Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
100% found this document useful (3 votes)
1K views

Method Statement For Testing Piling Works

This document provides a method statement for test piling works at the Nghi Son 2 Thermal Power Plant Project housing complex. It outlines the scope, preparation, materials, equipment, installation procedures, testing standards and plans, and quality assurance procedures for installing 6 test piles of various diameters and conducting compression, lateral, and uplift load tests on the piles. The test piles will be installed using a pile pressing machine and tested according to Vietnamese and ASTM standards to evaluate their load capacity.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
1K views

Method Statement For Testing Piling Works

This document provides a method statement for test piling works at the Nghi Son 2 Thermal Power Plant Project housing complex. It outlines the scope, preparation, materials, equipment, installation procedures, testing standards and plans, and quality assurance procedures for installing 6 test piles of various diameters and conducting compression, lateral, and uplift load tests on the piles. The test piles will be installed using a pile pressing machine and tested according to Vietnamese and ASTM standards to evaluate their load capacity.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 91

FOR APPROVAL

C 24.03.19 L.C.Hai Y.H.Lee J.T.Seo For Approval


B 15.03.19 L.C.Hai Y.H.Lee J.T.Seo For Approval
A 21.02.19 L.C.Hai Y.H.Lee J.T.Seo For Approval
Rev Date Prepared Checked Approved Details of Revision
Owner

Owner’s Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM


Sub-Supplier

Bắc Miền Trung Consultancy Investment Construction


And Trading Joint Stock Company

Project
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
(2 X 600 MW)
Title

(Housing Complex)Method Statement for Test Piling Works

Document No. Rev. Page No.


NS2-DD09-P0UYK-770001 C 89 Pages
RECORD OF REVISIONS

Rev. Date Page Affected Description of Revision

A 21.02.2019 All First Issue

B 15.03.2019 All Modified by Owner’s comment

C 24.03.2019 All Modified by Owner’s comment


[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Contents

1. SCOPE OF WORK
1.1 General Description
1.2 General Work Flow
2 STANDARD REFERENCES
3 PREPARATION WORK
3.1 Schedule of works
3.2 Organization chart
3.3 Preparation
3.4 Equipment and Materials
3.5 Survey work
4 PILE SUPPLY
4.1 Delivery of PHC pile segment to site
5 MOBILIZATION AND ASSEMBLY OF MACHINE
5.1 Mobilization and assembly of pressing machine
6 PILE INSTALLATION BY PRESSING MACHINE
6.1 Procedure of pile pressing machine
6.2 Pile installation by pressing machine
7 TESTING WORK
7.1 Scope of work
7.2 Personnel
7.3 Equipment
8 EXECUTION OF STATIC LOAD TEST
8.1 Requirement for construction of test pile
8.2 Testing Equipment
8.3 Testing Standard
8.4 Testing Procedure
8.5 Template of Site Record
8.6 Contents of report on testing results

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 1
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

9 EXECUTION OF STATIC LATERAL LOAD TEST


9.1 Testing equipment
10 EXECUTION OF STATIC TENSILE LOAD TEST
10.1 Requirement for construction of test pile
10.2 Testing Equipment
10.3 Testing Standard
10.4 Testing Procedure
10.5 Template of Site Record
10.6 Contents of report on testing results
11 QUANLITY ASSURANCE PROCEDURE
11.1 PHC Pile supply
11.2 Pile installation
11.3 Testing work
12.4 Documents for final acceptance
12 IMPLMENTATION
12.1 Manpower Mobilization Plan
12.2 Machine and equipment mobilization plan
12.3 Construction schedule plan
12.4 Job safety analysis
13 PROFILE OF LABORATORY
13.1 Company information
13.2 Main activities
13.3 Quality management system
13.4 Laboratory certificate
14 TESTING PILE LAYOUT MASTER PLAN

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 2
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

1 SCOPE OF WORK
1.1 General Description
This Method Statement describes the pile pressing and testing works of Housing Complex Work
of Nghi Son 2 Thermal Power Plant Project located at Nghi Son, Tinh Gia District, Thanh Hoa
Province. The statement consists of Site preparation, Material Supply and Installation,
Construction Procedure, Inspection Procedure, and Quality Assurance related to
Subcontractor’s responsibility for implementation of the whole Housing Complex Work Package
following requirements mentioned in Specification and Designs as well as the relevant standard
of the Project.

The tentative quantities of pile are shown in table 1.1.


Table 1.1 Quantity of piling and testing works

No. Description Unit Quantity


I Supply of Test Piles
Pretentioned spun High strength Concrete pile PHC D350, class A, (1ea
1 ea 03
– 29.49 m, 1ea – 30.59 m, 1ea – 21.75 m)
Pretentioned spun High strength Concrete pile PHC D450, class A (1ea
2 ea 03
– 31.49 m, 1ea – 22.05 m, 1ea-31.69 m)
II Install of Test Piles
Static Pile Driving
1 –PHC D350 class A: 03 ea ea 06
–PHC D450 class A: 03 ea
III Tests & Reports
1 Pile Compression Tests ea 02
2 Pile Lateral Load Tests ea 02
3 Uplift Tests ea 02

1.2 General Work Flow


The scope of method statement covers the following:
- Pile installation for 03 piles PHC D350 class A and 03 piles PHC D450 class A.
- Pile test for 02 piles compression test.
- Pile test for 02 piles lateral load test.
- Pile test for 02 piles uplift test.

Test pile installation shall be applied as table below:


Table 1.2 Pile driving method
No. Pile No. Area Diameter
Building for Technicians and Operators -1
1 PTN-1 and Building for Technicians and Operators D450
-2
Building for Technicians and Operators -1
2 PTN-2 and Building for Technicians and Operators D350
-2
Building for Technicians and Operators -2
3 PTN-3 D350
and Swimming Pool
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 3
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

No. Pile No. Area Diameter


Apartment Style Building and Auxiliary
4 PTN-4 D350
Building
Apartment Style Building and Auxiliary
5 PTN-5 D450
Building
Building for Technicians and Operators -2
6 PTN-6 D450
and Swimming Pool

2 STANDARD REFERENCES

Requirements for testing and piling works shall conform to the latest revisions and
amendments of the following Standards.
Table 2.1: List of applicable standard and specification
The piling works shall conform to the following standards:

TCVN 6260-2009 Portland Blended Cement- Specification.

TCVN 4506: 2012 Water for concrete and mortar – Technical specifications.

TCVN 7570: 2006 Aggregates for concrete and mortar –Specifications.

