Pipeline Irrigation Network Guidelines
Pipeline Irrigation Network Guidelines
GOVERNMENT OF INDIA
JULY 2017
APPENDIX ............................................................................................................................ 92
PART-II
Table- 11.1 Cropping pattern for Rabi & Kharif ........................................................................................................115
Table-11.2 Parameters to compute capacity of pump .........................................................................................116
ACKNOWLEDGEMENTS
SOURCE TO OUTLET
Historically Irrigation development in the country capita water availability has reduced drastically
has been undertaken as Canal Distribution from 5177 cum in the year 1951 to 1567 cum in
Network emanating from rivers, dams and the year 2011. As per international standards, now
reservoirs for the purpose of carrying water mostly India is already in water stress zone (if water
through gravity up to outlets and from outlets to availability is between 1000 to 1700 cum per year)
agricultural field through water courses or field with threats of climate change may further
channels. In earlier times canals were unlined; aggravate the problem. By the year 2050, with
later on these unlined canals have been improved projected population of the order of 1.6 Billion, the
by lining to increase their water carrying efficiency water availability will further reduce to 1140 cum
which led to extend water deliveries to additional nearing to water scarce situation. India as a
fields which had not been irrigated previously. country has to adopt itself to this changed scenario.
Canals are designed hydraulically to provide the Efficiency has to be brought in each water use
most efficient cross section for the transportation activity including irrigation for sustaining the food,
of irrigation water. There is no further scope in water, shelter and employment requirement of the
improving the efficiency of the hydraulically most human and animal population.
efficient canals section with most efficient lining.
Therefore the overall efficiency that can be Piped Irrigation System provides one of such
achieved by canal conveyance and distribution has options which if implemented properly can curtail
reached the upper limit which is about 35-60%. irrigation water demand without compromising
with net irrigation requirement (NIR) but by
With the increasingly greater demand on limited improving the water use efficiency. The estimated
water supplies in many parts of country, there is an overall efficiency with piped irrigation network is
urgent need for its efficient utilization by reducing of the order of 70-80%. Experience gained from
losses at various reaches in the irrigation system. several States and many Countries in arid and
Replacement of existing canals with pipe lines or semi-arid zones has shown that Piped Irrigation
new schemes with pipe lines wherever feasible in Network (PIN) techniques are replacing
order to improve irrigation efficiency or to further successfully the traditional open canal methods.
extend the area of irrigated agriculture is the need However, some of the projects already constructed
of the hour. Field application of water through with PIN are not showing expected performance
micro irrigation methods improves overall due to various reasons including improper
efficiency of the project to a great extent. Piped planning and lack of maintenance.
irrigation can be accomplished many a times
through gravity and/or use of pumps to lift the For proper planning, design and implementation
water into the distribution network. of Piped Irrigation Network in the country, the
need for suitable guidelines is felt necessary by the
With rising population, demand for commodities Ministry of Water Resources, River Development
and change in life style, more and more demand and Ganga Rejuvenation (MoWR, RD&GR) and
for water resources from other sectors is projected, Central Water Commission (CWC). Accordingly,
leaving less water for irrigation as the availability this guideline on PIN has been prepared.
is finite in nature. With rising population, per
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTRODUCTION 2
This Guideline consists of two Parts. Part- I ii. Cross Drainage and Cross Masonry
covers Planning and Design of Piped Irrigation (Communication) structures can be omitted or
Network (PIN) from the Source of water to minimized.
Outlet. iii. Irrigation works become obstacles in the way
The Portion below the Outlet to Field / Micro of free drainage of water during rainy season
Irrigation is dealt in the Part-II of the Guidelines and thus results in submerging standing crops
(Below Minor Up To Micro Irrigation System in and even villages.
the Field) iv. No damage due to heavy rainfall or flood
during monsoon.
1.1 Piped Irrigation Network (PIN)
v. More Suitable option for flood prone area.
A Piped Irrigation Network (PIN) is a network of vi. No hindrance in movement to the farmers and
installation consisting of pipes, fittings such as farm equipments.
valves, pumps (if necessary) and other devices vii. Increase in CCA as compared to canals, as the
properly designed and installed to supply water water losses are negligible and acquired land
under pressure from the source of the water to the for canal network can also be used for
irrigable area. cultivation as Piped Irrigation Network is under
For surface irrigation method, where large heads ground.
are not required, the underground pipe line system viii. Better option for undulating fields.
is used which is essentially a low pressure system, ix. Because of shorter transit times for water from
also known as ‗open or semi closed’ system. This source to field, lower conveyance losses and
system is open to atmosphere and where the the smaller volumes of water in the conveyance
operating pressure seldom exceeds 5m to 6m. The system, pipe systems can deliver a supply
available level differences of falling topography which is more flexible in both duration and
provide the operating head for the system under timing, in a way not possible CDN, so enabling
gravity for the low pressure flows. intensification and diversification into higher
value crops.
Where large heads are required, underground pipe x. Less execution time for PIN as compared to
line system is used which is essentially a high CDN.
pressure system, also known as ‗closed‘ system. xi. The important targets of the modernization of
This system is not open to atmosphere and where irrigation schemes and digital management will
the operating pressure exceeds 10m for drip and be achieved when water is delivered through
20m for sprinklers. Usually gravity head is not Piped Irrigation Network.
sufficient to create such a high pressure; therefore, xii. In case of canals, the marshes and the ponds
pumps are used for this kind of system. caused by excessive seepage, in course of time
1.2 Advantages of Piped Irrigation become the colonies of the mosquito, which
Network over Canal Distribution gives rise to vector borne diseases and this can
Network (CDN) be minimized by adopting Piped Irrigation
Network. Further salinity and water logging
The following are the advantages of PIN over can be reduced.
Canal Distribution Network (CDN): xiii. Increase in project efficiency of the Piped
i. As most of a piped distribution system Irrigation Network is about 20% as compared
underground, right of way problems are to CDN.
significantly reduced, allowing more direct and xiv. Fertilizers/chemical can also be mixed with the
rational layouts to be chosen. Because outlet water.
location is not limited by topography, pipe xv. Quantity of water supplied by Piped Irrigation
systems are better able to accommodate Network is easily measureable; hence water
existing patterns of land ownership with the auditing can be accurately measured.
minimum of disruption compared with new
irrigation development using CDN.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTRODUCTION 3
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTRODUCTION 4
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 2
2. PIPED IRRIGATION NETWORK (PIN) PLANNING
2.1 General
A Piped irrigation network is a network most direct routes from the water source to fields,
installation consisting of pipes, fittings and other and minimizes the loss of productive land (since
devices properly designed and installed to supply crops can be planted on the fields above the
water under pressure from the source of the water pipelines).
to the irrigable area.
An analogy between the Canal Distribution
Pipelines also permit the conveyance of water
Network (CDN) and Pipe Irrigation Network
uphill against the normal slope of the land and,
(PIN) is pictorially depicted in Fig 2.1 & Fig 2.2
unlike open channels, can be installed on non-
below.
uniform grades. The use of buried pipe allows the
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPED IRRIGATION NETWORK (PIN) PLANNING 6
2.2 Piped Irrigation Network Planning with the department of agriculture and the
agriculturist of the area proposed to be served
The planning and layout of Piped Irrigation
allowing for the anticipated change in crop pattern
Network unlike CDN is not controlled by the
due to introduction of wet farming in the area.
command area to be irrigated and the source of
Knowing thus the duty for various crops, the area
supply. The layout of main lines and branches is
under cultivation under different crops, the
generally fixed on the consideration of economy.
intensity of irrigation, the culturable area to be
For the layout of minors and distributaries, points
commanded shall be worked out and marked on
of off take may be suitably selected but their
the map. Areas that are higher and may not be
layout is more or less governed by the blocks of
supplied with the flow/gravity irrigation should be
areas to be irrigated taking into consideration
marked on the map with separate colour and the
watersheds and drainages. The main lines and
pumping requirements for that area need to be
branches are feeder lines for distributaries and
worked out separately. Main steps in planning of
generally no irrigation is done directly from them.
Piped Irrigation Network Scheme as per FAO
Irrigation outlets are provided on distributaries or
shown in fig 2.3.
minors off taking from distributaries.
2.3 Data Required for Piped Irrigation
The stage for general planning and layout of Piped Network Planning
Irrigation Network arises after the general
The following data is required for planning and
feasibility of the project has been established. The
layout of a Pipe system:
area to be irrigated by pipe line system shall be
i. Topographical map of the area
planned by preparing land use maps, preferably on
ii. Subsurface data
a scale of 1:50,000, showing on them the area
iii. Texture and salt component of the soil
already under cultivation, soil types, habitation
iv. Soil characteristics including mechanical
roads, drainage and contours of the area. The
properties and shear parameters
intensity of irrigation to be provided in the project
v. Permeability of the soil in relation to seepage
shall be decided after taking into account the
losses
factors like socio economic factor, area and
vi. Rainfall data
intensity of the irrigation being achieved on the
vii. Water availability Subsoil water level in the
other projects in the neighborhood etc.
area and quality of the underground water
viii. Possibility of water logging and salination
The important crops of the area and their water
ix. Availability of suitable construction material
requirements shall be determined in consultation
x. Existing drainage and drainage facilities
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPED IRRIGATION NETWORK (PIN) PLANNING 7
It is essential to decide the master plan of WUA & line. By adding canal/pipe line loses
their water entitlement at design stage. The (efficiencies) the gross water requirement
canal/pipe carrying capacity shall be decided such (GIR) is calculated. The season wise and
that due water entitlement will be supplied to all fortnightly gross water entitlement and net
the WUAs in command area of all lines of project. water entitlement for canal/pipe shall be
worked out. On the basis of fortnightly water
To calculate the canal/pipe carrying capacity on requirement, the canal/pipe design carrying
basis of water entitlement, following guidelines capacity shall be decided.
