Design and Optimization of Steam Distribution Systems For Steam Power Plants
Design and Optimization of Steam Distribution Systems For Steam Power Plants
Design and Optimization of Steam Distribution Systems For Steam Power Plants
pubs.acs.org/IECR
ABSTRACT: This paper presents a systematic methodology for the design of a steam distribution network (SDN) which satisfies
the energy demands of industrial processes. A superstructure is proposed to include all potential configurations of steam systems,
and a mixed-integer nonlinear programming (MINLP) model is formulated accordingly to minimize the total annualized cost. The
proposed model determines simultaneously (i) the structure and operational configuration of a steam system and (ii) the interaction
between the steam system and the heat recovery system. A series of case studies are presented to demonstrate the feasibility and
benefit of the proposed approach.
r 2011 American Chemical Society 8097 dx.doi.org/10.1021/ie102059n | Ind. Eng. Chem. Res. 2011, 50, 8097–8109
Industrial & Engineering Chemistry Research ARTICLE
pressure levels are selected at saturated steam pressure corre- entering the boiler b in a certain period p (fbfw bp ) equals the
sponding to the minimum temperature requirements. Specifi- steam to the steam header i (fbip) and the effluent of blowdown
cally, values not less than their saturated temperatures are bip ). Therein the blowdown is treated as a fixed j
water (fbd
suitable for choices of steam headers. The operating tempera- fraction of the boiler steam output and extracted at saturated
tures of headers are treated as decision variables to be optimized. liquid conditions (see Figure 2a). An energy balance is needed
For the simultaneous design of SDN and HEN, the level and the to ensure that the enthalpy entering the boiler equals that
amount of steam demands are not given. Both pressures and leaving (i.e., eq 2), where qbp denotes the heat absorbed by the
temperatures of headers are variables to be determined by the water stream.
optimization approach. X X
There are three types of power-generating devices in the
bfw
fbp ¼ fbip þ bd
fbip "b ∈ B, p ∈ P ð1Þ
i∈I i∈I
superstructure for satisfying power demands, i.e., gas turbines,
steam turbines, and electric motors. Turbines can generate X X bd sat, l
electricity or mechanical power. A gas turbine includes a com-
bfw deaer
fbp H þ qbp ¼ fbip hbip þ fbip Hi "b ∈ B, p ∈ P
pressor, a combustor, and a turbine, where the hot air exiting the i∈I i∈I
as heat input, the corresponding relations are derived below. headers. This device converts the energy of steam into
X power. Equations 23 and 24 describe the constraints to
fgp ¼ fgbp "g ∈ G , p ∈ P ð8Þ ensure that the operation does not exceed its design capa-
b ∈ HB cities. Moreover, it is possible to define a minimum partial
X load of units so that the actual output is not less than a given
Tgp ¼ Tgbp "g ∈ G , p ∈ P ð9Þ specified fraction.
b ∈ HB
Ω ii0 t zii0 tp e fii0 tp e Ωii0 t zii0 tp "i, i0 ∈ I , i < i0 ,
A gas turbine can generate electricity (g ∈ GE) or shaft power
(g ∈ GS ). If the latter operation is chosen, then the produced t∈T , p∈P ð23Þ
shaft power wgp is selected to meet the shaft demand j.
X Γ ii0 t zii0 tp e wii0 tp e Γii0 t zii0 tp "i, i0 ∈ I , i < i0 ,
wgp ¼ wgjp "g ∈ GS , p ∈ P ð10Þ
j∈J t∈T , p∈P ð24Þ
The following constraints are considered to reflect physical and The steam turbine can generate electricity (t ∈ TE) or shaft
practical limitations of the equipment. Equations 11 and 12 define power (t ∈ TS ). If the latter operation is chosen, the shaft power
the unit capacity that must comply with the maximum and minimum produced by the turbine t is to meet the shaft demand j.
