Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

BOQ and Estimates - CWR F

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 715

ABSTRACT

Shape and Type of Tank:- Reactangular with flat top slab

Capacity of SBC Earthquake Total Cost


Sr. No. Rate Rs. Per litr
CWR (KL) (T/sqm) Zone (in Rs.)

1 100 KL 10 Zone II 711248.770542 7.12 Zone III


2 150 KL 10 Zone II 897180.530926 5.99 Zone III
3 200 KL 10 Zone II 1128936.83614 5.65 Zone III
4 250 KL 10 Zone II 1374622.31518 5.5 Zone III
5 300 KL 10 Zone II 1610354.40969 5.37 Zone III
6 400 KL 10 Zone II 1999315.46492 5.00 Zone III
7 500 KL 10 Zone II 2390247.32784 4.79 Zone III
8 600 KL 10 Zone II 2768808.26054 4.62 Zone III
9 100 KL 10 Zone III 754749.531597 7.55
10 150 KL 10 Zone III 954111.696143 6.37
11 200 KL 10 Zone III 1202840.05175 6.02
12 250 KL 10 Zone III 1466014.89882 5.87
13 300 KL 10 Zone III 1718676.91465 5.73
14 400 KL 10 Zone III 2133159.44791 5.34
15 500 KL 10 Zone III 2552635.22112 5.11
16 600 KL 10 Zone III 2957550.04809 4.93
17 100 KL 10 Zone IV 798274.442547 7.99
18 150 KL 10 Zone IV 1029260.83423 6.87
19 200 KL 10 Zone IV 1300392.29636 6.51
20 250 KL 10 Zone IV 1586653.10923 6.35
21 300 KL 10 Zone IV 1831295.13021 6.11
22 400 KL 10 Zone IV 2309833.50546 5.78
23 500 KL 10 Zone IV 2766987.24026 5.54
24 600 KL 10 Zone IV 3206689.20767 5.35
25 100 KL 7 Zone II 801333.27801 8.02
26 150 KL 7 Zone II 1017043.53821 6.79
27 200 KL 7 Zone II 1300339.60472 6.51
28 250 KL 7 Zone II 1586027.93074 6.35
29 300 KL 7 Zone II 1872276.96527 6.25
30 400 KL 7 Zone II 2335275.03957 5.84
31 500 KL 7 Zone II 2809875.88635 5.62
32 600 KL 7 Zone II 3264739.4616 5.45
33 100 KL 7 Zone III 853226.374003 8.54
34 150 KL 7 Zone III 1085961.00415 7.24
35 200 KL 7 Zone III 1391383.09719 6.96
36 250 KL 7 Zone III 1698561.07593 6.8
37 300 KL 7 Zone III 1993293.45054 6.65
38 400 KL 7 Zone III 2502714.98003 6.26
39 500 KL 7 Zone III 3014226.63548 6.03
40 600 KL 7 Zone III 3503074.36926 5.84
41 100 KL 7 Zone IV 922464.599683 9.23
42 150 KL 7 Zone IV 1176932.0592 7.85
43 200 KL 7 Zone IV 1511560.50726 7.56
44 250 KL 7 Zone IV 1847104.8276 7.39
45 300 KL 7 Zone IV 2152949.47139 7.18
46 400 KL 7 Zone IV 2723735.70143 6.81
47 500 KL 7 Zone IV 3287957.02642 6.58
48 600 KL 7 Zone IV 3817676.44737 6.37
49 100 KL 18 Zone II 682879.040048 6.83
50 150 KL 18 Zone II 868198.42984 5.79
51 200 KL 18 Zone II 1082488.51458 5.42

52 250 KL 18 Zone II 1316401.84839 5.27


53 300 KL 18 Zone II 1536096.92512 5.13
54 400 KL 18 Zone II 1902900.139 4.76
55 500 KL 18 Zone II 2267037.39964 4.54
56 600 KL 18 Zone II 2621836.65893 4.37
57 100 KL 18 Zone III 722765.337811 7.23
58 150 KL 18 Zone III 919707.988458 6.14
59 200 KL 18 Zone III 1148149.4078 5.75
60 250 KL 18 Zone III 1397158.87823 5.59
61 300 KL 18 Zone III 1631045.33075 5.44
62 400 KL 18 Zone III 2018692.50058 5.05
63 500 KL 18 Zone III 2406264.21129 4.82
64 600 KL 18 Zone III 2782183.6975 4.64
65 100 KL 18 Zone IV 775415.250859 7.76
66 150 KL 18 Zone IV 987700.605834 6.59
67 200 KL 18 Zone IV 1234821.78685 6.18
68 250 KL 18 Zone IV 1503758.15761 6.02
69 300 KL 18 Zone IV 1756377.22619 5.86
70 400 KL 18 Zone IV 2171538.41787 5.43
71 500 KL 18 Zone IV 2590043.60266 5.19
72 600 KL 18 Zone IV 2993841.78842 4.99
% age increase
for III

0 7.55 Zone IV 798274.442547 7.99 6%


0 6.37 Zone IV 1029260.83 6.87 6%
0 6.02 Zone IV 1300392.30 6.51 7%
0 5.87 Zone IV 1586653.10923 6.35 7%
0 5.73 Zone IV 1831295.13 6.11 7%
0 5.34 Zone IV 2309833.51 5.78 7%
0 5.11 Zone IV 2766987.24026 5.54 7%
0 4.93 Zone IV 3206689.20767 5.35 7%
% age
increase for
IV 12500
12% 100 25000
15% 150
15% 200
15% 250
14% 300
16% 400
16% 500
16% 600
100
150
200
250
300
400
500
600 6.709957
100
150
200
250
300
400
500
600
100 12.64045
150
200
250
300
400
500
600
100
150
200
250
300
400
500
600
100
150
200
250
300
400
500
600
100 0.29 4.245974
150
200

250
300
400
500
600
100
150
200
250
300
400
500
600
100
150
200
250
300
400
500
600
ABSTRACT
Shape and Type of Tank:- Reactangular with flat top slab
Capacity of SBC Earthquake Total Cost
Sr. No. Rate Rs. Per litr
CWR (KL) (T/sqm) Zone (in Rs.)
1 100 KL 10 Zone II 711248.770542 7.12 100
2 150 KL 10 Zone II 897180.530926 5.99 150
3 200 KL 10 Zone II 1128936.83614 5.65 200
4 250 KL 10 Zone II 1374622.31518 5.5 250
5 300 KL 10 Zone II 1610354.40969 5.37 300
6 400 KL 10 Zone II 1999315.46492 5.00 400
7 500 KL 10 Zone II 2390247.32784 4.79 500
8 600 KL 10 Zone II 2768808.26054 4.62 600
9 100 KL 10 Zone III 754749.531597 7.55 100
10 150 KL 10 Zone III 954111.696143 6.37 150
11 200 KL 10 Zone III 1202840.05175 6.02 200
12 250 KL 10 Zone III 1466014.89882 5.87 250
13 300 KL 10 Zone III 1718676.91465 5.73 300
14 400 KL 10 Zone III 2133159.44791 5.34 400
15 500 KL 10 Zone III 2552635.22112 5.11 500
16 600 KL 10 Zone III 2957550.04809 4.93 600
17 100 KL 10 Zone IV 798274.442547 7.99 100
18 150 KL 10 Zone IV 1029260.83423 6.87 150
19 200 KL 10 Zone IV 1300392.29636 6.51 200
20 250 KL 10 Zone IV 1586653.10923 6.35 250
21 300 KL 10 Zone IV 1831295.13021 6.11 300
22 400 KL 10 Zone IV 2309833.50546 5.78 400
23 500 KL 10 Zone IV 2766987.24026 5.54 500
24 600 KL 10 Zone IV 3206689.20767 5.35 600
25 100 KL 7 Zone II 801333.27801 8.02 100
26 150 KL 7 Zone II 1017043.53821 6.79 150
27 200 KL 7 Zone II 1300339.60472 6.51 200
28 250 KL 7 Zone II 1586027.93074 6.35 250
29 300 KL 7 Zone II 1872276.96527 6.25 300
30 400 KL 7 Zone II 2335275.03957 5.84 400
31 500 KL 7 Zone II 2809875.88635 5.62 500
32 600 KL 7 Zone II 3264739.4616 5.45 600
33 100 KL 7 Zone III 853226.374003 8.54 100
34 150 KL 7 Zone III 1085961.00415 7.24 150
35 200 KL 7 Zone III 1391383.09719 6.96 200
36 250 KL 7 Zone III 1698561.07593 6.8 250
37 300 KL 7 Zone III 1993293.45054 6.65 300
38 400 KL 7 Zone III 2502714.98003 6.26 400
39 500 KL 7 Zone III 3014226.63548 6.03 500
40 600 KL 7 Zone III 3503074.36926 5.84 600
41 100 KL 7 Zone IV 922464.599683 9.23 100
42 150 KL 7 Zone IV 1176932.0592 7.85 150
43 200 KL 7 Zone IV 1511560.50726 7.56 200
44 250 KL 7 Zone IV 1847104.8276 7.39 250
45 300 KL 7 Zone IV 2152949.47139 7.18 300
46 400 KL 7 Zone IV 2723735.70143 6.81 400
47 500 KL 7 Zone IV 3287957.02642 6.58 500
48 600 KL 7 Zone IV 3817676.44737 6.37 600
49 100 KL 18 Zone II 682879.040048 6.83 100
50 150 KL 18 Zone II 868198.42984 5.79 150
51 200 KL 18 Zone II 1082488.51458 5.42 200

52 250 KL 18 Zone II 1316401.84839 5.27 250


53 300 KL 18 Zone II 1536096.92512 5.13 300
54 400 KL 18 Zone II 1902900.139 4.76 400
55 500 KL 18 Zone II 2267037.39964 4.54 500
56 600 KL 18 Zone II 2621836.65893 4.37 600
57 100 KL 18 Zone III 722765.337811 7.23 100
58 150 KL 18 Zone III 919707.988458 6.14 150
59 200 KL 18 Zone III 1148149.4078 5.75 200
60 250 KL 18 Zone III 1397158.87823 5.59 250
61 300 KL 18 Zone III 1631045.33075 5.44 300
62 400 KL 18 Zone III 2018692.50058 5.05 400
63 500 KL 18 Zone III 2406264.21129 4.82 500
64 600 KL 18 Zone III 2782183.6975 4.64 600
65 100 KL 18 Zone IV 775415.250859 7.76 100
66 150 KL 18 Zone IV 987700.605834 6.59 150
67 200 KL 18 Zone IV 1234821.78685 6.18 200
68 250 KL 18 Zone IV 1503758.15761 6.02 250
69 300 KL 18 Zone IV 1756377.22619 5.86 300
70 400 KL 18 Zone IV 2171538.41787 5.43 400
71 500 KL 18 Zone IV 2590043.60266 5.19 500
72 600 KL 18 Zone IV 2993841.78842 4.99 600
12500
25000

6.709957

12.64045
0.29 4.245974
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 490.09 m³ 164 80374.6944
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 19.96 m³ 4280 85421.952
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 52.32 m³ 7500 392416.2188
(b) Nominal slab 17.48 m³ 7500 131130
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 57.23 m³ 7700 440676.4824
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3991.68 kg 68 271434.24


Columns 270.08 kg 68 18365.10126
Vertical wall 7022.4 kg 68 477523.2
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 41.54 Sq.m 162 6729.589279
Column 23.02 Sq.m 254 5845.888176
Container 492.31 Sq.m 269 132430.6368
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 246.15 m² 220 54153.792


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 2993841.788

Total Cost 2993841.788


Cost of CWR/L 4.99

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.039598
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 396.95 m³ 164 65099.8656
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 19.96 m³ 4280 85421.952
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 43.36 m³ 7500 325193.022
(b) Nominal slab 13.67 m³ 7500 102555
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 50.05 m³ 7700 385394.4864
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3326.40 kg 68 226195.2


Columns 270.08 kg 68 18365.10126
Vertical wall 6160 kg 68 418880
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 38.01 Sq.m 162 6158.04457
Column 23.02 Sq.m 254 5845.888176
Container 444.90 Sq.m 269 119678.057
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 222.45 m² 220 48938.9824


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2590043.603

Total Cost 2590043.603


Cost of CWR/L 5.18

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.00296
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 331.53 m³ 164 54371.1168
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 16.63 m³ 4280 71184.96
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 33.70 m³ 7500 252783.1776
(b) Nominal slab 10.43 m³ 7500 78255
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 43.12 m³ 7700 332042.9728
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2550.24 kg 68 173416.32