shall be followed;
Efficiencies & design rotation period of canal to be
a) The master plan of all the probable WUAs in considered shall be as given in Table 2.1 below.
command area of project is to be prepared,
2.5.3 Design discharge of Pipe/canal on
once command area survey and tentative
basis of the operation schedule:
alignment of all the canals/Pipe line is
finalized. The ultimate aim of pipe/canal conveyance system
b) The locations where water is to be supplied to is to provide the irrigation water to the planned
the WUA is to be identified.(entry point in ICA of the project. In flow irrigation system the
jurisdiction of WUA) rotational water system is followed and water is
c) The water entitlement of the individual WUA supplied by rotations of 14 days as per the
and all the WUA on individual canal/Pipe line requirement. To supply the water in 14 days for
shall be worked out. The water entitlement of entire planned ICA in command, it is very
WUA and entire canal/pipe line shall be essential to prepare the operation schedule of all
decided on basis of the CCA of WUA and the minor, distributary, and branch Lines off taking
CCA of canal/pipe line. The total due water from main Line/Canal at design stage.
entitlement thus worked out shall be considered
as Net water requirement (NIR) of canal/pipe
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPED IRRIGATION NETWORK (PIN) PLANNING 9
PRELIMINARY
STUDIES
M ENVIRONMENTAL DECISION
A PARAMETERS PARAMETERS
SOURCE OF
P SUPPLY
NETWORK
C LAYOUT
CLIMATE CHOICE OF
0
POSITIONING OF CONDITIONS CROPPING
L HYDRANTS PATTERN
PEDOLOGIC
L
CONDITIONS COMPUTATION OF
F. PUMPING STATION THE CROP WATER
C WATER REQUIREMENTS
RESERVOIR
RESOURCES
T
CHOICE OF THE
I VERIFICATION IN FARMERS
ONFARM METHOD
FIELD CONDITIONS
O
N DECISION ON THE
NO TOTAL OR
OK PARTIAL
SATISFACTION OF
TIIF CROP WATER
C
REQUIREMENTS
O COMPUTATION OF
THE DISCHARGES MODULE OF THE
M HYDRANT
COMPUTATION OF
P THE PIPE
NUMBER OF
U DIAMETERS FARMERS
PER HYDRANT
T CALCULATION OF
THE RESERVOIR,
A AREA SERVED BY
PUMPING
EACH HYDRANT
STATION.
T REGULATION,
I PROTECTION, ETC DELIVERY
SCHEDULE
O
SIMULATION
S
N MODELS
I
S ANALYSIS OF
M
SYSTEM
U
L
NO
A OK
T
I
O
CONSTRUCTION
N MONITORING &
DATA
COLLECTION
O
ANAYSIS OF THE
M SYSTEM IN
ACTUAL
& CONDITIONS
M DIAGNOSIS &
IMPROVEMENT
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPED IRRIGATION NETWORK (PIN) PLANNING 10
iii. Estimate maximum running days of PIN b) Field Canal/Pipe line efficiency, Eb : Ratio
(Entire outlets) in the respective fortnight for between water received at the field inlet and
water requirement by using appropriate that received at the inlet of the block of fields.
efficiency from root zone to outlet head having
c) Field application Efficiency, Ea : Ratio
proportionate discharge.
between water directly available to the crop
iv. Determine carrying capacity of minor /
and that received at the field inlet.
distributary in different reaches considering
appropriate conveyance efficiency as given in d) Project Efficiency, Ep : Ratio between water
Table 2.1. made directly available to the crop and that
released at the head works, or Ep = Ea Eb Ec
2.8 Procedure for Deciding the
Carrying Capacity of Main / Branch e) Distribution Efficiency, Ed : Eb Ec
Line f) Farm Efficiency, Ef : Ea Eb
2.9.2 Project efficiency iv. The increased water demand due to the rich
Over all irrigation efficiency for micro irrigation cropping pattern (Water intensive) adopted by
with sprinkler shall not be less than 68% farmers in comparison with the cropping
(95%X.95%X0.75) against the present canal based pattern provided in Administrative Approved
conveyance system of 47.25% (70%X90%X0.75). Project Report.
Similarly for drip irrigation, it shall not be less v. The demand for letting the water in storage
than 81.23% (95% X 95% X 0.9) against the tanks in command area and recharging of the
present canal based conveyance system of 56.7% command area during monsoon period.
(70%X90%X0.90). vi. Increase in ICA of project with aging (ICA of
project becomes equal to CCA due to
2.9.3 Comparison of project efficiency conjunctive water use)
based on Canal Vs Pipes
The above are the unanticipated water demands
Table 2.1 gives a comparison of indicative project
which could not be avoided. However it becomes
Irrigation efficiency of Canal Distribution Network
very difficult to full fill the above demands
(CDN) and Piped Irrigation Network (PIN).
simultaneously with regular irrigation water
2.10 Capacity Factor: demands. Ultimately the rotation period of
canal/pipe line gets prolonged which badly affects
It is experienced that after construction of the
the irrigation management and resulting in
conveyance system, the various unanticipated
reduction in yield of the crops. In order to take
water demands as mentioned below arises due to
care of the unanticipated demands in future, some
various reasons which affects the carrying capacity
provision is to be made in the carrying capacity of
of system assumed at the time of design.
main and branch lines by adding capacity factor.
i. The drinking and industrial water requirement For the design purpose, a capacity factor of 1.10
demands.
shall be considered for Main line and Branch lines
ii. The letting out of water in rivers, nala during while deciding carrying capacity. No allowance is
scarcity period. made for distributaries and minors as the capacity
iii. The demands for lift irrigation schemes on of these can be increased by increasing velocity
uncommand side of the Canals/Lines. without much loss in head
Table 2.1 Comparison of Irrigation efficiency of CDN & PIN
Method of Micro Irrigation
Surface Irrigation
conveyance/ irrigation Sprinkler Drip
Conveyance Efficiency (%) 70 70 70
Canal based Field Canal Efficiency 90 90 90
Field Application efficiency (%) 75 90 60
Conveyance
Overall efficiency (%) 47.25 56.7 37.8
Source:
a) FAO,Irrigation Water Management: Irrigation Scheduling
b) Guidelines for Estimating Irrigation Water Requirement (Technical Series-2),Ministry of Irrigation,GoI,May 1984
Average increase in overall efficiency is about 20%. By adopting Piped Irrigation Network system the most
important goal of National Water Mission of improving irrigation efficiency by 20% can be achieved.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 3
3. HYDRAULICS OF PIPE FLOW
𝑝1 2 𝑝2 2
𝑍1 + 𝑤 + 𝑉1 2𝑔 + ∆𝐸 = 𝑍2 + 𝑤 + 𝑉2 2𝑔 + ∆𝐻
3.3.2 Law of Conservation of Energy Where,
The total energy of pipe flow consists of elevation ∆E is energy addition to the system by pump,
head, pressure bead and velocity head. Between ∆H is the total head loss between points (1) and
Point (1) and (2), total energy may be conserved in (2)
prefect fluid (Figure 3.4). However, if the water It is very important to estimate the head losses for
begins to move, head loss generated by friction hydraulic engineering in steady condition.
will occur. So, actually the energy equation will
be as follows.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
HYDRAULICS OF PIPE FLOW 16
Plastic(smooth) 0.011
Note: Values of n may be taken as 0.015 for unlined metallic pipes and 0.011 for plastic and other
smooth pipes.
d) Colebrook-white formula m2
For circular conduits, 𝜈20℃ for water =10−6 and
1 𝑘 2.51 m
s
= −2 log10 [ + ] g= 9.81 s 2
𝑓 3.7𝑑 𝑅𝑒 𝑓
where
The Modified Hazen William‘s formula derived as
f = Darcy‘s friction coefficient
𝑉 = 143.534𝐶𝑅 𝑟 0.6575 𝑆 0.5525
Re = Reynold‘s number
[𝐿(𝑄/𝐶𝑅 )1.81 ]
= velocity x Diameter/viscosity =
994.62𝐷 4.81
d = diameter of pipe
where
k = roughness projection (Table 3.3)
V = velocity of flow in m/s
CR = pipe roughness coefficient
e) Modified Hazen William’s formula (1 for smooth; <1 for rough pipes; Table
The Modified Hazen William‘s formula has been 5.5)
derived from Darcy-Weisbach and Colebrook- r = hydraulic radius in m
White equations and obviates the limitations of s = friction slope
Hazen-Williams formula. D = internal diameter of pipe in m
(3.83 × 𝐶𝑅 × 𝑑 0.6575 × (𝑔 × 𝑆)0.5525 ) h = friction head loss in m
𝑉= L = length of pipe in m
𝜈 0.105
where Q = flow in pipe in m3 /𝑠
CR = coefficient of roughness ( Table 5.5)
The recommended 𝐶𝑅 Values in Modified Hazen-
D = pipe diameter in m
Williams Formula (at 200C) are given in table 3.4.
g = acceleration due to gravity (m/s2)
S = friction slope
v = viscosity of liquid (m2/s)
Table 3.2 Friction Factors In Darcy-Weisbach Formula
Sl. No. Pipe Material Diameter(mm) Friction Factor
New Design
1 Metallic pipes-Cast iron and Ductile Iron 0.15 *
2 Metallic Pipes-Mild Steel 0.06 *
3 Asbestos Cement, Cement Concrete, Cement Mortar or 0.035 0.035
epoxy lined steel, CI and DI pipes
4 PVC,GRP and other plastic pipes 0.003 0.003
Note : Reference may be made to IS: 2951 for roughness values of aged metallic pipes
S/D = 0.05 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
a/A = 0.05 0.1 0.2 0.36 0.48 0.6 0.71 0.81 0.89
fg (D =610 mm) 235 100 28 11 5.6 3.2 1.7 0.95 -
fg (D=762mm) 333 111 23 9.4 5.2 3.1 1.9 1.13 0.6
ϴ= 5 10 15 20 25 30 35 40 45 50 60 70 90
a/A = 0.91 0.83 0.7 0.66 0.58 0.5 0.43 0.36 0.29 0.23 0.13 0.06 0
fg = 0.24 0.52 0.9 1.54 2.51 3.91 6.22 10.8 18.7 32.6 118 751 ∞
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
HYDRAULICS OF PIPE FLOW 19
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 4
When the water is silt rich, design velocity of 4.5 Exit pressures at Irrigation Outlet
Piped Irrigation Network should not lower be than for Micro Irrigation
non-silting velocity. Non silting velocity should be
Outlet pressure for micro irrigation systems with
determined by experiments. The maximum
design working pressure between 0.2 MPa and 0.4
velocity may be limited to 3.0 m/s.
