Api 510 Exam 2021
Api 510 Exam 2021
Api 510 Exam 2021
1 Scope
1.1.1 Coverage
If in-service vessels are covered by requirements in the construction code and API 510 or if there is a conflict between the
two codes, the requirements of API 510 shall take precedence.
1.1.2 Intent
The intent of this code is to specify the in-service inspection and condition-monitoring program that is needed to
determine the integrity of pressure vessels and pressure-relieving devices.
1.2.2 Excluded and Optional Services
Some vessels exempted in accordance with the criteria in ASME Code, Section VIII, Division 1 should be considered for
inclusion based on risk (probability and consequence of failure) as determined by the owner/user.
2 Normative References
API Recommended Practice 578, Material Verification Program for New and Existing Alloy Piping Systems
3.1.15 defect
An imperfection whose type or size exceeds the applicable acceptance criteria and is therefore rejectable.
5.4.1 Inspection for Different Types of Damage Mechanisms and Failure Modes
e) Metallurgical changes:
1) graphitization—refer to API 571, Section 4.2.1;
2) temper embrittlement—refer to API 571, Section 4.2.3;
3) hydrogen embrittlement—refer to API 571, Section 4.5.6
5.4.4 Vessels in cyclic service (cycles of pressure, temperature, or combinations of both pressure and temperature) should
be evaluated for potential fatigue cracking failures and have appropriate inspections planned. The following
considerations should be evaluated where applicable for vessels in cyclic service.
5.6.2.5 CMLs and examination points should be permanently recorded, (e.g. marked on inspection drawings and/or on
the equipment) to allow repetitive measurements at the same CMLs. Repeating measurements at the same location
improves accuracy of the calculated damage rate.
5.7.2.3 Corrective procedures should be utilized when metal temperatures (typically above 150 °F [65 °C]) impact the
accuracy of the thickness measurements obtained. Instruments, couplants, and procedures should be used that will result
in accurate measurements at the higher temperatures. Typically, procedures will involve calibrating with hot test plates
or adjusting measurements by the appropriate temperature correction factor.
5.8.5.2 For sensitized austenitic stainless steel piping subject to Polythionic stress corrosion cracking, consideration should
be given to using an alkaline-water solution for pressure testing.
Pneumatic testing (including combined hydro pneumatic) may be used when hydrostatic testing is impracticable because
of limited supporting structure or foundation, refractory linings, or process reasons. When used, the potential personnel
and property risks of pneumatic testing shall be considered by an engineer before conducting the test. As a minimum, the
inspection precautions contained in the ASME Code shall be applied when performing any pneumatic test. A pneumatic
test procedure should be developed by the engineer.
5.8.7.2 To minimize the risk of brittle fracture during a pressure test, the metal temperature should be maintained at least
30 °F (17 °C) above the MDMT or MAT for vessels that are more than 2 in. (5 cm) thick and 10 °F (6 °C) above the MDMT
or MAT for vessels that have a thickness of 2 in. (5 cm) or less. The test temperature need not exceed 120 °F (50 °C) unless
there is information on the brittle characteristics of the vessel material indicating a higher test temperature is needed.
Pressure Testing Alternatives
5.8.8.1 Appropriate NDE (e.g. RT, UT, PT, MT, etc.) shall be specified and conducted when a pressure test is not performed
after a major repair or alteration. Substituting NDE procedures for a pressure test after an alteration or major repair may
be done only after the engineer and inspector have approved.
5.9.2 If a pressure vessel component experiences accelerated corrosion or should fail because an incorrect material was
inadvertently substituted for the specified material, the inspector shall consider the need for further verification of existing
materials in the pressure vessel or other pressure vessels in same or similar service.
5.10.3 Crack-like flaws and environmental cracking shall be assessed by an engineer (refer to API 579-1/ASME
FFS-1, Part 9) and/or corrosion specialist. Preferential weld corrosion shall be assessed by the inspector.
5.11 Inspection and Repair of Flanged Joints
5.11.2 Accessible flange faces should be examined for distortion and to determine the condition of gasket-seating
surfaces.
6.5.2.2 If the requirements of 6.5.2.1 b) are not met, the next inspection shall be an internal inspection. As an
alternate to the above limits, an on-stream inspection can be performed if an RBI assessment (per 6.3) determines that
risk associated with the vessel is acceptably low and the effectiveness of the external NDE technique(s) is adequate for
the expected damage mechanism. This assessment should include a review of past process conditions and likely future
process conditions.
7.4.2.2 Along the designated length, the thickness readings should be equally spaced. For areas of considerable size,
multiple lines in the corroded area may have to be evaluated to determine which length has the lowest average thickness.