Columns 260.43 kg 68 17708.91388
Vertical wall 5174.4 kg 68 351859.2
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 32.18 Sq.m 162 5213.868549
Column 23.02 Sq.m 254 5845.888176
Container 401.14 Sq.m 269 107906.4448
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 200.57 m² 220 44125.312


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2171538.418

Total Cost 2171538.418


Cost of CWR/L 5.43

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.04492
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 249.48 m³ 164 40914.72
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 13.31 m³ 4280 56947.968
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 25.88 m³ 7500 194117.3128
(b) Nominal slab 7.41 m³ 7500 55586.25
(iii) Columns 1.42 m³ 7500 10633.07219
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 36.81 m³ 7700 283429.916
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1995.84 kg 68 135717.12


Columns 173.62 kg 68 11805.94259
Vertical wall 4435.2 kg 68 301593.6
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 20.40 Sq.m 162 3304.552205
Column 15.34 Sq.m 254 3897.258784
Container 346.44 Sq.m 269 93191.9296
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 173.22 m² 220 38108.224


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1756377.226

Total Cost 1756377.226


Cost of CWR/L 5.85

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.126866
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 214.00 m³ 164 35095.7376
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.87 m³ 4280 37965.312
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 20.22 m³ 7500 151614.3668
(b) Nominal slab 5.90 m³ 7500 44237.8125
(iii) Columns 1.42 m³ 7500 10633.07219
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 31.91 m³ 7700 245697.76
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1609.69 kg 68 109458.8473


Columns 173.62 kg 68 11805.94259
Vertical wall 3942.4 kg 68 268083.2
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 22.46 Sq.m 162 3638.017152
Column 15.34 Sq.m 254 3897.258784
Container 319.09 Sq.m 269 85834.672
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 159.54 m² 220 35099.68


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1503758.158

Total Cost 1503758.158


Cost of CWR/L 6.02

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.157747
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 167.43 m³ 164 27458.3232
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.87 m³ 4280 37965.312
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 16.17 m³ 7500 121270.2183
(b) Nominal slab 4.39 m³ 7500 32906.25
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 25.95 m³ 7700 199851.8861
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1154.33 kg 68 78494.77392


Columns 104.81 kg 68 7126.818557
Vertical wall 3203.2 kg 68 217817.6
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 20.00 Sq.m 162 3239.966822
Column 12.08 Sq.m 254 3068.652412
Container 288.39 Sq.m 269 77575.98464
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 144.19 m² 220 31722.5216


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1234821.787

Total Cost 1234821.787


Cost of CWR/L 6.17

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.188365
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 131.95 m³ 164 21639.3408
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete
- -
(a) PCC 6.65 m³ 4280 28473.984
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 9.74 m³ 7500 73061.86388
(b) Nominal slab 2.96 m³ 7500 22165.3125
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 22.12 m³ 7700 170328.312
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 693.34 kg 68 47147.24902


Columns 76.86 kg 68 5226.333608
Vertical wall 2710.4 kg 68 184307.2
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 13.46 Sq.m 162 2181.053952
Column 12.08 Sq.m 254 3068.652412
Container 252.81 Sq.m 269 68004.9216
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 126.40 m² 220 27808.704


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 987700.6058

Total Cost 987700.6058


Cost of OHSR/L 6.58

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 90.92 m³ 164 14911.1424
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 5.54 m³ 4280 23728.32
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 7.51 m³ 7500 56334.67686
(b) Nominal slab 1.48 m³ 7500 11126.25
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 16.99 m³ 7700 130855.4016
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 464.63 kg 68 31594.82052


Columns 76.86 kg 68 5226.333608
Vertical wall 2094.4 kg 68 142419.2
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the CWR
including the work of making sub base
& base of approved materials
8.50 m³ 4280 36380
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 11.36 Sq.m 162 1840.132547
Column 12.08 Sq.m 254 3068.652412
Container 205.99 Sq.m 269 55411.4176
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 103.00 m² 220 22658.944


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 775415.2509

Total Cost 775415.2509


Cost of OHSR/L 7.75

T&P article
Mixer
Weigh batcher
Vibrator
---

0.037975
45074.33 N-m

337.3782

0.0305
580.7871
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 437.58 m³ 164 71763.12
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 17.82 m³ 4280 76269.6
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 46.72 m³ 7500 350371.6239
(b) Nominal slab 17.48 m³ 7500 131130
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 51.10 m³ 7700 393461.145
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3564.00 kg 68 242352


Columns 241.14 kg 68 16397.41184
Vertical wall 6270 kg 68 426360
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 37.09 Sq.m 162 6008.561856
Column 23.02 Sq.m 254 5845.888176
Container 439.56 Sq.m 269 118241.64
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 219.78 m² 220 48351.6


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 2782183.697

Total Cost 2782183.697


Cost of CWR/L 4.64

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.107496
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 354.42 m³ 164 58124.88
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 17.82 m³ 4280 76269.6
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 38.71 m³ 7500 290350.9125
(b) Nominal slab 13.67 m³ 7500 102555
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 44.69 m³ 7700 344102.22
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2970.00 kg 68 201960


Columns 241.14 kg 68 16397.41184
Vertical wall 5500 kg 68 374000
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 33.94 Sq.m 162 5498.25408
Column 23.02 Sq.m 254 5845.888176
Container 397.23 Sq.m 269 106855.408
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 198.62 m² 220 43695.52


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2406264.211

Total Cost 2406264.211


Cost of CWR/L 4.81

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.073706
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 296.01 m³ 164 48545.64
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 14.85 m³ 4280 63558
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 30.09 m³ 7500 225699.2657
(b) Nominal slab 10.43 m³ 7500 78255
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 38.50 m³ 7700 296466.94
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2277.00 kg 68 154836


Columns 232.52 kg 68 15811.53025
Vertical wall 4620 kg 68 314160
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 28.74 Sq.m 162 4655.239776
Column 23.02 Sq.m 254 5845.888176
Container 358.16 Sq.m 269 96345.04
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 179.08 m² 220 39397.6


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2018692.501

Total Cost 2018692.501


Cost of CWR/L 5.05

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.028627
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 222.75 m³ 164 36531
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 11.88 m³ 4280 50846.4
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 23.11 m³ 7500 173319.0293
(b) Nominal slab 7.41 m³ 7500 55586.25
(iii) Columns 1.27 m³ 7500 9493.814459
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 32.87 m³ 7700 253062.425
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1782.00 kg 68 121176


Columns 155.02 kg 68 10541.02017
Vertical wall 3960 kg 68 269280
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 18.21 Sq.m 162 2950.49304
Column 15.34 Sq.m 254 3897.258784
Container 309.32 Sq.m 269 83207.08
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 154.66 m² 220 34025.2


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1631045.331

Total Cost 1631045.331


Cost of CWR/L 5.44

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.046455
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 191.07 m³ 164 31335.48
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 7.92 m³ 4280 33897.6
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 18.05 m³ 7500 135369.9703
(b) Nominal slab 5.90 m³ 7500 44237.8125
(iii) Columns 1.27 m³ 7500 9493.814459
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 28.49 m³ 7700 219373
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1437.22 kg 68 97731.11365


Columns 155.02 kg 68 10541.02017
Vertical wall 3520 kg 68 239360
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 20.05 Sq.m 162 3248.2296
Column 15.34 Sq.m 254 3897.258784
Container 284.90 Sq.m 269 76638.1
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 142.45 m² 220 31339


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1397158.878

Total Cost 1397158.878


Cost of CWR/L 5.59

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.075676
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 149.49 m³ 164 24516.36
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 7.92 m³ 4280 33897.6
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 14.44 m³ 7500 108276.9806
(b) Nominal slab 4.39 m³ 7500 32906.25
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 23.17 m³ 7700 178439.184
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1030.66 kg 68 70084.61957


Columns 93.58 kg 68 6363.230854
Vertical wall 2860 kg 68 194480
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 17.86 Sq.m 162 2892.82752
Column 12.08 Sq.m 254 3068.652412
Container 257.49 Sq.m 269 69264.272
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 128.74 m² 220 28323.68


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1148149.408

Total Cost 1148149.408


Cost of CWR/L 5.74

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.104954
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 117.81 m³ 164 19320.84
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete
- -
(a) PCC 5.94 m³ 4280 25423.2
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 8.70 m³ 7500 65233.80703
(b) Nominal slab 2.96 m³ 7500 22165.3125
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 19.75 m³ 7700 152078.85
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 619.06 kg 68 42095.75805


Columns 68.62 kg 68 4666.369293
Vertical wall 2420 kg 68 164560
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 12.02 Sq.m 162 1947.3696
Column 12.08 Sq.m 254 3068.652412
Container 225.72 Sq.m 269 60718.68
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 112.86 m² 220 24829.2


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 919707.9885

Total Cost 919707.9885


Cost of OHSR/L 6.13

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 81.18 m³ 164 13313.52
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 4.95 m³ 4280 21186
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 6.71 m³ 7500 50298.81863
(b) Nominal slab 1.48 m³ 7500 11126.25
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 15.17 m³ 7700 116835.18
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 414.85 kg 68 28209.66117


Columns 68.62 kg 68 4666.369293
Vertical wall 1870 kg 68 127160
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the CWR
including the work of making sub base
& base of approved materials
8.50 m³ 4280 36380
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 10.14 Sq.m 162 1642.975488
Column 12.08 Sq.m 254 3068.652412
Container 183.92 Sq.m 269 49474.48
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 91.96 m² 220 20231.2


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 722765.3378

Total Cost 722765.3378


Cost of OHSR/L 7.23

T&P article
Mixer
Weigh batcher
Vibrator
---

0.037975
45074.33 N-m

337.3782

0.0305
518.5599
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 397.80 m³ 164 65239.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 16.20 m³ 4280 69336
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 42.47 m³ 7500 318519.6581
(b) Nominal slab 17.48 m³ 7500 131130
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 46.45 m³ 7700 357691.95
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3240.00 kg 68 220320


Columns 219.22 kg 68 14906.73804
Vertical wall 5700 kg 68 387600
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 33.72 Sq.m 162 5462.32896
Column 23.02 Sq.m 254 5845.888176
Container 399.60 Sq.m 269 107492.4
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 199.80 m² 220 43956


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 2621836.659

Total Cost 2621836.659


Cost of CWR/L 4.37

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.158934
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 322.20 m³ 164 52840.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 16.20 m³ 4280 69336
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 35.19 m³ 7500 263955.375
(b) Nominal slab 13.67 m³ 7500 102555
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 40.63 m³ 7700 312820.2
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2700.00 kg 68 183600


Columns 219.22 kg 68 14906.73804
Vertical wall 5000 kg 68 340000
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 30.85 Sq.m 162 4998.4128
Column 23.02 Sq.m 254 5845.888176
Container 361.12 Sq.m 269 97141.28
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 180.56 m² 220 39723.2


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2267037.4

Total Cost 2267037.4


Cost of CWR/L 4.53

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.127301
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 269.10 m³ 164 44132.4
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 13.50 m³ 4280 57780
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 27.36 m³ 7500 205181.1506
(b) Nominal slab 10.43 m³ 7500 78255
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 35.00 m³ 7700 269515.4
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2070.00 kg 68 140760


Columns 211.38 kg 68 14374.11841
Vertical wall 4200 kg 68 285600
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 26.12 Sq.m 162 4232.03616
Column 23.02 Sq.m 254 5845.888176
Container 325.60 Sq.m 269 87586.4
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 162.80 m² 220 35816


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 1902900.139

Total Cost 1902900.139


Cost of CWR/L 4.76

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.084345
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 202.50 m³ 164 33210
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 10.80 m³ 4280 46224
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 21.01 m³ 7500 157562.7539
(b) Nominal slab 7.41 m³ 7500 55586.25
(iii) Columns 1.15 m³ 7500 8630.740418
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 29.88 m³ 7700 230056.75
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1620.00 kg 68 110160


Columns 140.92 kg 68 9582.745609
Vertical wall 3600 kg 68 244800
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 16.56 Sq.m 162 2682.2664
Column 15.34 Sq.m 254 3897.258784
Container 281.20 Sq.m 269 75642.8
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 140.60 m² 220 30932