MPa shall be used.
4.2.2 Minimum velocity 4.6 Determination of pipe diameter
Designers must specify pipe diameters and flow The diameter of the pipe can be preliminarily
rates that allow for a minimum operational water determined based on the design discharge and
velocity, especially for irrigation systems that permissible velocity in a particular section.
utilize emitters with small apertures such as drip
and micro sprinklers. This will ensure that any 4.7 Overburden for buried pipes
sediment or solids are flushed through the lines. A minimum overburden of 1.2 m shall be provided
Minimum velocity should not be below 0.6 m/s. for Main and Branch lines and 0.6m for
distributaries and minors to avoid land acquisition
problem.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
DESIGN STANDARDS FOR PIPED IRRIGATION NETWORK 22
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
DESIGN STANDARDS FOR PIPED IRRIGATION NETWORK 23
4.17 Bedding for Pipes to give the curved seating, as shown in Fig. 1B and
Fig. 1C ( Fig.4.2).
The bottom of the trench shall be properly
trimmed to permit even bedding of the pipe-line. 4.18 Maximum size of ICA for single
For pipes larger than 1200 mm diameter in earth point pumping for Micro Irrigation
and murum the curvature of the bottom of the
The Maximum size of ICA for single point
trench should match the curvature of the pipe as
pumping for Micro Irrigation should not exceed
far as possible, subtending an angle of about 120‖
2000 ha or 1.5 cumec.
at the centre of the pipe as shown in Fig. 1A.
Where rock or boulders are encountered, the 4.19 Size of silt to be removed
trench shall be trimmed to a depth of at least 100
Silt particle of size greater than 150 microns shall
mm below the level at which the bottom of the
be removed to prevent clogging of nozzle of drip
barrel of the pipe is to be laid and filled to a like
points in micro-irrigation.
depth with lean cement concrete or with non-
compressible material like sand of adequate depth
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
DESIGN STANDARDS FOR PIPED IRRIGATION NETWORK 24
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 5
Once the source, water availability, proposed i. Tree Piped Irrigation Network: In the Tree
command area, location of outlets and discharge Piped Irrigation Network, each outlet gets its
cut-off schedule have been finalized, the next step supply from one and only one route.
is the fixation of layout of conveyance network ii. Loop Piped Irrigation Network: In the Loop
(i.e. pipes layout) and optimization of diameters Piped Irrigation Network, each outlet gets its
within the available head loss. supply from more than one route.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 26
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 27
arriving at the most suitable and economical pipe construction cost and then capitalized over the
diameters and proper selection of pipe material. project period.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 28
Table 5.1 Illustration of computations for LCC Analysis based on assumed parameters
INPUT DATA :
Original Cost
14 No Of Days The Pipe Runs In A Year Considering Two 240 days
Crops
15 Water Charges, Rs (Assumed) 7 per cum
16 Combined Efficiency Of Pump - Motor Unit 75 %
CALCULATIONS :
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 30
The above calculation is for computing the Life undertakings and therefore are of particular
Cycle Cost for one particular pipe material and importance. Pipe materials shall have to be
similar calculation shall be carried out for different judiciously selected not only from the point of
pipe materials with appropriate input parameters. view of durability, life and overall cost but also
The final decision may be taken based on the Life their suitability in performing the required function
Cycle Cost Analysis. throughout the design life of the pipe network.
5.5 Pipe Materials 5.5.1 Selection of Pipe Materials
Pipelines are major investments in water supply Selection of Pipe Material must be based on the
projects and as such constitute a major part of the following considerations.
assets of water authorities. Pipes represent a large
proportion of the capital invested in water supply
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 31
i. The initial carrying capacity of the pipe and its pipes available in the market is exhaustive and due
reduction with use, defined, for example, by the to space constraints, comparisons of typical pipe
Modified Hazen Williams coefficient materials only has been given.
(C).Values of C vary for different conduit
materials and their relative deterioration in
service. They vary with size and shape to some
extent.
ii. The strength of the pipe as measured by its
ability to resist internal pressure and external
loads.
iii. The life and durability of pipe as determined by
the resistance of cast iron and steel pipe to
corrosion; of concrete and A.C. pipe to erosion
and disintegration and plastic pipe to cracking
and disintegration. Normally, the design period
of pipelines is considered as 50 years.
iv. The ease of transportation, handling and laying
and jointing under different conditions of
topography, geology and other prevailing local
conditions.
v. The safety, economy and availability of
manufactured sizes of pipes and specials.
vi. The availability of skilled personnel for
construction of pipelines.
vii. The ease of difficulty of operations and
maintenance.
viii. Nominal pressure of chosen pipe material
should not be less than the sum of design
working pressure and water hammer pressure.
ix. Connection between pipe and pipes, fittings
and accessories should be simple and reliable.
x. Nominal pressure of fittings and accessories
should not be less than that of pipe; dimension
and deviation should meet sealing
requirements.
xi. When the sulphate concentration in soil
exceeds 1%, concrete pipes and metal pipes
should not be used
The cost of pipe material and its durability or
design life are the two major governing factors of
selection of pipe material. The pipeline may have
very long life but may also be relatively expensive
in terms of capital recurring costs and, therefore, it
is very necessary to carry out a detailed economic
analysis before selecting pipe materials.
Design Flexible Semi Flexible Flexible Structure Flexible Flexible Structure Rigid Structure Rigid Structure Rigid Structure Based on semi
Concept Structure Structure Structure rigid pipe theory
Bedding The bottom of Where pipes are to The pipe should be The trench Polyethylene pipe Types of Bedding Bedding Bedding
Requirement the trench be bedded directly uniformly and bottom shall be requires no special bedding requirements are requirements are requirements are
shall be on the bottom of the continuously supported constructed to bed preparation suggested as minimal due to minimal due to minimal due to
properly trench, it should be through its whole provide a firm, for laying the pipe per IS 783 Rigid nature. rigid nature. semi rigid nature.
trimmed to trimmed and levelled length with firm stable stable and underground, Smaller diameter
permit even to permit even bedding material. Pipe uniform support except that there 1) Type A Types of pipes upto 600
bedding of the bedding of the bedding material for the full shall be no sharp Bedding – Types of bedding bedding mm are rigid in
pipeline. For pipeline and should should be sand or length of the objects around the concrete suggested as per suggested as nature.
pipes larger be free from all gravel as per the pipeline. There pipe. However, cradle support IS 783 per IS 783
to the pipe
than 1200 mm extraneous matter requirements on the should be no while laying in
(continuous 1) Type A 1) Type A
diameter in which may damage backfill material. sharp objects rocky areas
concrete Bedding – Bedding –
earth and the pipe or the pipe that may cause suitable sand cradle of concrete cradle concrete cradle
murum the coating. Additional The bedding should be point loading. bedding should be monolithic support to the pipe support to the
curvature of excavation should be placed so as to give Any large provided around cross section (continuous pipe
the bottom of made at the joints of complete contact rocks, hard pan, the pipe and if concrete cradle of (continuous
the trench the pipes so that the between the bottom of or stones larger compacted. (Refer unreinforced) monolithic cross concrete cradle
should match water main is the trench and the pipe than 20 mm Cl. No. 6.3 of IS section if of monolithic
the curvature supported along its and should be should be 7634 Part 2 : 2) Type B unreinforced) cross section if
of the pipe as entire length. Where compacted to provide a removed to 2012) Bedding – unreinforced)
far as excavation is minimum compaction permit a Sand or other 2) Type B
possible, through rocks or corresponding to 90% minimum granular Bedding – Sand 2) Type B
subtending an boulders, the maximum dry density. bedding material or other granular Bedding –
angle of about pipeline should be thickness of shaped to fit material shaped to Sand or other
1200 at the bedded on concrete If the pipe is supported 100-150 mm lower curved fit lower curved granular
centre of the bedding or on at on grade elevation with under the pipe. shape of the shape of the pipe. material shaped
pipe. Where least 150 mm of fine use of timber or of For pipes of pipe. 3) Type C to fit lower
rock or grained material, or tapered wedges, they diameters 100 Bedding – curved shape of
boulders are other means are used must be removed and mm or greater, 3) Type C Ordinary Type of the pipe.
encountered, to protect the pipe not left in place. They bell holes in the Bedding – Bedding with 3) Type C
the trench and its coating. can usually be pulled bedding, under Ordinary Type normal care Bedding –
shall be Material harmful to out after the bedding each socket of Bedding Ordinary Type
trimmed to a the pipeline should has been compacted to joint, shall be with normal 4) In rocky portion, of Bedding
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 33
depth of at not be used.(Refer the specified minimum provided by care where excavation is with normal
least 100 mm Cl. No. 4.2.5 and compaction. The voids removing some 4) In rocky through rock, the care
below the 4.2.6 of IS 12288: from which the timber of the bedding portion, where trench should be
level at which 1987) has been removed must material, to excavation is excavated 150mm 4) In rocky
the bottom of be properly filled and accommodate through rock, more and filled with portion, where
the barrel of compacted. (Refer Cl. the larger the trench fine granular excavation is
the pipe is to No. 7.1 of IS diameter of the should be material. through rock, the
be laid and 13916:1994) joint and to excavated 150 trench should be
filled to a like permit the joint mm more and excavated
depth with to be made filled with fine 150mm more
lean cement properly. granular and filled with
concrete or Prepare the material fine granular
with non- bedding by material.
compressible laying on soft
material like soil and
sand of alternatively
adequate compacting and
depth to give watering
the curved sparingly until
seating. an effective
(Refer Cl. thickness of
No. 4.2.1 of 100 to 150 mm
IS 5822 : is achieved.