X
limits. Equation 13 limits the operation range of a temperature. wii0 tp ¼ wii0 tjp "i, i0 ∈ I , i < i0 , t ∈ TS , p ∈ P
Ω g zgbp e fgbp e Ωg zgbp "g ∈ G , b ∈ HB, p ∈ P ð11Þ j∈J
ð25Þ
Γ g zgjp e wgjp e Γg zgjp "g ∈ G , j ∈ J , p ∈ P ð12Þ
Γ ii0 t zii0 tjp e wii0 tjp e Γii0 t zii0 tjp "i, i0 ∈ I , i < i0 ,
Φ g zgbp e Tgbp e Φg zgbp "g ∈ G , b ∈ HB, p ∈ P ð13Þ t ∈ TS , j ∈ J , p ∈ P ð26Þ
Similar to the relation between a boiler and a steam header, Also, operation for multiperiod problems should be consid-
eqs 1418 describe the connection and operation between a gas ered, which is like the boiler and gas turbine units discussed
turbine and a HRSG. If a gas turbine is chosen, a corresponding previously. Equations 27and 28 are the constraints of steam
HRSG is automatically included, and vice versa. turbines.
X zii0 t g zii0 tp "i, i0 ∈ I , i < i0 , t ∈ T , p ∈ P ð27Þ
zg ¼ zgb " g ∈ G ð14Þ
b ∈ HB X
X zii0 t e zii0 tp "i, i0 ∈ I , i < i0 , t ∈ T ð28Þ
zb ¼ zgb " b ∈ HB ð15Þ p∈P
g∈G Similar to a gas turbine, constraints for the pair between steam
turbines and shaft demands are presented in eqs 2931.
zgb g zgbp "g ∈ G , b ∈ HB, p ∈ P ð16Þ X
X zii0 t ¼ zii0 tj "i, i0 ∈ I , i < i0 , t ∈ T ð29Þ
zgb e zgbp "g ∈ G , b ∈ HB ð17Þ j∈J
p∈P
X
X fpw Hpw þ fip hip þ fpc hcp
zii0 t e 1 "i0 ∈ I , t ∈ MT ð34Þ
i∈I
i∈I
!
i < i0
X X
¼ bfw
fbp þ fipld H deaer "p ∈ P ð42Þ
The decomposition of a multistage steam turbine is shown in b∈B i∈I
Figure 4, and the corresponding superstructure is shown in
Figure 2e. A multistage steam turbine is decomposed into several
4.1.5. Steam Headers. Figure 2g shows the stream balance for a
single-stage turbines which are connected in series so that the
steam header. The mass balance is given by eq 43. For the top
original single-stage equipment performance model can be used
steam header, the highest pressure steam header, there are no
to determine its properties without new model. Equations 35 and
input streams from steam turbines or let-down stations, and there
36 describe the mass balance of a multistage steam turbine, where
is no output vented steam to the environment. The bottom steam
the higher quality steam (f0 ii0 tp) flows through a multistage
header is a condensing header, in which its flow rates of input
turbine t and then lower quality steam is delivered to a header
streams from let-down stations or back-pressure steam tur-
i0 (fii0 tp) and to the next stage i00 (fii0 i0 0 tp) as its steam input (f0 ii0 0 tp).
X
bines are zero and its output condensate water is sent to a
"i, i0 ∈ I , i < i0 , t ∈ MT , p ∈ P
0
fii0 tp ¼ fii0 tp þ fii0 i00 tp deaerator. Equation 44 is an energy balance for a header to
i00 ∈ I
ensure that the total amount of enthalpy entering the header
i < i0 < i00 equals that leaving. It should be noted that a variable for
enthalpy hip (hip = fn(Ti,Pi)) is employed because of the
ð35Þ flexible consideration.
