Method Statement For Testing Piling Works
Method Statement For Testing Piling Works
Owner’s Engineer
Contractor
Project
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
(2 X 600 MW)
Title
Contents
1. SCOPE OF WORK
1.1 General Description
1.2 General Work Flow
2 STANDARD REFERENCES
3 PREPARATION WORK
3.1 Schedule of works
3.2 Organization chart
3.3 Preparation
3.4 Equipment and Materials
3.5 Survey work
4 PILE SUPPLY
4.1 Delivery of PHC pile segment to site
5 MOBILIZATION AND ASSEMBLY OF MACHINE
5.1 Mobilization and assembly of pressing machine
6 PILE INSTALLATION BY PRESSING MACHINE
6.1 Procedure of pile pressing machine
6.2 Pile installation by pressing machine
7 TESTING WORK
7.1 Scope of work
7.2 Personnel
7.3 Equipment
8 EXECUTION OF STATIC LOAD TEST
8.1 Requirement for construction of test pile
8.2 Testing Equipment
8.3 Testing Standard
8.4 Testing Procedure
8.5 Template of Site Record
8.6 Contents of report on testing results
1 SCOPE OF WORK
1.1 General Description
This Method Statement describes the pile pressing and testing works of Housing Complex Work
of Nghi Son 2 Thermal Power Plant Project located at Nghi Son, Tinh Gia District, Thanh Hoa
Province. The statement consists of Site preparation, Material Supply and Installation,
Construction Procedure, Inspection Procedure, and Quality Assurance related to
Subcontractor’s responsibility for implementation of the whole Housing Complex Work Package
following requirements mentioned in Specification and Designs as well as the relevant standard
of the Project.
2 STANDARD REFERENCES
Requirements for testing and piling works shall conform to the latest revisions and
amendments of the following Standards.
Table 2.1: List of applicable standard and specification
The piling works shall conform to the following standards:
TCVN 4506: 2012 Water for concrete and mortar – Technical specifications.
ASTM D1143-07(2013) Standard test method for pile under Static Axial Compression Load
ASTM D3966-07(2013) Standard Test Methods for Deep Foundations Under Lateral Load
Standard Test Methods for Deep Foundations Under Static Axial Tensile
ASTM D3689-07(2013)
Load
TCVN 9394: 2012 Pile driving and static jacking works – Construction, check and acceptance
3 PREPARATION WORK
3.1 Schedule of work
- PHC D450 Class A
No. Pile No. Duration Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12
1 Pressing test pile PTN1 (D450) 1Day
2 Pressing test pile PTN5 (D450) 1Day
3 Pressing test pile PTN6 (D450) 1Day
4 Testing pile PTN1 (Compression Load Test) 2 Days
5 Testing pile PTN5 (Uplift Load Test) 1Day
6 Testing pile PTN6 (Lateral Load Test) 2 Days
Arch.Dept.M Cons.Engineer
Lee Yong Ha Nguyen Van Lang
038 559 0538 096 811 6904
3.3 Preparation
Construction site shall be prepared stably enough for machine movement and safety operation,
detail as following:
- The Subcontractor shall use steel plate for construction area of soft ground.
- Temporary facilities shall be set up and provided for the securities, safety and operation of
the whole work.
All materials used for the Project shall be approved before using and submitted with quality
certificate of manufacture and testing result as the Project’s requirement.
Center point coordinate must be set out by total station and marked by suitable stakes.
Figure 3.1: Survey work
4 PILE SUPPLY
4.1 Delivery of PHC pile segment to site
Normally, sample testing for compressive strength shall be carried out at 3 days or 5 days, if
the strength of concrete sample reaches over 75% of designed strength (R28), those pile
segments can be delivered to the site.
To ensure that non-conforming material is not delivered at site. Any material found damaged or
unsuitable for use in permanent works will be segregated. Inspection of the conforming
materials with the Engineer.
Pile will be inspected and accepted by Engineer, there are following documents:
- Delivery certificate;
- Pile delivery slip;
- Result of concrete compression test.