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1536096.925

Total Cost 1536096.925


Cost of CWR/L 5.12

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.014463
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 173.70 m³ 164 28486.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 7.20 m³ 4280 30816
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 16.41 m³ 7500 123063.6094
(b) Nominal slab 5.90 m³ 7500 44237.8125
(iii) Columns 1.15 m³ 7500 8630.740418
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 25.90 m³ 7700 199430
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1306.57 kg 68 88846.46696


Columns 140.92 kg 68 9582.745609
Vertical wall 3200 kg 68 217600
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 18.23 Sq.m 162 2952.936
Column 15.34 Sq.m 254 3897.258784
Container 259.00 Sq.m 269 69671
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 129.50 m² 220 28490


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1316401.848

Total Cost 1316401.848


Cost of CWR/L 5.27

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.013501
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 135.90 m³ 164 22287.6
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 7.20 m³ 4280 30816
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 13.12 m³ 7500 98433.61875
(b) Nominal slab 4.39 m³ 7500 32906.25
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 21.07 m³ 7700 162217.44
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 936.96 kg 68 63713.29052


Columns 85.07 kg 68 5784.755322
Vertical wall 2600 kg 68 176800
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 16.23 Sq.m 162 2629.8432
Column 12.08 Sq.m 254 3068.652412
Container 234.08 Sq.m 269 62967.52
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 117.04 m² 220 25748.8


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1082488.515

Total Cost 1082488.515


Cost of CWR/L 5.41

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.041763
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 107.10 m³ 164 17564.4
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete
- -
(a) PCC 5.40 m³ 4280 23112
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 7.91 m³ 7500 59303.46094
(b) Nominal slab 2.96 m³ 7500 22165.3125
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 17.96 m³ 7700 138253.5
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 562.78 kg 68 38268.87096


Columns 62.38 kg 68 4242.153903
Vertical wall 2200 kg 68 149600
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 10.93 Sq.m 162 1770.336
Column 12.08 Sq.m 254 3068.652412
Container 205.20 Sq.m 269 55198.8
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 102.60 m² 220 22572


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 868198.4298

Total Cost 868198.4298


Cost of OHSR/L 5.79

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 18T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 73.80 m³ 164 12103.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 4.50 m³ 4280 19260
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 6.10 m³ 7500 45726.19875
(b) Nominal slab 1.48 m³ 7500 11126.25
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 13.79 m³ 7700 106213.8
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 377.13 kg 68 25645.14652


Columns 62.38 kg 68 4242.153903
Vertical wall 1700 kg 68 115600
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the CWR
including the work of making sub base
& base of approved materials
8.50 m³ 4280 36380
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 9.22 Sq.m 162 1493.61408
Column 12.08 Sq.m 254 3068.652412
Container 167.20 Sq.m 269 44976.8
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 83.60 m² 220 18392


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 682879.04

Total Cost 682879.04


Cost of OHSR/L 6.83

T&P article
Mixer
Weigh batcher
Vibrator
---

0.037975
45074.33 N-m

337.3782

0.0305
471.4181
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 816.82 m³ 164 133957.824
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 33.26 m³ 4280 142369.92
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 104.64 m³ 7500 784832.4376
(b) Nominal slab 32.31 m³ 7500 242328.24
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 57.23 m³ 7700 440676.4824
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 5544.00 kg 68 376992


Columns 337.59 kg 68 22956.37658
Vertical wall 7724.64 kg 68 525275.52
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 64.91 Sq.m 162 10514.98325
Column 28.35 Sq.m 254 7202.134233
Container 615.38 Sq.m 269 165538.296
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 307.69 m² 220 67692.24


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 3817676.447

Total Cost 3817676.447


Cost of CWR/L 6.36

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.224683
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 661.58 m³ 164 108499.776
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 33.26 m³ 4280 142369.92
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 86.72 m³ 7500 650386.044
(b) Nominal slab 25.27 m³ 7500 189521.64
(iii) Columns 2.66 m³ 7500 19937.01036
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 50.05 m³ 7700 385394.4864
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 4620.00 kg 68 314160


Columns 337.59 kg 68 22956.37658
Vertical wall 6776 kg 68 460768
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 59.39 Sq.m 162 9621.94464
Column 28.35 Sq.m 254 7202.134233
Container 556.12 Sq.m 269 149597.5712
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 278.06 m² 220 61173.728


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 3287957.026

Total Cost 3287957.026


Cost of CWR/L 6.58

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.265703
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 552.55 m³ 164 90618.528
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 27.72 m³ 4280 118641.6
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 67.41 m³ 7500 505566.3551
(b) Nominal slab 19.28 m³ 7500 144615.24
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 43.12 m³ 7700 332042.9728
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3542.00 kg 68 240856


Columns 325.53 kg 68 22136.14236
Vertical wall 5691.84 kg 68 387045.12
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 50.29 Sq.m 162 8146.669608
Column 28.35 Sq.m 254 7202.134233
Container 501.42 Sq.m 269 134883.056
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 250.71 m² 220 55156.64


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2723735.701

Total Cost 2723735.701


Cost of CWR/L 6.81

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.310632
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 415.80 m³ 164 68191.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 22.18 m³ 4280 94913.28
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 51.76 m³ 7500 388234.6256
(b) Nominal slab 13.70 m³ 7500 102723.39
(iii) Columns 1.18 m³ 7500 8812.770579
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 32.98 m³ 7700 253934.219
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2772.00 kg 68 188496


Columns 217.02 kg 68 14757.42824
Vertical wall 4878.72 kg 68 331752.96
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 31.87 Sq.m 162 5163.36282
Column 18.57 Sq.m 254 4715.683129
Container 433.05 Sq.m 269 116489.912
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 216.52 m² 220 47635.28


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 2152949.471

Total Cost 2152949.471


Cost of CWR/L 7.18

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.381301
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 356.66 m³ 164 58492.896
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 14.78 m³ 4280 63275.52
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 40.43 m³ 7500 303228.7335
(b) Nominal slab 10.90 m³ 7500 81751.4775
(iii) Columns 1.42 m³ 7500 10633.07219
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 31.91 m³ 7700 245697.76
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2235.68 kg 68 152026.1768


Columns 217.02 kg 68 14757.42824
Vertical wall 4336.64 kg 68 294891.52
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 35.09 Sq.m 162 5684.4018
Column 18.90 Sq.m 254 4801.422822
Container 398.86 Sq.m 269 107293.34
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 199.43 m² 220 43874.6


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1847104.828

Total Cost 1847104.828


Cost of CWR/L 7.39

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.42209
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 279.05 m³ 164 45763.872
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 14.78 m³ 4280 63275.52
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 32.34 m³ 7500 242540.4366
(b) Nominal slab 8.11 m³ 7500 60810.75
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 25.95 m³ 7700 199851.8861
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1603.24 kg 68 109020.5193


Columns 131.01 kg 68 8908.523196
Vertical wall 3523.52 kg 68 239599.36
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 31.25 Sq.m 162 5062.44816
Column 14.88 Sq.m 254 3780.579772
Container 360.48 Sq.m 269 96969.9808
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 180.24 m² 220 39653.152


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1511560.507

Total Cost 1511560.507


Cost of CWR/L 7.56

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.454693
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 219.91 m³ 164 36065.568
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 11.09 m³ 4280 47456.64
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 19.48 m³ 7500 146123.7278
(b) Nominal slab 5.46 m³ 7500 40961.4975
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 22.12 m³ 7700 170328.312
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 962.97 kg 68 65482.2903


Columns 96.07 kg 68 6532.91701
Vertical wall 2981.44 kg 68 202737.92
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 21.04 Sq.m 162 3407.8968
Column 14.88 Sq.m 254 3780.579772
Container 316.01 Sq.m 269 85006.152
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 158.00 m² 220 34760.88


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 1176932.059

Total Cost 1176932.059


Cost of OHSR/L 7.85

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 151.54 m³ 164 24851.904
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 9.24 m³ 4280 39547.2
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 15.02 m³ 7500 112669.3537
(b) Nominal slab 2.74 m³ 7500 20561.31
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 16.99 m³ 7700 130855.4016
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 645.32 kg 68 43881.69516


Columns 96.07 kg 68 6532.91701
Vertical wall 2303.84 kg 68 156661.12
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
10.00 m³ 4280 42800
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 17.75 Sq.m 162 2875.207104
Column 14.88 Sq.m 254 3780.579772
Container 257.49 Sq.m 269 69264.272
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 128.74 m² 220 28323.68


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 922464.5997

Total Cost 922464.5997


Cost of OHSR/L 9.22

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 729.30 m³ 164 119605.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 29.70 m³ 4280 127116
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 93.43 m³ 7500 700743.2479
(b) Nominal slab 28.85 m³ 7500 216364.5
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 51.10 m³ 7700 393461.145
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 4950.00 kg 68 336600


Columns 301.42 kg 68 20496.7648
Vertical wall 6897 kg 68 468996
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 57.95 Sq.m 162 9388.3779
Column 25.32 Sq.m 254 6430.476994
Container 549.45 Sq.m 269 147802.05
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 274.73 m² 220 60439.5


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 3503074.369

Total Cost 3503074.369


Cost of CWR/L 5.84

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.123761
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 590.70 m³ 164 96874.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 29.70 m³ 4280 127116
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 77.43 m³ 7500 580701.825
(b) Nominal slab 22.56 m³ 7500 169215.75
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 44.69 m³ 7700 344102.22
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 4125.00 kg 68 280500


Columns 301.42 kg 68 20496.7648
Vertical wall 6050 kg 68 411400
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 53.03 Sq.m 162 8591.022
Column 25.32 Sq.m 254 6430.476994
Container 496.54 Sq.m 269 133569.26
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 248.27 m² 220 54619.4


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 3014226.635

Total Cost 3014226.635


Cost of CWR/L 6.03

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.16033
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 493.35 m³ 164 80909.4
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 24.75 m³ 4280 105930
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 60.19 m³ 7500 451398.5314
(b) Nominal slab 17.22 m³ 7500 129120.75
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 38.50 m³ 7700 296466.94
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3162.50 kg 68 215050


Columns 290.65 kg 68 19764.41282
Vertical wall 5082 kg 68 345576
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 44.90 Sq.m 162 7273.81215
Column 25.32 Sq.m 254 6430.476994
Container 447.70 Sq.m 269 120431.3
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 223.85 m² 220 49247


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2502714.98

Total Cost 2502714.98


Cost of CWR/L 6.26

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.204279
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 371.25 m³ 164 60885
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 19.80 m³ 4280 84744
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 46.22 m³ 7500 346638.0586
(b) Nominal slab 12.23 m³ 7500 91717.3125
(iii) Columns 1.16 m³ 7500 8709.201694
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 31.21 m³ 7700 240348.7625
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2475.00 kg 68 168300


Columns 193.77 kg 68 13176.27521
Vertical wall 4356 kg 68 296208
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 28.46 Sq.m 162 4610.145375
Column 16.88 Sq.m 254 4286.984663
Container 386.65 Sq.m 269 104008.85
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 193.33 m² 220 42531.5


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1993293.451

Total Cost 1993293.451


Cost of CWR/L 6.64

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.278868
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 318.45 m³ 164 52225.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 13.20 m³ 4280 56496
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 36.10 m³ 7500 270739.9406
(b) Nominal slab 9.73 m³ 7500 72992.39063
(iii) Columns 1.27 m³ 7500 9493.814459
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 28.49 m³ 7700 219373
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1996.14 kg 68 135737.6579


Columns 193.77 kg 68 13176.27521
Vertical wall 3872 kg 68 263296
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 31.33 Sq.m 162 5075.35875
Column 16.88 Sq.m 254 4286.984663
Container 356.13 Sq.m 269 95797.625
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 178.06 m² 220 39173.75


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1698561.076

Total Cost 1698561.076


Cost of CWR/L 6.79

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.307726
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 249.15 m³ 164 40860.6
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 13.20 m³ 4280 56496
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 28.87 m³ 7500 216553.9613
(b) Nominal slab 7.24 m³ 7500 54295.3125
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 23.17 m³ 7700 178439.184
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1431.47 kg 68 97339.7494


Columns 116.97 kg 68 7954.038568
Vertical wall 3146 kg 68 213928
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 27.90 Sq.m 162 4520.043
Column 13.29 Sq.m 254 3375.517653
Container 321.86 Sq.m 269 86580.34
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 160.93 m² 220 35404.6