TCVN 1651-2008 Steel for the reinforcement of concrete

JISA5373- 2010 Precast prestressed concrete products

TCVN 7888-2014 Pretensioned spun pile concrete piles

ASTM D1143-07(2013) Standard test method for pile under Static Axial Compression Load

ASTM D3966-07(2013) Standard Test Methods for Deep Foundations Under Lateral Load
Standard Test Methods for Deep Foundations Under Static Axial Tensile
ASTM D3689-07(2013)
Load
TCVN 9394: 2012 Pile driving and static jacking works – Construction, check and acceptance

TCVN 1961:1975 Manual arc welding

TCVN 9398:2012 Surveying in construction – General requirements

TCVN 5308-1991 Code of practice for building safety technique

TCVN 4055: 2012 Organization of construction activities

46/2015/NĐ-CP Decree of quality management of construction works

3 PREPARATION WORK
3.1 Schedule of work
- PHC D450 Class A
No. Pile No. Duration Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12
1 Pressing test pile PTN1 (D450) 1Day
2 Pressing test pile PTN5 (D450) 1Day
3 Pressing test pile PTN6 (D450) 1Day
4 Testing pile PTN1 (Compression Load Test) 2 Days
5 Testing pile PTN5 (Uplift Load Test) 1Day
6 Testing pile PTN6 (Lateral Load Test) 2 Days

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 4
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- PHC D350 Class A


No. Pile No. Duration Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12
1 Pressing test pile PTN2 (D350) 1Day
2 Pressing test pile PTN3 (D350) 1Day
3 Pressing test pile PTN4 (D350) 1Day
4 Testing pile PTN2 (Compression Load Test) 2 Days
5 Testing pile PTN3 (Lateral Test) 1Day
6 Testing pile PTN4 (Uplift Load Test) 2 Days

3.2 Organization chart


Doosan BMT
Site Representative Site Manager
Lim Kwang Jae Le Quy Duong
091 312 8811 096 128 8810

EHS.Dept.GM QA/QC.Dept.GM EHS.Dept.M


Won Ong In Kang Dae Geun Luu Dinh Man
032 734 8897 086 562 0100 090 300 3861
Arch.Dept.GM Cons. Dept.M
Seo Jeng Taek Do Thanh Kien
091 976 3657 097 291 2555

Arch.Dept.M Cons.Engineer
Lee Yong Ha Nguyen Van Lang
038 559 0538 096 811 6904

Arch.Chief.M Arch.Engineer Pile Pressing Team Testing Team


Le Cong Hai Nguyen Huu Cuong
090 966 7989 098 667 9586

3.3 Preparation
Construction site shall be prepared stably enough for machine movement and safety operation,
detail as following:
- The Subcontractor shall use steel plate for construction area of soft ground.
- Temporary facilities shall be set up and provided for the securities, safety and operation of
the whole work.

Temporary facilities include the following items:


- Set up site office, toilet, parking area. All these temporary facilities shall be set up at suitable
place which approved by the Supervisor and/or Owner.
- The Subcontractor shall use our own generators for electric supply.

3.4 Equipment and Materials


Machine and equipment used for the Project are calibrated by legal department according to
the regulation and approved before using.

All materials used for the Project shall be approved before using and submitted with quality
certificate of manufacture and testing result as the Project’s requirement.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 5
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

3.5 Survey work


Benchmark of the project includes:
- Benchmark system provided by the contractor;
- Axis plan;
- Secondary benchmark system.

Center point coordinate must be set out by total station and marked by suitable stakes.
Figure 3.1: Survey work

4 PILE SUPPLY
4.1 Delivery of PHC pile segment to site
Normally, sample testing for compressive strength shall be carried out at 3 days or 5 days, if
the strength of concrete sample reaches over 75% of designed strength (R28), those pile
segments can be delivered to the site.

To ensure that non-conforming material is not delivered at site. Any material found damaged or
unsuitable for use in permanent works will be segregated. Inspection of the conforming
materials with the Engineer.

Pile will be inspected and accepted by Engineer, there are following documents:
- Delivery certificate;
- Pile delivery slip;
- Result of concrete compression test.

The storage area of pile at the site must be a flat and stable. Each pile’s stack should have no
more than 1 layers.

When using the pile should be hanged from stack top to bottom layer by layer. Pulling and
pushing out a pile from stack inside is not permitted.

At the site, pile segments shall be arranged to have the advantage of moving equipment and
avoid damages to pile segments during execution period.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 6
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 4.1 Transporting pile segment Figure 4.2 Storage of pile segment

5 MOBILIZATION AND ASSEMBLY OF MACHINE


5.1 Mobilization and assembly of pressing machine
The capacity of Pressing machines should be more than 1.4 times maximum pressing load.

Total weight of Pressing machines should be more than 1.1 times maximum pressing load.

5.1.1 Selection of pressing machine

The number and type of Pressing machine to be used for pressing pile is shown in table
below.
No. Pressing Machine Capacity (ton) Quantity (set) Diameter of pile
1 Robot ZYJ 680B 680 01 D350, D450

Figure 5.1 Pressing machine

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 7
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

5.1.2 Sequence of pressing machine erection

Requirement to assembly and disassembly site: Space for pressing machine, transport
vehicles and service crane. The planes and hardness of ground should meet the
requirement for pressing machine erection, transport vehicles over 50 ton, service crane
over 25 ton.

Mobilization of service crane, lifting the 2 longitudinal motion legs and set them parallel.

Figure 5.2 Longitudinal motion legs

The transport vehicles go ahead between the 2 longitudinal motion legs. Low down the 4
cylinders of the Pressing machine's main part to the 2 longitudinal motion legs.

Figure 5.3 Main part of pressing machine

Lifting the 2 cross motion legs.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 8
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 5.4 Cross motion legs

Lifting the pile pressing cylinder, counter weight on the Robot’s main part.

Figure 5.5 Counter weight

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 9
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

6 PILE INSTALLATION BY PRESSING MACHINE


6.1 The procedure of pile pressing works
Pile installation will be carried out as per the following flow chart shown as below:

Fabrication of pile segments Pile delivery and inspection Erection of pile pressing machine

Installation of
Inspection with Engineer safety devices

Setting-out location of piles

Survey with Engineer

PILE INSTALLATION

Setting 1st pile segment to the location


1st STEP
Checking for vertical at 2 directions

Monitoring by Engineer

Pressing of pile by robot machine

Monitoring with Engineer

Setting next pile segment to location


NEXT STEPS
Checking for vertical at 2 directions

Monitoring by Engineer

Welding the joint by welding machine


Inspection with Engineer/
Photographic record
Continue pressing pile by pressing
machine

If not Ok
Check condition Next pile
Pmin ≤P≤ Pmax segment

Ok
Shift to
Checking pile top elevation next pile
Finishing
Inspection with Engineer
Site clean up

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 10
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

6.2 Pile installation by pressing machine


6.2.1 Pile installation by pressing method

Every fabricated pile’s segment must be checked and approved the official quality
certificates prior to be set into the designed position.