0
X X X X X
fii00 tp ¼ fii0 i00 tp "i, i00 ∈ I , i < i00 , t ∈ MT , p ∈ P fbip þ fi0 itp þ fi0 ip þ fipld þ fip
ps
i0 ∈ I b∈B t∈T
i0 ∈ I i0 ∈ I
0 00
i<i <i 0
i <i i0 < i
ð36Þ X X X pd
¼ fii0 tp þ fii0 p þ fip þ fipvent þ fip
The following constraints are considered for this multistage t∈T
i0 ∈ I i0 ∈ I
unit. Equations 3740 are used to ensure that the stage i00 only i0 > i i0 > i
can accept one steam stream from preceding stages and stage i0
only can deliver steam to one next stage. "i ∈ I , p ∈ P ð43Þ
zii0 tp g zii0 i00 tp "i, i0 , i00 ∈ I , i < i0 < i00 , t ∈ MT , p ∈ P ð37Þ X X X X
fbip hbip þ fi0 itp hi0 itp þ ps ps
fi0 ip hi0 p þ fipld H deaer þ fip Hip
X b∈B 0
i ∈I
t∈T 0
i ∈I
zii0 i00 tp e 1 "i, i00 ∈ I , i < i00 , t ∈ MT , p ∈ P i0 < i i0 < i
0 1
i0 ∈ I
i < i0 < i00 B C
B C
B C
B X X X C
ð38Þ ¼B fii0 p þ fip þ fipvent þ fip C
pd
B fii0 tp þ Chip "i ∈ I , p ∈ P
X B
B i0 ∈ I t∈T C
C
0 0
zii0 i00 tp e 1 "i, i ∈ I , i < i , t ∈ MT , p ∈ P @ i0 ∈ I A
i0 > i i0 > i
i00 ∈ I
i < i0 < i00 ð44Þ
ð39Þ
4.1.6. Power Balances. Equation 45 ensures that the actual
0 00 0 00 power delivered by all the drives attached to the common shaft
Ωzii0 i00 tp e fii0 i00 tp e Ωzii0 i00 tp "i, i , i ∈ I , i < i < i ,
meets the corresponding demands in each operating period. A
t ∈ MT , p ∈ P ð40Þ gas turbine g, a steam turbine t, and an electric motor m can be
8101 dx.doi.org/10.1021/ie102059n |Ind. Eng. Chem. Res. 2011, 50, 8097–8109
Industrial & Engineering Chemistry Research ARTICLE
cp Ωzcp e 0
qhu "c ∈ C , p ∈ P ð65Þ
hu Table 1. Site Conditions
total working hours 8600 h/year
fuel oil no. 2 LHV 45 000 kJ/kg
4.2.8. Calculation of Approach Temperatures. For determin-
natural gas LHV 50 244 kJ/kg
ing the area requirement of the heat exchanger, approach
electric prices 0.07 $/kWh
temperatures are used to calculate the log mean temperature
difference (LMTD) approximated by using the Chen equation.13 fuel oil no. 2 price 0.19 $/kg
The area requirement of each match will be incorporated in the natural gas price 0.22 $/kg
objective function. The constraints 6669 are expressed as raw water price 0.05 $/ton
inequalities since the cost of the exchanger decreases with higher
values for the approach temperatures.