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1391383.097

Total Cost 1391383.097


Cost of CWR/L 6.96

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.339036
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 196.35 m³ 164 32201.4
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 9.90 m³ 4280 42372
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 17.40 m³ 7500 130467.6141
(b) Nominal slab 4.88 m³ 7500 36572.76563
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 19.75 m³ 7700 152078.85
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 859.80 kg 68 58466.33063


Columns 85.78 kg 68 5832.961616
Vertical wall 2662 kg 68 181016
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 18.78 Sq.m 162 3042.765
Column 13.29 Sq.m 254 3375.517653
Container 282.15 Sq.m 269 75898.35
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 141.08 m² 220 31036.5


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 1085961.004

Total Cost 1085961.004


Cost of OHSR/L 7.24

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 135.30 m³ 164 22189.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.25 m³ 4280 35310
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 13.41 m³ 7500 100597.6373
(b) Nominal slab 2.45 m³ 7500 18358.3125
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 15.17 m³ 7700 116835.18
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 576.18 kg 68 39180.08496


Columns 85.78 kg 68 5832.961616
Vertical wall 2057 kg 68 139876
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
10.00 m³ 4280 42800
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 15.85 Sq.m 162 2567.1492
Column 13.29 Sq.m 254 3375.517653
Container 229.90 Sq.m 269 61843.1
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 114.95 m² 220 25289


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 853226.374

Total Cost 853226.374


Cost of OHSR/L 8.53

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 663.00 m³ 164 108732
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 27.00 m³ 4280 115560
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 84.94 m³ 7500 637039.3163
(b) Nominal slab 26.23 m³ 7500 196695
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 46.45 m³ 7700 357691.95
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 4500.00 kg 68 306000


Columns 274.02 kg 68 18633.42255
Vertical wall 6270 kg 68 426360
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 52.68 Sq.m 162 8534.889
Column 23.02 Sq.m 254 5845.888176
Container 499.50 Sq.m 269 134365.5
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 249.75 m² 220 54945


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 3264739.462

Total Cost 3264739.462


Cost of CWR/L 5.44

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.047304
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 537.00 m³ 164 88068
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 27.00 m³ 4280 115560
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 70.39 m³ 7500 527910.75
(b) Nominal slab 20.51 m³ 7500 153832.5
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 40.63 m³ 7700 312820.2
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3750.00 kg 68 255000


Columns 274.02 kg 68 18633.42255
Vertical wall 5500 kg 68 374000
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 48.21 Sq.m 162 7810.02
Column 23.02 Sq.m 254 5845.888176
Container 451.40 Sq.m 269 121426.6
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 225.70 m² 220 49654


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2809875.886

Total Cost 2809875.886


Cost of CWR/L 5.62

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.081665
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 448.50 m³ 164 73554
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 22.50 m³ 4280 96300
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 54.71 m³ 7500 410362.3013
(b) Nominal slab 15.65 m³ 7500 117382.5
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 35.00 m³ 7700 269515.4
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2875.00 kg 68 195500


Columns 264.23 kg 68 17967.64802
Vertical wall 4620 kg 68 314160
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 40.82 Sq.m 162 6612.5565
Column 23.02 Sq.m 254 5845.888176
Container 407.00 Sq.m 269 109483
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 203.50 m² 220 44770


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2335275.04

Total Cost 2335275.04


Cost of CWR/L 5.84

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.123709
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 337.50 m³ 164 55350
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 18.00 m³ 4280 77040
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 42.02 m³ 7500 315125.5078
(b) Nominal slab 11.12 m³ 7500 83379.375
(iii) Columns 1.15 m³ 7500 8630.740418
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 29.88 m³ 7700 230056.75
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2250.00 kg 68 153000


Columns 176.15 kg 68 11978.43201
Vertical wall 3960 kg 68 269280
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 25.87 Sq.m 162 4191.04125
Column 15.34 Sq.m 254 3897.258784
Container 351.50 Sq.m 269 94553.5
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 175.75 m² 220 38665


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1872276.965

Total Cost 1872276.965


Cost of CWR/L 6.24

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.201225
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 289.50 m³ 164 47478
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 12.00 m³ 4280 51360
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 32.82 m³ 7500 246127.2188
(b) Nominal slab 8.85 m³ 7500 66356.71875
(iii) Columns 1.15 m³ 7500 8630.740418
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 25.90 m³ 7700 199430
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1814.67 kg 68 123397.8708


Columns 176.15 kg 68 11978.43201
Vertical wall 3520 kg 68 239360
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 28.48 Sq.m 162 4613.9625
Column 15.34 Sq.m 254 3897.258784
Container 323.75 Sq.m 269 87088.75
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 161.88 m² 220 35612.5


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1586027.931

Total Cost 1586027.931


Cost of CWR/L 6.34

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.221087
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 226.50 m³ 164 37146
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 12.00 m³ 4280 51360
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 26.25 m³ 7500 196867.2375
(b) Nominal slab 6.58 m³ 7500 49359.375
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 21.07 m³ 7700 162217.44
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1301.33 kg 68 88490.68128


Columns 106.34 kg 68 7230.944153
Vertical wall 2860 kg 68 194480
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 25.37 Sq.m 162 4109.13
Column 12.08 Sq.m 254 3068.652412
Container 292.60 Sq.m 269 78709.4
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 146.30 m² 220 32186


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1300339.605

Total Cost 1300339.605


Cost of CWR/L 6.50

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.251418
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 178.50 m³ 164 29274
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 9.00 m³ 4280 38520
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 15.81 m³ 7500 118606.9219
(b) Nominal slab 4.43 m³ 7500 33247.96875
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 17.96 m³ 7700 138253.5
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 781.64 kg 68 53151.20966


Columns 77.98 kg 68 5302.692379
Vertical wall 2420 kg 68 164560
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 17.08 Sq.m 162 2766.15
Column 12.08 Sq.m 254 3068.652412
Container 256.50 Sq.m 269 68998.5
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 128.25 m² 220 28215


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 1017043.538

Total Cost 1017043.538


Cost of OHSR/L 6.78

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ OF R.C.C CWR-100 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 6.5 m
Width of tank= 4.5 m
Outside length of tank = 6.8 m
Outside width of tank= 4.8 m
Ht of Tank including FB= 3.8 m
No of columns inside tank= 1
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.18 m
Avg thickness of wall= 0.165 m
Dia of inside column= 0.23 m
No of columns= 4
Length of column footing= 1.25 m
Width of column footing= 1.25 m
Thickness of column footing= 0.25 m
Size of toe= 0.3 m
Size of heel slab= 1.25 m
Length of Wall footing (Out)= 7.46 m
Width of Wall footing (Out)= 5.46 m
Thickness of wall footing= 0.3 m
Length of Nominal slab= 4m
Width of Nominal slab= 2m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 7.46 m
Width of tank for PCC= 5.46 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 8.96 m
Width of tank for plinth protection= 6.96 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 6.80 x 4.80 x 0.15 4.90
1 x 6.80 x 4.80 32.64

2.00 Vertical wall 2 x 6.50 x 0.17 x 3.80 8.15


2 x 4.50 x 0.17 x 3.80 5.64
2 x 6.50 x 7.60 98.80
2 x 4.50 x 7.60 68.40

3.00 RCC Columns Inside tank p*0.25 x 0.23 x 3.80 x 4.00 0.63
p x 0.23 x 3.80 x 4.00 10.98
Extra for column capital 0.06 1.10
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 7.46 x 5.46 x 0.30 12.22


Bottom nominal slab -1 x 4.00 x 2.00 x 0.15 -1.20
1 x 4.00 x 2.00 x 0.15 1.20
1 x 7.46 x 5.46 x 0.30 7.75
Bottom nominal slab 1 x 4.00 x 2.00 x 0.30 3.60
Sump 1.10 0.78

Column footing x 1.25 x 1.25 x 0.25 x 4.00 1.56


x 1.25 x 1.25 x 0.25 x 4.00 5
5.00 Stairs and Platform 2.00
TOTAL 36.27 229.05

6.00 Excavation footings 1 x 7.46 x 5.46 x 2.00 82.00

7.00 PCC footing 1 x 7.46 x 5.46 x 0.10 5.00

7.00 Plinth protection 1 x 8.96 x 6.96 x 0.15 10.00


304 85.71429
319.06 8.571429

25 251.2595

102.375

Length
(m) HYSD Steel (MT)
0.90% 0.40 81.69935

1.50% 1.00 122.6843


1.50% 0.70 172
1.10% 0.057

1.10% 0.006 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 0.70 Total depthDepthXX c b Ir OO II
0.70% -0.10
0.35% 0.00

0.35% 0.03
83.75
0.75% 0.100

1.50% 0.20
3.09 85.30441 3093.872

30.93872

0.362686

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 7T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 123.00 m³ 164 20172
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 7.50 m³ 4280 32100
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 12.19 m³ 7500 91452.3975
(b) Nominal slab 2.23 m³ 7500 16689.375
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 13.79 m³ 7700 106213.8
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 523.80 kg 68 35618.25906


Columns 77.98 kg 68 5302.692379
Vertical wall 1870 kg 68 127160
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
10.00 m³ 4280 42800
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 17.86 Sq.m 162 2893.87728
Column 12.08 Sq.m 254 3068.652412
Container 209.00 Sq.m 269 56221
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 104.50 m² 220 22990


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 801333.278

Total Cost 801333.278


Cost of OHSR/L 8.01

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 101.02 m³ 164 16567.936
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 6.16 m³ 4280 26364.8
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 10.02 m³ 7500 75112.90248
(b) Nominal slab 1.83 m³ 7500 13707.54
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 16.69 m³ 7700 128518.698
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 516.26 kg 68 35105.35613


Columns 76.86 kg 68 5226.333608
Vertical wall 2057 kg 68 139876
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
10.00 m³ 4280 42800
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 12.68 Sq.m 162 2053.71936
Column 13.29 Sq.m 254 3375.517653
Container 183.92 Sq.m 269 49474.48
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 91.96 m² 220 20231.2


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 798274.4425

Total Cost 798274.4425


Cost of OHSR/L 7.98

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 146.61 m³ 164 24043.712
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 7.39 m³ 4280 31637.76
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 12.99 m³ 7500 97415.8185
(b) Nominal slab 3.64 m³ 7500 27307.665
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 22.12 m³ 7700 170328.312
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 770.38 kg 68 52385.83224


Columns 76.86 kg 68 5226.333608
Vertical wall 2710.4 kg 68 184307.2
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 16.83 Sq.m 162 2726.31744
Column 14.88 Sq.m 254 3780.579772
Container 252.81 Sq.m 269 68004.9216
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 126.40 m² 220 27808.704


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 1029260.834

Total Cost 1029260.834


Cost of OHSR/L 6.86
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 186.03 m³ 164 30509.248
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 9.86 m³ 4280 42183.68
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 21.56 m³ 7500 161693.6244
(b) Nominal slab 5.41 m³ 7500 40540.5
(iii) Columns 0.86 m³ 7500 6418.799317
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 25.95 m³ 7700 199851.8861
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1282.59 kg 68 87216.41547


Columns 104.81 kg 68 7126.818557
Vertical wall 3203.2 kg 68 217817.6
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 25.00 Sq.m 162 4049.958528
Column 14.88 Sq.m 254 3780.579772
Container 288.39 Sq.m 269 77575.98464
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 144.19 m² 220 31722.5216


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1300392.296

Total Cost 1300392.296


Cost of CWR/L 6.50

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.251469
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 237.78 m³ 164 38995.264
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 9.86 m³ 4280 42183.68
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 26.95 m³ 7500 202152.489
(b) Nominal slab 7.27 m³ 7500 54500.985
(iii) Columns 1.42 m³ 7500 10633.07219
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 31.91 m³ 7700 245697.76
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1788.54 kg 68 121620.9414


Columns 173.62 kg 68 11805.94259
Vertical wall 3942.4 kg 68 268083.2
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 28.07 Sq.m 162 4547.52144
Column 18.90 Sq.m 254 4801.422822
Container 319.09 Sq.m 269 85834.672
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 159.54 m² 220 35099.68


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1586653.109

Total Cost 1586653.109


Cost of CWR/L 6.35

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.221568
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 277.20 m³ 164 45460.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 14.78 m³ 4280 63275.52
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 34.51 m³ 7500 258823.0838
(b) Nominal slab 9.13 m³ 7500 68482.26
(iii) Columns 1.42 m³ 7500 10633.07219
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 32.87 m³ 7700 253062.425
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2217.60 kg 68 150796.8