Procedure of pressing method:

The pressing machine shall be set on the desired position for pressing the pile segment
into the finish elevation specified on the approved drawings.

At the site, pile segments shall be arranged to have the advantage of moving equipment
and avoid damages to pile segments during execution period.

The following steps shall be followed:

Step 1: Setting of 1st pile segment

The 1st pile segment will be set into pressing frame by crane and the segment will be
installed to elevation top pile +1.2m to +1.4m ground surface elevation.

Figure 6.1 Installation of 1st pile segment

The pressing machine will be adjusted to ensure the plane of pressing machine is always
horizontal, and the pile is always vertical during pressing the whole pile.

Verticality of the pile can also be set by leveling the pressing machine using the circular
level meter in pressing cabin. The air bubble in the center of the level meter means the
pressing machine is in the horizontal plane. Refer to Figure below also showing picture
of circular level meter.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 11
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 6.2 Checking levelness of Pressing Machine by Circular Level Meter

Step 2: Installation of second pile segment

After setting the verticality of the 2nd pile by leveling the pressing machine, manual
checking using level bar and/or Theodolite will be conducted to verify, check and ensure
verticality in 2 directions and then install the first pile segment to the elevation top pile
+1.20m ~ +1.40m from the ground surface.

Figure 6.3 Confirmation of verticality by plumb in two directions

The 2nd pile segment will be set into pressing frame by crane. The joints between the two
pile segments will be welded connected. The 2nd pile segment will then be installed by
Pressing machine. The pile’s verticality will be checked by leveling of the pressing
machine will be set by the circular level meter and then finally checked by a level bar in
two directions after welding it on the installed first pile segment. If pressing load not
reaches Pmax, the next pile segment shall be added and welded to the second pile
segment.

Step 3: Installation of the next pile segment

The next pile segment will be set on the top of the second pile segment and then
connected by welding at the joint. The next pile segment will be pushed down by the
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 12
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

pressing machine.

The setting and pressing of succeeding pile segment will stop after attaining the required
maximum finishing load and then pressing machine will be transferred to the next pile
location.

The final pile segment will be used steel dolly pile for pressing.

Figure 6.4 Installation of next pile and succeeding pile

Step 4: Moving of equipment to next pile position

Pressing machine will be shifted to the next position.

Repeat procedure from step 1 to step 3.

Figure 6.5 Top View of pressing machine

Technical requirements of pile installation:

Deviation of pile installing: All of tolerance of co-ordinate, vertically must be ensure


acceptance tolerance follows technical TCVN 9394–2012: ''Pile Pressing and driving –
Standard for construction, checking and acceptance'' and Specification of Piling works of
Project.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 13
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- Deviation of pile center:  0.3D (D: Diameter of pile)

- Deviation of verticality: 1%

- Pressure value, pressing load versus penetrating depth during installation.

Pressing load at finishing: Pmin  P  Pmax


Table 6.1 Design load and pressing load
Pdesign Pmin (200%) Pmax(250%)
No. Type of pile
(ton) (ton) (ton)
1 PHC D350 A 70 140 175

2 PHC D450 A 120 240 300

Combination of pile, pile length and pile top elevation at finishing.

Direction of execution:

Organize and divide clearly the execution area for each machine so that the
implementation carries out conveniently and safety.

Resolve problem during pressing pile:

Some problems may arise such as:


- The tip of pile meets an obstacle cause the pile oblique more than permission.

- Pressure depth of pile reaches Lmax but pressing load less than Pmin.
- Pressing load reaches Pmax but pressure depth of pile less than Lmin.

In all above conditions, the Contractor immediately informs to the Consultant to find a
suitable and opportune resolving way.

The drawing which describes the pressing sequence is attached.

6.2.2 Welding work

Welding material, equipment and gas:

Semi-automatic welding equipment with welding wire shall be used for welding joint of
pile.
- Welding machine and gas suppliers
- Welding gun with the contact tube of 10-15mm for the current <250A and 15-25mm for the
current >250A.
- Wire feeder motor;

- Connection cables;
- Shielding gas (CO2)
- Welding wires: (0.9-1.2mm)

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 14
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 6.6 Welding machine

Welding process:
- The pile head should be cleaned by grinder first before moving to the welding position.
- Check the welding equipment: working condition: currency, machines, welding equipment:
electricity cables, welding cables, joints….
- Check the currency: during the welding process, the currency should be in range of 110-300 A
(Current) and 20-26V (Voltage).
- Check CO2 flow meter: the shield gas for using in MAG welding is CO2, the specifications of
CO2 are: percent composition: 99.8%, the out flow: 18-25l/min. The gas meter should be
checked in order to ensure that it is in normal working condition.

- Adjust the shield gas to the requirement.


- Turn on the power.
- Choose the welding mode.

- Testing the welding machines: adjust the currency and gas flow to the above requirement.

Figure 6.7 Cleaning the pile head

All welding joints shall be carried out by skilled worker, who has welding certificate, under
carefully supervise about thickness, quality as well as the verticality of two pile segments
before and after welding.
- Welding work shall be only started to meet the following conditions:
- The axis of pile segment shall be corrected at least two directions.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 15
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- The axis of second pile segment coincides with the axis of first pile segment.
- Surfaces of two pile head tightly contact together.

The welding joint shall be filling-up all around the gap between the two piles- end flanges
by at least 2 layers welding.

Figure 6.8 Welding by welder

Start welding: The pile diameter is divided into two part, each welder is in charge of
welding part. In order to ensure that the temperature shall not increase suddenly, the two
welder shall start welding in opposite position rather than in the same position, they also
need to follow the same direction during welding. Moreover, during the welding process,
the speed of welding gun movement should not exceed 240mm/min, the welder should
also weld the pile connection in at least 2 layers so that the welding height can meet the
specifications.

Keeping 10 – 15% design load during welding period for pressed pile for surface of two
piles head tightly contact.

The welding joint is met requirement to height, width and homogeneity as design before
continue pressing pile.

Checking quantity of welding joint: PT checking of 100% joints of installed piles, detail as

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 16
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

following:
- Pre-cleaning: The test surface is cleaned to remove any dirt, paint, oil, grease or any loose
scale that could either keep penetrant out of a defect, or cause irrelevant or false indications.
- Application of Penetrant: The penetrant is then applied to the surface of the item being tested.
Wait for at least 5 minutes for penetration.

