tie
beams. Floor beams frame into the tie beams at their tql.
Diagonal bracir¥3 resists transverse loads on the structure.
I
Floor beams support a series of IOr¥3ibrlinal strir¥3ers. 'nle
strir¥3ers rest on either fixed or sliding bearings which isolate
I
the floor beams fran lTOVerrent of the deck. Because the tie beam
must be rigid in the longitudinal direction to resist tension,
the deck lIUst act separately i f it is to be prevented fran
I
develqling tensile stresses. la¥Jitudinal strains occur fran
live loads and thermal loads. 'nle joints in the deck are called
stress relief joints.
I
'nle IlOSt CCIlIlDn method of construction of tied arches is
to place falsework in the span to support the tie beam and arch
I
ribs during erection. 'nle falsework nay be kept in place durirv:!
erection of the deck system and castir¥3 of the deck. 'Ibis is I
done to minimize unsyrrmetrical loads durirv:! construction which
might cause overstresses in the arch ribs.
I
2.2 Problems With Present Practice
I
'!he steel weight of the tied arch brid:le is not significantly
2 . 3 . 1 General
I '!he proposed method involves the use of precast deck units
am a dead load tie manber connect ing the eros of the arch ribs
I acting as the tie beam for dead loads . It also assists the tie
beam in carrying live am superiroposed dead loads . '!he arch
ribs remain similar in awearance to conventional tied arch
I designs . Calstruction differs significantly fran normal in that
the alternate structure may be erected without falsewark . '!he
deck is made of precast concrete units . '!hese units include
I segnents of the two tie beams cast integrally with the deck as
sOOwn in Figure 2 . 2 . '!he units are post tensicoed to overCOlle
tensile stresses in them due to thrust fran the arch ribs am
I local effects .
I
8 I
Reik and Hansel describe a similar bric'kJe in Gennany. 'Ihe I
Gennan structure utilized a p:>St tensiC11ed cast in place deck .
'Ihe tie beams were steel (Ref . 4) .
I
Each precast deck unit is equal in length to the hanger spacing .
'Ihe deck units are hoisted into place using the hangers and other
stabilizing lines as shown in Figure 2. 3 . Transverse floor beams I
are spaced to permit the deck to span across the floor beams
withaJt longitudinal stringers . 'lllree floor beams per precast
unit is usually sufficient. Floor beams are CUllfXJSite with the I
deck for all dead and live loads . steel has been used for the
floor beams to minimize weight and to reduce forming . 'Ibere
are no dia~<:JllS between floor beams . 1hls reduces ooncern I
for secxn::lary web bending which may cause fatigue problems .
'Ihe deck is able to resist lateral loads since it is an integral
element without stress relief joints. 'Ihere shwld be no need I
for a lateral bracing system.
I
I
- ~ __ HQngers
I + ... + ~
I ...
Rolled cr Welded Steel Floor Beams
I
I
t
I Concrete Tie Beam
Typ. Post Tensioning Ducts
I
I Match
face _ Hangers
I inn
I
I
I
I
I
I Hanger s paci ng
I
SECTION A-A
I DECK AND TIE BEAM UNIT
I Fig 2.2
10 I
Line
I
I
I
splices I
Temporary Tie cable~
I
F.ig 2.3A
I
I
I
r bl
•
Tie Backs
/ Fiel d splice
I
I
Sec 4
Sec 3
I
2 I
I
Temporar), · Tie Cable
I
I
ARCH ERECTION SCHEME I
I
Fig 2,38
I
:.;
I ...
'n
11
I Figure 2.5 shows the schena for erection of the deck units.
'!be deck units are precast off-site and barged to the bridge
site where they are lifted into place by hoists attached to the
I arch ribs. Olril'B this process, the arch thrust is resisted
by the dead load tie cable .
I As the units are lifted into place , they are joined to the
previoos unit with minimal post tensi~. 'Ibis is necessary
to set the joints and to insure that wind loads duril'B construction
I ooy be transferred to the ends of the span . When the first units
are lifted into place , they are connected to the arch ribs by
shear pins which insure that the units will be laterally stable .
I Units are lifted into place as shcMn in Figure 2. 5 . Note that
liftil'B lines are oonnected at the outside floor beams in the
units provi~ stability duril'B erection . '!be hoists could
I be attached at different ~er positions on the arch to provide
further stability. By usil'B separate anchors for lif~ and
for pennanent support, the cost of ~ers is doubled . An ~tion
I would be to use the lifting anchors as permanent ~ers as shcMn
on the right of Figure 2. 5 . SUch a configuration would increase
the ~er forces , particularly on the ends where the sl~ of
I the ~ers beccrnes less vertical . Horizontal force oust be
considered in design of the post tensioning of the deck and tie
beam units .
I When the units are in place small donut type gaskets are
inserted to seal the ducts at the joints. A few strands are
I installed to seat the joints and to insure that the units act
as an integral unit during the erection prooess. '!be ranainil'B
p:>st tensi~ is installed when the center closure section
I of the deck , as shcMn in Figure 2.6, has been cast.
I Alternative hanger
arrangement
I
I
I
I
I
I
I
I
I Bracing
I 1 _ - - Arch Rib
I
I Cable
I I
I_----Hoist
I
I
I
Fig 2.5
I
14 I
Typ Precast Deck Unll
I
. . .
/ Typ Hanger
I
• • • • . . • .' • . • • .
~ ~ I
~
%
. . • . . . • • • . . . . . • .~
Cenl.r closure
I
Arch RI b.
I
DECK PLAN I
(Shaded orea 10 be casl-In-place)
I
DECK UNIT LAYOUT
Fig 2.6
I
I
Next the deck. is to be oonnected to the arch ribs, The end
sections of the deck are now cast. '!he end sections are cx:rnposed
of portions of the deck. between the arch ribs and portions of I
the tie beams between the end of the precast units and the arch
ribs as shown in Figure 2.7. Final post tensioni~ is then drne
to form a full manent oonnection between the arch and the tie I
beams. 'lhis will cause a slight decrease in the post tensic:t'lirg
stress already in the deck..
I
To minimize weight, a concrete str~ of 8000 psi is suggested
where good aggregate is available. Sane research iIrlicates that
high str~ concrete tends to creep less. I
Tie beams are designed for vertical beIrli~ induced by the
floor beams framing into than. They rust also resist berrling I
induced by the arch ribs and ~ers.
."
I
I
I
I r Dead
Tie
load
Cables
Containment
I
'1- - - - - - -- - - - - - --
I I
~--------------
I
Post Tensioning Ducts
I AI
- t:t..!
I I
l-
I
Arch Erectlan Pin
/ '\
I
I END ELE VAT'I 0 N
I
Fig 2.7
I
16 I
2.3.4 Advantages of the Alternate /oEthod
I
'l1le proposed alternate method of <XlI1Structioo eliminates
the earlier outlined disadvantages of the tied arch. 'l1le problem
I
of noo-redundancy in the tie beams is eliminated by the Illlltiple
wires in the dead load tie cable and the post tensiooir¥j strand
in the deck units. Instead of a large sir¥jle element tie beam,
I
multiple small wires are used to resist thrust fran the arch
ril:s.
I
'l1le oostly stress relief joints in the deck are eliminated
by post tensiooir¥j the deck. Falsework is also eliminated.
'lhls is nade possible by the dead load tie cable which provides
I
support durir¥j <XlI1Structioo of the deck. HqJefully, <XlI1Structioo
will be nuch faster and navigatioo channels will be un-obstructed
except for short periods.
I
Reduced steel weight should oontribJte to lo./er oosts through
both less base naterial and oonnectir¥J naterial such as splice
I
plates and bolts. Fewer splices also lead to reduced field labor.
I
'l1le use of steel and ooncrete appears at first to be in
reverse of good practice in that steel is used for the arch which
is viewed as mainly a canpressioo member while the deck coocrete
I
is used as part of the tie member which is viewed as nainly a
tension member. H<:7ft'ever, the arch is also a flexural member
subjected to rather large be!rlir¥J stresses. D..irir¥J <XlI1Struction,
I
loads nay induce net tensile stresses in the arch rib. 'l1le deck
is used as part of the tie member which rrakes the overall design
IOClre efficient. 'l1le tie member is actually canposed of high
I
strength steel wire strand with respect to dead load applied
prior to post tensiooir¥j. Tensile forces have been isolated
fran the flexural loads. 'lhls permits the use of efficient high
I
st.rer¥jth strand.
