Maintenance Management System Guideline For Maintenance Operating Procedures Extraordinary Maintenance
Maintenance Management System Guideline For Maintenance Operating Procedures Extraordinary Maintenance
Maintenance Management System Guideline For Maintenance Operating Procedures Extraordinary Maintenance
Page
Extraordinary Maintenance
ABSTRACT
This guideline supports the activities to perform Extraordinary Maintenance both for Budget definition and for extra Budget
phase.
Documento riservato di proprietà di Eni S.p.A.- Divisione Exploration & Production. Esso non sarà mostrato a Terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni S.p.A. – Exploration & Production Division. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
MODIFICATION SHEET
Rev. 01 Revised “Glossary” and “Fig. 2.1.1: Workflow Map” in order to reflect the inclusion of the “Minor
Corrective Maintenance” type
Eni S.p.A. Document Class: Doc. N°. Rev. Page
FOREWORD
The presented maintenance flows are described according to the “Guidelines for organisational charts”
[SVI.DMS.GL.0001] and “Guidelines for job description” [SVI.DMS.GL.0002] of the new Development
Projects/Production Fields.
The Maintenance Management System is part of the Technology Management System (TMS).
Eni S.p.A. Document Class: Doc. N°. Rev. Page
TABLE OF CONTENTS
MODIFICATION SHEET............................................................................................................. 2
FOREWORD ............................................................................................................................... 3
ACRONYMS ............................................................................................................................... 5
JOB ACRONYMS ....................................................................................................................... 5
GLOSSARY ................................................................................................................................ 6
KEY TO WORKFLOW ................................................................................................................ 8
1. INTRODUCTION ............................................................................................................ 9
2. GUIDELINE OBJECTIVE AND SCOPE...................................................................... 10
2.1 OBJECTIVES ............................................................................................................... 10
2.2 SCOPE ......................................................................................................................... 12
2.3 APPLICABILITY ........................................................................................................... 12
3. REFERENCES ............................................................................................................. 13
4. WORKFLOW DIAGRAM ............................................................................................. 14
4.1 EXTRAORDINARY MAINTENANCE WORKFLOW .................................................... 14
4.2 EXTRAORDINARY MAINTENANCE EXTRA BUDGET .............................................. 14
5. WORKFLOW STEPS DESCRIPTION ......................................................................... 17
6. RESPONSIBILITY MATRIX SUMMARY..................................................................... 19
Eni S.p.A. Document Class: Doc. N°. Rev. Page
ACRONYMS
JOB ACRONYMS
GLOSSARY
KEY TO WORKFLOW
step code job acronym Stands for intellectual or manual process. In the upper-left
corner, the step code is placed, while in the upper right corner
Intellectual or manual
process the job acronym is placed. The box colour of step code and job
acronym depends on the main job involved (see table below).
step code job acronym Stands for a process that could be performed by CMMS means
or by CMMS itself (i.e. WO automatic generation). The box
CMMS process colour of step code and job acronym depends on the main job
involved (see table below).
step code
Stands for a macro-process. In the upper-left corner, the subject
macro-process
detailed procedure code is placed, while the upper right corner
is blanketed.
linked
procedure Stands for a reference link to the mentioned procedure.
linked
step
Stands for a reference mark made for the step mentioned within
the on-going procedure.
PSMG
GMG OFMG
MRSI
OMG FPCO
HSEQ
1. INTRODUCTION
This document supports a specific element of the Maintenance Management System. The Maintenance
Management System has been developed to provide a comprehensive and structured set of knowledge
and an integrated framework to manage maintenance activities, thus ensuring effective and efficient use
of the Company’s resources.
The set of procedures of Maintenance Management System describes in detail the steps to be executed
in order to perform relevant activities with the eventual support of CMMS.
This document is written as a guideline and therefore represents recommended format and content
rather than a mandatory, prescriptive procedure. Individual projects may deviate from, or modify the
typical contents described here, wherever such deviations are appropriate to fit in the organizational
structure.
This document is managed by O&M Project Team, all the changes of and contributions to this document
will be shared with and validated by O&M Project Team and a new release of this document will be
issued by O&M Project Team.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
2.1 OBJECTIVES
• To describe the workflow to perform Extraordinary Maintenance activities both for Budget definition
and for extra Budget phase.
• To define responsibility, interfaces and methods to be followed in the Extraordinary Maintenance
application.
