TCL Chennai Soil Stabilization Works - Micropiling Project Subject
TCL Chennai Soil Stabilization Works - Micropiling Project Subject
TCL Chennai Soil Stabilization Works - Micropiling Project Subject
120 Rmtr length of shore line ( Approx 120nos depending on the profile may increase or decrease as per Site)
Mobilization of necessary men and
1 machinery, marking excavation line and
piles
Micro pile boring 4P/day - 1Rigs
Micro pile grouting 4piles/day
Micro pile Concreting 120nos of piles
Excavation from 0.0m to 1.0m depth
and fixing capping beam 20mtr/day ISMB -200 Welding & fixing
2
weldmesh fixing ,nailing and 240Sqm shotcreting+530 nos
Shotcreting nails
Excavation from 1.0m to 2.5m 180Sqm+120 nos
depth,weldmesh fixing,nailing and GR Nails+798 nos
3
grouted nailing, whaler beam fixing soil nail 120 Rmtr W
and Shotcreting beam
Excavation from 2.5m to 4.0m
180Sqm+120 nos GR
depth,weldmesh fixing,nailing and
4 Nails+798 nos soil nail
grouted nailing, whaler beam fixing
120 Rmtr W beam
and Shotcreting
Excavation from 4.0m to 5.5m
depth,weldmesh fixing and grouted
5 180Sqm+120 nos GR
nailing, whaler beam fixing and
Shotcreting
Excavation from 5.5m to 7.0m
180Sqm+60 nos GR
depth,weldmesh fixing and grouted
6 Nails+ 120 Rmtr W
nailing, whaler beam fixing and
beam
Shotcreting