Columns 173.62 kg 68 11805.94259
Vertical wall 4435.2 kg 68 301593.6
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 25.50 Sq.m 162 4130.690256
Column 18.90 Sq.m 254 4801.422822
Container 346.44 Sq.m 269 93191.9296
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 173.22 m² 220 38108.224


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1831295.13

Total Cost 1831295.13


Cost of CWR/L 6.10

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.174932
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 368.37 m³ 164 60412.352
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 18.48 m³ 4280 79094.4
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 44.94 m³ 7500 337044.2368
(b) Nominal slab 12.85 m³ 7500 96410.16
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 43.12 m³ 7700 332042.9728
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2833.60 kg 68 192684.8


Columns 260.43 kg 68 17708.91388
Vertical wall 5174.4 kg 68 351859.2
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 40.23 Sq.m 162 6517.335686
Column 28.35 Sq.m 254 7202.134233
Container 401.14 Sq.m 269 107906.4448
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 200.57 m² 220 44125.312


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2309833.505

Total Cost 2309833.505


Cost of CWR/L 5.77

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.111466
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 441.06 m³ 164 72333.184
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 22.18 m³ 4280 94913.28
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 57.81 m³ 7500 433590.696
(b) Nominal slab 16.85 m³ 7500 126347.76
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 50.05 m³ 7700 385394.4864
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3696.00 kg 68 251328


Columns 270.08 kg 68 18365.10126
Vertical wall 6160 kg 68 418880
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 47.52 Sq.m 162 7697.555712
Column 28.35 Sq.m 254 7202.134233
Container 444.90 Sq.m 269 119678.057
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 222.45 m² 220 48938.9824


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2766987.24

Total Cost 2766987.24


Cost of CWR/L 5.53

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.065155
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone IV
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 544.54 m³ 164 89305.216
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 22.18 m³ 4280 94913.28
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 69.76 m³ 7500 523221.6251
(b) Nominal slab 21.54 m³ 7500 161552.16
(iii) Columns 2.13 m³ 7500 15949.60829
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 57.23 m³ 7700 440676.4824
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 4435.20 kg 68 301593.6


Columns 270.08 kg 68 18365.10126
Vertical wall 7022.4 kg 68 477523.2
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 51.93 Sq.m 162 8411.986598
Column 28.35 Sq.m 254 7202.134233
Container 492.31 Sq.m 269 132430.6368
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 246.15 m² 220 54153.792


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 3206689.208

Total Cost 3206689.208


Cost of CWR/L 5.34

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.028682
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 90.20 m³ 164 14792.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 5.50 m³ 4280 23540
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 8.94 m³ 7500 67065.0915
(b) Nominal slab 1.63 m³ 7500 12238.875
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 15.17 m³ 7700 116835.18
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 460.94 kg 68 31344.06797


Columns 68.62 kg 68 4666.369293
Vertical wall 1870 kg 68 127160
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
10.00 m³ 4280 42800
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 12.68 Sq.m 162 2053.71936
Column 13.29 Sq.m 254 3375.517653
Container 183.92 Sq.m 269 49474.48
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 91.96 m² 220 20231.2


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 754749.5316

Total Cost 754749.5316


Cost of OHSR/L 7.55

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 130.90 m³ 164 21467.6
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 6.60 m³ 4280 28248
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 11.60 m³ 7500 86978.40938
(b) Nominal slab 3.25 m³ 7500 24381.84375
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 19.75 m³ 7700 152078.85
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 687.84 kg 68 46773.0645


Columns 68.62 kg 68 4666.369293
Vertical wall 2420 kg 68 164560
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 15.03 Sq.m 162 2434.212
Column 13.29 Sq.m 254 3375.517653
Container 225.72 Sq.m 269 60718.68
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 112.86 m² 220 24829.2


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 954111.6961

Total Cost 954111.6961


Cost of OHSR/L 6.36
---

45074.33 N-m

337.3782
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 166.10 m³ 164 27240.4
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.80 m³ 4280 37664
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 19.25 m³ 7500 144369.3075
(b) Nominal slab 4.83 m³ 7500 36196.875
(iii) Columns 0.76 m³ 7500 5731.070819
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 23.17 m³ 7700 178439.184
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1145.17 kg 68 77871.79952


Columns 93.58 kg 68 6363.230854
Vertical wall 2860 kg 68 194480
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 22.32 Sq.m 162 3616.0344
Column 13.29 Sq.m 254 3375.517653
Container 257.49 Sq.m 269 69264.272
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 128.74 m² 220 28323.68


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1202840.052

Total Cost 1202840.052


Cost of CWR/L 6.01

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.157587
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 212.30 m³ 164 34817.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.80 m³ 4280 37664
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 24.07 m³ 7500 180493.2938
(b) Nominal slab 6.49 m³ 7500 48661.59375
(iii) Columns 1.27 m³ 7500 9493.814459
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 28.49 m³ 7700 219373
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1596.91 kg 68 108590.1263


Columns 155.02 kg 68 10541.02017
Vertical wall 3520 kg 68 239360
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 25.06 Sq.m 162 4060.287
Column 16.88 Sq.m 254 4286.984663
Container 284.90 Sq.m 269 76638.1
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 142.45 m² 220 31339


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1466014.899

Total Cost 1466014.899


Cost of CWR/L 5.86

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.128688
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 247.50 m³ 164 40590
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 13.20 m³ 4280 56496
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 30.81 m³ 7500 231092.0391
(b) Nominal slab 8.15 m³ 7500 61144.875
(iii) Columns 1.27 m³ 7500 9493.814459
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 32.87 m³ 7700 253062.425
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1980.00 kg 68 134640


Columns 155.02 kg 68 10541.02017
Vertical wall 3960 kg 68 269280
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 22.77 Sq.m 162 3688.1163
Column 16.88 Sq.m 254 4286.984663
Container 309.32 Sq.m 269 83207.08
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 154.66 m² 220 34025.2


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1718676.915

Total Cost 1718676.915


Cost of CWR/L 5.73

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.102678
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 328.90 m³ 164 53939.6
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 16.50 m³ 4280 70620
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 40.12 m³ 7500 300932.3543
(b) Nominal slab 11.48 m³ 7500 86080.5
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 38.50 m³ 7700 296466.94
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2530.00 kg 68 172040


Columns 232.52 kg 68 15811.53025
Vertical wall 4620 kg 68 314160
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 35.92 Sq.m 162 5819.04972
Column 25.32 Sq.m 254 6430.476994
Container 358.16 Sq.m 269 96345.04
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 179.08 m² 220 39397.6


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 2133159.448

Total Cost 2133159.448


Cost of CWR/L 5.33

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.026453
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 393.80 m³ 164 64583.2
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 19.80 m³ 4280 84744
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 51.62 m³ 7500 387134.55
(b) Nominal slab 15.04 m³ 7500 112810.5
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 44.69 m³ 7700 344102.22
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3300.00 kg 68 224400


Columns 241.14 kg 68 16397.41184
Vertical wall 5500 kg 68 374000
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 42.42 Sq.m 162 6872.8176
Column 25.32 Sq.m 254 6430.476994
Container 397.23 Sq.m 269 106855.408
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 198.62 m² 220 43695.52


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2552635.221

Total Cost 2552635.221


Cost of CWR/L 5.11

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.01736
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone III
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 486.20 m³ 164 79736.8
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 19.80 m³ 4280 84744
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 62.29 m³ 7500 467162.1653
(b) Nominal slab 19.23 m³ 7500 144243
(iii) Columns 1.90 m³ 7500 14240.72169
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 51.10 m³ 7700 393461.145
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3960.00 kg 68 269280


Columns 241.14 kg 68 16397.41184
Vertical wall 6270 kg 68 426360
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 46.36 Sq.m 162 7510.70232
Column 25.32 Sq.m 254 6430.476994
Container 439.56 Sq.m 269 118241.64
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 219.78 m² 220 48351.6


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 2957550.048

Total Cost 2957550.048


Cost of CWR/L 4.93

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.05124
BOQ for Construction of CWR at-------------------

Capacity of CWR: 600KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 442.00 m³ 164 72488
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 18.00 m³ 4280 77040
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 56.63 m³ 7500 424692.8775
(b) Nominal slab 17.48 m³ 7500 131130
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 28.23 m³ 7700 217359.45
(v) Vertical walls 46.45 m³ 7700 357691.95
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3600.00 kg 68 244800


Columns 219.22 kg 68 14906.73804
Vertical wall 5700 kg 68 387600
Top slab 2100 kg 68 142800
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 199.80 m² 117 23376.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
41.00 m³ 4280 175480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 42.15 Sq.m 162 6827.9112
Column 23.02 Sq.m 254 5845.888176
Container 399.60 Sq.m 269 107492.4
Top slab 188.19 Sq.m 269 50623.11
Platform 12.00 Sq.m 268 3216
[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 199.80 m² 220 43956


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 94.10 m² 55 5175.225


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 35,000 35000
Total cost 2768808.261

Total Cost 2768808.261


Cost of CWR/L 4.61

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.111787
BOQ OF R.C.C CWR-600 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 15 m
Width of tank= 12 m
Outside length of tank = 15.3 m
Outside width of tank= 12.3 m
Ht of Tank including FB= 3.7 m
No of columns inside tank= 6
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.315 m
Avg thickness of wall= 0.2325 m
Dia of inside column= 0.3 m
No of columns= 6
Length of column footing= 1.3 m
Width of column footing= 1.3 m
Thickness of column footing= 0.3 m
Size of toe= 0.4 m
Size of heel slab= 1.3 m
Length of Wall footing (Out)= 16.43 m
Width of Wall footing (Out)= 13.43 m
Thickness of wall footing= 0.3 m
Length of Nominal slab= 12.4 m
Width of Nominal slab= 9.4 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 16.43 m
Width of tank for PCC= 13.43 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 17.93 m
Width of tank for plinth protection= 14.93 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 15.30 x 12.30 x 0.15 28.23
1 x 15.30 x 12.30 188.19

2.00 Vertical wall 2 x 15.00 x 0.23 x 3.70 25.81


2 x 12.00 x 0.23 x 3.70 20.65
2 x 15.00 x 7.40 222.00
2 x 12.00 x 7.40 177.60

3.00 RCC Columns Inside tank p*0.25 x 0.30 x 3.70 x 6.00 1.57
p x 0.30 x 3.70 x 6.00 20.92
Extra for column capital 0.16 2.09
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 16.43 x 13.43 x 0.30 66.20


Bottom nominal slab -1 x 12.40 x 9.40 x 0.15 -17.48
1 x 12.40 x 9.40 x 0.15 17.48
1 x 16.43 x 13.43 x 0.30 17.92
Bottom nominal slab 1 x 12.40 x 9.40 x 0.30 13.08
Sump 4.87 1.79

Column footing x 1.30 x 1.30 x 0.30 x 6.00 3.04


x 1.30 x 1.30 x 0.30 x 6.00 9.36
5.00 Stairs and Platform 5.00
TOTAL 155.52 652.95

6.00 Excavation footings 1 x 16.43 x 13.43 x 2.00 442.00

7.00 PCC footing 1 x 16.43 x 13.43 x 0.10 23.00

7.00 Plinth protection 1 x 17.93 x 14.93 x 0.15 41.00


304 85.71429
612 8.571429

25 251.2595

Length
(m) HYSD Steel (MT)
0.90% 2.10 74.3929

1.50% 3.20 123.995


1.50% 2.50 172
1.50% 0.200

1.50% 0.019 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 3.80 Total depthDepthXX c b Ir OO II
0.70% -1.00
0.35% 0.50

0.35% 0.10
83.75
0.75% 0.200

1.50% 0.60
12.22 78.57115 12219.22

122.1922

1.555179

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 500KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 358.00 m³ 164 58712
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 18.00 m³ 4280 77040
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 46.93 m³ 7500 351940.5
(b) Nominal slab 13.67 m³ 7500 102555
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 23.29 m³ 7700 179313.75
(v) Vertical walls 40.63 m³ 7700 312820.2
(vi) Stair case 5.00 m³ 7700 38500
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 3000.00 kg 68 204000


Columns 219.22 kg 68 14906.73804
Vertical wall 5000 kg 68 340000
Top slab 1700 kg 68 115600
Platform 600 kg 68 40800
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 180.56 m² 117 21125.52
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
34.00 m³ 4280 145520
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 38.57 Sq.m 162 6248.016
Column 23.02 Sq.m 254 5845.888176
Container 361.12 Sq.m 269 97141.28
Top slab 155.25 Sq.m 269 41762.25
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 180.56 m² 220 39723.2