I
I
I
I
I
I
17
3 . 1 General
I 'll1e best way to determine the feasibility of the proposed
metlxxi i s to perform a design study . 'll1e objective of this
I study is not to develop a o:xnplete design , rut to examine the
obvious probl ems in sufficient detail to determine feasibility
of the method.
I An existing design was selected as a basis for the design
study . 'll1e original design was chan3ed only where necessary
I to aCCUlllodate the alternate approach.
interesti\'¥j a:mparisons of member sizes
This permitted sane rather
and design forces .
AASH'ro Load Factor provisions were used in the study .
I Table 3 . 1 shows a a:mparison of the original and alternate
designs . Figure 3 . 1 shcMs an isanetric view of the design example.
I TABLE 3 . 1 - DESIGl EXAMPLE a:MPARISCN
None
I JOINTS IN
DEn<
Every 36 . 5 ft 620 . 5 ft
I HANGER SPACING 36 . 5 it
11 ft deep (steel)
Same
9 ft deep (concrete)
TIE BEAM
I
18 I
'!he arch ribs rises 128 feet above the deck. '!hey are
unchanged fran the original design except that the plates are
I
kept at a cx:nstant thickness across the entire span. In the
original design, the plates are thinner in the center of the
span. '!he cross sectioo of the arch ribs is shawn in Figure
I
3.2.
Figure 3.3 sl'x:lws the deck units. '!he floor systan in the
I
original design utilizes floor beams at 36.5 feet which supports
stringers spaced at 8' -0" and an 8.0 inch thick ooncrete cast-in-
place deck. 'lbere are lateral bracing menobers in planes of both
I
top and l:ottan fl.an:3es of the floor beams. 'l11e alternate design
utilizes floor beams spaced at 12' -2" with 00 loogitudinal string-
ers or lateral bracing systan. External to the deck units, the
I
dead lced tie cables take thrust fran the arch ribs due to the
dead load of the deck units. I
'l11e deck is 9.0" thick in the center 50 feet in the alternate
design. 'Ibis thickness is sufficient to span between the floor I
beams. At the tie beams, the deck is 1'-3" thick to provide
adequate shear strength for transfer of shear fran the tie beam
to the deck. I
\,1>• I
Honger
/ I '--;--.--r--...L
Arch Rib
I
I
I
I
I
I
I
DESIGN STUDY EXAM PLE
I
Fig 3.1
I
19
I for fatigue.
I
I
I . --. ---,
I ;'6 01 .2 " . t.
/ Top 0.0 boll ...
I c:::::=====::5
I Are a • 324 1,,& I . . . 1310001,,4
I
Flo 3.2
I
20 I
I
i
36' - 6"
, -- Hangers
I
72 sq in
Tie Cable
Dead Load Deck tape rs over
I
I
20'-0" length
/
/+
-CD
I
Floor Beam I
I I
I
~ ... ~ - - - I
I r-...l>
v
I 91' - 0"
I j
I 3 Lones ~ Lones
t t
I nn 11. •
,...J
I
I
I
,. CROSS
DESIGN EXAMPLE
SECTION OF DE CK UNIT
I FiO 3.4
I
I
I
I
I
I
I
I
I
22 I
Six 12-foot traffic lanes are pennitted 00 the structure. '!he I
live load is six feet wide am may rrove within its 12 foot lane
as lol'¥3 as it stays two feet fran the edge of its lane . Each
12 foot lane may be !rOved transversely , rut must not override I
an adjacent lane.
I
3. 2.2 Dead Laid
'!he stresses in the arch ribs duril'¥3 their erectioo are not
I
reported . However, oanputatioos were made to determine that
erection stresses in the ribs were not critical with practical
length stiff legs am tie backs . Coostructioo stresses in the
I
arch ribs just prior to placanent of the deck units rust be kn<7,.m
so they can be added to stresses fran subsequent loads. These
stresses are given.
I
Placanent of the deck units is examined in sane detail. Pairs
of deck units are assumed placed simultaneously on the structure.
I
Each deck unit is canposed of three steel floor beams am their
portioo of deck slab am two tie beam segments. I
At this point, the dead load tie cable is the ally member
resistil'¥3 thrust of the arch ribs . The deck units are oonnected
to the eros of the span by shear pins to resist lateral loads
I
am insure that the deck does not sway . Each unit is sufficiently
post tensioned to the prior unit to set the joint am resist
wind loads duril'¥3 erectioo.
I
I
I
,'"
'!l
I ,.,
''1
'0 23
I When all units have been erected and the center closure portien
has been cast, the deck units are finally post tensiened.
I
24
I
IDsses due to =eep and shrinkage as well as anchorage and
I
friction are oonsidered in the design study. '!he age of the
units, relative humidity and several other factors are not
oonsidered but sOOuld be oonsidered in a detailed design.
I
Preliminary post tensioning of the precast units is perfonned
iJlInediately after they are lifted into place. '!he majority of
I
post tensioning is perfonned after all of the units are ccnnected
and the center closure section is cast. '!he norent oonnecticn
between the deck and the arch ribs is made by post tensionir¥J
I
the deck to the cast in-place em sections. Final tensioning
terrls to unload the tensioning in the other and is acoounted
for by over tensioning the precast units.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
'!l
I ....·~
'0
25
I 4.1 General
I using the finite elerrent metrod . FESAP, the finite element CCJJp.lter
pro:JLam that is utilized in the study, is licensed to BSDI by
BaJxxx:k & Wilcox.
I 4. 2 Floor Beam
I 'Ille floor beams are designed first so that they can be properly
m:Jdeled in the integrated m:Jdel am so the proper deck. thickness
is kmwn . '!his permits the weight to be rrore closely estimated
I when examining staging of the deck. units .
I
26
I
'nUrteen nodes are evenly spaced over tte 91.5 foot width . The
I
deck was lTOdeled using eight-rode solid elanents. Six elanents
were used across tte 36 '-6" deck sectioo. The deck is connected
to the steel girder elanents with very rigid beam elanents in
I
the vertical orientatioo . 'nUs insures full CCJ!ilOSite actioo.
The rrodel is sl1o.m in Figure 4.1. The rrodulus of elasticity
for the ooncrete and steel were input based on MSHro.
I
The ooncrete rrodulus is adjusted by a factor of three (3.0)
to account for creep and shrinkage when analyzing for dead load.
I
The analysis is performed by hand since the BRIlXiE-5YSTEMsm loader
works only in tte longitudinal directioo. The design is performed
in interactive design programs USing the properties described. The
I
design program permits the user to m:Jdify plate sizes and check
stresses using tte MSHro wad Factor Design criteria. I
I
I
I
I
I
I
,Iemenll
8 Node lolid I
~
elemenll
b.
Plole
elemenl I
\ 6 • 6 ( SBS)
r.action Illmlntl
Top and bottom
beam ellmlnta
I
I
FLOOR BEAM AND DECK MODEL
I
Fig 4.1
I
I ; 27
'"
'D
.,n
4. 3 . 1 Arch Rib
I cable and tie beam 00 ate side of the bridJe were n'Odeled . 'Il'e
IOOdeI i s shown in Figure 4. 2. Since the arch rib is actually
IOOdeled using 30 elerrents , a third reaction at the t:q:I of the
y = 0.001288(616 . 91Ox-x2 ).
I 'Il'e elanents for the arch rib extend be~ har¥;Jer locations
aloog the parabolic shape of the arch . Figure 3 . 2 shows the
I box cross sectioo and properties of the arch rib . In the design
stoo.y, the plate thicknesses are held constant over the entire
span. '!here are 34 elerrents in each arch rib. All elerrents
I are straight .
Tie beams are not connected to the arch ribs at this time.
I 'lllree beam elerrents are used to represent the tie beam and deck
between each har¥;Jer . Fach node in the tie beam represents the
locatioo where a floor beam is CXXlI'Iected . 'Il'e weight of each
I deck unit is applied as three (3 ) coocentrated loads at the nodes
of the units being placed . '!his arrar¥Jerrent is shown in Fig 4. 2
I
26 I
Arch Rib divided Into
34 Beam
I
I
Lateral
reatlon
I
I
lS", EI.m", ,,,
dead load Tie Coble
I
I
I
Beam E.lemenTS - 51 for
Unl t - I
/he complete Tie Beam I
t4--.----.,.-+_~
----Applied loadli
I
116 kp Each I
77 kp
DETAIL" A" I
I
I
H2 / "",,-2.8 I
--.--+-~-
I
116 kp Each
I
DETAIL" s"
ARCH RIS AND STAGING MODEL
I
Fig 4.2 I
':!>
I -0
~
, , 29
I 4. 3 . 4 BeariI'¥Js
Stage 1-
I '!he secoro
analysis is m3.de by adding the first four beam
elements on each end of the structure. '!hey are connected to
I the end of the arch rib and to the first hanger . l'IcIr¥Jer are
connected to the arch ribs . '!hese units are sho.In in place in
Figure 4. 3A and B. '!his analysis represents the first pair of
I deck units placed on the structure. Although the units would
actually be lifted singly , they are treated as if lifted in pairs
and placed synnetrically . Units shoold be placed synnetrically
I in or der to minimize bendir¥J in the arch ribs . '!he resultiI'¥J
analyses includir¥J nanents and thrusts in the arch rib , har¥Jer
tension , tie cable tension and reactions are reported.