The storage area of pile at the site must be a flat and stable. Each pile’s stack should have no
more than 1 layers.
When using the pile should be hanged from stack top to bottom layer by layer. Pulling and
pushing out a pile from stack inside is not permitted.
At the site, pile segments shall be arranged to have the advantage of moving equipment and
avoid damages to pile segments during execution period.
Figure 4.1 Transporting pile segment Figure 4.2 Storage of pile segment
Total weight of Pressing machines should be more than 1.1 times maximum pressing load.
The number and type of Pressing machine to be used for pressing pile is shown in table
below.
No. Pressing Machine Capacity (ton) Quantity (set) Diameter of pile
1 Robot ZYJ 680B 680 01 D350, D450
Requirement to assembly and disassembly site: Space for pressing machine, transport
vehicles and service crane. The planes and hardness of ground should meet the
requirement for pressing machine erection, transport vehicles over 50 ton, service crane
over 25 ton.
Mobilization of service crane, lifting the 2 longitudinal motion legs and set them parallel.
The transport vehicles go ahead between the 2 longitudinal motion legs. Low down the 4
cylinders of the Pressing machine's main part to the 2 longitudinal motion legs.
Lifting the pile pressing cylinder, counter weight on the Robot’s main part.
Fabrication of pile segments Pile delivery and inspection Erection of pile pressing machine
Installation of
Inspection with Engineer safety devices
PILE INSTALLATION
Monitoring by Engineer
Monitoring by Engineer
If not Ok
Check condition Next pile
Pmin ≤P≤ Pmax segment
Ok
Shift to
Checking pile top elevation next pile
Finishing
Inspection with Engineer
Site clean up
Every fabricated pile’s segment must be checked and approved the official quality
certificates prior to be set into the designed position.
The pressing machine shall be set on the desired position for pressing the pile segment
into the finish elevation specified on the approved drawings.
At the site, pile segments shall be arranged to have the advantage of moving equipment
and avoid damages to pile segments during execution period.
The 1st pile segment will be set into pressing frame by crane and the segment will be
installed to elevation top pile +1.2m to +1.4m ground surface elevation.
The pressing machine will be adjusted to ensure the plane of pressing machine is always
horizontal, and the pile is always vertical during pressing the whole pile.
Verticality of the pile can also be set by leveling the pressing machine using the circular
level meter in pressing cabin. The air bubble in the center of the level meter means the
pressing machine is in the horizontal plane. Refer to Figure below also showing picture
of circular level meter.
After setting the verticality of the 2nd pile by leveling the pressing machine, manual
checking using level bar and/or Theodolite will be conducted to verify, check and ensure
verticality in 2 directions and then install the first pile segment to the elevation top pile
+1.20m ~ +1.40m from the ground surface.
The 2nd pile segment will be set into pressing frame by crane. The joints between the two
pile segments will be welded connected. The 2nd pile segment will then be installed by
Pressing machine. The pile’s verticality will be checked by leveling of the pressing
machine will be set by the circular level meter and then finally checked by a level bar in
two directions after welding it on the installed first pile segment. If pressing load not
reaches Pmax, the next pile segment shall be added and welded to the second pile
segment.
The next pile segment will be set on the top of the second pile segment and then
connected by welding at the joint. The next pile segment will be pushed down by the
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 12
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001
pressing machine.
The setting and pressing of succeeding pile segment will stop after attaining the required
maximum finishing load and then pressing machine will be transferred to the next pile
location.
The final pile segment will be used steel dolly pile for pressing.
Direction of execution:
Organize and divide clearly the execution area for each machine so that the
implementation carries out conveniently and safety.
- Pressure depth of pile reaches Lmax but pressing load less than Pmin.
- Pressing load reaches Pmax but pressure depth of pile less than Lmin.
In all above conditions, the Contractor immediately informs to the Consultant to find a
suitable and opportune resolving way.
Semi-automatic welding equipment with welding wire shall be used for welding joint of
pile.
- Welding machine and gas suppliers
- Welding gun with the contact tube of 10-15mm for the current <250A and 15-25mm for the
current >250A.