1994) (Refer Cl. No.
6.2.3 & 6.2.7 of
IS 7634 Part 3
: 2003)
Backfill Backfilling For the purpose of Back filling should be Excavated Only soft earth For Type A,B For Type A,B and Backfill Backfill
Materials / should closely backfilling, the depth placed in layers not material should and gravel of good and C , C ,Bedding – compaction is compaction is
Compaction follow the of the trench shall be exceeding a depth per be deposited at quality free from Bedding – minimally minimally
Required welding of considered as layer which can be a sufficient boulders, roots selected fill selected fill important due to important due to
joints of the divided into the compacted to a distance away vegetable matter, material material compacted rigid nature as semi rigid nature
pipe so that following three minimum of 85% from the trench etc, shall be used compacted in in layers not the pipe does not as the pipe does
the protective zones from maximum dry density. to prevent first. If sufficient layers not exceeding 150 mm rely upon side not rely upon side
coating should the bottom of the Lift should normally damage to the quantity of exceeding 150 to a height of 300 support. support.
not be trench to its top: not be greater than 30 pipeline suitable (sharp mm to a height mm above top of
subsequently Zone - A: From the cm in height and the through falling edge stone free) of 300 mm the pipe in case of
damaged. bottom of the trench height differential on stones or excavated earth is above top of the earth foundation
Material to the level of the each side of the pipe debris. not available, the pipe in case of and 150 mm in case
harmful to the centre line of the should be limited to trench shall be earth of rock foundation.
foundation and (Refer IS 783 :
pipeline shall pipe, this amount so as to The first side- filled by borrowed
150 mm in case
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 34
not be used Zone - B: From the prevent lateral fill or gravel or material of rock 1985)
for level of the centre movement of the pipe. haunching layer up to 300 mm foundation.
backfilling. line of the pipe to a should be above top of the (Refer IS 783 :
Refilling shall level 300 mm, above Most coarse grained placed by hand pipe. 1985)
be done in the top of the pipe, soil are acceptable. and compacted
layers not and This may comprise of in layers under Care shall be
exceeding 300 Zone - C: From a gravel or sand. the lower taken during back
mm. Each level 300 mm above However, silty sand, quadrants of the filling for not to
layer shall be the top of the pipe to clayey sand, silty and pipe upto the damage the pipe
consolidated the top of the trench. clayey gravel shall not spring level or joints. Filling
by watering Back-fill material be used unless (half the has to be carried
and ramming, shall be free from proposed to be used in vertical out simultaneously
care being cinders, ashes, slag, conjunction with gravel diameter) of the on the both sides
taken to refuse, rubbish, or clean sand. pipe. of the pipes so that
prevent vegetable or organic Compaction unequal pressure
damage to the material, lumpy or It is very important that can be done by does not occur.
pipeline. The frozen material, the pipe zone backfill careful Load on the buried
filling on the boulders, rocks or material dose not wash trampling with pipeline shall not
two sides of stone or other away or migrate into the feet or with be permitted
the pipeline material, which in the native soil. tamping tools. unless the trench
should be the opinion of the Likewise, potential Successive has been filled to
carried out authority, is migration of the native layers of the height of at
simultaneousl unsuitable or soil into the pipe zone backfill of 75 least 300 mm over
y. deleterious. backfill must also be mm thickness the top of the pipe.
However, material prevented. may then be Filling shall be
The spiders containing stones up placed over and done in layers of
provided to 200 mm as their Heavy earth moving compacted to a 150 mm, with the
during greatest dimension equipment used for height above first layer watered
assembly and may be used in Zone backfilling should not the crown of and compacted by
welding shall C, unless specified be brought until the not less than stamping or by
be retained otherwise herein. minimum cover over 150 mm. Light mechanical
until the the pipe is 90 cm in the vibrating means.
trench is The excavated case of wide tracked machinery may
refilled and material may be used bulldozers or 120 mm be used, but not The initial back
consolidated. for backfill in the in the case of wheeled directly above fill up to 150 mm
Where following cases: roaders or roller the pipe. above the crown
timbers are compactors. of the pipe should
placed under In Zone C, in cases On completion be compacted with
the pipeline to where settlement is Vibratory methods are of the surround screened
aid alignment, unimportant and preferably for to the pipe, excavated material
these shall be when shown on the compaction. suitable free of sharp
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 35
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 36
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 37
Compaction
of Backfill
essential
Supplementa Cathodic Polyethylene Sleeve Not required. Not required. Not required. In aggressive, In aggressive, In aggressive, In aggressive,
l External Protection. (Refer Cl. No. 16.2, buried buried buried buried
Protection Annex - D of IS environments, environments, coal environments, environments,
8329 : 2000) coal tar epoxy tar epoxy paint is coal tar epoxy coal tar epoxy
paint is generally used paint is generally paint is generally
generally used used used
Jointing Plain ends or Push-on Flexible Unrestrained - Solvent a) Fusion welding: Socket & Spigot and socket Easy to assemble Steel socket and
beveled ends Joint, Mechanical Coupling or Socket or Cementing joint 1) Butt fusion Spigot – roll on type with rubber , Reliable Spigot joints rings
for butt Flexible Joint, Spigot Gasket Joint Elastomeric welding; joints or ring or with steel confined joint made of profile
welding Restrained Joint and Restrained - Coupling sealing ring 2) Socket fusion confined gasket joint rings system made steel & formed to
unless Flanged Joint. or Socket or Spigot joint welding; and joint, flush embeddedat ends with gasket, accurate
otherwise (Refer Cl. No. 3.9 to Gasket Joint with (Refer Cl. No. 3) Electro fusion jointed and for site welding. In Flexible joint dimensions
agreed, 3.14 of IS 8329 : supplemental 7.2 of IS welding; collar jointed case of pipes for beyond Elastic
beveled ends 2000) restraining elements 4985:2000) (Refer Cl. No. culverts, joints may Limit, Sliding
shall be Butt Joint b) Insert type 6.3 of IS be spigot and overlap welded
beveled to an Socket and Spigot with joints; 458:2003) socket, roll on rigid joints which
angle of 300 laminated overlay c) Compression gasket joint, ensure 100%
(+5/-0)
Socket and Spigot with fittings/push fit confined gasket water tightness,
measured adhesive bonded joints; joint or flush joint Option for
from a line Flanged d) Flanged joints; (Refer Cl. No. confined rubber
drawn Mechanical and 11.1, Amendment ring joints
perpendicular (Refer Cl. No. 8 of IS e) Spigot and 2 of IS 784:2001)
to the axis of 12709 : 1994) socket joints
the pipe. The (Refer Cl. No.
root face shall 3.1.1 of IS 7634
be 1.6±0.8 Part 2:2012)
mm.
Joints with
sleeves joint
or swelled and
plain ends for
welding.
(Refer Cl.
No. 17.1, of
IS 3589 :
2001)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 38
Handling The pipes and Ductile iron pipes Steel cables or ropes As UPVC pipes It is softer than Concrete pipes Concrete pipes Concrete pipes Pipes are easy
specials shall are less susceptible shall not be used for are durable and metals, it is prone have to be have to be have to be for handling and
be handled in to cracking or lifting and light, they are to damage by properly properly handled, properly installation
such a manner breaking on impact transportation of pipes. more 1ikcly to abrasion and by handled, bedded and back- handled,
as not to but the precautions Ropes shall not be pass be mishandled. objects with a bedded and filled, bedded and
distort their set out should be through the section of Care should be cutting edge. Such back-fined, if to carry safely the back-filled,
circularity or taken to prevent pipes end to end. taken to ensure practices as they have to full design to carry safely
cause any damage to the Straight continuous that pipes are dragging pipes carry safely the loads. the full design
damage to protective coating length of pipe may be not damaged over rough ground full design loads.
their and brushing or lifted at one point. during should therefore loads. Even the (Refer Cl. No. 0.3,
outcoating. damage of the However, owing to its handling, be avoided. If highest quality Foreword (Refer Cl. No.
Pipes shall not jointing surfaces. very smooth surface it storage and handling of concrete of IS 783 : 1985) 0.3, Foreword
be thrown (Refer Cl. No. 7.1 of is usually safer for the transport. equipment is not pipes of IS 783 :
down from the IS 12288 : 1987) pipe to be lifted at two UPVC pipes used, techniques, manufactured 1985)
trucks nor points. should be which are not in accordance
shall they be handled likely to damage with the
dragged or Pipes shall not be keeping in the pipe are to be specifications
rolled along dropped to avoid mind that they chosen. (Refer Cl. may be
hard surfaces. impact or bump. If any are made of No. 12.3 of IS destroyed by
Slings of time during handling or plastic and are 7634 Part 2 : improper
canvas on during installation, any also susceptible 2012) handling,
equally non- damage such as gouge, to damage if bedding and
abrasive crack or fracture mishandled. back filling.
material of occurs, the pipe shall They should (Refer Cl. No.
suitable width be repaired if so not be thrown, 0.3, Foreword
or special permitted by the dropped or of IS 783 :
attachment competent authority dragged. (Refer 1985)
shaped to fit before Cl. No. 4 &
the pipe ends installation.(Refer Cl. 4.2.1 of IS
shall be used No. 4.3.1, 4.3.2, 4.3.4 7634 Part 3 :
to lift and of IS 13916 : 1994) 2003)
lowercoated
pipes so as to
eliminate the
risk of
damage to the
coating.
(Refer Cl.