I Stage 2-
I
30
I
Shear connection only
I
between deck unit and
arch rib
I
I
I
Unit - 2
I
\ I
STAGE 2 I
No bending 5tiff neS5
Fi g 4.3A
between deck and arch
I
during conUruct Ion
I
I
I
I
I
Unit - 8
~ I
I
STAGE :3
I
STAGING OF DECK UNITS
I
Fig 4.38 I
,"~
I ''l
'0 31
I
I units. ~ts in the tie beam are not reported rut IoKlUld be
used to cnnpute stresses in the tie beam and deck during erection.
They are not cnnputed because the roodel is crude and the value
I of moment is small.
Stage 3-
I stage 4-
I 3 are ignored and their loads are raroved. The two units in stage
4 are adjacent to the units in Stage 2.
I stages 5 and 7-
I
32
I
I
Detail "A"
I
I
I
I
ELEVATION OF ARCH
I
Arc·h Rib I
12' - 2" Ty p
Deck Element
Floor B eams
--- Hanger
Deck
I
I
Beam
E Ie men ta \ I==::;;~===:;:::;-;L=====l
/ I
, I
""
Reaction . I
Floor Beam
Spacing
Dead load Tie Coble
I
Tie Beam
I
DETAIL "A" I
INTEGRATED MODEL- OVE.RVIEW
I
I
Fig 4.4
I
I '0'~ 33
.",
I '!be tie beam web is g'-O" deep . Table 4.1 provides properties
and sizes of the two designs examined. Design 1 was perfOI:lTB:l
I 4.4.3 Deck
I the tie beam web in roth designs. 'Ibe deck is rrodeled by a series
of 12 eight-node solid elanents across the bridge between tie
beams as shcwn in Figure 4.5. 'Ibe portion of ~ deck outOOard
I '.0'~ 35
I J
4
I
I
I ......... K ./"
L
I H 5
/5 / l / 5 /
I ....
-
.-" - -- :...-'
B/
'\ \\ \
\
I "- C
\
o E F G
I
I
~
2' - 0" ABT 7' - 6"
I ,I .1 6
I
I 2 7 9
I 5
I -o
I
I
I 8
Local bendir¥;j in the deck due to live and dead loads is CCIll{:Uted I
by hand according to MSHro-3.24.3.2. nus method dces not allow
for the flexibility of the flcor beams. It also is tOOu,ht to
be rather conservative. Influence surfaces based 00 the deck
I
and flcx:>r beams is expected to yield lower bending stresses.
L .L . ( Interstate)
I
/ I
60
L.L. ( H S 20)
I
I
-...
Q.
40 I
~
a:
I
'"
UJ
:r D.L.• /'" I
VI 20
I
I
0 10 20 30 40 I
I
HALF SPAN f ee t )
I
FLOOR BEAM SHEAR ENVELOPE
I
'fIg 5.2
I
I ':!l
' ,.,~
.
.'!j
.,) 41
I With only foor oonnecting ocrles per floor beam between the deck
and the steel, the ooncentrated unit loads are not distri.bJted
I to the floor beam oorrectly. When unit loads are placed over
the ocrles with beam stud oonnectors to the floor beam, the load
I Figure 5.4 shaws the influence line for the stress in the oottan
of the floor beam based on the 3D rrodel. Also, for cx:roparisoo
the influence line based on a simple span is shown. '!be influence
I
I 2- 4
u
• 0'875" Stud sheor connector. Plr row
-
at lOll spoc ln g . •
I 110 Rows 220 Stud.
I
I
t. 60",0'75" (A36)
I ,
...
0
30" 3 at 90" 3 al 90" JO"
I
11
4"" 0 '312.5 Stiff nor I y p -
I
I ( A36)
r. IS", 1'375",60'- 0" (.4572)
(A36)
I
TYPICAL FLOOR BEAM
I
I Fill 5.~
42
I
I
I
I
I
"
I \
\
I
I \
20 t I
I
IS
I
-
•
Q.
I
I
.>t:
~
I-
I
z 10
w
~
0
3D Mod e l I
~
I
5
I
I
0 I
SPAN
I
FLOOR BE AM IN FLUENCE LI NE
I
Fi g 5 .4 I
I
I ·n
~
.;p
.,!) 43
."
I 5.3 Arch Ribs
I 5.3.1 General
I ARCli
DL
oo.y
UNIT 1
0
728
378
10139
514
6700
470 326 137 -49 -194 -273
3755 1300 -664 -2140 -3120 -3611
DL UNIT 2 -752 5600 12380 7194 2872 -584 -3176 -4905 -5770
I OL
DL
UNIT
UNIT
8
3
418
-116
-3986
1710
-9155
6476
-10400 -9324 -5938
11778 5527
-240 7772 18097
526 -3224 -5724 -6975
DL UNIT 4 108 -135 1044 4576 9398 3040 -1726 -4905 -6495
I DL
DL
UNIT
UNIT
5
6
108
117
-1603
-2871
-1987
-4327
-1020 1892 7099 1470 -2282 -4160
-4390 -3030 222 6520 2305 198
DL UNIT 7 131 -3789 -6066 -6808 -6009 -3533 1237 9102 6828
I
TABLE 5.2 - DEAD LOAD TIiRUSTS IN ARCli RIB WE TO STAGIN:;
I (KIPS)
Wcation 0 1 2 3 4 5 6 7 8
I ARCli oo.y -531 -504 -482 -464 -448 -437 -428 -423 -421
DL UNIT 1 -124 -129 -133 -137 -140 -142 -143
I OL
DL
UNIT
UNIT
2
8
-333
-418
-768
-119
-402
-727
-218
-754
-227
-754
-234
-750
-242
-740
-247
-724
-250
-701
-251
-672
I DL
DL
UNIT
UNIT
3
4
-484
-573
-506
-570
-488
-577
-328
-566
-340
-432
-349
-444
-357
-454
-536
-361
-460
-543
-363
-462
-545
DL UNIT 5 -654 -647 -639 -636 -632 -524
I DL
DL
UNIT
UNIT
6
7
-717
-762
-711
-756
-702
-748
-693
-739
-685
-729
-683
-721
-601
-711
-609
-657
-612
-660
I
44 •
TABLE 5. 3 - J\£Xl.MJIMID DEAD I.OI\D IOlENl'S IN AROi RIB WE 'ro STAGING •
Locatioo 0 1 2
(F'I'-K)
3 4 5 6 7 8 •
AROi CtlLY
'lUI'AL UNl
0
728
378
10517
514
7214
470 326
4225 1626
137
-527
-49
-2189
-194
-3314
-273
-3884 •
'lUI'AL
'lUI'AL
UN2
UN8
741
755
16276
10471
19586
10437
11408 4486
1048 -4776
-1125
-6979
-5378
-5513
-8235
-341
-9668
8564
•
•
'lUI'AL lin 755 13162 17037 12783 698 -6513 -8803 -6136 1517
'lUI'AL UN4 755 13132 18575 17453 10039 -3538 -10601 -11117 -5056
'1UI'AL LN5 755 10853 15887 16235 12145 3675 -9006 -13267 -9079
•
'lUI'AL UN6 755 6842 9953 10468 8634 4509 -1894 -10334 -8235
'1UI'AL UN7 755 1656 1817 1617 1307 932 553 75 -62
•
•
TABLE 5.4 - ACXl.MJLATED 'IHRusr AROi WE 'ro srAGING
(KIPS)
•
Locatioo 0 1 2 3 4 5 6 7 8
AROi CtlLY -531 -504 -482 -464 -448 -437 -428 -423 -421
•
'lUI'AL UNl -864 -623 -606 -593 -581 -574 -568 -565 -564
'1UI'AL LN2 -1282 -1025 -824 -820 -815 -816 -815 -815 -815
'1UI'AL UN8 -2050 -1752 -1578 -1574 -1565 -1556 -1539 -1516 -1487
•
'1UI'AL LN3 -2534 -2258 -2066 -1902 -1905 -1905 -1896 -1877 -1850
'lUI'AL UN4 -3107 -2828 -2643 -2468 -2337 -2349 -2350 -2337 -2312
'1UI'AL UN5 -3761 -3475 -3282 -3104 -2969 -2873 -2886 -2880 -2857
•
'lUI'AL UN6 -4478 -4186 -3984 -3797 -3654 -3556 -3487 -3489 -3469
'1UI'AL UN7 -5240 -4942 -4732 -4536 -4383 -4277 -4198 -4146 -4129
•
J\ccunulated mcments and thrusts for each stage are plotted
in Figure 5. 5 and 5. 6, respectively. It is evident that the
•
•
mcment in the arch rib in the vicinity the deck unit being placed
is positive while in other locations it is negative . In order
to keep mcments in the arch nore evenly balanced, the two center
•
deck units were ad1ed as the third stage. 'lllese units would
not be lifted into place, rut susperoed fran the arch.
