Jimmy D Kumana, Consulting Engineer, Houston, Texas
Jimmy D Kumana, Consulting Engineer, Houston, Texas
Jimmy D Kumana, Consulting Engineer, Houston, Texas
Equations: Equations:
1. Steam gen = capacity x operating rate 1. Power, kw = output rate x steam flow
2. Blowdown = fraction x steam gen rate 2. Hs,o = Hs,i – 3412/kw
3. Feedwater = stm gen + blowdown 3. To = f(Po, Hs,o), from steam props data base
4. Hs = f(P,T), from steam properties data base
5. Fuel input = Stm (Hs – hBFW)/η Back-pressure steam turbine (rigorous)
Operating mode = swing, variable efficiency Input parameters = Pi, Ti, Po, power output required,
linked to process model, turbine performance curve
Input parameters = max operating capacity, operating (from manufacturer’s data) that expresses the steam
pressure and temp, blowdown rate (as % of steam flow rate as a function of power output for the given
generation) Pi, Ti, and Po.
Equations: Equations:
1. Steam gen = Total steam production required 1. Steam flow = f(required power output)
(trial value in overall computational algorithm) – 2. Hs,o = Hs,i – 3412/kw
combined steam generated in all other boilers 3. To = f(Po, Hs,o), from steam props data base
2. Blowdown = fraction x steam gen rate
3. Feedwater = stm gen + blowdown Deaerator
4. Hs = f(P,T), from steam properties data base
5. Operating rate (%) = Stm gen / Capacity Operating mode = steady state (see Figure 2)
6. Efficiency η = f(operating rate), equation to be
provided by user, from manufacturer’s data Input parameters = condensate flow and temp from
7. Fuel input = Stm (Hs – hBFW)/η process, condensate flow and temp from condensing
steam turbine, economizer duty, pressure of steam
Boiler model 3 (rigorous) used in economizer, DA operating pressure, temp of
makeup water (after preheating), vent vapor flow
Operating mode = base load from DA
Deaerator
Deaerator Mixed condensate
tank
BFW pump
Process heat recovery
Cold DI water
makeup
If the swing fuel were gas, however, then the cost One must keep in mind that the foregoing
savings would be $910/yr, which is more typical, and conclusions are valid only for the fuel/power costs
would be accomplished by shutting down package and equipment capacity/efficiency numbers that have
boilers #5 and 6. The model shows that nearly a been used. Under a different set of technical and
million dollars a year (including maintenance and economic conditions, the optimum operating policy
operating labor cost savings) could be achieved by could be quite different. The estimated cost savings
minimizing flow through the condensing section of and key parameters for all of the various projects
the turbines, at zero capital cost. discussed above are summarized in Table 1.
Case Number
0 1 2 3 4 5 6 7 8
Economizer duty, MMBtu/h 10 10 10 30 0 10 10 10 10
Condensate recovery, % 56 56 56 56 56 70 70 70 70
DA feedwater temp, F 73 73 73 73 73 73 150 150 150
Heat rec into DFW, MMBtu/h 0 0 0 0 0 0 31.5 26.7 26.7
Process LP steam savings, Klb/h 0 0 0 0 0 0 0 200 200
Total boiler steam gen, Klb/h 1591 1479 1477 1494 1468 1439 1380 1270 1162
Total power generated, MW 76.2 66.1 66.1 66.6 65.6 63.9 60.6 48.1 61.7
Operating cost, MM$/yr 17.22 17.85 16.31 16.32 16.32 15.91 15.61 14.56 16.93
Cumulative savings, MM$/yr 0 -0.63 0.91 0.90 0.90 1.31 1.61 2.66 0.29
Incremental savings, MM$/yr 0 -0.63 1.54 -0.01 0.00 0.41 0.30 1.05 -2.37
Note: Numbers in BOLD in the table are the primary changes made in each case listed.
15
14 0.6
13
12 0.4
0 50 100 150 200 250 300