- Wire feeder motor;
- Connection cables;
- Shielding gas (CO2)
- Welding wires: (0.9-1.2mm)
Welding process:
- The pile head should be cleaned by grinder first before moving to the welding position.
- Check the welding equipment: working condition: currency, machines, welding equipment:
electricity cables, welding cables, joints….
- Check the currency: during the welding process, the currency should be in range of 110-300 A
(Current) and 20-26V (Voltage).
- Check CO2 flow meter: the shield gas for using in MAG welding is CO2, the specifications of
CO2 are: percent composition: 99.8%, the out flow: 18-25l/min. The gas meter should be
checked in order to ensure that it is in normal working condition.
- Testing the welding machines: adjust the currency and gas flow to the above requirement.
All welding joints shall be carried out by skilled worker, who has welding certificate, under
carefully supervise about thickness, quality as well as the verticality of two pile segments
before and after welding.
- Welding work shall be only started to meet the following conditions:
- The axis of pile segment shall be corrected at least two directions.
- The axis of second pile segment coincides with the axis of first pile segment.
- Surfaces of two pile head tightly contact together.
The welding joint shall be filling-up all around the gap between the two piles- end flanges
by at least 2 layers welding.
Start welding: The pile diameter is divided into two part, each welder is in charge of
welding part. In order to ensure that the temperature shall not increase suddenly, the two
welder shall start welding in opposite position rather than in the same position, they also
need to follow the same direction during welding. Moreover, during the welding process,
the speed of welding gun movement should not exceed 240mm/min, the welder should
also weld the pile connection in at least 2 layers so that the welding height can meet the
specifications.
Keeping 10 – 15% design load during welding period for pressed pile for surface of two
piles head tightly contact.
The welding joint is met requirement to height, width and homogeneity as design before
continue pressing pile.
Checking quantity of welding joint: PT checking of 100% joints of installed piles, detail as
following:
- Pre-cleaning: The test surface is cleaned to remove any dirt, paint, oil, grease or any loose
scale that could either keep penetrant out of a defect, or cause irrelevant or false indications.
- Application of Penetrant: The penetrant is then applied to the surface of the item being tested.
Wait for at least 5 minutes for penetration.
- Excess Penetrant Removal: The excess penetrant is then removed from the surface towards
one direction either vertically or horizontally as the case may be. The removal method is
controlled by the type of penetrant used.
- Application of Developer: After excess penetrant has been removed, a white developer is
applied to the sample. Choice of developer is governed by penetrant compatibility and by
inspection conditions. The developer draws penetrant from defects out onto the surface to form
a visible indication, commonly known as bleed-out. Any areas that bleed out can indicate the
location, orientation and possible types of defects on the surface. Interpreting the results and
characterizing defects from the indications found may require some training and/or experience
[the indication size is not the actual size of the defect].
- Inspection: The inspector will use visible light with adequate intensity for visible dye penetrant.
Ultraviolet (UV-A) radiation of adequate intensity along with low ambient light levels for
penetrant examinations.
- Post Cleaning: The test surface is often cleaned after inspection and recording of defects.
After finishing each pile pressing, if the top of pile is higher than working ground level, the
Subcontractor will temporary cut piles head at about 20-30cm higher than working level
by manpower and portable cutting machine.
This temporary cutting level is only for movement of the pile pressing machine, and this
temporary cutting level must be always higher than designed pile cut-off level.
After temporary pile head cutting, covering the top of pile by wooden plate and sand bag
for protection of pile head during moving the pile pressing machine.
Record the initial pressure: Note down the initial pressure then keep record at each 1m
or 2m interval length until the pile penetrates to the finishing depth. If the hand of the
gauge moves abnormally then record the depth and pressure on the installation record or
construction journal. Pile installation record shall be kept until the designed length is
obtained. When the pressure reaches Pmin, keep record at each 20cm and continue until
finishing for pile pressing.