•
•
1= 45
A CCUM UL ATED ARCH MOMENTS ( kp ft )
1
1
1
21000
Arch only
1 14000
1.000
1 -7000
o
-14000
1 21000 2 U nl t 8
1
14000
1000
o
/
1 .....a.
~
-1000
1 .. -1 4 000
21000 Un i t 3
... 14 000
1 c:
•E
7000
o
o
1 ::I -1000
-14000
1 2rOOO
14.000
1000
1 o
-7000
1 -14000
1 / U';' 7
1
7000
-7000
o
I ( Fi nol )
1
1 Fi g 5,5
ACCUMULATED TRUST IN
46
ARCH RIB ( kp)
I
,........--- r--,........., I
/,/ "t'--
I
~ ~
I
a
- 1000
-2000 /
I
I
-3000 t Arch on ly
I
o I
~
-10 0 a
-2000
P-unl-t 27-1-/- - \ u - n l t - . I
- 3000
I I
- 1000
0
I
- 2000
-3000 I
- 4000 Uni t ·3 U nl t 4
I
0
- J
-2000
00 0
Unlt5 \ U nl t 6 I
- 3000
-4000
I
-5000
0
I
- 1000
- 2000
- 3000 / FlnOI
" 4000
- 5000
Fig 5,6
I :;
.",
.ct> 47
'n
1 (KS1)
1 I.ocatioo 0 1 2 3 4 5 6 7 8
1
J\CCl.MJIATED smESS IN OOl'lCM OF AROI RIB
1 OOEoro~
(KSI)
1 I.ocatioo 0 1 2 3 4 5 6 7 8
1
smESS = (1OIENl' (FT-K) X 12 ) X ( C=24) / 1=131000 IN**4) +
1 ('lllRUST (KIPS) / ARFA=324 SO. IN . )
1
48 I
Figure 5.7 sl1a.Is the stress envelope of maximum tensile and
I
maximum CXlI1Pressive stresses in the arch rib during placanent
of the deck units. The envelopes are based on Table 5.5. They
daronstrate the critical locations. The unfactored stress in
I
both top and botton of the arch rib approach the yield stress
so the sectioo of the arch rib co..Jld be increased, or the erectioo
sequence might be IrOdified to lower stresses. A factor of safety
I
of at least 1.25 would be expected. Stresses in the arch rib
after all deck units have been placed are plotted on the sane
figure for CXJI1Parison. The thrust is seen to be about 15 ksi
I
while the bending stress does not exceed 10 ksi. DJring staging,
rranent daninated the loading over thrust. The parabolic shape
of the arch ribs keeps bending to a minimum when loads are applied
I
unifonnly along the span.
I
I
I
I 50
40
I /MaXlmum tension
30
I
20
I
10
I
0
I -10 /
Final bottom
I -30
I -40
I -50
Maximum compression /
I
I
I r i g 5.7
I
I
50 I
5.3.4 Tarpmiture I
'lhe results of the thental analysis are presented in Tables
5.6 and 5. 7. In this case, the force is caused by the arch attan- I
pting to expand and tension in the ~ers attanptil'¥1 to restrain
the arch fran rising. 'lhese actions cause a positive rranent in
the arch ribs . I
I
TABLE 5.6 - Sl»lARY OF ARCH RIB t-nlENl'S
(Fr-K) I
Han:Jer I£x:: -) 0 1 2 3 4 5 6 7 8
I
DL 755 1656 1817 1617 1307 932 553 75 -62
original DL 1048 765 924 970 940 934 936 842 863
I
SIMP 874 132 64 73 68 54 39 28 22
originalSUp 314 124 102 110 117 125 132 136 139
I
TEMP 3151 3174 3177 3176 3173 3170 3167 3163 3159
IL+I (+) 799 202 409 596 648 644 574 443 386
I
IL+I final 961 585 880 1111 1222 1201 1057 836 693
orig IL+I 556 777 1229 1442 1509 1444 1254 1002 842
I
IL+I (-) -74 -238 -461 -555 -596 -561 -468 -345 -234
IL+I final
orig IL+I
-377
134
-461
-455
-754
-899
-993 -1115
-1084 -1167
-1112
-1111
-983
-945
-759
-693
-598
-476
I
TABLE 5. 7 - Sl»1ARY OF ARCli RIB 'lllRusrs
I
(KIPS)
Han:Jer I£x:: -) 0 1 2 3 4 5 6 7 8
I
DL
orig DL
-5240 -4942 -4732 -4536 -4383 -4277 -4198 -4146 -4129
-4736 -4712 -4516 -4131 -4169 -4033 -3925 -3846 -3800
I
SIMP
orig Sup
-1215 -1172
-476 -476
-1125
-458
-1082 -1046
-440 -423
-1017
-409
-998
-398
-983
-390
-981
-385
I
TEMP -93 -88 -84 -81 -79 -77 -75 -74 -74 I
IL+I -907 -878 -845 -801 -785 -763 -749 -739 -736
LL+I final
orig IL+I
-425
-836
-410
-836
-393
-805
-378
-773
-366
-745
-355
-720
-349
-701
-343
-686
-342
-677
I
I
51
I 'n1e nonent results are ocrnbined in Table 5.8 for each case
to detel:mi.ne the oontrollir¥J oorditioo which is used to canpute
I
52 I
TABIE 5. 8 - FACImEIl fo01ENl'S IN AROi RIB I
(K-FT)
Hanger Loc -) 0 1 2 3 4 5 6 7 8 I
DL
SIMP
755
874
1656
132
1817
64
1617 1307
73 68
932
54
553
39
75
28
-62
22 I
TEMP 3151 3174 3177 3176 3173 3170 3167 3163 3159
LL+I final
LL+I final
961
-377
585
-461
880
-754
1111 1222 1201
-993 -1115 -1112
1057
-983
836
-759
693
-598 I
CASE I +
CASE I final
3833
4200
7686
3593
8222
4351
8088
4603
5331
4435
1862
3883
-433 -1540
3060 1945
-1944
1450 I
CASE I -
CASE I final
1941
1302
6733
1325
6337
811
5593
46
2635
-628
-748 -2689
-1127 -1361
-3246
-1510
-3288
-1348
I
CASE II + 7236 11637 11997 11700
CASE II final 7463 7211 7719 7770
8894
7501
5425
6964
3187
6261
2188
5332
1828
4956
I
CASE II - 6101
CASE II final 5724
11065 10866 10203
5851 5595 5035
7276
4463
3859
3958
1834
3608
1164
3260
1021
3277
I
CASE I
CASE I final
3833
4200
7686
3593
8222
4351
8088
4603
5331
4435
1862 -2689
3883 3060
-3246 -3288
1945 1450
I
CASE II 7236 11637 11997 11700
CASE II final 7463 7211 7719 7770
8894
7501
5425
6964
3187
6261
2188
5332
1828
4956
I
I
TABLE 5.9 - FACl'CRED 'ffiRUSl' IN AROi RIB
(KIPS) I
DL -5240 -4942 -4732 -4536 -4383 -4277 -4198 -4146 -4129
SIMP
TEMP
-1215
-93
-1172
-88
-1125 -1082
-84 -81
-1046
-79
-1017
-77
-998
-75
-983
-74
-981
-74
I
LL+I -907 -878 -845 -801 -785 -763 -749 -739 -736
CASE I -10357 -9851 -9445 -9039 -8759 -8535 -8378 -8269 -8238
I
CASE I final -9312 -8836 -8465 -8122 -7851 -7652 -7511 -7412 -7385
CASE II -9692 -9204 -8822 -8450 -8181 -7974 -7826 -7725 -7696
I
CASE IIfinal -9065 -8595 -8234 -7900 -7636 -7444 -7306 -7210 -7184
I
I
I
53
I '!be stresses in the arch rib are sumnarized for all cases
in Table 5.1 0 . Subsequently , they are factored and canbined
I into the two cases described earlier. It is seen that the arch
rib is slightly overstressed at several locations when the
teIJllerature CCI1ditioo is oonsidered in Design 1. Temperature
I
TABLE 5 . 10 - S!M11\R¥ OF S'IRESSFS IN 'lQP AND OOI"ltJl1 OF AROl RIB
I
S1RESS'lQP (KS1)
I cr.sE I -41 -48 -48 -46 -39 -31 -20 -18 -18
CASE I final -38 -35 -36 -35 -34 -32 -30 -27 -26
I cr.sE I I -46 -54 -54 -52 -45 -37 -31 -29 -28
CASE II final -44 -42 -42 -41 -40 -38 -36 -34 -33
I
S1RESS 00l'KM (KSI)
I cr.sE I -23 -13 -10 -9 -15 -22 -32 -33 -33
cr.sE I final -19 -19 -17 -15 -14 -15 -16 -19 -20
I cr.sE I I -14 -2 -0 0 -5 -13 -18 -20 -20
CASE II final -12 -11 -8 -7 -7 -8 -9 -11 -11
I
I 5 . 4 Hangers
5 . 4 . 1 General
I '1be hangers are vertical in both analyses . In Design 1 the
hanger area is 3 . 5 in2 , whereas it is twioe that in Design 2 .