- Excess Penetrant Removal: The excess penetrant is then removed from the surface towards
one direction either vertically or horizontally as the case may be. The removal method is
controlled by the type of penetrant used.
- Application of Developer: After excess penetrant has been removed, a white developer is
applied to the sample. Choice of developer is governed by penetrant compatibility and by
inspection conditions. The developer draws penetrant from defects out onto the surface to form
a visible indication, commonly known as bleed-out. Any areas that bleed out can indicate the
location, orientation and possible types of defects on the surface. Interpreting the results and
characterizing defects from the indications found may require some training and/or experience
[the indication size is not the actual size of the defect].
- Inspection: The inspector will use visible light with adequate intensity for visible dye penetrant.
Ultraviolet (UV-A) radiation of adequate intensity along with low ambient light levels for
penetrant examinations.
- Post Cleaning: The test surface is often cleaned after inspection and recording of defects.

6.2.3 Pile head temporary cutting and protection

After finishing each pile pressing, if the top of pile is higher than working ground level, the
Subcontractor will temporary cut piles head at about 20-30cm higher than working level
by manpower and portable cutting machine.

This temporary cutting level is only for movement of the pile pressing machine, and this
temporary cutting level must be always higher than designed pile cut-off level.

After temporary pile head cutting, covering the top of pile by wooden plate and sand bag
for protection of pile head during moving the pile pressing machine.

6.2.4 Piling records

Record the initial pressure: Note down the initial pressure then keep record at each 1m
or 2m interval length until the pile penetrates to the finishing depth. If the hand of the
gauge moves abnormally then record the depth and pressure on the installation record or
construction journal. Pile installation record shall be kept until the designed length is
obtained. When the pressure reaches Pmin, keep record at each 20cm and continue until
finishing for pile pressing.

The records of piling works shall contain the following:


- Number and size of pile;
- Full detail of driving and handling equipment;

- Date of production;

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 17
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- Date of pressing;
- Ground level;
- Pressure value and pressing load at interval of 1-2m depth and final pressing load;
- Interruptions of pressing;

- Period of pressing;
- Any further information required by the Architect/Engineer.

7 TESTING WORK
7.1 Scope of work
The quantities of testing work are shown in this table.
Pile Pile Design Testing
Item Work Note
No. Diameter load (ton) load (ton)
BUILDING FOR Compression
PTN-1 D450 120 300
TECHNICIANS Tests
AND OPERATORS Compression
PTN-2 D350 70 175
1 & BUILDING Tests
FOR
TECHNICIANS
AND OPERATORS
2
BUILDING FOR Pile Lateral
PTN-3 D350 6 15
TECHNICIANS Load Test
AND OPERATORS Pile Lateral
PTN-6 D450 10 25
2 & SWIMMING Load Test
POOL

APARTMENT Uplift Tests PTN-4 D350 20 50


STYLE BUILDING
Uplift Tests PTN-5 D450 35 87.5
& AUXILIARY
BUILDING

7.2 Personnel
- List of personnel for testing work is as follow:
STT Name Qualification Duty

1 Bui Tien Binh Site Engineer Site manager

2 Vu Ngoc Bao Site Engineer Tester & Reporter

3 Pham Trung Quan Worker Tester

4 Vu Duc Trong Worker Tester

5 Doan Tien Hung Worker Tester

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 18
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- Certificate:

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 19
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 20
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 21
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

7.3 Equipment
- List of equipment for testing work is as follow:

STT Equipment Serial No. Calibration No. Remark

1 Hydraulic jack 500 ton SS0108 HC03.00089 Compression Test

2 Hydraulic jack 100 ton 290508 HC03.00104 Lateral Test

3 Hydraulic jack 250 ton 16128 CN5.M.204.19 Uplift Test

4 Pressure gauge GP-10S HC02.00111 Monitoring

5 Pressure gauge D18656 AK1.0333-18 Monitoring

6 Settlement gauge LFR220 HC02.00100 Monitoring

7 Settlement gauge RNV195 HC02.00104 Monitoring

8 Settlement gauge RQM967 HC02.00090 Monitoring

9 Settlement gauge KRW136 HC02.00097 Monitoring

10 Settlement gauge KKU644 HC02.00103 Monitoring

- Calibration Certificate:

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 22
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 23
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 24
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 25
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 26
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 27
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 28
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 29
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 30
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 31
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 32
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 33
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 34
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 35
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

8 EXECUTION OF STATIC LOAD TEST


8.1 Requirement for construction of test pile
The test piles must be constructed in the same method and procedure applied for all piles in
the stage of mass construction.

All the test shall be only commenced at least 07 days after finishing installation of the pile.

Grinding the surface of pile head or pouring the SikaGrout on surface of pile head so that it is
flat and perpendicular with center line of pile before carrying out the test.

8.2 Testing equipment


Using counter-weight is pressing machinery itself The set including:

8.2.1 Equipment for loading

Using hydraulic jacks with capacity of 500 tons for test piles, total capacity of the jacks
shall be exceed by 20% or more the required maximum test load, these jacks connecting
with hydraulic pump and pressure gauge, put directly on the top of test pile to create a
load on pile center. The load on pile top is controlled by hydraulic pump of adequate
capacity with a pressure gauge.

Hydraulic Jack and pressure gauge have been calibrated.

Figure 7.1 Hydraulic jack

8.2.2 Counter – Weight methods

Main beam is steel beam: (H1210xW600xL10000mm) or I800(800x300x11000mm) or


(600x200x2650mm), placed directly on the hydraulic jack system then on pile top in a
manner that the center of main beam system and center of hydraulic jacks are all in
vertical pile centerline.

The Counter – Weight is robot’s Self- weight and the steel blocks of the pile pressing
machine (Automatic robot). The general Weight and steel blocks of the pressing machine
and cast – iron (more than 110% of maximum testing load).

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 36
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 7.2. Counter-weight is Pressing Machine’s Self- weight

8.2.3 Monitoring of pile settlement


The settlement of test pile shall be monitored by 04 dial gauges with 0.01mm precision.
They shall be fixed with reference beams of L5 with 3.0m length. The beams are set
independently to the testing system by jointing them into 2 steel bars L50mm in corners,
these bars are embedded about 1.5m into the ground, at adequate distance (more than
2.4m) between center of the testing pile and cushions, in order to eliminate effects from
displacement of piles and cushions on readings of the dial gauges.