- Date of production;
- Date of pressing;
- Ground level;
- Pressure value and pressing load at interval of 1-2m depth and final pressing load;
- Interruptions of pressing;
- Period of pressing;
- Any further information required by the Architect/Engineer.
7 TESTING WORK
7.1 Scope of work
The quantities of testing work are shown in this table.
Pile Pile Design Testing
Item Work Note
No. Diameter load (ton) load (ton)
BUILDING FOR Compression
PTN-1 D450 120 300
TECHNICIANS Tests
AND OPERATORS Compression
PTN-2 D350 70 175
1 & BUILDING Tests
FOR
TECHNICIANS
AND OPERATORS
2
BUILDING FOR Pile Lateral
PTN-3 D350 6 15
TECHNICIANS Load Test
AND OPERATORS Pile Lateral
PTN-6 D450 10 25
2 & SWIMMING Load Test
POOL
7.2 Personnel
- List of personnel for testing work is as follow:
STT Name Qualification Duty
- Certificate:
7.3 Equipment
- List of equipment for testing work is as follow:
- Calibration Certificate:
All the test shall be only commenced at least 07 days after finishing installation of the pile.
Grinding the surface of pile head or pouring the SikaGrout on surface of pile head so that it is
flat and perpendicular with center line of pile before carrying out the test.
Using hydraulic jacks with capacity of 500 tons for test piles, total capacity of the jacks
shall be exceed by 20% or more the required maximum test load, these jacks connecting
with hydraulic pump and pressure gauge, put directly on the top of test pile to create a
load on pile center. The load on pile top is controlled by hydraulic pump of adequate
capacity with a pressure gauge.
The Counter – Weight is robot’s Self- weight and the steel blocks of the pile pressing
machine (Automatic robot). The general Weight and steel blocks of the pressing machine
and cast – iron (more than 110% of maximum testing load).
Load step (%
Cycle Holding time for each load step
design load)
At least 1 hour until the settlement rate is less than 0.25mm per hour and
25%
with a maximum of 2 hours
50% Ditto
I 75% Ditto
100% Ditto
50% Monitoring in 30 minutes
0% Monitoring in 60 minutes
At least 1 hour until the settlement rate is less than 0.25mm per hour and
50%
with a maximum of 2 hours
100% Ditto
125% Ditto
150% Ditto
175% Ditto
200% At least 12 hour until the settlement rate is less than 0.25mm per hour
II 175% Monitoring in 30 minutes
150% Monitoring in 30 minutes
125% Monitoring in 30 minutes
100% Monitoring in 30 minutes
75% Monitoring in 30 minutes
50% Monitoring in 30 minutes
25% Monitoring in 30 minutes
0% Monitoring in 60 minutes
50% Monitoring in 20 minutes
100% Monitoring in 20 minutes
150% Monitoring in 20 minutes
200% Monitoring in 20 minutes
210% Monitoring in 20 minutes
220% Monitoring in 20 minutes
230% Monitoring in 20 minutes
III
240% Monitoring in 20 minutes
250% Monitoring in 20 minutes
200% Monitoring in 20 minutes
150% Monitoring in 20 minutes
100% Monitoring in 20 minutes
50% Monitoring in 20 minutes
0% Monitoring in 20 minutes
In each loading step, the data is obtained at each time of 1, 10, 20, 30, 45, 60, 90, 120, 180,
240, 300…, then taken interval of 60 minutes.
- The totals of pile’s settlement are greater than 15% of pile’s diameter.
Package: ……………………………………………….………………………
Location: ……………………………………………….………………………
150% 10 minutes
200% 10 minutes
210% 15 minutes
220% 15 minutes
230% 15 minutes
240% 15 minutes
250% 30 minutes
200% 10 minutes
150% 10 minutes
100% 10 minutes
50% 10 minutes
0% 10 minutes
In each loading step, the data is obtained at each time of 1, 5, 10,15, 20, 30, 45, 60
minutes. Test shall be completed when:
- Test according to the above procedure is completed.
- Material of pile is damaged.