I '1be original design has hanger areas of about 7 in2 . '1bere are
actually foor hanger cables in the actual arran::jement . If the
alternate arran::jement of inclined hangers is used , there will
I be ooly two hanger cables per attachrent.
I
I
54 I
5.4.2 Dead Load I
'!he deck \IDits were placed 00 the stnx::ture as described
in Sectioo 4. '!he force in the first harger is the weight of I
half of the deck \IDit. Table 5.11 sOOws the harger forces for
each stage of loadirq. sane of the forces cha.n:Je as subsequent
loads are added because of the stiffness that was assured I
effective between the \IDits after they are placed . stage three
is out of the ncmnal sequence because it is the center two deck
\IDits which were placed to balance arch rib lOCIlleIlts . Table 5. 12 I
sOOws the accumulated I'la.rqer dead load forces . In Table 5 . 13
they are carpared to the original dead loads . It is interestirq
that the dead load of the deck in Design 2 is nearly balanced I
by the additiooal steel weight of the original design.
I
TABLE 5 . 11 - HANGER FCRCES FeR DEAD LOAD STlIGING
(KIPS)
I
Har;;er I.oc - > 1 2 3 4 5 6 7 8
I
DL UNIT 1 366 o
DL
DL
UNIT 2
UNIT 8 -5
347
5 347
o I
DL UNIT 3 1 1 347 o
DL
DL
UNIT 4
mIT 5
1 1
1
346
3 345
o
o
I
DL UNIT 6 4 344 o
DL mIT 7 -1 8 341 o I
TABLE 5 . 12 - ACXl.MJLATED HANGER FeRCE FCR DEAD LOAD STAGING
I
( KIPS )
I 'nle hanger forces are nearly equal exoept for the ooe closest
to the arch rib which is slightly less than the others because
the berrling stiffness of the tie beam transmits sane of the load
I directly to the supports .
I 5 . 4. 4 Temperature
I 'nle results are equal for all rut the first hanger . 'nle
force is a result of the arch attempting to lift upward . 'nle
upward novanent is approximately proportional to the stiffness
I of the deck unit. 'nle force in the first hanger is larger for
the sane reason that the first hanger foroe was smaller in the
superinp:>sed dead load case .
I
5 . 4 . 5 Live Load
I Live load was found to be oontrolled by lane load rather
than vehicle load. 'nle triOOtary area may be larger in the
I alternate deck than for the original design where the stress
relief joints tend to limit the trirutary area . Also , the tie
beam in the original design was less rigid . However , the
I differences bet.....een the alternate am original designs are not
large.
I
I
I
I
I
I
I
56 I
TABLE 5. 13 - SlMlARY CF F'CRCES IN HANGE&S I
(KIPS)
Hanger Loc -) 1 2 3 4 5 6 7 8
I
FINAL DL
Original
362
275
354
295
349
297
349
297
348
300
352
303
341
303
347
303
I
SIMP DL
Original
74
31
90
35
93
36
93
36
93
36
92
36
92
36
92
36
I
10 7 7 7 7 7 7 7
I
lL+I(+) 61 72 74 74 74 74 75 75
Original 55 62 64 64 65 65 65 65 I
CASE I 699 733 735 735 733 737 725 733
CASE II 658 680 680 679 678 682 669 677 I
AREA = 6. 9 SO IN . I
S'ffiESS (KSI)
.~
.
~
57
I to rroderate the uplift Cl'l the deck due to the raisirg of the
arch ribs.
I Live load causes maximum thrust in the tie cable when the
thrust in the arch ribs are maximum and positive nanent in the
arch is maximum. '!here is no live load that can cause a reductiCl'l
I for live load than for superimposed dead load. '1hus, the deck
is assigned a larger portion of the live load than it is for
the superimposed dead load.
I
I
58 I
TABLE 5.1 4 - REACl'IOOS OOE TO STAGING (F DID< UNITS I
(KIPS)
TIE CABLE 452 3719 168 -1248 87 4426 3178 5829 4131
I
Tie cable stress (ksi) 61.5 44.2 81.0 57 . 4
I
5.6 Tie Beam I
5.6.1 General
I 'fue dead load results were recanputed by harrl. 'fue values for
the tie beam are not cx:rnpared to the original design values because
The stress for maximum and positive dead load rrarent was
I 5.6.3 Temperature
I are reported as
on each side of
the average of the stresses in the two elements
that hanger. Results in the center element between
angers was used for the center lcx:ation.
I
I
I
60
I
I
I
I
116 kp 116 kp 116 k p 116 kp
I
l l J J I
~ ~ I
Hang. r Hanger
t
L: 36'- 6"
~ I
I
-III PL
I
I
·222 PL
I
I
MOMENT DIAGRAM I
DEAD LOAD MOMENT IN TIE -SEAM
I
I
Fig 5.8
I
I
I
I ::;.....r, 61
'....