8.3 Testing standard


Testing work shall be conformed to ASTM D1143-07(2013) - “Standard test method for pile
under Static Axial Compression Load” and specification requirement of project

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 37
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

8.4 Testing procedures


The Static load test shall be conformed to Testing procedure shall be conformed to Procedure
B: Maintained test - ASTM D1143-07(2013) - “Standard test method for pile under Static Axial
Compression Load”.
Procedure of Static Load Test for test piles
Required testing load = 250% Design load

Load step (%
Cycle Holding time for each load step
design load)
At least 1 hour until the settlement rate is less than 0.25mm per hour and
25%
with a maximum of 2 hours
50% Ditto
I 75% Ditto
100% Ditto
50% Monitoring in 30 minutes
0% Monitoring in 60 minutes
At least 1 hour until the settlement rate is less than 0.25mm per hour and
50%
with a maximum of 2 hours
100% Ditto
125% Ditto
150% Ditto
175% Ditto
200% At least 12 hour until the settlement rate is less than 0.25mm per hour
II 175% Monitoring in 30 minutes
150% Monitoring in 30 minutes
125% Monitoring in 30 minutes
100% Monitoring in 30 minutes
75% Monitoring in 30 minutes
50% Monitoring in 30 minutes
25% Monitoring in 30 minutes
0% Monitoring in 60 minutes
50% Monitoring in 20 minutes
100% Monitoring in 20 minutes
150% Monitoring in 20 minutes
200% Monitoring in 20 minutes
210% Monitoring in 20 minutes
220% Monitoring in 20 minutes
230% Monitoring in 20 minutes
III
240% Monitoring in 20 minutes
250% Monitoring in 20 minutes
200% Monitoring in 20 minutes
150% Monitoring in 20 minutes
100% Monitoring in 20 minutes
50% Monitoring in 20 minutes
0% Monitoring in 20 minutes
In each loading step, the data is obtained at each time of 1, 10, 20, 30, 45, 60, 90, 120, 180,
240, 300…, then taken interval of 60 minutes.

Test pile is failure when:


Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 38
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- The totals of pile’s settlement are greater than 15% of pile’s diameter.

* The testing shall be finished in cases:


- The procedure above is completed.
- The material on pile top is destroyed or the testing load cannot be increased because it
impossibly exceeds actual bearing capacity of the test pile.

* The testing shall be stopped when:


- Jack or dial gauge is deformed or broken.
- The joint of the load increment system or anchor system is not steady.
- The pile head cracked.
- The initial readings are not correct.

8.5 Template of Site Record


As below:
SITE RECORD OF STATIC LOAD TEST
Project: ……………………………………………….………………………

Package: ……………………………………………….………………………

Location: ……………………………………………….………………………

Work Item: ……………………………………………….………………………

Pile No.: .............. Design load: ….…. ton

Type of pile: ………… Testing load: ……... ton

Dimension: …………… Pile Length: ............(m)

Starting time: .....…..h …...’, Date …... Month...., 20...

Finishing time: ……...h …...’, Date …... Month...., 20...


Average
Value on Dial gauge
settlement Total
Elapsed Load Load Pressure reading
Time (mm) settlement
Time step (%) (ton) Gauge
(mm)
(KG/cm2) N1 N4

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 39
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

8.6 Contents of report on testing results


- General
- Features of testing piles
- Testing method
- Testing standard
- Testing equipment
- Testing procedures
- Summary of testing results
- Comments, conclusion
- Relation diagrams
- Appendix

9 EXECUTION OF STATIC LATERAL LOAD TEST


9.1 Testing equipment
9.1.1 Equipment for loading
Using hydraulic jacks with capacity of 100 tons for testing load, put perpendicularly with
the test pile to create the load applied lateral of pile. The lateral load on pile top is
controlled by hydraulic pump of adequate capacity connecting with a pressure gauge.

9.1.2 Monitoring of pile settlement


The settlement of test pile is monitored by 04 dial gauges with 0.01mm precision and
max stroke of 50mm. They are fixed with reference beams of steel stack L50x50x2mm
or I100mm with 3.0m in length. The beams are set independently to the testing system
by welding them into 2 steel bars in 2 corners, these bars are embedded about 1.5 m
into the ground, at adequate distance between the testing PHC pile and cushions, in
order to eliminate effects from displacement of piles and cushions on readings of the
dial gauges.
Auto level shall be used to check the stability of reference beams, the mount, and the
counter weight.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 40
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 9.1 Lateral load test

9.1.3 Testing standard


The Lateral load test shall be in accordance with ASTM D3966-07 (2013).

9.1.4 Testing procedure


The Lateral load test shall be conformed to Testing procedure shall be conformed to
Procedure B: Excess Loading - ASTM D3966-07 (2013) - “Standard Test Methods for
Deep Foundations Under Lateral Load”.
Procedure of lateral load test for test piles
Required testing load = 250% Design load

Load step (% of Design


Holding time
load)
25% 10 minutes
50% 10 minutes
75% 15 minutes
100% 20 minutes
125% 20 minutes
150% 20 minutes
170% 60 minutes
180% 20 minutes
190% 20 minutes
200% 60 minutes
150% 10 minutes
100% 10 minutes
50% 10 minutes
0% 10 minutes
50% 10 minutes
100% 10 minutes
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 41
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

150% 10 minutes
200% 10 minutes
210% 15 minutes
220% 15 minutes
230% 15 minutes
240% 15 minutes
250% 30 minutes
200% 10 minutes
150% 10 minutes
100% 10 minutes
50% 10 minutes
0% 10 minutes

In each loading step, the data is obtained at each time of 1, 5, 10,15, 20, 30, 45, 60
minutes. Test shall be completed when:
- Test according to the above procedure is completed.
- Material of pile is damaged.

10 EXECUTION OF STATIC TENSILE LOAD TEST


10.1 Requirement for construction of test pile
The test piles must be constructed in the same method and procedure applied for all piles in the
stage of mass construction.
The static tensile load test shall be only commenced at least 07 days after finishing installation
of the pile.

10.2 Testing equipment


10.2.1 Equipment for loading
Using hydraulic jacks with capacity of 250 tons, connecting with hydraulic pump and
pressure gauge, put directly on the top of test beam(s). Place the test beam(s) to center
the load on reaction beams or cribbing, and reaction beams to center the load on reaction
piles or cribbing. These jacks, beam etc. shall have flat, parallel bearing surfaces. The
load on pile top is controlled by hydraulic pump of adequate capacity with a pressure
gauge. Hydraulic Jack and pressure gauge have been calibrated.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 42
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Figure 10.1 Example arrangement of tensile load test

10.2.2 Monitoring of pile's upward movement


The upward movement of test pile shall be monitored by 04 dial gauges with 0.01mm
precision. They shall be fixed with reference beams of L5with 3.0m length. The beams are
set independently to the testing system by jointing them into 2 steel bars L50mm in
corners, these bars are embedded about 1.5m into the ground, at adequate distance (more
than 2.4m) between center of the testing pile and cushions, in order to eliminate effects
from displacement of piles and cushions on readings of the dial gauges.