Load step (%
Cycle Holding time for each load step
design load)
At least 1 hour until the uplift movement rate is less than 0.25mm
25% per hour and with a maximum of 2 hours
50% Ditto
I
75% Ditto
100% Ditto
50% Monitoring in 30 minutes
0% Monitoring in 60 minutes
At least 1 hour until the uplift movement rate is less than 0.25mm
50%
per hour and with a maximum of 2 hours
100% Ditto
125% Ditto
150% Ditto
175% Ditto
At least 12 hour until the settlement rate is less than 0.25mm per
200%
hour
II 175% Monitoring in 30 minutes
150% Monitoring in 30 minutes
125% Monitoring in 30 minutes
100% Monitoring in 30 minutes
75% Monitoring in 30 minutes
50% Monitoring in 30 minutes
25% Monitoring in 30 minutes
0% Monitoring in 60 minutes
50%, Monitoring in 20 minutes
100% Monitoring in 20 minutes
150% Monitoring in 20 minutes
200% Monitoring in 20 minutes
210% Monitoring in 20 minutes
220% Monitoring in 20 minutes
230% Monitoring in 20 minutes
III
240% Monitoring in 20 minutes
250% Monitoring in 120 minutes
200% Monitoring in 20 minutes
150% Monitoring in 20 minutes
100% Monitoring in 20 minutes
50% Monitoring in 20 minutes
0% Monitoring in 20 minutes
In each loading step, the data is obtained at each time of 1, 10, 20, 30, 45, 60, 90, 120, 180,
240, 300..., then taken interval of 60 minutes.
* Test pile is failure when:
- The totals of pile's uplift movement are greater than 15% of pile's diameter.
* The testing shall be finished in cases:
- The procedure above is completed.
- The material on pile top is destroyed or the testing load cannot be increased because it
impossibly exceeds actual bearing capacity of the test pile.
* The testing shall be stopped when:
Package: ……………………………………………….………………………
Location: ……………………………………………….………………………
Average
Value on Dial gauge
movement Total Uplift
Elapsed Load step Load Pressure reading
Time (mm) movement
Time (%) (ton) Gauge
(mm)
(KG/cm2) N1 N4
Termination criterial:
- For pile pressing: Final Pressing loads are obtained Pmin ≤ Pfinal ≤ Pmax.
- Welding checking:
- Checking the certification of worker.
- Checking all the welding lines about: dimensions, height, number of layer welding, clean
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 46
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001
12 IMPLEMENTATION
12.1 Manpower mobilization plan
12.1.1 Site organization
- Geotechnical section
- HSE section
- Survey section.
QA/QC section in charge of the implementation of test and inspection plan, inspection
sheets, all document of the project and working quantity for payment stages.
Survey section is in charge of controlling benchmark, axis plan and as-built drawing.
- Site manager;
- Site engineer;
- Quality control engineer;
- HSE engineer;
- Geotechnical engineer;
- Surveyor.
- Duties of each personnel position as below:
- Participating meetings discussion with the Main contractor, the Engineer for matters beyond
capacity and responsibility the Site manager,
- Final reports.
machine, material to executing and completing works including test work of all type according
to the requirement of safety, quality and schedule approved,
- Daily site arrangement in line with detailed schedule. Supervise activities of manpower, re-
organizing if necessary,
- Holding and being obliged to take care of internal meetings for daily construction,
- Report to Project’s parties, following close to implementation of progress and accomplishment
record of daily work, quantity inspection and approval,
- Manager and follow and evaluate suppliers/subcontractors,
- Participate in meetings with the Client and/or Engineer for exchanging information, reporting
working plan, taking action for any site work matters that need to be solved,
- Site Manager is supposed to understand thoroughly Project’s Specification and requirements.
He is the chief site staff, he takes care of Contract’s obligation implementation in terms of
schedule, safety, quality and approved acceptance of works.