Table 2. Demand Data (All in MW) for Case 1
dthckp e thkp tchkp þ Γð1 zhckp Þ "h ∈ H , c ∈ C , period
k∈K, p∈P ð66Þ
1 2 3 4
X d∈D
þ ðzt Cfix
t þ Ct G t Þ
var t γ X X X γ
t∈T þ ðzhck Cfix
hck þ Chck Ghck Þ
var hck
where x2 is a vector of variables, and Ω2 is a feasible searching 5.1. Case 1. SDN Design Problem Associated with Multi-
space delimited by the constraints. period Demands. Let us first consider the SDN design problem
8 9 associated with multiperiod demands in a chemical process. The
>
>
hu
dtcp ; dthckp ; dthp
cu bfw
; fbp ; fbip ; fbip ; fb ; fbup ; fchkp ; fgp
bd max >
> set of the energy demands is given in Table 2. As can be seen,
>
> >
>
>
> 0 0 >
>
>
> fgbp ; fhckp ; fii0 tp ; fii0 tp ; fii0 i00 tp ; fii00 tp ; fpw ; fip ; fpc ; fipld ; fii0 p >
> there is a demand for electricity, three shaft power demands, and
>
> >
>
>
> ps pd
fip ; fipvent ; fip ; fDmax ; hbip ; hii0 tp ; hip ; hcp ; tchkp ; tckp ; tcp >
> demands for high, medium, and low pressure steam. The operat-
>
>
out;hu
>
>
>
< >
= ing pressures of steam headers and the corresponding saturated
thckp ; thkp ; Tgp ; Tgbp ; qbp ; qbup ; qhu cp ; qgp ; qhckp ; wgp ; wgjp ; wii0 tp
x2 temperatures are shown in Table 3. In order to discuss the effect
>
> max max max imp;e exp;e
wii0 tjp ; wg ; wt ; wmjp ; wm ; wp ; wp ; zb ; zbp ; zbi ; zbip ; zhu >
>
>
> cp > > of the header temperatures, three scenarios are considered in
>
> >
> zg ; zgp ; zgb ; zgbp ; zgj ; zgjp ; zhckp ; zhp ; zt ; zii0 t ; zii0 tp ; zii0 tj ; zii0 tjp ; zii0 i00 tp >
>
cu >
> this case study. The investment cost functions are taken from
>
> >
>
>
> "b ∈ B; ∈ C ; ∈ D ; ∈ G ; ∈ H ; 0 00
; ∈ I >
> Bruno et al.4 and are presented in Table 7 in the Appendix. The
>
>
c d g h i; i i >
>
>
: >
; annualized capital recovery factor adopted is 0.15.
j ∈ J ;k ∈ K ;m ∈ M ;p ∈ P;t ∈ T ;u ∈ U
5.1.1. Scenario 1: Specified Steam Header Temperatures. In
this scenario, specified temperatures of steam headers are used
Ω2 ¼ fx2 jeqs 169g for the design. More specifically, the temperatures are treated as
given constants (not decision variables), and then an MINLP
5. CASE STUDIES model is solved accordingly to synthesize the steam distribution
In this section, two case studies are presented to demonstrate network. The specified header temperatures adopted in this
the application of the proposed MINLP model. In case 1, SDN scenario are presented in Table 3. A two-period problem with
design with the given steam demands is studied. The process data equal operating time (50%) is studied. Note that electricity
are taken from the work of Bruno et al.,4 which was originally export is not considered in this study.
solved for the single period operation only. The other period The optimal configuration obtained in the first scenario has a
demands are added in the present example to facilitate a multi- TAC of $13.97 million year1 and is shown in Figure 5. There are
period SDN design. In case 2, simultaneous design for SDN and one boiler, three steam turbines, and one electric motor installed
HEN is studied, where the interaction between a steam system in the steam system. A high pressure (HP) boiler is chosen for the
and a heat recovery system can be optimized. steam production. A HPmedium pressure (MP) back-pressure
The site conditions for case studies are presented in Table 1. steam turbine is used for the electricity generation. Part of
The optimization platform employed was the General Algebraic electricity import is required, which is 205 and 2319 kW for
Modeling System (GAMS).14 The solver used was SBB15 for the periods 1 and 2, respectively. Shaft power demands 1 and 2 are
MINLP model. An Intel Core 2 Duo CPU 2.53 GHz computer satisfied with steam turbines (two MPlow pressure (LP) back-
with 1 GB of RAM was used. pressure steam turbines). The remaining shaft power demand is
satisfied with an electric motor.
From the result, it is found that the specified header tempera-
ture strategy restricts the design of SDN. Some feasible structure
Table 3. Steam Header Conditions for Case 1 or operating opportunities may be excluded due to the tempera-
P (bar) saturated temp (C) specified temp (C) ture restriction.