No. 5.2.4 of
IS 5822 :
1994)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 39
Transportati Delivery of Pipes should be All pipes section and When When transporting Pipes should be Pipes should be
on the pipes and loaded in such a way fittings shall be transporting straight loaded at the loaded at the works
specials and that they are secured supported on timber pipes, flat bed polyethylene works for for transportation,
appurtenances and that no saddles spaced at 4 m vehicles should pipes, use flat transportation, in such a way that
shall be taken movement should centers with a be used. The bedded vehicles. in such a way they are secure and
from the take place on the maximum overhang of bed should be The bed shall be that they are that no movement
stockyard of vehicle during 2 m. Stock height free from nails free from nails and secure and that can take place on
the authority transit. should not generally and other other projections. no movement the vehicle during
and The pipes should be exceed 2 m. Pipes shall projections. The polyethylene can take place transit. The same
transported to loaded on vehicles in be strapped to the When practical, pipes shall rest on the vehicle care is needed if
the site of pyramid or straight vehicle over the pipes should uniformly in the during transit. pipes are to be
laying and sided formation. In support points using rest uniformly vehicle over their The same care transferred from
stacked along case of pyramid non-metallic pliable on the vehicle long length. All is needed if one vehicle to
the route on loading, the pipes in straps or ropes only. over the whole support posts shall pipes are to be another.
timber skids. the bottom layer length. All be flat with no transferred
Padding shall should be restrained Pipes and fittings with support posts sharp edges. from one Pipes may be
be provided by the use of broad diameter of less than 1 should be flat Polyethylene pipes vehicle to placed directly on
between wooden wedges m may be stored with no sharp shall not be another. the ground provided
coated pipes secured to the directly on sandy soil, edges. (Refer transported with it is reasonably
and vehicle being loaded. the ground should be Cl. No. 4.1 of other metallic Pipes may be level and free from
timberskids to The pyramid is to be flat and free from sharp IS 7634 Part 3 items in the same placed directly rocks and other
avoid damage formed by resting projection stones/rocks : 2003) vehicle. (Refer on the ground projections.
to the coating. pipes between the bigger than 40 mm in Cl. No. 12.4 of IS provided it is Stacking in tiers is
Suitable gaps pairs of pieces in the diameter or other 7634 Part 2 : reasonably permissible
in the pipes preceding layer with potentially damaging 2012) level and free provided timber
stacked the sockets in layers debris. from rocks and bearer are placed
should be left reversed. Straight Pipes with diameter other between succeeding
at intervals to sided loading may be greater than 1 m may projections. tiers. If pipes arc to
permit access used with supports be stored on their Stacking in be stacked more
from one side along the sides of the delivery cradles at a tiers is than two tiers high,
to the other. vehicles. The use of maximum distance of 6 permissible reference should be
(Refer Cl. straight sided m c/c. If the surface is provided timber made to
No. 5.2.2 of loading is not flat or sloping , bearer are manufacture for
IS 5822 : advantageous for then all the pipes shall placed between advice before
1994) utilizing full be checked to prevent succeeding exceeding the two
capacity of the rolling. All rubber tiers. If pipes tiers specified. Cl.
vehicle. (Refer Cl. rings, gasket and other arc to be No. 15.1.1 and
No. 7.2 of IS 12288 items shall be stored in stacked more 15.1.3 of IS 783 :
: 1987) a cold, dry and dark than two tiers 1985)
place to avoid damage high, reference
of any kind. (Refer Cl. should be made
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 40
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 41
Limitation Never to be DI pipes are not to Not in area where Not in location Not in location Not in In contaminated In contaminated In contaminated
used near be used near buried future works may subjected to subjected to aggressive soils ground or possibly ground or ground or possibly
electricity electricity affect the pipes side vehicular load vehicular load and / ground water contaminated possibly contaminated
transmission transmission high support. and has has insufficient or tidal zone ground by certain contaminated ground by certain
cables. tension cables. Not in ground insufficient cover. chemicals in ground by chemicals in
contaminated or cover. (Refer RCC-2 concentrations certain concentrations
Never to be Wherever used possibly contaminated Not in areas Not in areas of Appendix A where it can affect chemicals in where it can affect
used below above ground by certain chemicals in subjected to subjected to third 3-10, Part A of the life of concrete , concentrations the life of concrete
ground unless supports at each pipe concentrations third party party interference, CPHEEO additional barrier where it can , additional
proper length shall be deleterious to the resin interference, e.g. excavations Manual). coating of coal tar affect the life of barrier coating of
protection ensured without any of the pipe. e.g. excavations within 2m of epoxy paint is to be concrete , coal tar epoxy
against subsidence. Do not use within 2m of pipeline by other provided and additional barrier paint is to be
corrosion pipes/couplings with pipeline by parties. Sulphate resisting coating of coal provided and
from soil and Pipes with external chips, cracks, crazing, other parties. Not in ground cement to be used tar epoxy paint is Sulphate resisting
soil water is synthetic coatings layer delamination or Not in ground offering low side for manufacturing to be provided cement to be used
ensured. not to be used in exposed fibres or ends offering low support strength to pipes . and Sulphate for manufacturing
marine coastal of pipes not sealed with side support the pipe. resisting cement pipes .
Choice of environments to resin. strength to the to be used for
spiral welded prevent leaching of Do not use pipe and pipe. Not in ground manufacturing
Vsor constituent couplings, stored which allows pipes .
horizontal chemicals into the unprotected from Not in ground migration of pipe
welded pipes environment. sunlight for more than which allows embedment In Black Cotton
shall be (Refer CIDI-1, 9 months. migration of material into it. Soil (Expansive
evaluated with CIDI-2 and CIDI-3 Do not use in ground pipe Soil) care has to
respect to of Appendix A 3- conditions having low embedment Not in ground be taken for
overburden. 10, Part A of stiffness, e.g. tidal material into it. contaminated with bedding and
(Refer MS-1, CPHEEO Manual). zone. deleterious back filling.
MS-2 & MS- Not in location Not in ground chemicals.
4 of subjected to vehicular contaminated
Appendix A load and has with deleterious Not suitable for
3-10, Part A insufficient cover. chemicals. above ground
of CPHEEO Not in areas subject to installation.
Manual). excavations by other Not suitable for
service providers above ground (Refer SP-1 to
within 2m radial installation. SP-6 of Appendix
distance of pipeline. A 3-10, Part A of
Not in ground subject (Refer SP-1 to CPHEEO
to differential SP-6 of Manual).
settlement of extreme Appendix A 3-
movement. 10, Part A of
Not in ground offering CPHEEO
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 42
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 43
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 44
5.6 Structure and Layout of Piped on a network serving 1000 ha showed that there
Irrigation Networks could be nine percent cost reduction in comparison
to initial layout when optimized. This cost reduction
A Piped Irrigation Network/ Pressure pipe irrigation was obtained essentially in the range of pipes
network system consists mainly of buried pipes and is having diameters of 400 mm or more.
therefore relatively free from topographic constraints.
The aim of the network is to connect all the hydrants In general it may be said that the field of application
to the source by the most economic and hydraulically of network layout optimization mainly concerns the
efficient layout. The source can be a pumping station principal elements of the network (pipe diameters of
on a river, a canal or well delivering water through an 400 mm and upwards). Elsewhere land tenure and
elevated reservoir or directly into the network. ease of maintenance (accessibility of junctions, etc.)
generally outweigh considerations of reduction of
Generally tree networks are adopted or considered pipe costs.
since they cost less than looped networks. Loops are b) Case of a rectangular pattern of plots
only introduced where it becomes necessary to
reinforce existing networks or to guarantee the security In the case of schemes where the land tenure has
of supply. been totally redistributed to form a regular check-
work pattern of plots, the pipe network can follow
5.6.1 Layout of branching networks the same general layout with the average plot
representing the basic module or unit. The layout
Principles of the pipe network is designed so as to be
integrated with the other utilities, such as the roads
On-demand distribution imposes no specific and the drainage system.
constraints upon the layout of the network: where the
land-ownership structure is heterogeneous, the plan of 5.7 Optimization of the Layout of
the hydrants represents an irregular pattern of points, Branching Networks
each of which is to be connected to the source of The method commonly used (FAO-Clement
water. and Galland 1979) involves three distinct
A method of arriving at the optimal network layout stages:
involves the following three step iterative process: a) Proximity layout
i. Proximity Layout: the source or the shortest b) 120o layout
connection of hydrants to source. c) Least-cost layout
ii. 120o Layout: where the proximity layout is
shortened by introducing junctions (nodes) other 5.7.1 Proximity layout:
than the hydrants. The aim is to connect all hydrants to the source by
iii. Least Cost Layout: where the cost is again the shortest path without introducing intermediate
reduced, this time by shortening the larger junctions here denominated as nodes. This may be
diameter pipes which convey the higher flows done by using a suitable adaptation of Kruskal's
and lengthening the smaller ones. classic algorithm from the theory of graphs.
The last step presupposes the knowledge of If a straight line drawn between hydrants is called
the pipe diameters. a Section and any closed circuit a loop, then the
algorithm proposed here is the following:
5.6.2 Fields of application of pipe network
optimization Proceeding in successive steps a section is drawn
at each step by selecting a new section of
a) Case of a dispersed land tenure pattern
minimum length which does not form a loop with
A search for the optimal network layout can lead to the sections already drawn. The procedure is
substantial returns. An in depth study (ICID 1971)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 45
illustrated in Figure 5.7 (a) for a small network 5.8). A node M is introduced whose position is such
consisting of six hydrants only. that the sum of the lengths MA + MB + MC is
minimal.