The following criteria must be met in order to use thickness averaging:
— the region of metal loss has relatively smooth contours without notches (i.e. negligible local stress
concentrations),
— the equipment does not operate in the creep range,
— the component is not in cyclic service,
— a minimum of 15 thickness readings should be included in the data set,
— minimum reading must be included in the thickness average;
— lowest individual reading cannot be less than 50 % of t required.
7.4.2.4 a) When performing thickness averaging near a nozzle, the designated length shall not extend within the limits of
the reinforcement as defined in the construction code.
8.1.4 Design
New vessel nozzles, connections, or replacement parts shall meet the design requirements of the applicable construction
code. The design of replacement parts and new nozzles shall employ the same allowable stress criteria as used for the
vessel design.
8.1.6.3 Filler Metal Strength for Overlay and Repairs to Existing Welds
If a filler metal is used that has a minimum specified tensile strength lower than the minimum specified tensile strength
of the base metal, the compatibility of the filler metal chemistry with the base metal chemistry shall be considered
regarding weldability and service damage. In addition, all of the following shall be met.
a) The repair thickness shall not be more than 50 % of the required thickness of the base metal (this excludes corrosion
allowance).
b) The thickness of the repair weld shall be increased by a ratio of minimum specified tensile strength of the base metal
and minimum specified tensile of the filler metal used for the repair.
Tfill = d S × base ⁄ Sfill
8.1.6.4 Repairs to Stainless Steel Weld Overlay and Cladding
8.1.6.4.3 For equipment exposed to atomic hydrogen migration in the base metal (operates in hydrogen service at an
elevated temperature or has exposed base metal areas open to corrosion), these additional factors must be considered
by the engineer when developing the repair plan:
a) outgassing base metal;
8.1.7.3 Preheating
Preheat temperature used in making welding repairs shall be in accordance with the applicable code and qualified welding
procedure.
8.2 Rerating
a) Calculations performed by either the manufacturer or an owner/user engineer (or his/her designated representative)
experienced in pressure vessel design, fabrication, or inspection shall justify rerating.
c) Current inspection records verify that the pressure vessel is satisfactory for the proposed service conditions and that
the corrosion allowance provided is appropriate. An increase in allowable working pressure or design temperature shall
be based on thickness data obtained from a recent internal or on-stream inspection.
API 571
3.8 Atmospheric Corrosion
3.8.3 Critical Factors
f) Corrosion rates increase with temperature up to about 250 °F (120 °C). Above 250 °F (120 °C), surfaces are usually too
dry for corrosion to occur except under insulation.
3.27 Erosion/Erosion-Corrosion
3.27.5 Appearance or Morphology of Damage
a) Erosion and erosion-corrosion are typically characterized by a localized loss in thickness in the form of grooves, gullies,
waves, rounded holes, valleys, or simply a greater amount of thinning in a localized area such as the outer radius of a
piping elbow. These losses often exhibit a directional pattern.
API 576
4.4 Pilot-operated Pressure-relief Valves
A pilot-operated pressure-relief valve consists of a major relieving device or main valve, which is combined
with and controlled by a self-actuated auxiliary pressure-relief valve (pilot). Just as with direct-acting valves,
the pilot-operated valve can be a safety valve (also called a snap action design), relief, or safety relief valve
(also called a modulating acting design) type.
Pilot-operated pressure-relief valve are generally used: where a low differential exists (operating margin) between the
normal pressure equipment (vessel and piping) operating pressure and the set pressure of the valve.
If the initial pop is at a pressure higher than the CDTP, the valve should be tested a second time. If it then pops near the
CDTP, the valve may not have originally popped at the CDTP because of deposits. If on the second try the valve does not
pop within the tolerances allowed by the ASME BPVC, either the valve setting may have been originally in error or it
changed during operation. Pressure-relief valves that do not pop at inlet pressures of 150 % of CDTP should be considered
as stuck shut.
Normally, for ASME BPVC Section VIII valves, the deviation of the as-found set pressure from the nameplate set pressure
should not exceed ±2 psi (±15 kPa) for pressures less than or equal to 70 psi (500 kPa) or ±3 % for pressures greater than
70 psi (500 kPa).
API 572
3 Terms and Definitions
3.1.33 weld buildup
The use of weld metal of similar composition to the base metal for the purpose of restoring base metal thickness.
API 577
9.9.3 Ultrasonic Examination System Calibration
Calibration system checks should be performed prior to and at the completion of an examination. In addition, a
system check is required with any change in the search unit, cabling, and examiner.
Table 11—Brinell Hardness Limits for Steels in Refining Services (two questions)
API 578
5 Material Verification Programs
5.1 General
The owner/user shall establish a written material verification program indicating the extent and type of PMI to
be conducted during the construction of new assets, retroactively on existing assets, and during the maintenance, repair,
or alteration of existing assets.