Container
(b) Stair case 8 m² 220 1760
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 77.63 m² 55 4269.375


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 30,000 30000
Total cost 2390247.328

Total Cost 2390247.328


Cost of CWR/L 4.78

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.079871
BOQ OF R.C.C CWR-500 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 13.2 m
Width of tank= 11.2 m
Outside length of tank = 13.5 m
Outside width of tank= 11.5 m
Ht of Tank including FB= 3.7 m
No of columns inside tank= 6
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.3 m
Avg thickness of wall= 0.225 m
Dia of inside column= 0.3 m
No of columns= 6
Length of column footing= 1.3 m
Width of column footing= 1.3 m
Thickness of column footing= 0.3 m
Size of toe= 0.3 m
Size of heel slab= 1.3 m
Length of Wall footing (Out)= 14.4 m
Width of Wall footing (Out)= 12.4 m
Thickness of wall footing= 0.3 m
Length of Nominal slab= 10.6 m
Width of Nominal slab= 8.6 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 14.4 m
Width of tank for PCC= 12.4 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 15.9 m
Width of tank for plinth protection= 13.9 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 13.50 x 11.50 x 0.15 23.29
1 x 13.50 x 11.50 155.25

2.00 Vertical wall 2 x 13.20 x 0.23 x 3.70 21.98


2 x 11.20 x 0.23 x 3.70 18.65
2 x 13.20 x 7.40 195.36
2 x 11.20 x 7.40 165.76

3.00 RCC Columns Inside tank p*0.25 x 0.30 x 3.70 x 6.00 1.57
p x 0.30 x 3.70 x 6.00 20.92
Extra for column capital 0.16 2.09
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 14.40 x 12.40 x 0.30 53.57


Bottom nominal slab -1 x 10.60 x 8.60 x 0.15 -13.67
1 x 10.60 x 8.60 x 0.15 13.67
1 x 14.40 x 12.40 x 0.30 16.08
Bottom nominal slab 1 x 10.60 x 8.60 x 0.30 11.52
Sump 3.99 1.61

Column footing x 1.30 x 1.30 x 0.30 x 6.00 3.04


x 1.30 x 1.30 x 0.30 x 6.00 9.36
5.00 Stairs and Platform 5.00
TOTAL 131.24 577.95

6.00 Excavation footings 1 x 14.40 x 12.40 x 2.00 358.00

7.00 PCC footing 1 x 14.40 x 12.40 x 0.10 18.00

7.00 Plinth protection 1 x 15.90 x 13.90 x 0.15 34.00


304 85.71429
502.656 8.571429

25 251.2595

Length
(m) HYSD Steel (MT)
0.90% 1.70 73.00054

1.50% 2.70 122.8501


1.50% 2.30 172
1.50% 0.200

1.50% 0.019 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 3.10 Total depthDepthXX c b Ir OO II
0.70% -0.80
0.35% 0.40

0.35% 0.10
83.75
0.75% 0.200

1.50% 0.60
10.52 80.1531 10519.22

105.1922

1.31239

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 400KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 299.00 m³ 164 49036
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 15.00 m³ 4280 64200
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 36.48 m³ 7500 273574.8675
(b) Nominal slab 10.43 m³ 7500 78255
(iii) Columns 1.73 m³ 7500 12946.11063
(iv) Top slab 19.00 m³ 7700 146326.95
(v) Vertical walls 35.00 m³ 7700 269515.4
(vi) Stair case 4.00 m³ 7700 30800
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 2300.00 kg 68 156400


Columns 211.38 kg 68 14374.11841
Vertical wall 4200 kg 68 285600
Top slab 1400 kg 68 95200
Platform 500 kg 68 34000
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 162.80 m² 117 19047.6
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
29.00 m³ 4280 124120
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 32.65 Sq.m 162 5290.0452
Column 23.02 Sq.m 254 5845.888176
Container 325.60 Sq.m 269 87586.4
Top slab 126.69 Sq.m 269 34079.61
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 175 Kg 90.5 15837.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 162.80 m² 220 35816


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 63.35 m² 55 3483.975


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 75,000 75000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 1999315.465

Total Cost 1999315.465


Cost of CWR/L 5.00

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
-0.037951
BOQ OF R.C.C CWR-400 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 12 m
Width of tank= 10 m
Outside length of tank = 12.3 m
Outside width of tank= 10.3 m
Ht of Tank including FB= 3.7 m
No of columns inside tank= 6
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.28 m
Avg thickness of wall= 0.215 m
Dia of inside column= 0.3 m
No of columns= 6
Length of column footing= 1.3 m
Width of column footing= 1.3 m
Thickness of column footing= 0.275 m
Size of toe= 0.35 m
Size of heel slab= 1.3 m
Length of Wall footing (Out)= 13.26 m
Width of Wall footing (Out)= 11.26 m
Thickness of wall footing= 0.275 m
Length of Nominal slab= 9.4 m
Width of Nominal slab= 7.4 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 13.26 m
Width of tank for PCC= 11.26 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 14.76 m
Width of tank for plinth protection= 12.76 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 12.30 x 10.30 x 0.15 19.00
1 x 12.30 x 10.30 126.69

2.00 Vertical wall 2 x 12.00 x 0.22 x 3.70 19.09


2 x 10.00 x 0.22 x 3.70 15.91
2 x 12.00 x 7.40 177.60
2 x 10.00 x 7.40 148.00

3.00 RCC Columns Inside tank p*0.25 x 0.30 x 3.70 x 6.00 1.57
p x 0.30 x 3.70 x 6.00 20.92
Extra for column capital 0.16 2.09
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 13.26 x 11.26 x 0.28 41.06


Bottom nominal slab -1 x 9.40 x 7.40 x 0.15 -10.43
1 x 9.40 x 7.40 x 0.15 10.43
1 x 13.26 x 11.26 x 0.28 13.49
Bottom nominal slab 1 x 9.40 x 7.40 x 0.28 9.24
Sump 3.06 1.35

Column footing x 1.30 x 1.30 x 0.28 x 6.00 2.79


x 1.30 x 1.30 x 0.28 x 6.00 8.58
5.00 Stairs and Platform 4.00
TOTAL 106.64 507.96

6.00 Excavation footings 1 x 13.26 x 11.26 x 2.00 299.00

7.00 PCC footing 1 x 13.26 x 11.26 x 0.10 15.00

7.00 Plinth protection 1 x 14.76 x 12.76 x 0.15 29.00


304 85.71429
393.176 8.571429

25 251.2595

Length
(m) HYSD Steel (MT)
0.90% 1.40 73.67064

1.50% 2.30 120.4693


1.50% 1.90 172
1.50% 0.192

1.50% 0.019 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 2.30 Total depthDepthXX c b Ir OO II
0.70% -0.60
0.35% 0.30

0.35% 0.10
83.75
0.75% 0.200

1.50% 0.50
8.61 80.75017 8611.384

86.11384

1.066423

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 150KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 119.00 m³ 164 19516
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 6.00 m³ 4280 25680
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 10.54 m³ 7500 79071.28125
(b) Nominal slab 2.96 m³ 7500 22165.3125
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 7.31 m³ 7700 56251.3875
(v) Vertical walls 17.96 m³ 7700 138253.5
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 625.31 kg 68 42520.96773


Columns 62.38 kg 68 4242.153903
Vertical wall 2200 kg 68 149600
Top slab 500 kg 68 34000
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 102.60 m² 117 12004.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
13.00 m³ 4280 55640
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 13.66 Sq.m 162 2212.92
Column 12.08 Sq.m 254 3068.652412
Container 205.20 Sq.m 269 55198.8
Top slab 48.70 Sq.m 269 13100.9725
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 102.60 m² 220 22572


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 24.35 m² 55 1339.31875


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 10,000 10000
Total cost 897180.5309

Total Cost 897180.5309


Cost of OHSR/L 5.98

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ OF R.C.C CWR-150 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 7.75 m
Width of tank= 5.75 m
Outside length of tank = 8.05 m
Outside width of tank= 6.05 m
Ht of Tank including FB= 3.8 m
No of columns inside tank= 1
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.2 m
Avg thickness of wall= 0.175 m
Dia of inside column= 0.23 m
No of columns= 4
Length of column footing= 1m
Width of column footing= 1m
Thickness of column footing= 0.2 m
Size of toe= 0.3 m
Size of heel slab= 1.1 m
Length of Wall footing (Out)= 8.75 m
Width of Wall footing (Out)= 6.75 m
Thickness of wall footing= 0.2 m
Length of Nominal slab= 5.55 m
Width of Nominal slab= 3.55 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 8.75 m
Width of tank for PCC= 6.75 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 10.25 m
Width of tank for plinth protection= 8.25 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 8.05 x 6.05 x 0.15 7.31
1 x 8.05 x 6.05 48.70

2.00 Vertical wall 2 x 7.75 x 0.18 x 3.80 10.31


2 x 5.75 x 0.18 x 3.80 7.65
2 x 7.75 x 7.60 117.80
2 x 5.75 x 7.60 87.40

3.00 RCC Columns Inside tank p*0.25 x 0.23 x 3.80 x 4.00 0.63
p x 0.23 x 3.80 x 4.00 10.98
Extra for column capital 0.06 1.10
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 8.75 x 6.75 x 0.20 11.81


Bottom nominal slab -1 x 5.55 x 3.55 x 0.15 -2.96
1 x 5.55 x 3.55 x 0.15 2.96
1 x 8.75 x 6.75 x 0.20 6.20
Bottom nominal slab 1 x 5.55 x 3.55 x 0.20 3.64
Sump 0.89 0.62

Column footing x 1.00 x 1.00 x 0.20 x 4.00 0.80


x 1.00 x 1.00 x 0.20 x 4.00 3.2
5.00 Stairs and Platform 2.00
TOTAL 41.45 279.64

6.00 Excavation footings 1 x 8.75 x 6.75 x 2.00 119.00

7.00 PCC footing 1 x 8.75 x 6.75 x 0.10 6.00

7.00 Plinth protection 1 x 10.25 x 8.25 x 0.15 13.00


304 85.71429
319.06 8.571429

25 251.2595

155.9688

41547.56 415.4756

Length
(m) HYSD Steel (MT)
0.90% 0.50 68.44276

1.50% 1.30 126.1218


1.50% 0.90 172
1.10% 0.057 71 105

1.10% 0.006 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 0.70 Total depthDepthXX c b Ir OO II
0.70% -0.20
0.35% 0.10

0.35% 0.03
83.75
0.75% 0.000

1.50% 0.20
3.59 86.5479 3587.693

35.87693

0.414533

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 82.00 m³ 164 13448
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 5.00 m³ 4280 21400
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 8.13 m³ 7500 60968.265
(b) Nominal slab 1.48 m³ 7500 11126.25
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 4.90 m³ 7700 37699.2
(v) Vertical walls 13.79 m³ 7700 106213.8
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 419.04 kg 68 28494.60725


Columns 62.38 kg 68 4242.153903
Vertical wall 1700 kg 68 115600
Top slab 400 kg 68 27200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 83.60 m² 117 9781.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
10.00 m³ 4280 42800
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 11.52 Sq.m 162 1867.0176
Column 12.08 Sq.m 254 3068.652412
Container 167.20 Sq.m 269 44976.8
Top slab 32.64 Sq.m 269 8780.16
Platform 6.00 Sq.m 268 1608
[8] Supply & fixing in cement mortar 50 Kg 90.5 4525
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 83.60 m² 220 18392


Container
(b) Stair case 5 m² 220 1100
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 16.32 m² 55 897.6


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 2.00 Cum 3950 7900
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 3,000 3000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 7,500 7500
Total cost 711248.7705

Total Cost 711248.7705


Cost of OHSR/L 7.11

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
BOQ OF R.C.C CWR-100 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 6.5 m
Width of tank= 4.5 m
Outside length of tank = 6.8 m
Outside width of tank= 4.8 m
Ht of Tank including FB= 3.8 m
No of columns inside tank= 1
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.18 m
Avg thickness of wall= 0.165 m
Dia of inside column= 0.23 m
No of columns= 4
Length of column footing= 1m
Width of column footing= 1m
Thickness of column footing= 0.2 m
Size of toe= 0.3 m
Size of heel slab= 1.1 m
Length of Wall footing (Out)= 7.46 m
Width of Wall footing (Out)= 5.46 m
Thickness of wall footing= 0.2 m
Length of Nominal slab= 4.3 m
Width of Nominal slab= 2.3 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 7.46 m
Width of tank for PCC= 5.46 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 8.96 m
Width of tank for plinth protection= 6.96 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 6.80 x 4.80 x 0.15 4.90
1 x 6.80 x 4.80 32.64