- Supervising construction quality, accepting works part and works items (within BMT, the Owner/
Consultant)
- Ensure following safety regulation, coordinating with Engineer for all construction manner,
working environment, machine and equipment,
- Ensure following and supervising personal protection by using equipment,
- Check and test machine and equipment for safety at intervals,
- Execute and implement safety training all persons working on site,
- Provide information in order to prevent danger; collect, analyze safety data and disperse,
- In case of incident or accident, HSE officer shall be the first person to act, he find out reason
and proposes improvement method.
Duty of Surveyor:
- Responsible for all surveying works,
- Receive and hand over survey benchmarks, locating and setting out building and axis, assuring
precision and auditing hand-over benchmarks,
- Set up method for survey, work out location of piles, carry all measuring on site.
- Report to Site manager all matters related to surveyor, and other works assigned by the senior
staff.
After signing the contract, site organization shall be established, in which includes
experienced and educated people. Have job description for each position for the smooth
operation of the site organization. Project information shall be informed to each person
by kick-off meeting. Organize, arrange and balance resources reasonably and efficiently.
Establish and control construction schedule in month, week, day. Record and update daily
construction schedule for controlling. From that, optimize construction organization and
take action for overcoming in case of late schedule.
Control the duration of repetitive work, optimize working procedure and improve
construction productivity.
Organize internal training for improve working skill and specification capacity of manpower.
Organize extra activities for encouraging personnel’s spirit.
BMT established our own risk management for ensuring project schedule within planned
budget and meeting project specification. In theory, risk is defined as a positive or negative
deviation of a variable from its expected value. In fact, risk is understood only as a loss.
The aim of risk management is to response and control loss. The risk management
process comprises several steps as below:
- Risk identification;
- Risk assessment;
- Risk response;
- Risk monitoring and control.
Risk identification is the first and perhaps the most important step in the risk management
process, as it attempts to identify the source and type of risks. It includes the recognition
of potential risk event conditions in the construction.
There are four strategies for risk response are risk avoidance, risk transfer, risk mitigation
and risk acceptance.
The goal of risk controlling is not to eliminate risks completely from the project. The
monitoring of the risk helps guarantee that the risk position of the project corresponds to
the risk situation strived for.
Operator,
Workers falling Wear safety rope when
3 engineer,
down from height working at height over 2m
worker
13 PROFILE OF LABORATORY
13.1 COMPANY INFORMATION
Company name: BACDANG TESTING SURVEY AND CONSTRUCTION JOINT STOCK
COMPANY.
Trading name: BACDANG TESTING SURVEY AND CONSTRUCTION JOINT
STOCK COMPANY
Abbreviation: BACHDANGTSC
Address: No. 268 Tran Nguyen Han,Niem Nghia Ward, Le Chan District, Hai Phong City
LAS-XD09 Building Materials Laboratory was recognized by the Ministry of Construction and
granted the operating license to the Laboratory for the first time in 1988 and for the ninth
time in 2014, issued ISO 9001-2008 Certification in August 2010.
Decided by the Ministry of Construction to establish the TESTING AND SURVEY
CONSTRUCTION CENTER in accordance with Decision No. 1912 QD - BXD dated
14/11/2001.Transformed the operation model into a joint stock company according to
Decision No. 54/ QD - HDQT dated 24/6/2016 of the Board of Directors of Bach Dang
Construction Corporation (Business Registration No. 0201734963 dated 19/07/2016)
Business license No.: 0201734963 by the Department of Planning and Investment of Hai
Phong city of July 19th 2016.
Certificate of registration tax code No. 00201734963 of July 19th 2016
Tax management office: Haiphong City tax department
Leader: Tran Huu Son - Director
Bank account number VNĐ: 16 031 485 100 9154
At Vietnam Export Import Joint stock Commercial Bank – Haiphong Branch
Telephone: 0225 3856433
Email: bachdangtsc@gmail.com
LIST OF LEADER
Mr. Nguyen Van Nam De Ms. Dang Thi Mat Mr. Le Ba Thanh Dep
puty laboratory chief Laboratory Chief uty Laboratory chief
Mr. Vu Van Tam Site Mr. Pham Hong Truong Mr. Dang Ba Ca Site
Laboratory Manager Site Laboratory Manager Laboratory Manager