Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Boq (Civil)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

B.O.

Q FOR CIVIL PART UP TO PLINTH LVL FOR SHED _ SUBASH JI


PROJECT NO. = S/PEB/20-146
DRAWING NO. = F-01 / F-02
ROAD LVL / NATURAL GROUND LVL = ± 0 m
EXCAVATION LEVEL FOR FOOTING FROM R.L/N.G.L = - 1.75 m
FLOOR FINISH LVL FROM R.L/N.G.L = + 0.75 m

(A) CIVIL WORK


Approx
S.NO. ITEM DES. NOS. L(m) B(m) H(m) QTY. UNIT AMOUNT
RATE

1 EXCAVATION & BACK FILLING F-1 10 3.40 2.95 1.75 175.53


F-2 6 2.60 2.30 1.75 62.79
238.32 CUM

2 PCC(1:4:8) F-1 10 3.10 2.65 0.10 8.22


F-2 6 2.30 2.00 0.10 2.76
under Periphery Plinth beam 1 109.00 0.40 0.10 4.36
15.34 CUM

3 RCC(M-25) F-1 10 2.90 2.45 0.45 31.97


F-2 6 2.10 1.80 0.45 10.21
P-1 6 0.90 0.45 2.40 5.83
P-2 4 0.90 0.68 2.40 5.83
P-3 6 0.60 0.30 2.40 2.59
Plinth-beam(PB1)L/S 2 27.45 0.30 0.60 9.88
Plinth-beam(PB1)S/S 2 27.45 0.30 0.60 9.88
Tie-beam(TB1)L/S 2 27.45 0.23 0.23 2.90
Tie-beam(TB2)S/S 2 27.45 0.23 0.23 2.90
Wall column 16 0.23 0.23 3.00 2.54
84.55 CUM

4 SHUTTERING F-1 10 10.70 0.45 48.15


F-2 6 7.80 0.45 21.06
P-1 6 2.70 1.95 31.59
P-2 4 3.15 1.95 24.57
P-3 6 1.80 1.95 21.06
Plinth-beam(PB1)L/S 2 54.90 0.60 65.88
Plinth-beam(PB1)S/S 2 54.90 0.60 65.88
Tie-beam(TB1)L/S 2 54.90 0.23 25.25
Tie-beam(TB2)S/S 2 54.90 0.23 25.25
Wall column 16 0.92 3.00 44.16
372.86 SQM

5 REINF. STEEL
8# ____ Kg
10# ____ Kg
12# ____ Kg
16# ____ Kg
0.6 kg/sqft of total area i.e. 8100x0.6 = 4860 Kg

7 BRICK-WALL(9" THK) Long Side 2 27.45 3.00 164.70


Short Side 2 27.45 3.00 164.70
329.40 SQM

8 PLASTER(1:6) Long Side(inner/outer) 4 27.45 3.00 329.40


INNER/OUTER Short Side(inner/outer) 4 27.45 3.00 329.40
658.80 SQM

9 SOIL FILLING Within Box area only 27.45 27.45 0.38 282.56
282.56 CUM

10 G.S.B(6")+W.M.M(3" THK) Within Box area only 1 27.45 27.45 753.50


753.50 SQM

11 V.D.C (5" THK) Within Box area only 1 27.45 27.45 753.50
With Joint Cutting& Filling 753.50 SQM

You might also like