I 5 . 6 Live Load
(PSI)
I Hanger Lee -) 0 1 2 3 4 5 6 7 8
I DL
SIMP DL
-205
140
-205
172
-205
172
-205
165
-205
150
-205
140
- 205
135
-205
120
-205
115
TEMPER 447 260 135 13 -90 -175 -235 -280 -302
I LL+I TENS
LL+I m1P
520
-379
583
-360
836
-576
1018
-765
1092
-836
1055
-795
947
-669
799
-434
687
-364
Hanger Lee -) 0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9
I DL 103 103 103 103 103 103 103 103 103
SIMP DL 200 225 210 192 179 169 157 159 157
I TEMPER
LL+I TENS
315
440
201
680
74
1210
-41
1098
- 135
1035
-207
895
-260
802
-292
690
-304
550
LL+I m1P -613 -462 -790 -910 -816 -750 -602 -410 - 322
I
I
62
I
TABLE 5.16 - TIE BEAM S'rnESSES Wl'ltM CF WEB AT H1INGEltS
I
Frn DESI~ 2
(PSII I
Hanger Loc -) 0 1 2 3 4 5 6 7 8
SERVICE I£lAD
I
CASE I (+1 1324 1291 1687 1979 2071 1961 1690 1345 1099 I
CASE II (+1 2320 2031 2158 2440 2097 1823 1426 994 699
POST-TENSICNING
I
---------------
REXm.AR -2474 -2474 -2474 -2474 -2474 -2474 -2474 -2474 -2474 I
MAXlMJM crMPRESSI(]II 0i0CK
-------------------------
I
SERVICE I£lAD
I
CASE I (-) -742 -622 -1033 -1513 -1734 -1717 -1508 -1177 -934
CASE II (-I 254 118 -562 -1052 -1708 -1855* -1772 -1528 -1334
I
-2474 -1855 (HANGER 51 = -4329 ) 3200 PSI NG
= -4825
'I'EMP(EARY -2474 + 20% -1855 ) 4400 PSI NG
I
FACICmD POST TENSI(]IIE[) S'ffiESS = 1.3 (-2474 + 20 %1 = -3859 KSI
FJ\CIUm) I
FACl' P-T -3859 -3859 -3859 -3859 -3859 -3859 -3859 -3859 -3859
I
CASE I (-) -1705 -1482 -2322 -3312 -3752 -3684 -3210 -2477 -1942
CASE II (-I 330 154 -730 -1367 -2220 -2411 -2304 -1987 -1734
I
FINAL I -4179 -3956 -47% -5786 -6226 -6158 -5684 -4951 -4416
FINAL
FINAL
II
I
-2144 -2320
-5565 -5341
-3204
-6181
-3841
-7171
-4694
-7611*
-4885
-7543
-4778 -4461
-7069 -6337
-4208
-5801 I
FINAL II -3529 -3706 -4590 -5226 -6080 -6270 -6163 -5846 -5594
(PSI)
I Hanger I.oc -> 0-1 1-2 2-3 3-4 4-5 5-6 6- 7 7-6 6-9
I DL
SIMP DL
94
376
94
350
94
267
94
236
94
195
94
165
94
143
94
130
94
125
I TEMPER
LL+I TENS
LL+I CXMP
671
1063
-713
606 347 126 -60 - 204
1336 1746 1999 2035 1665 1566
-310
I srnVICE LOAD
I CASE I (+)
CASE II (+)
1535
2406
1762
2390
2127 2329
2474* 2455
2324
2264
2124
1920
1605
1495
1473
1095
1252
643
I POST-TENSIrnING
-------------
RmJLAR -2474 -2474 -2474 -2474 -2474 -2474 -2474 -2474 -2474
I
MAXIK.M a:MPRESSICN rnEO<
I -------------------------
srnVICE LOAD
I CASE I (-I
CASE II (-)
-241
630
-455
153
-979
-632
-1327
-1201
-1427
-1467
-1309 -1016
-1513* -1326
-705
-1063
-510
-919
I FACKRID
I FAcr P-T -3659 -3659 -3659 -3659 -3659 -3659 -3659 -3659 - 3659
CASE I (-) -930 -1370 -2451 -3162 -3343 -3060 -2411 -1721 -1294
I CASE II (-I 619 199 -622 -1562 -1933 -1966 -1727 -1406 -1194
FINAL I -4790 -5230 -6311 -7021 -7202* -6919 -6271 -5560 -5153
I FINAL II -3040 -3660 -4661 -5421 -5793 -5626 -5566 -5267 -5054
I
64
I
5.7 Deck
I
5.7.1 General I
Deck stress results are needed to detennine the arrount of
post tensionin:] steel required. All ooncrete is post tensiooed
to avoid tensile stress. Since the deck varies in thickness
I
arrl the stress levels vary across the width of the bridge, it
is necessary to examine deck stresses in several locatiCX'lS across
the width arrl al.cn3 the length of the span. Sane loads enter
I
the deck fran the arch rib arrl must be transferred into the entire
deck through shear actien. Local effects are not a functien
of shear lag.
I
Total stress in the deck is a <XIl\bination of overall thrust
fran the arch rib; overall berrling in the deck units due to flexi-
I
bility of the arch ribs; local berrling between floor beams; arrl
to sane degree bendiI¥J between han;jers. I
Stresses en I::oth top arrl I::ottan of the deck were recorded
aloo:; the three lines "A", "B", arrl "en shc1Hn in Figure 5.9.
Since cnly stresses in the center of each element length are
I
obtained, cusps near ha.rBers are not observed directly fran the
results. Live load influence surfaces were not developed to
examine local effects in the deck. Canp.ltation of local stresses
I
is presented in section 5.7.2.
= 1 bt = 1(1)(0.75) = 0.0351
I I
S
12 12
= I/(t/2) = 0.0351/0.375 = 0.09375
ft
ft
I Dead I.Dad stress
I
I ...~ 67
STRESS AT TOP OF DECK DUE TO SOL AND TEMPERATURE
"
I
I
I
I 150 A LIne B
I 100
I 50
O~
Line C /
______________________________ ~
I
LI ne A
I
I
250
200
/
I 150
, ..,...~ Llne 8
I ..
0.
100
Line C - -·\1
I
~
50
I o
I - 50
I TEMPERATURE
I
Fig 5.10
I
68
STRESS AT TOP OF DECK DUE TO SOL AND TEMPERATURE
I
~-
-:--
r---. . . . . .
I
/<"'"
"',,- I
~
150
Line A Line B
'" I
I
.
~
0-
~
100 \ I
0
LI ne C / I
SUPERIMPOSED DEAD LOAD
I
300
Li ne A
I
250
\ I
-..
~
200
Line. B
I
0-
~
150
I
100 II ne C
I
50
II
0
-50
I
- 100
I
TE MPER ATURE
I
Fig 5.11 I
I
1'....1> 69
STRESS AT BOTTOM OF DECK DUE TO SOL AND TEMPERATURE
1
I
I
I 2 00
I 150 LI ne A LIne B
I .
~
100
-
~
50
I 0
LI ne C
I
SUPERIMPOSED DEAD LOAD
I
L i ne A
I 250
I 200
I 150
I
'"
-
~
100
L i ne 8 LI ne C
/
I 50
0
I
I TEMPERATURE
I Fig 5.1 2
I
70 I
5.7.5 Tanperature I
'1lle results for this analysis were obtained in the same manner
as for super~ dead load. This run did not produce observable I
variation in deck stresses between hangers since there were no
vertical loads applied. Temperature has t'n'O apparent effects
en the deck: '1lle arch is attempting to lift the deck U~i I
and the arch is attempting to lengthen the deck due to expansion
roth longitudinally and vertically of the arch ribs and l~
of the dead load tie cable. In the analysis, the tie cable actually I
pulled on the deck whereas is the actual structure, it would
anount to a transfer of the dead load thrust fran the cable to
the deck and tie beam units. I
As in super:iJrposed dead load, there is a large difference
is stress across the deck at the ends of the span. This occurs I
because the force in the deck is introduced by the arch rib and
dead load tie cable. In fact, shear lag is so severe that the
center of the deck reverses sign to maintain equilibriun. At
I
the quarter point of the span tensile force is equal across the
bridge width and remains equal over the center portion.
I
5.7 . 6 Live I£>ad
I
'1lle local effects were cc::Ilputed by haOO as was local dead
load stress. The overall stresses were determined fran the loader
which positicns the live load to produce maximum and minimum
I
stresses in each elarent investigated . '1lle reported values
are the average of the t'n'O elarents en each side of a hanger .
'!be influences surfaces are produced by loading only positions
over floor beams at hangers, thus the local effects of bending
over floor beams are not evident in these results. '1lle haOO
calculated local stresses are added to the stresses determined
by the loader.
I
I
I
I
I
I
I .!)