2.00 Vertical wall 2 x 6.50 x 0.17 x 3.80 8.15


2 x 4.50 x 0.17 x 3.80 5.64
2 x 6.50 x 7.60 98.80
2 x 4.50 x 7.60 68.40

3.00 RCC Columns Inside tank p*0.25 x 0.23 x 3.80 x 4.00 0.63
p x 0.23 x 3.80 x 4.00 10.98
Extra for column capital 0.06 1.10
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 7.46 x 5.46 x 0.20 8.15


Bottom nominal slab -1 x 4.30 x 2.30 x 0.15 -1.48
1 x 4.30 x 2.30 x 0.15 1.48
1 x 7.46 x 5.46 x 0.20 5.17
Bottom nominal slab 1 x 4.30 x 2.30 x 0.20 2.64
Sump 0.67 0.52

Column footing x 1.00 x 1.00 x 0.20 x 4.00 0.80


x 1.00 x 1.00 x 0.20 x 4.00 3.2
5.00 Stairs and Platform 2.00
TOTAL 31.00 223.45

6.00 Excavation footings 1 x 7.46 x 5.46 x 2.00 82.00

7.00 PCC footing 1 x 7.46 x 5.46 x 0.10 5.00

7.00 Plinth protection 1 x 8.96 x 6.96 x 0.15 10.00


304 85.71429
319.06 8.571429

25 251.2595

102.375

Length
(m) HYSD Steel (MT)
0.90% 0.40 81.69935

1.50% 1.00 122.6843


1.50% 0.70 172
1.10% 0.057

1.10% 0.006 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 0.50 Total depthDepthXX c b Ir OO II
0.70% -0.10
0.35% 0.00

0.35% 0.02
83.75
0.75% 0.000

1.50% 0.20
2.78 89.7312 2781.423

27.81423

0.309973

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 250KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 193.00 m³ 164 31652
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.00 m³ 4280 34240
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 21.88 m³ 7500 164084.8125
(b) Nominal slab 5.90 m³ 7500 44237.8125
(iii) Columns 1.15 m³ 7500 8630.740418
(iv) Top slab 12.14 m³ 7700 93442.3875
(v) Vertical walls 25.90 m³ 7700 199430
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1451.74 kg 68 98718.29662


Columns 140.92 kg 68 9582.745609
Vertical wall 3200 kg 68 217600
Top slab 900 kg 68 61200
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 129.50 m² 117 15151.5
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 22.79 Sq.m 162 3691.17
Column 15.34 Sq.m 254 3897.258784
Container 259.00 Sq.m 269 69671
Top slab 80.90 Sq.m 269 21762.7725
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 129.50 m² 220 28490


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 40.45 m² 55 2224.81875


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 4.00 Cum 3950 15800
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1374622.315

Total Cost 1374622.315


Cost of CWR/L 5.50

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.058325
BOQ OF R.C.C CWR-250 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 9.75 m
Width of tank= 7.75 m
Outside length of tank = 10.05 m
Outside width of tank= 8.05 m
Ht of Tank including FB= 3.7 m
No of columns inside tank= 4
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.25 m
Avg thickness of wall= 0.2 m
Dia of inside column= 0.3 m
No of columns= 4
Length of column footing= 1.4 m
Width of column footing= 1.4 m
Thickness of column footing= 0.25 m
Size of toe= 0.3 m
Size of heel slab= 1.2 m
Length of Wall footing (Out)= 10.85 m
Width of Wall footing (Out)= 8.85 m
Thickness of wall footing= 0.25 m
Length of Nominal slab= 7.35 m
Width of Nominal slab= 5.35 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 10.85 m
Width of tank for PCC= 8.85 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 12.35 m
Width of tank for plinth protection= 10.35 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 10.05 x 8.05 x 0.15 12.14
1 x 10.05 x 8.05 80.90

2.00 Vertical wall 2 x 9.75 x 0.20 x 3.70 14.43


2 x 7.75 x 0.20 x 3.70 11.47
2 x 9.75 x 7.40 144.30
2 x 7.75 x 7.40 114.70

3.00 RCC Columns Inside tank p*0.25 x 0.30 x 3.70 x 4.00 1.05
p x 0.30 x 3.70 x 4.00 13.95
Extra for column capital 0.10 1.39
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 10.85 x 8.85 x 0.25 24.01


Bottom nominal slab -1 x 7.35 x 5.35 x 0.15 -5.90
1 x 7.35 x 5.35 x 0.15 5.90
1 x 10.85 x 8.85 x 0.25 9.85
Bottom nominal slab 1 x 7.35 x 5.35 x 0.25 6.35
Sump 1.81 0.99

Column footing x 1.40 x 1.40 x 0.25 x 4.00 1.96


x 1.40 x 1.40 x 0.25 x 4.00 5.6
5.00 Stairs and Platform 2.00
TOTAL 68.96 378.03

6.00 Excavation footings 1 x 10.85 x 8.85 x 2.00 193.00

7.00 PCC footing 1 x 10.85 x 8.85 x 0.10 10.00

7.00 Plinth protection 1 x 12.35 x 10.35 x 0.15 20.00


304 85.71429
319.06 8.571429

25 251.2595

256.9125

Length
(m) HYSD Steel (MT)
0.90% 0.90 74.16334

1.50% 1.80 124.7401


1.50% 1.40 172
1.50% 0.128

1.50% 0.013 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 1.40 Total depthDepthXX c b Ir OO II
0.70% -0.30
0.35% 0.20

0.35% 0.05
83.75
0.75% 0.100

1.50% 0.20
5.89 85.44735 5892.662

58.92662

0.689625

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 200KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 151.00 m³ 164 24764
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 8.00 m³ 4280 34240
[3] Providing and casting in situ C.C in
grade M30 for container part
/columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 17.50 m³ 7500 131244.825
(b) Nominal slab 4.39 m³ 7500 32906.25
(iii) Columns 0.69 m³ 7500 5210.064381
(iv) Top slab 9.45 m³ 7700 72765
(v) Vertical walls 21.07 m³ 7700 162217.44
(vi) Stair case 2.00 m³ 7700 15400
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1041.07 kg 68 70792.54502


Columns 85.07 kg 68 5784.755322
Vertical wall 2600 kg 68 176800
Top slab 700 kg 68 47600
Platform 200 kg 68 13600
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 117.04 m² 117 13693.68
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
16.00 m³ 4280 68480
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 20.29 Sq.m 162 3287.304
Column 12.08 Sq.m 254 3068.652412
Container 234.08 Sq.m 269 62967.52
Top slab 63.00 Sq.m 269 16947
Platform 8.00 Sq.m 268 2144
[8] Supply & fixing in cement mortar 125 Kg 90.5 11312.5
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 117.04 m² 220 25748.8


Container
(b) Stair case 6 m² 220 1320
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 31.50 m² 55 1732.5


[10] Providing, fabricating and erecting MS 4 Mtr 1390 5560
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 3.00 Cum 3950 11850
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 15,000 15000
Total cost 1128936.836

Total Cost 1128936.836


Cost of CWR/L 5.64

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.086464
BOQ OF R.C.C CWR-200 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 8.7 m
Width of tank= 6.7 m
Outside length of tank = 9m
Outside width of tank= 7m
Ht of Tank including FB= 3.8 m
No of columns inside tank= 4
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.21 m
Avg thickness of wall= 0.18 m
Dia of inside column= 0.23 m
No of columns= 4
Length of column footing= 1.3 m
Width of column footing= 1.3 m
Thickness of column footing= 0.25 m
Size of toe= 0.3 m
Size of heel slab= 1.1 m
Length of Wall footing (Out)= 9.72 m
Width of Wall footing (Out)= 7.72 m
Thickness of wall footing= 0.25 m
Length of Nominal slab= 6.5 m
Width of Nominal slab= 4.5 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 9.72 m
Width of tank for PCC= 7.72 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 11.22 m
Width of tank for plinth protection= 9.22 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 9.00 x 7.00 x 0.15 9.45
1 x 9.00 x 7.00 63.00

2.00 Vertical wall 2 x 8.70 x 0.18 x 3.80 11.90


2 x 6.70 x 0.18 x 3.80 9.17
2 x 8.70 x 7.60 132.24
2 x 6.70 x 7.60 101.84

3.00 RCC Columns Inside tank p*0.25 x 0.23 x 3.80 x 4.00 0.63
p x 0.23 x 3.80 x 4.00 10.98
Extra for column capital 0.06 1.10
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 9.72 x 7.72 x 0.25 18.76


Bottom nominal slab -1 x 6.50 x 4.50 x 0.15 -4.39
1 x 6.50 x 4.50 x 0.15 4.39
1 x 9.72 x 7.72 x 0.25 8.72
Bottom nominal slab 1 x 6.50 x 4.50 x 0.25 5.50
Sump 1.44 0.87

Column footing x 1.30 x 1.30 x 0.25 x 4.00 1.69


x 1.30 x 1.30 x 0.25 x 4.00 5.2
5.00 Stairs and Platform 2.00
TOTAL 55.10 329.45

6.00 Excavation footings 1 x 9.72 x 7.72 x 2.00 151.00

7.00 PCC footing 1 x 9.72 x 7.72 x 0.10 8.00

7.00 Plinth protection 1 x 11.22 x 9.22 x 0.15 16.00


304 85.71429
319.06 8.571429

25 251.2595

204.015

Length
(m) HYSD Steel (MT)
0.90% 0.70 74.07407

1.50% 1.50 126.0335


1.50% 1.10 172
1.50% 0.077

1.50% 0.008 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 1.10 Total depthDepthXX c b Ir OO II
0.70% -0.30
0.35% 0.10

0.35% 0.04
83.75
0.75% 0.100

1.50% 0.20
4.63 83.96093 4626.137

46.26137

0.550987

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 300KL Rectangular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 225.00 m³ 164 36900
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 12.00 m³ 4280 51360
[3] Providing and casting in situ C.C in
grade M30 for container part
columns/raft using granite, quartzite
trapmetal of size 12mm to 20mm and
6mm to 12mm incl. scaffolding,
centering, formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete(excl. cost of
reinforcement)
- -
(i) Foundation raft
(a) Wall footing 28.01 m³ 7500 210083.6719
(b) Nominal slab 7.41 m³ 7500 55586.25
(iii) Columns 1.15 m³ 7500 8630.740418
(iv) Top slab 14.26 m³ 7700 109771.2
(v) Vertical walls 29.88 m³ 7700 230056.75
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1800.00 kg 68 122400


Columns 140.92 kg 68 9582.745609
Vertical wall 3600 kg 68 244800
Top slab 1000 kg 68 68000
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 140.60 m² 117 16450.2
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
22.00 m³ 4280 94160
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 20.70 Sq.m 162 3352.833
Column 15.34 Sq.m 254 3897.258784
Container 281.20 Sq.m 269 75642.8
Top slab 95.04 Sq.m 269 25565.76
Platform 10.00 Sq.m 268 2680
[8] Supply & fixing in cement mortar 150 Kg 90.5 13575
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 140.60 m² 220 30932


Container
(b) Stair case 10 m² 220 2200
[9] Providing & applying Anti carbonation - -
paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 95.04 m² 55 5227.2


[10] Providing, fabricating and erecting MS 5 Mtr 1390 6950
ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[11] Providing, fabricating and erecting MS 0 Mtr 3450 0


ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.
[12] Providing, fabricating and erecting 0 Mtr 780 0
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading,
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[13] Supply, fabricating & fixing of 5 Mtr 1500 7500


anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.