10.3 Testing standard


Testing work shall be conformed to ASTM D3689-07 (2013) “Standard Test Methods for Deep
Foundations Under Static Axial Tensile Load” and specification requirement of project.

10.4 Testing procedures


The Static load test shall be conformed to Testing procedure shall be conformed to Procedure
B: Maintained test - ASTM D3689-07(2013) - “Standard Test Methods for Deep Foundations
Under Static Axial Tensile Load”.

Procedure of Static Tensile Load Test for test piles


Required testing load = 250% Design load

Load step (%
Cycle Holding time for each load step
design load)
At least 1 hour until the uplift movement rate is less than 0.25mm
25% per hour and with a maximum of 2 hours
50% Ditto
I
75% Ditto
100% Ditto
50% Monitoring in 30 minutes

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 43
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

0% Monitoring in 60 minutes
At least 1 hour until the uplift movement rate is less than 0.25mm
50%
per hour and with a maximum of 2 hours
100% Ditto
125% Ditto
150% Ditto
175% Ditto
At least 12 hour until the settlement rate is less than 0.25mm per
200%
hour
II 175% Monitoring in 30 minutes
150% Monitoring in 30 minutes
125% Monitoring in 30 minutes
100% Monitoring in 30 minutes
75% Monitoring in 30 minutes
50% Monitoring in 30 minutes
25% Monitoring in 30 minutes
0% Monitoring in 60 minutes
50%, Monitoring in 20 minutes
100% Monitoring in 20 minutes
150% Monitoring in 20 minutes
200% Monitoring in 20 minutes
210% Monitoring in 20 minutes
220% Monitoring in 20 minutes
230% Monitoring in 20 minutes
III
240% Monitoring in 20 minutes
250% Monitoring in 120 minutes
200% Monitoring in 20 minutes
150% Monitoring in 20 minutes
100% Monitoring in 20 minutes
50% Monitoring in 20 minutes
0% Monitoring in 20 minutes

In each loading step, the data is obtained at each time of 1, 10, 20, 30, 45, 60, 90, 120, 180,
240, 300..., then taken interval of 60 minutes.
* Test pile is failure when:
- The totals of pile's uplift movement are greater than 15% of pile's diameter.
* The testing shall be finished in cases:
- The procedure above is completed.
- The material on pile top is destroyed or the testing load cannot be increased because it
impossibly exceeds actual bearing capacity of the test pile.
* The testing shall be stopped when:

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 44
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- Jack or dial gauge is deformed or broken.


- The joint of the load increment system or anchor system is not steady.
- The pile head cracked.
- The initial readings are not correct.
10.5 Sample of Site Record
For instance of Site Record as next page.

SITE RECORD OF STATIC TENSILE LOAD TEST


Project: ……………………………………………….………………………

Package: ……………………………………………….………………………

Location: ……………………………………………….………………………

Work Item: ……………………………………………….………………………

Pile No.: .............. Design load: ………. ton

Type of pile: ………… Testing load: …….... ton

Dimension: ………… Pile Length: .............. (m)

Starting time: .....…..h …...’, Date …... Month...., 20...

Finishing time: ……...h …...’, Date …... Month...., 20...

Average
Value on Dial gauge
movement Total Uplift
Elapsed Load step Load Pressure reading
Time (mm) movement
Time (%) (ton) Gauge
(mm)
(KG/cm2) N1 N4

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 45
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

EMPLOYER CONSULTANT CONTRACTOR TESTING UNIT

10.6 Contents of report on testing results


- General
- Features of testing piles
- Testing method
- Testing standard
- Testing equipment
- Testing procedures
- Summary of testing results
- Comments, conclusion
- Relation diagrams
- Appendix

11 QUANLITY ASSURANCE PROCEDURE


11.1 PHC Pile supply
Every fabricated pile’s segment shall be inspected. The inspection shall be made on
appearance, shape, dimensions:
- Appearance: PHC pile shall be free from such defects as harmful flaw and crack.
- Shape: The PHC pile shall be composed of main body of hollow cylindrical shape, and shall
have the suitable end, jointing end or head.
Table 11.1: Dimension and dimensional tolerance

External diameter Thickness of pile Length


Classification
mm mm m

D300 – D600 - 2 to + 5 + Not specified ± 0.3(%) of


D700-D1200 - 4 to + 7 -0 length

11.2 Pile installation


Check the calibration of all equipment.

Termination criterial:
- For pile pressing: Final Pressing loads are obtained Pmin ≤ Pfinal ≤ Pmax.
- Welding checking:
- Checking the certification of worker.
- Checking all the welding lines about: dimensions, height, number of layer welding, clean
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)
Work Item : Testing Piling Works Page 46
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

lines and quality of line welding.


- Deviation of pile installing: All of tolerance of coordinate, vertically must be ensure
acceptance tolerance follows technical TCVN 9394-2012: “Pile Pressing and Driving –
Standard for construction, checking and acceptance” and Specification of Piling works of
project are bellows:
- Inclined to vertical: ≤ 1%.
- Central pile deviation: ≤ 0.3D (D: diameter of pile).

11.3 Testing work


Checking the certification and accuracy of all equipment testing.

Installing the equipment comply with the design.

Executing the regulations, accuracy of all step in testing procedure.

Testing engineer always monitoring, writing the test result.

11.4 Documents for final acceptance


Final documents of piling work consist of the following:
- Input material documents: Cement, Sand, Coarse aggregate, fine aggregate, admixture and
proportions of concrete mix design, rebar testing result.
- Pile Quality documents: delivery order, factory certificate, results of compressing concrete
sample at 7 days, 28days.
- Monitoring of pile installation documents: Pilling installing monitoring sheet, diary.
- As - built document: Deviation of pile location.

12 IMPLEMENTATION
12.1 Manpower mobilization plan
12.1.1 Site organization

Project Department contain 5 sections:


- QA/QC/ section
- Construction Management section

- Geotechnical section
- HSE section
- Survey section.

QA/QC section in charge of the implementation of test and inspection plan, inspection
sheets, all document of the project and working quantity for payment stages.

Construction Management section is in charge of the implementation of construction


schedule, working procedure and site arrangement plan.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 47
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Equipment Management section in charge of monitoring and advising construction


section.