5.1.2. Scenario 2: Optimized Steam Header Temperatures. In
45 257.4 369.0 scenario 2, a more practical design strategy is proposed. The
17 204.3 265.0 same problem is solved again without the specified temperature
4.5 147.9 148.0 constraints. Each steam header temperature is treated as a
Table 4. Comparative Economic Parameters for the Major Table 5. Process Stream Data of Case 2
Results of Case 1
steam type and number CP (kW/C) Tin (C) Tout (C)
scenario 1 scenario 2 scenario 3
H1 205 388 110
total annualized cost ($105) 139.72 134.75 120.63 H2 152 210 60
overall fuel cost ($105) 121.75 123.78 119.90 C1 753 100 200
overall electricity cost ($105) 7.60 0.00 10.73 C2 377 140 255
annualized capital cost ($105) 9.91 10.51 11.03 C3 143 70 140
variable to be optimized. It is expected to find appropriate scenario 1. A HPMP steam turbine and a MPLP steam
temperatures for each steam header throughout all periods. turbine are installed to meet the need of shaft demands 1 and 3,
Figure 6 shows the resulting network structure. One can see respectively, which replace the original MPLP turbine and the
that the optimal configuration is different from the result of electric motor. An electric motor is installed for the shaft demand
8105 dx.doi.org/10.1021/ie102059n |Ind. Eng. Chem. Res. 2011, 50, 8097–8109
Industrial & Engineering Chemistry Research ARTICLE
2. An HPLP steam turbine is installed to meet the requirement As can be seen, optimized header temperatures are determined.
of electricity. The electricity import decreases to 0 kW. The Clearly, the operating temperatures are not unique, which are
optimized temperatures of steam headers are 356.3, 284.9, and changed with varying demands. Mechanical demands are satis-
159.9 C (period 1) and 399.8, 297.7, and 185.9 C (period 2) fied with one steam turbine and two electric motors. The high
for high, medium, and low pressure, respectively. The corre- pressure steam turbine exhausts mainly to the medium pressure
sponding TAC is $13.47 million year1. It is evident that the header for electricity generation. Steam systems tend to generate
TAC can be reduced under the proposed flexible strategy. more electricity during the first, second, and third time period,
5.1.3. Scenario 3: Multiperiod Operating Design. In this and therefore the excess electricity is exported. Electricity import
scenario, four periods with equal operating time (25%) are is necessary only in the last period. Since the steam demands are
considered to show the capability for the design of multiperiod lower than in other periods, the steam available to generate elec-
operating. The set of demands is presented in Table 2. HP steam tricity is lower, too. In this example the ability of the proposed
demands are requested in period 3 and period 4. Note that model to choose the best option for electricity generation and the
electricity export is allowed and its price is assumed the same as optimal configuration of power generating devices, and their
the import price. influence on the operation, can be demonstrated.
Figure 7 shows the network layout and the corresponding From the result of these scenarios, it is evident that if the
operating state. The TAC of this design is $12.06 million year1. flexible model is considered for the SDN design, the lower TAC
can be accomplished. More detailed information for these
Table 6. Demand Data (All in kW) of Case 2 scenarios is shown in Table 4.
power demands 5.2. Case 2. Simultaneous SDN and HEN Design Problem.
Let us consider a chemical process in which the heat capacity flow
electricity demand 4500 rates (CP) of two hot streams and three cold streams are
shaft power demand 1 2000 identified (see Table 5). Single-period operation is considered.
shaft power demand 2 1200 Electricity and mechanical power demands are required and are
Table 7. Investment Cost Data4 hand, header temperatures are treated as temperature-indepen-
dent and therefore operation and design possibilities may be
unit investment cost ($/year)
restricted. In scenario 2, the header temperatures are considered
(1) field erected boiler (VHP) 22970F0.82fp1 as decision variables and a one-step procedure is developed with
F, maximum steam flow rate (tons/h) fp1 = 0.6939 þ 0.1214P the ability to optimize the network structure and the operating
3.79843P2 conditions simultaneously. It is appreciated that the better design
P, pressure (MPa)
and operation can be accomplished under this approach. In
scenario 3, four periods with electricity import and export are
(2) large package boiler 4954F0.77fp2
studied. The result reveals that steam turbines for the electricity
F, maximum steam flow rate (tons/h) fp2 = 1.3794 0.5438P
generation are preferred due to the higher operating flexibility.