In the case of an extensive network, the application
For three hydrants, it follows therefore that the
of this algorithm becomes impractical since the
angle AMB BMC and CMA are each equal to 120o.
number of sections which have to be determined
and compared increases as the square of the The optimal position of the node M can readily be
number of hydrants: (n2 -n)/2 for ‗n‘ hydrants. For determined by construction with the help of a piece
this reason it is usual to use the following of tracing paper on which are drawn three
adaptation of Sollin's algorithm. converging lines subtending angles of 120o. By
displacing the tracing paper over the drawing on
Selecting any hydrant as starting point, a section is which the hydrants A, B, C have been disposed, the
drawn to the nearest hydrant thus creating a 2- position of the three convergent lines is adjusted
hydrant sub network. without difficulty and the position of the node
determined,
This sub-network is transformed into a 3-hydrant A new node can only exist if the angle ABC is less
sub-network by again drawing a section to the than 120o.When the angle is greater than 120°, the
nearest hydrant. This in fact is an application of a initial layout ABC cannot be improved by
simple law of proximity, by which a sub-network introducing a node and it represents the shortest
of n-1 hydrants becomes a network of n hydrants path. Conversely, it can be seen that the smaller is
by addition to the initial network. This procedure, the angle ABC, the greater will be the benefit
which considerably reduces the number of sections obtained by optimizing.
which have to be compared at each step, is
illustrated in Figure 5.7(b).
a) b)
It should be noted moreover that the step which initial layouts of the network can be tested. The
leads from the 120o layout to the least-cost layout first of these should be the proximity layout. The
requires knowledge of the pipe sizes and it can others can be defined empirically by the designer,
therefore only be taken once the pipe sizes have on the basis of the information available -
been optimized. elevation of the hydrants and distance from the
source - which enables potentially problematic
The 120o layout is an improvement on the initial hydrants to be identified.
proximity layout and that the least-cost layout is a
further refinement of the 1200 layout. It is not By a series of iterations it is possible to define a
certain however that the complete process "good" solution, if not the theoretical optimum.
produces the best result in all cases.
Example of layout of a small network designed to
The optimum attained is relative to a given initial supply irrigation water to 240 ha (net) is shown on
layout of which the proximity layout is only the Figures 5.12. The successive design phases
shortest path variant. It could be that a more produced the following results as given in Table
economic solution might be found by starting with 5.4.
a different intuit layout, differing from that which
Estimates as given in Table 5.4 are based on the
results from proximity considerations, but which
cost of engineering works only. They do not
takes into account hydraulic constraints.
include the purchase of land, right-of-way or
In practice, by programming the methods compensation for damage to crops which might
described above for computer treatment, several occur during construction, all of which would
increase the cost of the optimum network.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 48
Table 5.4 Details of methods applied optimum. Furthermore, it should be noted that the
Length Cost Method Figure above estimates are based on the cost of
(Rmt) (k$) No engineering works only. They do not include the
105.9 - Proximity 5.12(A) purchase of land, right-of-way and/or
Layout compensation for damage to crops which might
100 108.2 120 0 layout 5.12(B) occur during construction, all of which would
104.6 100 Least Cost 5.12(C) affect and increase the cost of the network and
Layout might induce to modify the optimal layout.
126.9 107.6 Empirical 5.12(D) 5.8 Piped Irrigation Network Design
layout,
connecting the 5.8.1 Simple Piped Irrigation Network
same hydrants In a Water Distribution Network (WDN), the sub-
by following networks are represented by an equivalent pipe.
roads, tracks and The network is categorized as pipes in series or
plot boundaries parallel as explained below:
a) Pipes in series: A network and a pipe are
5.7.4 Applicability of the layout equivalent when both carry the same discharge
optimization methods for the same head-loss.
There is no doubt that the 120° layout is an
improvement on the initial proximity layout and
that
the least-cost layout is a further refinement of the
120° layout. It is not certain however that the
complete process produces the best result in all
cases. Figure 5.13 Pipes in Series
𝐿𝑒 = 𝑛𝑖=1 𝐿𝑖
Usually, ―rules of thumb‖ are applied by designers 𝐾𝑒 = 𝑛𝑖=1 𝐾𝑖
in selecting the best suitable layout and, later, 𝑄 = 𝑄1 = 𝑄2 = ….𝑄𝑛
optimization algorithms are applied for computing Pipes in parallel: When pipes are connected in
the pipe sizes. The optimum attained is relative to parallel, the head loss in each pipe between the
a given initial layout of which the proximity layout junctions will be the same.
is only the shortest path variant. It could be that a 𝐿 1 = 𝐿 2 = 𝐿 3 = ⋯
more economic solution is possible by starting 𝑄 = 𝑄1 + 𝑄2
with a different initial layout, differing from that and
which results from proximity considerations, but 𝐿 𝐿 𝐿
which takes into account hydraulic constraints. ( )1/𝑛 = ( )1/𝑛 + ( )1/𝑛
𝐾𝑒 𝐾1 𝐾2
or
In practice, by programming the methods 1 1 1
described above for computer treatment, several ( )1/𝑛 = ( )1/𝑛 + ( )1/𝑛
𝐾𝑒 𝐾1 𝐾2
initial layouts of the network can be tested. The or
first of these should be the proximity layout. The
others can be defined empirically by the designer, 𝑉1 𝑓2 𝐿2 𝐷2
=
on the basis of the information available (elevation 𝑉2 𝑓1 𝐿1 𝐷1
of the hydrants and distance from the source)
which enables potentially problematic hydrants to
be identified. By a series of iterations it is possible
to define a "good" solution, if not the theoretical
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 50
Q‘s values. The LTM has several distinct vi. Once the values of Ki’s and Qi’s, are obtained
advantages over the Hardy Cross or Newton from the previous step, we can use these
Raphson method. First, it does not require an values to modify coefficients in the energy
initialization and secondly, it always converges in equation. Thus, the value of ‗K‘ and ‗n‘ in
a relatively fewer iterations. However, its use in Exponential formula may be modified and so
solving head oriented or collective loop oriented the value of Ki‘s.
equations is not recommended. vii. Repeat the procedure with modified energy
equations and obtain the values of Ki’s and
Linear Theory transforms the non-linear loop
Qi’s for the second iteration.
equations into linear equations, approximating the
viii. Use average of the flow rates obtained from
head in each pipe by:
first and second iteration to define again the
hLi = K i Q i 0 n−1 Qi = K′i Qi
coefficients in energy equation for third
Combining these artificial linear loop equations
iteration and Later from second and third
with J-1 continuity equations (J is number of
iteration to define the coefficients in energy
junctions), we get a system of ‗N‘ linear equations
equation for fourth iteration.
that can be solved by linear algebra.
ix. Carry on these iterations till the last two
In applying the LTM, it is not necessary to supply
iterations for Qi’s and Ki’s are similar upto a
the initial guess. Instead, for the first iteration,
desired accuracy.
each Ki’ is set equal to Ki, which implies all flow
rates Qi (0) are set equal to unity. Also, since the 5.9 Software Programmes
successive iterations tend to oscillate about the
The following software programmes are available
final solution, hence when two iterative solutions
for the optimization of the network design:
are obtained, then each flow rate used in
computation can be the average flow rate from last 1) EPANET
two iterations. i.e. 2) KYPIPE
𝑄𝑖 = 𝑄𝑖 𝑛 − 1 + 𝑄𝑖 𝑛 − 2 /2 3) PIPE FLOW EXPERT
4) VADISO
Steps in Linear Theorem
5) LOOP
i. Obtain ‗K‘ and ‗n‘ for Exponential Formula
6) HARDY
for a range of realistic flow rates. The ‗K‘ and
7) LINGO/LIGDO
‗n‘ values may be obtained for any of the
8) WATER GEMS
previously discussed equations such as Darcy
Weisbach, Hazen William etc. 5.10 Water Hammer
ii. Form equivalent pipes for those pipes All irrigation distribution systems are susceptible
containing global valves and orifice meter to pressure surge or water hammer. Surges occur
etc. when the velocity of water within the system
iii. Write J-1 continuity equations, with due changes from a steady state condition to another.
regard to sign of flow rates. As per
convention, flow rates for pipes whose flows The most severe surges usually occur on starting
are assumed into the junction may be taken as and stopping pumps or instantaneous opening and
positive and those out from junction may be closing of a valve in a pipeline. It may be caused
taken as negative. by nearly instantaneous or too rapid closing of a
iv. Linearize the head loss equations by forming valve in the line, or by an equivalent stoppage of
a coefficient Ki’ for each Qi which equals the flow such as would take place with the sudden
product of Ki and Qi (0) n-1. failure of electricity supply to a motor driven
v. For the first iteration, assume each Qi (0) = 1. pump.
Now, you get a set of linearized energy Pressure surges may be high and can result in
equations, which can be solved using significant damage to piping, pumps and other
Gaussian elimination, Gauss Jordan components of the irrigation system. Designers
elimination or other appropriate methods. should be aware that water hammer effects are
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 52
always possible and must consider possible effects pipelines, some of which are automatically
on the design loads for the system. controlled quick closing valves, automatically
controlled by passes and pressure relief valves.
Water velocity contributes significantly to the
To obtain greatest effectiveness, the relief
effects of water hammer. Lower velocities limit
valve or other form of suppressor should be
the adverse effects of water hammer. A water
located as close as possible to the source of
hammer analysis (Hydraulic Transient Analysis of
disturbance.
Piped Irrigation Network) may be necessary and
mitigation measures specified to lessen the risk of Since the maximum water hammer pressure in
damage. Such analysis is complex and specialized meters is about 125 times the velocity of flow in
engineering services may be required to analyze m/s and the time of closure of gate valves varies
the proposed mainline design. inversely with the size of the main, water hammer
is held within bounds in small pipelines by
5.10.1 Control Measures operating them at moderate velocities of 1 to 2
The internal design pressure for any section of a m/s. In large mains, the pressure is held down by
pipeline should not be less than the maximum changing velocities at sufficiently slow rate so that
operating pressure or the pipeline static pressure the relief valve returns to position of control before
obtaining at the lowest portion of the pipeline excessive pressures are reached. If this is not
considered including any allowance required for practicable, pressure relief or surge valves are
surge pressure. used.