HSE section is in charge of safety training and controlling on site.

Survey section is in charge of controlling benchmark, axis plan and as-built drawing.

12.1.2 Duties of Major Personnel

Main personnel of the project as below:


- Project manager;

- Site manager;
- Site engineer;
- Quality control engineer;
- HSE engineer;
- Geotechnical engineer;

- Surveyor.
- Duties of each personnel position as below:

Duty of Project Manager


- Approving and submitting the site construction schedule plan, mobilization plan (for manpower,
machine, material) assurance of safety, quality plan in accordance with the Project’s
requirements,
- Approving the method statement, quality control plan and safety plan,
- Being responsible for manpower organization, assigning for management of construction works,

- Proposing and taking part in choosing suppliers,

- Approving cost plan and control Project’s cost,


- Taking part in dealing, negotiating subcontract and scope of works,

- Participating meetings discussion with the Main contractor, the Engineer for matters beyond
capacity and responsibility the Site manager,
- Final reports.

Duty of Site manager:


- Setting up and being responsible site construction schedule plan, mobilization plan (for
manpower, machine, material) assurance of safety, quality plan in accordance with the Project’s
requirements, machine, material for assurance of safety, quality and schedule as Project’s
requirements,
- Setting up the method statement, quality control plan, safety plan,
- Proposing the site organization for detail construction execution,
- Propose the cost method and plan,
- Being present on site for the implementation of works from mobilization of plant, manpower,

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 48
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

machine, material to executing and completing works including test work of all type according
to the requirement of safety, quality and schedule approved,
- Daily site arrangement in line with detailed schedule. Supervise activities of manpower, re-
organizing if necessary,
- Holding and being obliged to take care of internal meetings for daily construction,
- Report to Project’s parties, following close to implementation of progress and accomplishment
record of daily work, quantity inspection and approval,
- Manager and follow and evaluate suppliers/subcontractors,
- Participate in meetings with the Client and/or Engineer for exchanging information, reporting
working plan, taking action for any site work matters that need to be solved,
- Site Manager is supposed to understand thoroughly Project’s Specification and requirements.
He is the chief site staff, he takes care of Contract’s obligation implementation in terms of
schedule, safety, quality and approved acceptance of works.

Duty of Site engineer:


- Being assistant, reporting to the Site Manager,
- Implementing schedule, works method statement ensuring quality, in progress and safety way,
- Working with execution staff, with the main contractor and/or Engineer,

- Taking care of site inspection and work approval in writing,


- Coordinating materials and machines,

- Supervising operators, construction teams and supplier/Subcontractor,

- Recording daily work.

Duty of Quality Control engineer:


- Independently responsible for quality of works,
- Submitting for approval: Quality plan, material plan, inspection-testing plan,
- Taking part in and checking works procedure, implementing test, calibration and acceptance,

- Supervising construction quality, accepting works part and works items (within BMT, the Owner/
Consultant)

- Shop drawings, controlling drawings and quality documents, as-built documents,


- Controlling forms records of acceptance works,
- Report on non-conformity and countermeasure and supervise remedial/rectification,
- Implement site diary,
- Controlling completion quantity, progress payment and final payment of the Project.

Duty of HSE officer:


- Setting up plan for safety working, security, site cleaning,

- Implementing and controlling safety plan, environmental affection of site activities,

- Taking care health of all site team in compliance with regulation,

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 49
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

- Ensure following safety regulation, coordinating with Engineer for all construction manner,
working environment, machine and equipment,
- Ensure following and supervising personal protection by using equipment,
- Check and test machine and equipment for safety at intervals,
- Execute and implement safety training all persons working on site,
- Provide information in order to prevent danger; collect, analyze safety data and disperse,
- In case of incident or accident, HSE officer shall be the first person to act, he find out reason
and proposes improvement method.

Duty of Geotechnical engineer:


- Comply with state and local regulations, laws, rules and company’s rules. Be subject to the
management of Site manager.
- To study the geotechnical documents to advise the construction team
- To monitor and supervise the pile installation results during the test pile works

Duty of Surveyor:
- Responsible for all surveying works,

- Receive and hand over survey benchmarks, locating and setting out building and axis, assuring
precision and auditing hand-over benchmarks,
- Set up method for survey, work out location of piles, carry all measuring on site.

- Involving in the technical inspection document.

- Report to Site manager all matters related to surveyor, and other works assigned by the senior
staff.

12.2 Machine and equipment mobilization plan


The list and plan for the mobilization of equipment and machine are detailed in Appendix 14.4
List of equipment

12.3 Construction schedule plan


12.3.1 Schedule guarantees system

Schedule is guaranteed by the following methods:

After signing the contract, site organization shall be established, in which includes
experienced and educated people. Have job description for each position for the smooth
operation of the site organization. Project information shall be informed to each person
by kick-off meeting. Organize, arrange and balance resources reasonably and efficiently.

Establish and control construction schedule in month, week, day. Record and update daily
construction schedule for controlling. From that, optimize construction organization and
take action for overcoming in case of late schedule.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 50
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Control the duration of repetitive work, optimize working procedure and improve
construction productivity.

Organize internal training for improve working skill and specification capacity of manpower.
Organize extra activities for encouraging personnel’s spirit.

12.3.2 Risk management

BMT established our own risk management for ensuring project schedule within planned
budget and meeting project specification. In theory, risk is defined as a positive or negative
deviation of a variable from its expected value. In fact, risk is understood only as a loss.
The aim of risk management is to response and control loss. The risk management
process comprises several steps as below:
- Risk identification;
- Risk assessment;
- Risk response;
- Risk monitoring and control.

Risk identification is the first and perhaps the most important step in the risk management
process, as it attempts to identify the source and type of risks. It includes the recognition
of potential risk event conditions in the construction.

The risk assessment comprises the qualitative assessment and quantitative


measurement of individual risks including the interrelationship of their effects. Qualitative
risk analysis assesses the impact and likelihood of the identified risk and develops
prioritize list of the risks for further analysis or direct mitigation. Quantitative risk analysis
attempts to estimate the frequency of risk and the magnitude of their consequences.

There are four strategies for risk response are risk avoidance, risk transfer, risk mitigation
and risk acceptance.

The goal of risk controlling is not to eliminate risks completely from the project. The
monitoring of the risk helps guarantee that the risk position of the project corresponds to
the risk situation strived for.