þ 0.1879P2 Thus, the steam system can maintain higher operating efficiency
P, pressure (MPa) throughout all periods.
(3) heat recovery steam generator 941Ffg0.75 In case 2, simultaneous design for SDN and HEN is studied.
Ffg, maximum flue gas flow rate (tons/h) The proposed model can determine both the moderate operating
(4) steam turbine 81594 þ 18.052Wst conditions and the corresponding network for the steam system
Wst, maximum power (kW) and the heat recovery system. The operating condition deter-
(5) gas turbine 321350 þ 67.618Wgt mination can affect the operation efficiency for steam systems
Wgt, maximum power (kW) and the heat recovery circumstance for the given chemical
(6) electric generator 8141 þ 0.6459Weg
process. In this work, the interaction between two systems can
be optimized.
Weg, maximum power (kW)
(7) electric motor 1601 þ 27.288Wel
Wel, maximum power (kW) 7. CONCLUSION
(8) deaerator 7271 þ 79.25FB Changes in specifications, composition of feed, and seasonal
FB, maximum BFW flow rate (tons/h) product demands may cause several process conditions with
(9) condensor 3977 þ 1.84Fc variation in the energy requirements during an annual horizon. In
Fc, maximum cooling the first part, an MINLP model, based on unit superstructures,
water flow rate (tons/h)
has been developed to design a steam system with variable utility
demands. Complex multiperiod scenarios were studied that
(10) centrifugal pump (475.3 þ 34.95Pw
together consider the design and operation of steam power
0.0301Pw2)fpw
systems in an industrial plant. In the second part, a novel
Pw, power (kW) methodology has been developed to address the design of a
fpw = 1 (<1.03 MPa) steam system and a heat recovery network. This work determines
fpw = 1.62 (1.033.45 MPa) the optimal structure for both SDN and HEN, and also estimates
fpw = 2.12 (>3.45 MPa) the moderate operating conditions. The results from the case
studies demonstrate that better energy management and utiliza-
shown in Table 6. The annual cost is 1200[area (m2)]0.6 for all tion can be realized with the proposed model.
exchangers.12 The minimum temperature difference for the
design of HEN is 10 K. In this case, the objective is to optimize ’ APPENDIX
the interaction between SDN and HEN. The investment cost data according to Bruno et al.4 are
The optimal SDN is presented in Figure 8. Three steam itemized in Table 7.
headers are suggested for SDN, where their properties are HP
(50.9 bar, 398.8 C), MP (19.1 bar, 297.6 C), and LP (4.7 bar, ’ AUTHOR INFORMATION
229.7 C). It is mentioned that the steam levels are not specified
previously, but are optimized by the proposed approach. This Corresponding Author
steam system provides the multiple utilities for the heat recovery *Tel.: 886-2-33663039. Fax: 886-2-23623040. E-mail: CCL@
network. The steam level decisions are the trade-off results of ntu.edu.tw.
simultaneous consideration for SDN and HEN. In SDN, one HP
boiler and three back-pressure steam turbines are included. Two
turbines are used for the shaft power demands and one is for ’ ACKNOWLEDGMENT
electricity generation. A part of the electricity demand is satisfied Financial support of the National Science Council of ROC
with the steam system (2040 kW), and another part is from the (under Grants NSC98-3114-E-002-009 and NSC100-3113-
import (2707 kW). The optimal HEN is shown in Figure 9, E-002-004) is appreciated.