The maximum surge pressure should be calculated For mains larger than 1.75 m, which operate
and the following allowances made. economically at relatively high velocities of 2 to 3
m/s and cannot be designed to withstand water
i. If the sum of the maximum operating pressure
hammer without prohibitive cost, the energy is
or the maximum pipeline static pressure
dissipated slowly by employing surge tanks.
whichever is higher and the calculated surge
pressure does not exceed 1.1 times the internal Once the whole network Piped Irrigation Network
design pressure, no allowance for surge is finalised, the whole system needs to be checked
pressure is required, for water hammer condition.
ii. If the sum exceeds 1.1 times the internal design
5.11 Some examples of Pipe Network
pressure, then protective devices should be
analysis
installed and
iii. In no case the sum of the maximum operating The pipe network can also be analyzed by using
pressure and the calculated surge pressure commonly used software, WHAMO (Water
should exceed the field hydrostatic test pressure Hammer and Mass Oscillation) which is used for
Hydraulic Transient analysis in Hydroelectric
Depending upon the layout of the network, the
plants. This was developed by US Army Corps of
profile and the length of the pipeline, surging in
Engineers.
pipelines can be counteracted in two
fundamentally different ways It is important to note that major pipe networks
need to be checked for any possible failure which
i. By checking the formation of the initial
can occur due to water hammer pressure
reduced pressure wave itself by means of
fluctuations (pressure rise or fall) arising out of
flywheels ( which lengthen the slowing down
sudden closure or opening of some of the outlets
time of the pump ) and air vessels (which
by the farmer. This type of hydraulic transient
continue to feed water into the pipeline until
conditions can be easily analyzed in
the reflected pressure wave again reaches the
WHAMO.Some simple network analysis has been
pump) and
done using WHAMO and the results are as below.
ii. By neutralizing the reflected wave from the
reservoir by installing special devices in the
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 53
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 54
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 55
Figure 5.18 Schematic diagram of the model of the pipe network with two loops
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 56
There are 8 links of 1000m each. Hazen William network with two loops have been analysed in
friction factor C=130 for all pipes. The above pipe WHAMO and the results are shown below:
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPE IRRIGATION NETWORK DESIGN 57
Crushed rock
Crushed rock
MS Pipe Thickness (mm)
As per WRD - MP
300 4 1.5 100 200 400 1000 3000 1.6% 1.5% 1.2% 0.8% 0.4%
350 4 1.5 100 200 400 1000 3000 2.7% 2.3% 1.8% 1.1% 0.5%
400 4 1.5 100 200 400 1000 3000 4.1% 3.3% 2.4% 1.3% 0.5%
450 4 1.5 100 200 400 1000 3000 5.8% 4.5% 3.0% 1.6% 0.6%
500 4 1.5 100 200 400 1000 3000 7.8% 5.7% 3.7% 1.8% 0.7%
600 4 1.5 100 200 400 1000 3000 12.2% 8.1% 4.9% 2.2% 0.8%
700 6 1.5 100 200 400 1000 3000 9.0% 6.7% 4.5% 2.3% 0.9%
800 6 1.5 100 200 400 1000 3000 12.9% 9.1% 5.7% 2.7% 1.0%
900 6 1.5 100 200 400 1000 3000 17.3% 11.5% 6.8% 3.1% 1.1%
1000 6 1.5 100 200 400 1000 3000 21.9% 13.8% 7.9% 3.5% 1.2%
4. Check for Buckling 𝐻 = height of ground surface above top of
pipe in cm;
Steel pipe embedded in soil may buckle because of 𝐻𝑤 = height of water above top of pipe in cm;
excessive loads and deformations. The total 𝐵′ = empirical coefficient of elastic support;
permanent pressure must be less than the allowable 1
buckling pressure = 1 + 4𝑒 (−0.0021 ∗𝐻)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 6
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 64
Figure 6.3 Wet Intake tower standing in the river Figure 6.4 Dry Intake tower standing in the
or reservoir river or reservoir
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 65
Figure 6.6 Typical Installation in an Earth dam-sloping Intake (Ref: IS: 11570- 1985)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 66
Figure 6.7 Approach Geometry- Semicircular Type Intake Structure (Ref: IS: 11570- 1985)
Figure 6.8 Typical Installation in an Earth dam-Tower Type Intake (Ref: IS: 11570- 1985)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 67
Figure 6.9 Typical Installation in an Earth dam-Tower Type Intake (Type II) (Ref: IS: 11570- 1985)
Figure 6.10 Typical Installation in a Concrete/Masonry dams (Ref: IS: 11570- 1985)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 68
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 69
Figure 6.11 Water is drawn from Canal Intake through Syphonic action in Balh Valley Medium Irrigation Project
in HP
PRINCIPLE OF TUBE SETTLERS degree the units lose efficiency rapidly whereas
with angles less than 60 degree, sludge will not
Tube settlers or inclined plate settlers are
slide down the floors. Under such situations,
examples of high rate settlers. Here what we are
hosing down the sediments may have to be
doing is we are providing excess surface so that
resorted to. With horizontal tubes (normally
the surface overflow rate will be decreased. We
inclined at 5 degree) auxiliary scouring of settled
have sedimentation tank like this say some 3.5
solids is necessary. While tube-settlers have been
meters depth so if you provide many plates
used for improving the performance of existing
parallely in the settling zone so what will happen
basins, they have also been successfully used in a
is the effective surface area will be increasing
number of installations as a sole settling unit. It
because many surfaces are available for the
has been found that if one fifth of the outlet end of
settling or many planes are available for settling.
a basin is covered with tube or plate settlers, the
So, effectively what will happen is it will be
effective surface loading on the tank is nearly
considerably reducing the surface overflow rate or
halved or the flow though the basin can be nearly
in other words it will be increasing the efficiency
doubled without impairment of effluent quality.
of the tank. That is the principle of these tube
settlers. Here the design is based upon the surface overflow
rate so here we are providing many tube or
Tube configurations can be horizontal or steeply inclined plates at an angle of 45 to 60 degree
inclined. In inclined tubes (about 60 degree) above the horizontal. Why we are providing this
continuous gravity drainage of the settleable 45 to 60 degree angle is because the particles will
material can be achieved. At angle greater than 40
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 70
be settling on the plates or the tubes so if you L = Relative length of settler = I/d
provide an angle 45 to 60 degree then whatever the dimensionless
particle that is settled on the tubes or the plates l, d = Length and diameter (width) of the
will be sliding back to the system with the self tube settlers, (L)
weight so cleaning will be very easy.
If the value S equals or exceeds a critical value, S
for any particle, it is completely removed in the
tube settlers under ideal conditions. For laminar
flow regime in tube settlers, the value of S have
been determined as 4/3, 11/8 and 1 for circular,
square and parallel plates type of tube settlers
assuring uniform flow. It is found that the
performance of tube settlers is improved
significantly with L values of up to 20 and
insignificantly beyond 20. Therefore, it is
desirable to design tube settlers, beyond 40 degree,
results in deterioration in their performance.
Essentially horizontal tube settlers perform better
than steeply inclined tube settlers. It is opined that
from relative economics point of view, the order of
Figure 6.13 Lamella clarifier preference for tube settlers is parallel plates
followed by circular tubes and square conduits.
The tubes may be square, circular, hexagonal,
diamond shaped, triangular, and rectangular or
chevron shaped. A widely used material for their
construction is thin plastic sheet (1.5mm) black in
color, though plastic and asbestos cement pipes
have also been used. There are number of
proprietary devices such as Lamella clarifier. This
tube settler system has been proposed in the
Medium Irrigation Project in Hamirpur district in
Himachal Pradesh.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 71
Figure 6.15 Tube settler type desilting arrangement in Nadaun Medium Irrigation Project, HP.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
INTAKE AND DESILTING ARRANGEMENTS 72
Figure 6.16 Aerial View of Tube settler type desilting arrangement provided in Balh Valley Medium Irrigation
Project, HP
normally adopted to store water upto 4 hours of
6.3 Diggy
water supply. The water shall be supplied from
It is manmade structure which is constructed at diggy to outlet.
the each outlet to provide a source of water to
micro irrigation. The capacity of Diggy is
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
Table 6.1 Design of Tube Settlers
Design Steps:
Estimation of effective length of tube
1000
Compute relative length of settler, 𝐿𝑅 = = 20
50
Effective relative length of tube, L = 𝐿𝑅 − 0.058𝑁𝑅
= 𝐿𝑅 − 0.058 × 𝑉𝑂 𝑑 𝜗
= 20 − (0.058 × 𝑉𝑂 × 0.05) 1.01 × 10−6 × 86400
= 20 − 0.033𝑉𝑂
Where 𝑉𝑂 is flow through velocity for tube settler in m/d
Determine Flow Velocity through Tubes:
𝑆 = 𝑉𝑠𝑐 𝑉𝑜 × sin 𝜃 + 𝐿 cos 𝜃
11 8 = 120 𝑉𝑜 × sin 60 + (20 − 0.033𝑉𝑂 ) cos 𝜃
𝑉𝑜 = 388.65 𝑚/𝑑
Compute Total Tube Entrance Area and No. of Tubes:
Tube entrance area, 𝑄 𝐴 = 255.1 × 24 388.65= 15.75 𝑚2
No .of tubes required = 15.75 0.05 × 0.05 = 6300
Provide 6400 square tubes of 0.05𝑚 × 0.05 𝑚 with 80 tubes along the length of the square module and 80
tubes along the width of the module
Length of the tube module = No. of tubes × (inside dimension of square
tubes + 2× thickness of tubes)
= 80 × 0.050 + 2 × 0.005 𝑚
= 4.24 m
Height of tube module for 1m length of square tubes inclined at an angle of 600
= 1 sin 600 = 0.866 m say 0.87m
Therefore overall dimension of tube module = 4.24m ×4.24m × 0.87m
Size of individual square tubes = 0.05m ×0.05m
Thickness of individual square tubes = 1.5mm
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 7
7. DESIGN OF PUMPS
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
DESIGN OF PUMPS 76
pump drops to zero and no pressure is available at d) Velocity Head – Changes in kinetic energy
the end of the discharge line. The pump of water from source to discharge point.
performance curve shows the relationship between Velocity head is calculated as the square of
discharge capacity and total head. the velocity divided by twice the acceleration
of gravity.