'~
·n
71
.-
~
I Ranger Lac -) 0 1 2 3 4 5 6 7 8
SIMP DL 152 63 72 73 77 78 80 80 80
I TEMPERA'IURE
lL+I TENS
217 236
242 352
167
458
190 220
551 580
243
570
260
508
272 277
410 309
lL+I aMP -68 -299 -453 -555 -590 -565 -492 -391 -299
I SERVICE LOAD WI'llU1l' LCX:AL
CASE I (+) 394 415 530 624 657* 648 588 490 389
I CASE II (+) 611 651 697 814 877 891* 848 762 666
I DL LCX:AL (+)
lL+ I LCX:AL (+)
72
304
72
304
72
304
72
304
72
304
72
304
72
304
72
304
72
304
SERVICE
I CASE I & II 376 376 376 376 376 376 376 376 376
I -------------------------------------------
RmJLI\R -891 -891 -891 -891 -891 -891 -891 -891 -891
LCX:AL -376 -376 -376 -376 -376 -376 -376 -376 -376
I 'rol'AL
-----------------------------------------------------
-1267 -1267 -1267 -1267 -1267 -1267 -1267 -1267 -1267
I Case I
'l'EMPCIlARY
-1033 -293 (HANGER 4)
-1033 + 20% -513
= -1326
= -1753
(
(
3200
4400
PSI
PSI
OK
OK
case II -1267 -293 (HANGER 5) = -1560 ( 4000 PSI OK
I 'l'EMPCIlARY -1267 + 20% -293 = -1813 ( 5500 PSI OK
I (LCX:AL)
CASE I -753 -753 -753 -753 -753 -753 -753 -753 -753
CASE II -489 -489 -489 -489 -489 -489 -489 -489 -489
I FINAL I -2680 -3296 -3618 -3837 -3907 -3852 -3692 -3472 -3273
FINAL II -2075 -2466 -2745 -2846 -2847 -2783 -2664 -2516 -2391
I
72
I
TABLE 5. 19 - OED< STRESSES a:Jl'l'Oo1 LINE "A"
(PSI) I
~er lDc-> 0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9
I
SIMP DL 162 41 49 52 56 59 61 63 63
TEMPERA'lURE
LL+I TENS
217
223
205
305
165 177
387 453
199 214
483 467
226
426
234
352
238
266 I
LL+I mtP -39 -250 -367 -440 -463 -440 -387 -309 -232
'lUl'AL
-----------------------------------------------------
-1267 -1267 -1267 -1267 -1267 -1267 -1267 -1267 -1267
I
MAXDlJM ru!PRESSIOO OlEn<
-------------------------
I
SERVICE IJ:W) (NO LOCAL)
CASE I (-I
CASE II (-)
123 -209
340 -4
-318
-153
-388 -407* -381
-211* -208 -167
-326
-100
-246
-12
-169
69
I
case I
~y
-1033
-1033
-407 (HANGER 4)
+ 20% -407
= -1440 < 3200 PSI
= -1647 < 4400 PSI
OK
OK
I
case II -1267 -211 (HANGER 5)= -1478 < 4000 PSI OK
~y -1267 + 20% -211 = -1731 < 5500 PSI OK I
TENSIONED VALUE = 1.3 (-1267 + 20 = -1977
FACTORED POOT
FACKRED I.OI\OO
%)
II
FAcr P-T -1977 -1977 -1977 -1977 -1977 -1977 -1977 -1977 -1977
CASE I (-)
CASE II (-)
126 -489 -732 -885 -931 -876 -759 -587 -421
442 -6 -199 -274 -271 -217 -130 -15 89
I
(LOCAL)
CASE I -753 -753 -753 -753 -753 -753 -753 -753 -753
I
CASE II -489 -489 -489 -489 -489 -489 -489 -489 -489
SIMP DL 12 87 87 89 90 92 93 93 93
I TEMPERA'IURE
LL+I TENS
7
58
8 149 191
203 334 401
219 242
426 406
259
357
270
285
276
223
LL+I a:MP -10 -246 -377 -453 -473 -453 -396 -319 -256
I SERVICE LOAD (NO IJX:AL )
CASE I (+) 70 290 421 490 516 498 450 378 316
I CASE II (+) 77 298 570 681 735 740* 709 648 592
IJX:AL BENDING
I DL IJX:AL ( +)
LL+I IJX:AL (+)
130
844
130
844
130
844
130
844
130
844
130
844
130
844
130
844
130
844
SERVICE
I CASEI&II 974 974 974 974 974 974 974 974 974
PC6T-TENSIOOING
I ---------------
RmJLAR -740 -740 -740 -740 -740 -740 -740 -740 -740
IJX:AL -974 -974 -974 -974 -974 -974 -974 -974 -974
I 'lUI'AL
-----------------------------------------------------
-1714 -1714 -1714 -1714 -1714 -1714 -1714 -1714 -1714
I MAXIM.JM CDlPRESSIOO
-------------------------
OID::K
I case I
~y
-1714 -383 (HANGER 4)
-1714 + 20% -383
= -2097
= -2440
<
<
3200
4400
PSI
PSI
OK
OK
case II -1714 -173 (HANGER 5) = -1887 < 4000 PSI OK
I ~y -1714 + 20% -173 = -2230 < 5500 PSI OK
I (IJX:AL)
CASE I -1997 -1997 -1997 -1997 -1997 -1997 -1997 -1997 -1997
CASE II -1266 -1266 -1266 -1266 -1266 -1266 -1266 -1266 -1266
I FINAL I -4676 -5091 -5374 -5537 -5578 -5533 -5408 -5240 -5104
FINAL II -3927 -4136 -4122 -4165 -4152 -4094 -3997 -3881 -3792
I
74
I
TABLE 5.21 - OED< STRESSES a::::tI'KM LINE ''Btl
(PSI) I
Hanger I.oc - > 0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9
I
SIMP DL 24 59 62 66 70 73 74 76 76
TEMPERAWRE
LL+I TENS
-10
29
184 164
227 256
172 184 195
285 299 294
203
270
208
250
211
223 I
LL+I <nIP -63 -88 -154 -193 -207 -198 -164 -125 -92
'lUl'AL
-----------------------------------------------------
-1714 -1714 -1714 -1714 -1714 -1714 -1714 -1714 -1714 I
MAXlMJM a:MPRESSICN <lim<
------------------------- I
smVICE LOI\D (NO LOCAL)
CASE I (-)
CASE II (-)
-39 -29
-49* 155
-92
72
-127
45
-137* -125
47 70
-90
113
-49
159
-16
195
I
case I
~y
-1714
-1714
-137 (HANGER 4)
+ 20% -137
= -1851
= -2194
(
(
3200
4400
PSI
PSI
OK
OK
I
case II -1714 -49 (HANGER 5) = -1763 ( 4000 PSI OK
~y -1714 + 20% -49 = -2106 ( 5500 PSI OK I
FACTORED PCST TENSIONED VALUE = 1.3 (-1714 + 20 %) = -2673
FACImED LOAC6
I
FACT P-T -2673 -2673 -2673 -2673 -2673 -2673 -2673 -2673 -2673
CASE I (-)
CASE II (-)
-104 -113 -254 -333 -358 -333 -259 -172 -100
-63 202 93 58 61 92 147 206 254
I
(LOCAL)
CASE I -1997 -1997 -1997 -1997 -1997 -1997 -1997 -1997 -1997
I
CASE II - 1266 -1266 -1266 -1266 - 1266 -1266 -1266 -1266 -1266
FINAL I -4775 -4783 -4924 -5003 -5028 -5003 -4930 -4843 -4770
I
FINAL II -4002 -3737 -3846 -3881 -3878 -3848 -3792 -3733 -3685
I
.::> 75
I .....-
'0 TABLE 5.22 - DEn< S'IRFSSFS 'lOP LINE "C"
I (PSI)
Hanger Loc -) 0 1 2 3 4 5 6 7 8
I SIMP DL 17 50 74 80 83 84 85 86 86
TEMPERA'lURE -38 -89 130 188 218 241 257 269 275
I IL+I TENS
IL+I a::MP
78 96
-29 -242
193 252 270 256
-324 -381 -396 -371
217 164 131
-334 -280 -246
CA'>E I & II 974 974 974 974 974 974 974 974 974
I FOOT-TENSIauNG
---------------
I RmJLAR
I.O:AL
-615
-974
-615
-974
-615
-974
-615
-974
-615
-974
-615
-974
-615
-974
-615 -615
-974 -974
-----------------------------------------------------
I 'lUl'AL -1589 -1589 -1589 -1589 -1589 -1589 -1589 -1589 -1589
= -1902
I Case I
'1'EMl'C:RARY
-1589
-1589
-313 (HANGER 41
+ 20% -313 = -2124
<
<
3200
4400
PSI
PSI
OK
OK
Case II -1589 -281 (HANGER 51 = -1870 < 4000 PSI OK
= -2188
I TEMPCRARY -1589 + 20% -281 < 5500 PSI OK
I (I.O:ALI
CA'>E I -1997 -1997 -1997 -1997 -1997 -1997 -1997 -1997 -1997
CASE II -1266 -1266 -1266 -1266 -1266 -1266 -1266 -1266 -1266
I FINAL I -4517 -4935 -5081 -5197 -5226 -5171 -5088 -4969 -4897
FINAL II -3809 -4110 -3900 -3891 -3868 -3804 -3734 -3646 -3595
I
76
I
TABLE 5.23 - DEO< S'ffiESSES roI'l'CM LINE "e"
(PSI) I
Hanger I.oc -)
SIMP DL
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9
I
19 38 60 68 73 75 77 78 78
TEMPERA'IURE
ILtI TENS
-5
19
170 136 175 197
270 299 319 328
212
328
224
314
232 235
295 280 I
ILtI a:MP -58 -92 -159 -207 -217 -202 -174 -140 -121
'IOTAL
-----------------------------------------------------
-1589 -1589 -1589 -1589 -1589 -1589 -1589 -1589 -1589 I
MAXIM.JM CDlPRESSICN OlEn<
------------------------- I
SERVICE l.OI\D (NO I.CX:AL)
CASE I (-)
CASE II (-)
-39 -54
-44* 116
-99
37
-139
36
-144* -127
53 85
-97
127
-62
170
-43
192 I
case I
TEMPCRARY
-1589
-1589
-144 (HANGm 4) = -1733 <
+ 20% -144 = -2051 <
3200
4400
PSI
PSI
OK
OK I
Case II -1589 -44 (HANGm 5) = -1633 < 4000 PSI OK
TEMPCRARY -1589 + 20% -44 = -1951 < 5500 PSI OK
I
FACTORED FOOT TENSIONED VALUE = 1.3 (-1589 + 20 %) = -2478
FACTORED IJ:lI\OO I
FACf P-T -2478 -2478 -2478 -2478 -2478 -2478 -2478 -2478 -2478
CASE I (-)
CASE II (-)
-102 -150 -266 -361 -375 -339 -277 -203 -161
-58 151 49 46 69 111 165 220 250
I
(I.CX:AL)
CASE I -1998 -1998 -1998 -1998 -1998 -1998 -1998 -1998 -1998
I
CASE II -1266 -1266 -1266 -1266 -1266 -1266 -1266 -1266 -1266
FINAL I -4578 -4626 -4742 -4837 -4852 -4816 -4753 -4679 -4637
I
FINAL II -3803 -3594 -3696 -3699 -3676 -3634 -3580 -3525 -3495
I
.