where four heat exchangers, two heaters, and one cooler are
included. Hot utilities are from an MP steam header (49.2 MW) ’ NOMENCLATURE
and an LP steam header (3.1 MW). The corresponding TAC is
$14.19 million year1. Indices
b = index for boilers
c = index for cold process or utility streams
6. DISCUSSION g = index for gas turbines
In scenario 1 of case 1, temperatures of steam headers are h = index for hot process or utility streams
specified before a network structure is available. On the other i = index for steam headers
8107 dx.doi.org/10.1021/ie102059n |Ind. Eng. Chem. Res. 2011, 50, 8097–8109
Industrial & Engineering Chemistry Research ARTICLE
Fcp = heat capacity flow rate for cold process stream c in period p, multistage steam turbine t in time period p, kg s1
kW/C f0ii0 i0 0 tp = steam flow rate from stage i0 to stage i00 for a multistage
Fhp = heat capacity flow rate for hot process stream h in period p, steam turbine t in time period p, kg s1
kW/C fii0 p = steam flow rate from header i to header i0 in time period p,
Gγ* * = coefficient function of units, where * = {b, c, d, g, h, m, t} kg s1
Hsat,l
i = enthalpy of saturated steam at steam header i level, fip = steam flow rate from header i to deaerator in time period p,
kJ kg1 kg s1
ps ld
Hip = enthalpy of steam supplied by processes and delivered at fip = desuperheating boiler feed water injected into header i in
header i in period p, kJ kg1 time period p, kg s1
Hwp = enthalpy of demineralized water makeup in period p, fpd
ip = steam process demand at header i in time period p, kg s1
kJ kg1 fip = steam from process entering header i in time period p, kg s1
ps
1
H deaer
= enthalpy of water leaving a deaerator, kJ kg1 fvent
ip = vented steam at header i in time period p, kg s
1
tp = number of operating hours in time period p, h period1
hrs c
fp = condensate return in period p, kg s
cp = inlet temperature of cold process stream c in period p, C
Tin fwp = demineralized water makeup in time period p, kg s1
cp = outlet temperature of cold process stream c in period p, C
Tout p = cooling water mass flow rate for condensers in time period
fcw
hp = inlet temperature of hot process stream h in period p, C
Tin p, kg s1
hp = outlet temperature of hot process stream h in period p, C
Tout hbip = enthalpy of steam generated by boiler b entering header i in
wdem,s
jp = shaft power demand j in time period p, kW period p, kJ kg1
8108 dx.doi.org/10.1021/ie102059n |Ind. Eng. Chem. Res. 2011, 50, 8097–8109
Industrial & Engineering Chemistry Research ARTICLE
hii0 tp = enthalpy of a discharge by steam turbine t entering header zii0 tj = denotes the existence of the connection between steam
i0 in period p, kJ kg1 turbine t and shaft demand j
hip = enthalpy of steam header i in period p, kJ kg1 zii0 tjp = denotes the existence of shaft demand j supplied by steam
hcp = enthalpy of returning condensate from processes in period p, turbine t in time period p
kJ kg1 zii0 tp = denotes the operating status of steam turbine t in time
qbp = heat added to the water in boiler b in time period p, kW period p
qhu
cp = heat exchanged between hot utility and cold stream c in
time period p, kW
qhckp = heat exchanged between hot stream h and cold stream c in ’ REFERENCES
stage k in period p, kW (1) Nishio, M.; Itoh, J.; Shiroko, K.; Umeda, T. A thermodynamic
qcu
hp = heat exchanged between hot stream h and cold utility in approach to steam-power system design. Ind. Eng. Chem. Process Des.
time period p, kW Dev. 1980, 19, 306.
tchkp = temperature of cold stream c at stage k in time period p, C (2) Chou, C. C.; Shih, Y. S. A thermodynamic approach to the design
tckp = temperature of cold stream c at hot end of stage k in time and synthesis of plant utility systems. Ind. Eng. Chem. Res. 1987, 26, 1100.
period p, C (3) Papoulias, S. A.; Grossmann, I. E. A structural optimization
Tgbp = exhaust gas temperature for gas turbine g delivered to approach in process synthesis—I. Comput. Chem. Eng. 1983, 7, 695.