The actions for execute and complete Extraordinary Maintenance will be developed as a case of work
management procedure.
On the overall maintenance workflow map, depicted on the next page, this guideline is represented by
the boxes with a bold outline.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
start
Extraordinary
Maintenance
start
Modifications &
Improvements
Emergency?
no start
yes
yes finish
Work scheduling
yes
Maintenance
strategy review
Urgent Work
Request & Work Work execution
Order creation
Maintenance Continuous
Reporting improvement
start start
Data base
Maintenance Master data
Budget updating
management
Management
finish
start start
Global Maintenance
Maintenance Processes
Services
finish finish
2.2 SCOPE
The scope of the Extraordinary Maintenance Procedure, described within this document, is to identify the
flow of actions that must be performed in order to satisfy the need to perform a maintenance event of
extraordinary type in terms of economic impact. The extraordinary maintenance can be planned and
forecasted into budget or can be performed as an extra budget work.
2.3 APPLICABILITY
The procedure described in this document is referred to the production phase of the facilities.
The present procedure shall be applied to any organization (external entity or internal department) in
charge of managing and executing Maintenance activities in any Production Unit, onshore or offshore,
fully owned by ENI E&P division or managed in joint venture with other partners.
Therefore, this procedure utilizes the organization chart, the job titles and the responsibilities and duties
described for these Production Units in ENI documents: SVI.DMS.GL.0001 “Guideline for Organizational
charts” and SVI.DMS.GL.0002 “Guideline for Job Descriptions”.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
3. REFERENCES
4. WORKFLOW DIAGRAM
start
5.01 POSI/MOSI
Procedure 1
Master Data
5.02
Management
The work is
to be charged to a No The Extraordinary
Cost Centre? Maintenance work
managed as a project Procedure 2
Preventive
Yes Maintenance
5.03 POSI
finish
Creates a Work Request
for Extraordinary
Maintenance
5.04 FPCO
5.05 MPSV
5.06 MPSV
5.07
Is it
Extraordinary Yes an extra Budget
Maintenance extra work?
Budget
5.07.01 No
5.08 Procedure 8
Maintenance
Extraordinary Budget
Maintenance for Budget
Management
5.07.07
5.09
Procedure 6
Continue with Work Work
Management Procedure Management
finish
5.07
5.07.01 POSI
Submits the budget for
extraordinary
maintenance to OFMG’s
approval
5.07.02 OFMG
Yes
5.07.03 OFMG
Verifies the possibility to
delay other works, inside
his competence field,
planned in budget
5.07.04 OFMG
Yes 5.07.04.01
5.07.05 OFMG
5.07.06 MESI
Updates Budget
5.07.07 MPSV
5.09
Eni S.p.A. Document Class: Doc. N°. Rev. Page
5.07.04
5.07.04.01 OMG
Yes
5.07.04.02 OMG
Can be delayed ?
No
5.07.04.03 OMG
Yes
5.07.04.04 OMG
5.07.06
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
5.01 POSI/MOSI Detects the necessity of extraordinary maintenance.
5.02 - Based on internal cost definition, the work can be charged at Cost
Centre level or at project level. The Extraordinary Maintenance
work can lead to a database updating and/or a preventive
maintenance modification. The work related to a project is not
covered into these procedures.
5.03 POSI POSI creates a work request into CMMS identifying the item,
describing the type of intervention required and the date of
required intervention.
5.06 MPSV Calculates in CMMS and analyses the estimated costs for each
work order of extraordinary maintenance.
5.07.03 OFMG Verifies the possibility to delay other works in budget for the
pertaining field in order to create economic disposal.
5.07.04 OFMG If it’s not possible to delay other works in budget for the field,
submits to OMG the request to delay works in budget for other
fields.
5.07.04.02 OMG Verifies the possibility to delay other works in budget for the other
fields.
5.07.04.03 OMG If it’s not possible to delay other works in budget for the other
fields, OMG add cost amount into Forecast. If the Forecast is not
approved, it stops the procedure.
5.07.06 MESI MESI update budget in order to implement the approved changes.
The updating activity is performed with the help of an informatics’
tool.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
5.07.07 MPSV MPSV delays planned works in CMMS in order to implement the
approved changes.
EVERY
OFMG
code
PSMG
DMSV
step
MPSV
MESV
CRSV
FPCO
EXEC
PPSV
MOSI
MRSI
MESI
POSI
OMG
GMG
Step description