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 51
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

12.4 Job safety analysis


POTENTIAL RELATED
WORK ITEM PRECAUTION MEASURE
HAZARD PERSONS
Must have certificates for
all machines and
equipment. Before Operator,
1 operating, check the engineer,
Surround people
surrounding area, make worker
affected because
1 sure do not have and
of the operation
obstacles
of crane
Get away from the
All worker at
2 preparation area of
site
machines and equipment

Check the underground


1
Unstable before operating
2
underground For unstable underground,
2
place plate on
Operator,
Make sure the capacity of engineer,
1 machines and equipment worker
Lifting and low- before use
1 down pile and Overload of
3
heavy item crane
Move the crane near the
2 heavy item to ensure the
capacity of crane

Check the cable, hook


1
before use Operator,
Heavy item falling
4 engineer,
down
worker
2 Check the brake system

File falling down,


Do not stand under the Operator,
5 damage for 1
hanging pile engineer
worker

The permit distance to pull


Pile cracking, 1
pile is <10m Operator,
piling machine
6 engineer,
falling down while Pull the pile near the piling
worker
pulling 2 machine then lifting the
hammer
The security cooperating
with the responsible
1
Mobilization and people to guide vehicle go Driver,
Accident while in an out the site
transportation security,
2 1 erecting and
piling machine, engineer,
demounting Erecting machines and
crane to the site operator
equipment at large place,
2
out of the construction
area

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 52
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Make sure tight the pile on


1 truck, do not use the truck
Accident while out of capacity
Driver,
2 delivering pile to
worker
the site
2 Drive in a right speed

The driver must stop and


check the distance
1 between the truck and the
Low electrical line electrical line when go in Driver,
1 on the way and out the site engineer,
access to the site Must have responsible worker
person to notice the
2
moving line of machines
and equipment
The move of piling
3 machine and Check the underground
1
crane before operating
Unstable Engineer,
2
underground For unstable underground, worker
2 need arrange the
excavator to stable it
The operator must have
Falling down of 1 Operator,
certificate
3 machine while engineer,
moving worker
2 Check the moving line

Earth connecting for


1
electrical equipment
Short circuit Operator,
1 because of rain, engineer,
storm worker
4 Electrical use Check regularly cover the
2
welding machine, knife, ...

Operator shall have


2 Because of user The operator
Certificate of working …

Place at dry place, get


1
away from fire Engineer,
Fire and explode Gas and oil
5 1 worker, store
at site leaking
Gather fuel at a private keeper
2
area with notice board

Accident for Get stuck at pile Park the vehicle at the


6 1 1 All persons
people and vehicle installed right place

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 53
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

on site Protect and notice all Engineer,


2
installed piles worker

Occupation Equip protection clothes


2 All persons
disease for all persons at site

Check all machines and


1
equipment before using

Must repair, maintain all Operator,


Tools and 2 machines and equipment
1 engineer,
equipment failure before moving to the site worker

While operating, if have an


Operating, accidents, must stop
3
maintaining and working then check and
7 repairing repair
equipment and
machines Do not throw tools and
1
equipment from height
Tools and Operator,
2 equipment falling engineer,
down from height worker
Have notice board for
2
each area

Operator,
Workers falling Wear safety rope when
3 engineer,
down from height working at height over 2m
worker

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 54
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

13 PROFILE OF LABORATORY
13.1 COMPANY INFORMATION
Company name: BACDANG TESTING SURVEY AND CONSTRUCTION JOINT STOCK
COMPANY.
Trading name: BACDANG TESTING SURVEY AND CONSTRUCTION JOINT
STOCK COMPANY
Abbreviation: BACHDANGTSC
Address: No. 268 Tran Nguyen Han,Niem Nghia Ward, Le Chan District, Hai Phong City
LAS-XD09 Building Materials Laboratory was recognized by the Ministry of Construction and
granted the operating license to the Laboratory for the first time in 1988 and for the ninth
time in 2014, issued ISO 9001-2008 Certification in August 2010.
Decided by the Ministry of Construction to establish the TESTING AND SURVEY
CONSTRUCTION CENTER in accordance with Decision No. 1912 QD - BXD dated
14/11/2001.Transformed the operation model into a joint stock company according to
Decision No. 54/ QD - HDQT dated 24/6/2016 of the Board of Directors of Bach Dang
Construction Corporation (Business Registration No. 0201734963 dated 19/07/2016)
Business license No.: 0201734963 by the Department of Planning and Investment of Hai
Phong city of July 19th 2016.
Certificate of registration tax code No. 00201734963 of July 19th 2016
Tax management office: Haiphong City tax department
Leader: Tran Huu Son - Director
Bank account number VNĐ: 16 031 485 100 9154
At Vietnam Export Import Joint stock Commercial Bank – Haiphong Branch
Telephone: 0225 3856433
Email: bachdangtsc@gmail.com

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 55
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

LIST OF LEADER

Mr. Tran Huu Son /


Chaiman of Managing Board
Director

Mr. Vu Ngoc Chau Mr. Bui Tien Binh


Vice Director Vice Director

Mr. Nguyen Van Nam De Ms. Dang Thi Mat Mr. Le Ba Thanh Dep
puty laboratory chief Laboratory Chief uty Laboratory chief

Mr. Vu Van Tam Site Mr. Pham Hong Truong Mr. Dang Ba Ca Site
Laboratory Manager Site Laboratory Manager Laboratory Manager

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 56
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 57
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 58
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 59
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

13.2 MAIN ACTIVITIES


- To carry out quality tests of the construction materials, automobile road bases, port
yards, geological survey of construction projects, static compression load tests for
foundations as well as for the reinforced concrete piles, pile quality testing by PIT,
PDA and ultrasonic devices.
- To test metals and metal welding joints using ultrasonic method.
- To provide consulting, supervising and managing services to construction projects.
- To carry out researches, applications and transfer of advanced technologies
regarding construction and measurement fields as well as trial production of all
kinds of construction materials suitable to coastal areas.
- Quality test and control to certify satisfaction to the project’s quality requirement.
13.3 QUALITY MANAGEMENT SYSTEM
13.3.1 Quality Management System

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 60
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 61
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

13.4 LABORATORY CERTIFICATE

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 62
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 63
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 64
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 65
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 66
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 67
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 68
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 69
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 70
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 71
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 72
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 73
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 74
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 75
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 76
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 77
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 78
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 79
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 80
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 81
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 82
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 83
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 84
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 85
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 86
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 87
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 88
[Housing Complex] Method Statement for Test Piling Works
NS2-DD09-P0UYK-770001

14 TESTING PILE LAYOUT MASTER PLAN

Project : Nghi Son 2 BOT Thermal Power Plant( 2 x 600MW)


Work Item : Testing Piling Works Page 89

You might also like