HRSG b in time period p, C (4) Bruno, J. C.; Fernandez, F.; Castells, F.; Grossmann, I. E. A
Tgp = exhaust gas temperature for gas turbine g, C rigorous MINLP model for the optimal synthesis and operation of utility
thckp = temperature of hot stream h at stage k in time period p, C plants. Chem. Eng. Res. Des. 1998, 76, 246.
(5) Chang, C. T.; Hwang, J. R. A multiobjective programming
thkp = temperature of hot stream h at hot end of stage k in time approach to waste minimization in the utility systems of chemical
period p, C processes. Chem. Eng. Sci. 1996, 51, 3951.
wmax
g = design/maximum gas turbine g power output, kW (6) Hui, C. W.; Natori, Y. An industrial application using mixed-
wgp = power produced by gas turbine g in time period p, kW integer programming technique: A multi-period utility system model.
wgjp = shaft power produced by gas turbine g to shaft demand j in Comput. Chem. Eng. 1996, 20, S1577.
period p, kW (7) Iyer, R. R.; Grossmann, I. E. Optimal multiperiod operational
wii0 tp = power produced by steam turbine t in period p, kW planning for utility systems. Comput. Chem. Eng. 1997, 21, 787.
wii0 tjp = shaft power produced by steam turbine t to shaft demand (8) Maia, L. O. A.; Qassim, R. Y. Synthesis of utility systems with
j in period p, kW variable demands using simulated annealing. Comput. Chem. Eng. 1997,
wmax 21, 947.
m = design/maximum power for electric motor m, kW
(9) Micheletto, S. R.; Carvalho, M. C. A.; Pinto, J. M. Operational
wmjp = shaft power produced by electric motor m to shaft demand optimization of the utility system of an oil refinery. Comput. Chem. Eng.
j in period p, kW 2008, 32, 170.
wmax
t = design/maximum steam turbine t power output, kW (10) Aguilar, O.; Perry, S. J.; Kim, J.-K.; Smith, R. Design and
wimp,e
p = electricity imported in time period p optimization of flexible utility systems subject to variable conditions,
wexp,e
p = electricity exported in time period p Part 1: Modelling Framework. Chem. Eng. Res. Des. 2007, 85, 1136.
(11) Aguilar, O.; Perry, S. J.; Kim, J.-K.; Smith, R. Design and
Binary Variables optimization of flexible utility systems subject to variable conditions,
zb = denotes the presence of boiler b Part 2: Methodology and Applications. Chem. Eng. Res. Des. 2007,
zbp = denotes the operating status of boiler b 85, 1149.
zbi = denotes the existence of the connection between boiler b (12) Yee, T. F.; Grossmann, I. E. Simultaneous optimization models
and header i for heat integration—II. Heat exchanger network synthesis. Comput.
zbip = denotes the existence of steam flow from boiler b to header Chem. Eng. 1990, 14, 1165.
(13) Chen, J. J. J. Letter to Editors: Comments on improvement on a
i in time period p replacement for the logarithmic mean. Chem. Eng. Sci. 1987, 42, 2488.
zhu
cp = denotes that hot utility exchanges heat with cold stream c in (14) GAMS: A User’s Guide; GAMS Development Corp.: Washington,
period p DC, 2008.
zg = denotes the presence of gas turbine g (15) GAMS: The Solver Manuals; GAMS Development Corp.:
zgb = denotes the existence of the connection between gas turbine Washington, DC, 2007.
g and boiler b
zgbp = denotes the existence of gas flow from gas turbine g to
boiler b in time period p
zgj = denotes the existence of the connection between gas turbine
g and shaft demand j
zgjp = denotes the existence of shaft demand j supplied by gas
turbine g in time period p
zgp = denotes the operating status of gas turbine g in time period p
zhckp = denotes the existence of match (h, c) in stage k in period p
zcu
hp = denotes that cold utility exchanges heat with hot stream h in
period p
zt = denotes the presence of steam turbine t
zii0 t = denotes the existence of the connection of steam turbine t
between i and i0 headers
zii0 i0 0 tp = denotes the existence of steam flow from stage i0 to stage
i00 of a multistage steam turbine t in time period p