[14] Brick work with FPS bricks of class


designation 75 in foundation and plinth
in:
Cement mortar 1:4 (1 cement : 4 coarse 5.00 Cum 3950 19750
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0
[16] Provision for checking the SBC of Site , 1 LS 65,000 65000
Drawing and Design of ESR & mix design
from recognised Engineering

[17] Provision for slogan 1 LS 5,000 5000


[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 20,000 20000
Total cost 1610354.41

Total Cost 1610354.41


Cost of CWR/L 5.37

T&P article
Mixer
Weigh batcher
Vibrator
---

45074.33 N-m

337.3782
0.03318
BOQ OF R.C.C CWR-300 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Reactangular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Length of tank= 10.5 m
Width of tank= 8.5 m
Outside length of tank = 10.8 m
Outside width of tank= 8.8 m
Ht of Tank including FB= 3.7 m
No of columns inside tank= 4
Thickness of wall at top= 0.15 m
Thickness of wall at bottom= 0.275 m
Avg thickness of wall= 0.2125 m
Dia of inside column= 0.3 m
No of columns= 4
Length of column footing= 1.4 m
Width of column footing= 1.4 m
Thickness of column footing= 0.275 m
Size of toe= 0.3 m
Size of heel slab= 1.2 m
Length of Wall footing (Out)= 11.65 m
Width of Wall footing (Out)= 9.65 m
Thickness of wall footing= 0.275 m
Length of Nominal slab= 8.1 m
Width of Nominal slab= 6.1 m
Thickness of nominal circular slab= 0.15 m
Length of tank for PCC= 11.65 m
Width of tank for PCC= 9.65 m
Thickness of PCC= 0.1 m
Length of tank for plinth protection= 13.15 m
Width of tank for plinth protection= 11.15 m

Volume Formwor
Sl. Items of Concrete Measurement (m3) k (m2)
1.00 Top slab 1 x 10.80 x 8.80 x 0.15 14.26
1 x 10.80 x 8.80 95.04

2.00 Vertical wall 2 x 10.50 x 0.21 x 3.70 16.51


2 x 8.50 x 0.21 x 3.70 13.37
2 x 10.50 x 7.40 155.40
2 x 8.50 x 7.40 125.80

3.00 RCC Columns Inside tank p*0.25 x 0.30 x 3.70 x 4.00 1.05
p x 0.30 x 3.70 x 4.00 13.95
Extra for column capital 0.10 1.39
4.00 Type of Foundation Wall footing

React footing- wall footing 1 x 11.65 x 9.65 x 0.28 30.92


Bottom nominal slab -1 x 8.10 x 6.10 x 0.15 -7.41
1 x 8.10 x 6.10 x 0.15 7.41
1 x 11.65 x 9.65 x 0.28 11.72
Bottom nominal slab 1 x 8.10 x 6.10 x 0.28 7.81
Sump 2.35 1.17

Column footing x 1.40 x 1.40 x 0.28 x 4.00 2.16


x 1.40 x 1.40 x 0.28 x 4.00 6.16
5.00 Stairs and Platform 3.00
TOTAL 83.71 418.44

6.00 Excavation footings 1 x 11.65 x 9.65 x 2.00 225.00

7.00 PCC footing 1 x 11.65 x 9.65 x 0.10 12.00

7.00 Plinth protection 1 x 13.15 x 11.15 x 0.15 22.00


304 85.71429
303.45 8.571429

25 251.2595

Length
(m) HYSD Steel (MT)
0.90% 1.00 70.1459

1.50% 2.00 121.1295


1.50% 1.60 172
1.50% 0.128

1.50% 0.013 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.70% 1.80 Total depthDepthXX c b Ir OO II
0.70% -0.40
0.35% 0.20

0.35% 0.10
83.75
0.75% 0.100

1.50% 0.40
6.94 82.91934 6940.923

69.40923

0.837069

121.5 30481.92
277.4429
LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ OF R.C.C CWR-300 KL CAPACITY AT SBC-100 KN/SQ.M

Shape of Tank:- Circular


Design Parameters of CWR
Thickness of Top Slab= 0.15 m
Internal Dia of Tank= 10 m
Outside dia of tank = 10.4 m
Ht of Tank including FB= 4.3 m
No of columns inside tank= 4
Thickness of wall at top= 0.2 m
Thickness of wall at bottom= 0.2 m
Avg thickness of wall= 0.2 m
Dia of inside column= 0.3 m
No of columns= 4
Length of column footing= 1.5 m
Width of column footing= 1.5 m
Thickness of column footing= 0.3 m
Size of toe= 0.3 m
Size of heel slab= 1.5 m
Inside dia of heel slab from centre= 7m
Outside dia of toe slab from centre= 11.6 m
Length of Wall footing= 2m
Width of Wall footing= 2m
Outside dia of tank upto footing 11 m
Thickness of wall footing= 0.3 m
Dia of Nominal circular slab= 7m
Thickness of nominal circular slab= 0.15 m
Dia of tank for PCC= 11.2
Thickness of PCC= 0.1 m
Dia for plinth protection= 12.7 m

Volume
Sl. Items of Concrete Measurement (m3)
1.00 Top Circular slab p x 5.20 x 1.00 x 0.15 12.74
p x 5.20 x 1.00

2.00 Vertical wall 2p x 5.00 x 0.20 x 4.30 27.02


2p x 5.00 x 8.60

3.00 RCC Columns Inside tank p*0.25 x 0.30 x 4.30 x 4.00 1.22
p x 0.30 x 4.30 x 4.00
Extra for column capital 0.12
4.00 Type of Foundation Circular footing

Circular footing- wall footing p x 3.50 x 5.80 x 0.30 20.16


p x 3.50 x 5.80 x 0.30
Bottom nominal slab p x 3.50 x 1.00 x 0.15 5.8
Sump 2.02

Column footing x 1.50 x 1.50 x 0.30 x 4.00 2.70


x 1.50 x 1.50 x 0.30 x 4.00
5.00 Stairs and Platform 3.00
TOTAL 74.75

6.00 Excavation footings p x 11.20 x 11.20 x 2.00 198.00

7.00 PCC footing p x 11.20 x 11.20 x 0.10 10.00

7.00 Plinth protection p x 12.70 x 12.70 x 0.15 20.00


4.6

3 23100 0.077
Formwor Length
k (m2) (m) HYSD Steel (MT)
1.20% 1.20 94.17452
84.95

1.50% 3.30 122.1422


270.18

1.10% 0.100
16.21
1.62 1.10% 0.011 #REF! #REF! #REF!

Volume of Annular Raft Foundation


0.75% 1.20 Total depthDepthXX c b Ir OO
17.53
0.40% 0.20
1.75 0.40% 0.10

0.75% 0.200
7.2
1.50% 0.40
399.44 6.71 89.78345 6710.918

67.10918

0.747456

121.5
II LL F=(2*OO)^G=(2*II)^2 DD=(2*c+bZZ=(2*c-b)i at outer radius
BOQ for Construction of CWR at-------------------

Capacity of CWR: 100KL Circular


SBC: 10T/sqm
Eartquake zone: Zone II
Sr.No Description of Item Quantity Unit Rate(Rs) Amount(Rs)
[1] Excavation for foundation/pipe
trenches in Ordinary Soil including
removing the excavated material upto
50 m and lifts as below, stacking and
spreading as directed by Enginner-in-
Charge, normal dewatering,preparing
the bed for foundation and excluding
backfilling etc., complete
- -
(a) For depth 0.0 to 1.5 m 198.00 m³ 164 32472
(b) For depth 1.5 to 3.0 m 0 m³ 175.5 0
[2] Providing and casting in situ mass
cement concrete in grade M15 (approx.
corresponding to prop 1:2:4) using
granite, quartzite trapmetal of size
12mm to 25mm incl.consolidation,
curing etc. complete

- -
(a) PCC 10.00 m³ 4280 42800
[3] Providing and casting in situ C.C in
grade M30 for container part and M 25
for staging/columns/raft using granite,
quartzite trapmetal of size 12mm to
20mm and 6mm to 12mm incl.
scaffolding, centering, formwork,
needle vibrated consolidation, curing
and hydraulic testing etc.
complete(excl. cost of reinforcement)
- -
(i) Foundation raft
(a) Wall footing 24.88 m³ 7500 186566.7005
(b) Nominal slab 5.77 m³ 7500 43295.07376
(iii) Columns 1.34 m³ 7500 10030.31994
(iv) Top slab 12.74 m³ 7700 98115.70848
(v) Vertical walls 27.02 m³ 7700 208036.2655
(vi) Stair case 3.00 m³ 7700 23100
[4] Supplying, Cutting, bending, binding -
and placing in position as per plan and
design and as per IS 2503 incl. cost of
steel and binding wire for reservoirs
only incl. lift upto 6 mt. height using
TMT bars confirning to relevent IS

Foundation 1700.00 kg 68 115600


Columns 110.92 kg 68 7542.446957
Vertical wall 3300 kg 68 224400
Top slab 1200 kg 68 81600
Platform 400 kg 68 27200
[5] Finishing with Epoxy paint (two or
more coats) at all locations prepared
and applied as per manufacturer's
specifications including appropriate
priming coat, preparation of surface,
etc. complete.
-
(a) On concrete work inside of 270.18 m² 117 31610.70528
containor
[6] Providing & casting in situ CC (1:2:4)
for plinth protection around the ESR
including the work of making sub base
& base of approved materials
20.00 m³ 4280 85600
[7]
Centering & shuttering with plywood
or steel sheets including strutting,
propping bracing both ways & removal
of form work for foundation in
basement rafts up to plinth level.
Foundation 26.48 Sq.m 162 4290.261505
Column 17.83 Sq.m 254 4529.246695
Container 270.18 Sq.m 269 72677.60445
Top slab 84.95 Sq.m 269 22851.19098

Platform 10.00 Sq.m 268 2680


[8] Supply & fixing in cement mortar 200 Kg 90.5 18100
welded hand railing made out of MS
round or square bars, flats etc. for
staircase as per design in all respect
with priming coat of red oxide.
Providing & applying 2 coats of water
based cement paint to unplastered
concrete surface at all level after
cleaning the surface of dirt, dust,
grease and applying paint @ 1 Lit for 2
Sqm including material, labour,
scaffolding complete as per cl 800 of
MORTH etc.

(a) Paint on External Surfaces of 135.09 m² 220 29719.4665


Container
(b) Stair case 10 m² 220 2200

[9] Providing & applying Anti carbonation - -


paint of approved manufacture & of
approved color in 2 coats to the
external surfaces of container including
scaffolding if necessary and preparing
the surface, curing etc., complete.

Top slab 84.95 m² 55 4672.176594

Providing, fabricating and erecting MS


ladder of 450mm wide made of 65 x 65
x 6mm angle iron and 20mm MS bars
for walkway to top of the OHSR
including cutting, hoistng, fixing in
position and applying a priming coat of 5 Mtr 1390 6950
approved steel primer complete in all
respect as per specifications and the
direction of the Engineer.

[10]
Providing, fabricating and erecting MS
ladder (with MS cage)of 450mm wide
made of 65 x 65 x 6mm angle iron,
20mm MS bars for walk way to top of
the OHSR and for cage flat 3 Nos-75 x
8 as vertical member and flat 40 x 5 as
horizontal member 300 c/c including
cutting, hoistng, fixing in position and 0 Mtr 3450 0
applying a priming coat of approved
steel primer all complete as per
specification and the direction of the
Engineer.

[11]
Providing, fabricating and erecting
hand railing for walkway, top dome
slab, balconey,staircase and landing
consist of two rows ( one at top and
other at middle level) of 20 mm GI
pipe class-B and 900 mm high vertical
angle 65X65X6 mm at spacing 1.50 m
c/c including welding, threading, 0 Mtr 780 0
applying a priming coat of approved
steel primer and embedding in cement
concrete floor complete in all respect as
per specification and the direction of
the Engineer.

[12]
Supply, fabricating & fixing of
anodised (20 to 25 micron) Aluminum
ladder of 450mm wide with 2 nos
rectangular section of 65 x 35 mm (3
mm thick) as vertical post and 25 mm 5 Mtr 1500 7500
bars steps at 300 mm c/c complete in
all respect as per the specification and
the direction of the Engineer.
[13]
Brick work with FPS bricks of class
designation 75 in foundation and plinth
[14] in:
Cement mortar 1:4 (1 cement : 4 coarse
10.00 Cum 3950 39500
sand)
[15] Provision for lightening arrestor 0 LS 40,000 0

Provision for checking the SBC of Site ,


Drawing and Design of ESR & mix design
[16] from recognised Engineering 1 LS 80,000 80000
[17] Provision for slogan 1 LS 5,000 5000
[18] Provision for water level indicator 1 LS 10,000 10000
[19] Provision for cawl type SS ventilator 1 No 5,000 5000
[20] Provision for puddle collars/bands 1 LS 25,000 25000
Total cost 1558639.167

Total Cost 1558639.167


Cost of OHSR/L 5.20

T&P article
Mixer
Weigh batcher
Vibrator
---
66.66667
0.066667

You might also like