I ·~
1.:0
.)
77
1 5.8.1 General
Cbncrete -
I fc' = 8000 psi
Density = 150 pef
I Young's Modulus = 5700 ksi
Allowable strand anchorage = 3000 psi.
I
78 I
5.8.2 Deck I
Post tensioning in the deck is divided into two parts. Q1e
part is used to IX'St tension the deck for local berrling stresses I
due to dead and live load. '1llee seo:xld part is used to post tension
for overall tensioo forces in the deck. CNerall forces are due
to superimposed dead load, tanperature and live loads. Post I
tensiooing for local m::rnents is placed eccentrically ooe sixth
the depth of the deck toward the tensile stress. At floor beams
the local berrli03 m::rnent is negative so the strand would be located I
t/6 above the center of gravity of the deck. By p.1tting strand
at this locatioo, a canpressive stress is irrluced on ooe side
equal to (2t/9)*Force. 'llle other side has zero cx:mpression.
I
'llle ranainin:J strand is placed at the center of the deck.
Assumpticns:
I Para. 9.16.2.1
I
I
I
I
, ....
.... 81
I
, CASE I
CASE II
0. 95*8000 > 1. 3(DL + 5/3 (LL+I ))
0.95*8000 > 1.3(DL + T + (LL+I))
,
Service
Before l osses
I CASE I
o::ncrete
I Ccmpression
0. 55*8000 = 4400 > DL + (LL+I) + Post tension*1.20
Tension = 0. 0
I CASE II
a:ncrete
I Ccmpression
0. 55*8000*1 . 25 = 5500 ) DL + (LL+I) + T + Post tension*1.20
Tension = 0.0
I steel 0. 7*270000 = 189000 psi before losses
I
, After Losses
o::ncrete
I
82 I
losses.
~termine the level of stress permitted in the stram before I
Final stress must be less than 172800 psi. I
Loss of prestress in steel = 37810 psi.
I Line "e"
"e"
I Since line
same.
is nearly the same as line ''B'', make the
----------------------------------------
I Total stram weight in deck
I Line
A
Ux::al
1. 5
Overall
10
Total
11.5
B 2. 5 8. 5 11.0
I e 2.5
Total
8.5 " .0
33 . 5 strand/ft
I
other Ccnsideratioos
I
I
I
I
I
I
I
I
I
I
I
86 I
6.0 Conclusions
I
It is the intent of the study to investigate design options
which may lead to more practical tied arch bridges. Based upoo
I
this design study, it appears that the ideas suggested warrant
further consideratien.
I
'!he total weight of the proposed structure is cnly slightly
IOClre than the conventional design. The steel weight of the
alternate is much less than that of the original design. '!he
I
arch ribs increased fran a.i:loot 1.7 million poUIXls to a.i:loot 1.85
million pounds. '!he arch bracing stayed the same at a.i:loot 925
t:OOusaOO p:>unds. The tie beams decreased fran a.i:loot 1.6 million
I
poUIXls to zero. '!he floor systan is decreased fran a.i:loot 2 million
poUIXls to atout 930 tOOusand p:>unds. I
'!he 8000 psi concrete strength is higher than that camonly
used in present practice. However, 8000 psi concrete is being
used on the Fast Huntington Bridge in West Virginia with no
I
rep:>rted prdllems (Ref.3). However, the analyses irrlicate that
6000 psi concrete ~d be adequate for this instance. I
'!he use of 15 inch thick deck at the tie beams appears to
be excessive. Shear lag appears to be critical cnly at the ends
of the span. It seems rea.scnable to expect that a 9 inch deck
I
with a large chamfer could be used over the entire span with
the exceptien of the ends of the span near the arch ribs. At
these locations a deck thickness of 15 inches is recamerrled.
I
'!hese p:>rtions are cast in-place so special deck units are not
required. 'Ibis IOCldification would further reduce weight. '!he
use of a cx::rrp:l5ite steel plate en the bottan of the deck in
I
these regions has been used for shear transfer in Germany (Ref. 4) •
SUch a cllar¥3e ~ further reduce structure weight. I
Erection of the arch ribs by rotating than into p:>sition
am splicing than has significant benefits in erection time am
freedan fran falsework obstructing water traffic. '!he erection
I
procedure was rep:>rted for a concrete arch bridge in Germany(Ref.1).
'!here the engineers felt that the method was econcmical for longer
spans.
I
Another configuration of the deck was examined where the
stiffness was less than that of the cases rep:>rted. An important
I
relationship between deck stiffness am arch rranents was evident.
As the deck becanes stiffer, arch live load rranents decreases.
'!he reascn for this is that the parabolic arch is designed for
I
a uniform load. If the deck equalizes the loads, the rranent
in the arch will be snaller, permitting thinner arch ribs. I
I
I~ 87
I '!be normal tied arch bridge deperrls ooly en the tie beam for
stiffness whereas the suggested method utilizes the entire deck
I stiffness . '!be tie beams were made 9 feet deep ~ to 11
feet en the original design . 'Ihis reductien in stiffness was
rrore than balanced by the aalitien of the deck. A greater depth
I would have reduced the rrcrnent in the arch rut the arch was cc:ntr-
olled by the erectien so no benefit would have resulted . '!be
reduced depth would lead to a decrease in wind loading .
I Since the deck is integral with the tie beam , lateral loads
may be resisted by the deck and tie beams . 'Ihls permitted the
I eliminatien of two levels of diagc:nal bracio:J required in the
original design.
I '!be use of the dead load tie cable and the {XlSt tensioned
tie beams insures that the ties are not fracture critical. '!bey
further simplify construction by reducir¥J the amount of field
I 001 tio;J .
I
I
I
I
I
I
I
I
I
88
I
7. 0 Acknowledgements
I
'lhls ~k was initiated at the request of the lvnerican Institute
of Steel Constructioo who fuOOed a portion of the ~k for which
I
we are greatful. '!hey al so provided the design drawings for
the original design fran which the alternate design was derived .
'!he interest aOO encouragement of AISC staff are also appreciated .
I
'!here have been fruitful discussions with several design
consultants concerning this ~k . Particularly helpful was the
I
finn of Al:vid Grant & Associates whan we learned, t:.c:Mard the
em of the ~k , had designed a bridge not dissimilar to that
proposed . Unfortunately , for various reasons not related to
I
the adequecy of the design , the structure was not bJilt.
I
'!he figures were drawn by G. !:avid Brierley~ of ESDI
who also reviewed the entire manuscript aOO made flUII'eI'OUS oootrib-
uticns . Lon B. VanFossen of ESDI produced the carrputer runs, I
made the carrputer rrodels used aOO reviewed the n.anuscript.
I
I
I
I
I
I
I
I
I
I
I
89
8.0 Bibliography
I
1. "Arch halves fall, making pivotal link in Germany"
I Engineering News Record, June 13, 1985.
1
1
I
1
1
1
1
I
I
I
I
I
I
I
I
I
I