7.3.5 Pipe Restrictions 𝑣2
𝐻𝑣 =
When water hits any restriction (valve or a 2𝑔
reducer), only a partial amount of the flowing Where,
water is be allowed to pass through. Restrictions 𝐻𝑣 = Velocity head in metres
increase the friction and decrease the discharge 𝑣 = Velocity of water ,𝑚/𝑠
capacity at the end of the pipe. The following g = 9.8 𝑚/𝑠 2
conditions may be helpful in the selection of pumps e) Water Horsepower (Output Horsepower) –
a) If the pumping water level (PWL) is less than is the energy transferred by a pump to the
6 meters, use a centrifugal pump (maximum water.
suction lift = 6 m). 𝑊𝐻𝑃 = 𝑄 × 𝑇𝐷𝐻/75
b) If the pumping water level is from 6-20 m, use Where,
jet pumps or a submersible. Q = Pump Discharge, LPS
c) If the PWL is greater than 20 m, use a TDH = Total Dynamic Head,m
submersible or a vertical line shaft turbine f) Brake Horsepower (BHP or Input
pump. Horsepower) – is the energy transferred to
7.4 Terminology and Definitions the prime mover of a pump. The BHP will
always be larger than the WHP due to losses
a) Total Dynamic Head (TDH) –is the sum of caused by friction, impeller slippages, etc.
static head, pipe friction and velocity head at BHP is expressed as:
the point of discharge. 𝑄 × 𝑇𝐷𝐻 𝑊𝐻𝑃
b) Static Head – difference in elevation 𝐵𝐻𝑃 = =
75 × 𝑒 𝑒
between suction level and discharge level. Where:
Refer to Figure 7.1. Q = Pump Discharge, LPS
c) Pipe Friction – Head loss due to friction of TDH = Total Dynamic head, m
the water as it moves along the pipes, fittings, e = pump efficiency
elbows, valves and suction entrance.
flow meter connected to the discharge port. For c) A service bay should be provided in the station
any anticipated total head, the discharge capacity with such space that the largest equipment can
can be determined. Pump performance curves are be accommodated there for overhauling and
available for each pump model. repair.
d) A ramp or a loading and unloading bay should
The Best Efficiency Point is the point at which be provided. In large installations the floors
effects of head (pressure) and flow converge to should be planned so that all piping‘s and
produce the greatest amount of output for the least valves can be laid on the lower floor and the
amount of energy. upper floor should permit free movement.
e) Head room and material handling tackle.
7.5 Dimensioning of Pump House
f) In the case of vertical pumps with hollow shaft
motors, the clearance should be clear to lift the
a) Sufficient space should be available in the
motor off the face of the coupling and also to
pump house to locate the pump, motor, valves,
carry the motor to the service bay without
piping‘s, control panels and cable trays in a
interference from any other apparatus. The
rational manner with easy access and with
clearance should also be adequate to dismantle
sufficient space around each equipment for
and lift the largest column assembly.
maintenance and repairs. The minimum space
g) In the case of horizontal pumps (or vertical
between two adjoining pumps or motors should
pumps with solid shaft motors) the head room
be 0.6m for small and medium units and 1m for
should permit transport of the motor above the
large units.
other apparatus with adequate clearance.
b) Space for the control panels should be planned
h) The mounting level of the lifting tackle should
as per the Indian Electricity (I.E.) Rules as
be decided considering the above needs and the
follows :
need of the head room for maintenance and
i. A clear space of not less than 915 mm in
repair of lifting tackle itself.
width shall be provided in front of the
i) The traverse of the lifting tackle should cover
switch board. In case of large panels, a draw
all bays and all apparatus.
out space for circuit breakers may exceed
j) The rated capacity of the lifting tackle should
915 mm. In such cases the
be adequate for the maximum weight to be
recommendations of the manufacturers
handled at any time.
should be followed.
ii. If there are any attachments or bare
7.6 Power Supply Arrangements
connections at the back of the switch board,
the space, if any behind the switch board For small capacity pumps up to 15HP existing
shall be either less than 230 mm or more power supply lines for irrigation shall be used. For
than 750 mm in width measured from the higher capacity pumps, separate power supply
farthest part of any attachment or conductor. lines are required. The cost of separate power lines
iii. If the switch board exceeds 760 mm in shall be included in the cost estimate.
width, there shall be a passage way from Solar Pumping may be used where the solar
either end of switch-board clear to a height energy is abundantly available.
of 1830 mm.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 8
8. OPERATION AND MAINTENANCE
Following checklist is provided to assist in 8.3 Check list for Operation during the
developing a good operation and maintenance irrigation season
plan. i. Whenever possible, open the new turnout
before closing the old one. Always close
valves slowly to prevent water hammer.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
OPERATION AND MAINTENANCE 80
ii. Inspect the pipeline inlet daily or more often maintenance, now is a good time to get it
if necessary. Remove trash or debris. Observe done.
flow conditions in the canal and make iii. If sediment build up in the line is a problem,
adjustments necessary to keep the pipeline flush the pipeline.
inlet submerged. iv. Close and lock the inlet structure gates and
iii. Check pressures regularly. A change means crack open all turnouts located at high points
there is probably an operational or in the line and all low lying turnouts.
maintenance problem. v. In case of frost condition, open all drains and
iv. Inspect flow meters at least monthly for allow the pipe to drain. Pump out all low
proper operation. spots in the pipeline.
v. Check pump and valves for noisy operation. vi. Remove flow meters and service if necessary,
Noise is an indication that cavitation may be then store in a dry place.
occurring. Cavitation can greatly reduce the vii. Remove pressure gauges or other accessories
life of the pump and valves. that may have water in them and store or fill
vi. Check that air-vacuum valves are seated and with anti-freeze.
not discharging water. viii. Close all gates, valves and other openings
where small animals or water could enter the
8.4 Maintenance Check List pipeline.
ix. Leave drain valves, drain plugs and in line
8.4.1 Pre-season Maintenance
valves open during the winter in frost
i. Check pumps impellers for wear. Repair if condition.
necessary.
ii. Re-pack bushings if necessary and lubricate 8.5 Choking of Pipes by excess silt
pump.
Minimum velocities as prescribed shall be
iii. Install the suction pipe on a centrifugal pump.
maintained for flushing of the pipes. During the
Make sure it is well supported and has no air
first irrigation, scour valves should be let open to
leaks. A vacuum gauge installed in the
scour out any foreign material deposited.
suction line is a good way to monitor suction
problems. 8.5.1 Repairs
iv. Make sure a pressure gauge is installed at the
Repairs of joint leakages and valve leakages
outlet and is operable. A good fluid filled
should be attended promptly to avoid wastages.
pressure gauge is a good monitoring tool.
10% of the fitting should be kept in spare for
v. Check power panel, wiring and pump
repair.
enclosure to make sure mouse nests, bird
nests, and other such problems are resolved. 8.5.2 Right of approach to the field
vi. Inlet screens should be cleaned and trash
The government or authorised agency has the right
removed from the structure. Repair screens as
of entry at any time with prior notice. During the
necessary.
repairs if standing crop is there, crop compensation
vii. Check headgates and valves for proper
shall be provided to the farmers.
operation. Grease gate stems.
viii. Check structures and pipeline for damage and 8.6 Maintenance of Pumps
repair as needed. Usually maintenance instructions are available
from manufacturers, pump users associations and
8.4.2 Winterizing system:
other technical organizations. For most engine or
i. Drain and pull the suction line on centrifugal electric motor driven pumps, checks and
pumps. inspections are for noise, vibration, leakage,
ii. Drain the pump and protect it from the temperatures of bearings and windings, fuel/power
elements. If the pump is in need of consumption, capacity and output (water discharge
and dynamic head), ventilation screens etc.
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
OPERATION AND MAINTENANCE 81
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
OPERATION AND MAINTENANCE 82
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 9
9. FIELD AUTOMATION AND CONTROL
9.2 Need for SCADA iv. Alarms: Alarms are implemented by indicating
lamps or hooters in field and SCADA
Understanding the underlying process with true
represents it with format. In the field area
animation makes it easy to understand. It can
alarms are generated for warnings or to monitor
communicate to any of protocols available in
the process. The format consists of Date, Time,
market since SCADA is not dedicated to any one
Status, Priorities and many such elements
type of application or industry. Distance as such
which can be used for generation of reports.
doesn‘t hamper SCADA operation. Hence we can
monitor processes at places which are inaccessible. v. Trends: Also called as XY plotters or data
SCADA is not 100% the controller. It is a software loggers, Trends represent values in wave
which is linked with controllers and hence to format and is one of the important features of
PLC/PID/DCS systems which in turn are connected SCADA. It plots value with reference to time.
to field instruments. Trend can be subdivided into real time
historical trends i.e present and past values of
9.3 Features of SCADA
the process can be stored and records can be
Following are the features of SCADA systems: maintained for the same.
i. Dynamic representation: Explains about the
vi. Scripts: These are combinations of logical
representation of various symbols of field
operators which are written in the form of
instruments which are present in tool library
statement. It is used to run the applications
which can be utilized in SCADA applications.
made or simulate before final execution.
SCADA is not dedicated to any specific
Various types of scripts make project execution
industry hence its library large and can
simpler for programmer.
accommodate requirements of any industry.
vii. Security: Every application has to be secured
ii. Database connectivity: Represents various
from unauthorized users by different security
symbols of field instruments which are present
levels. In SCADA this security can be given as
in tool library of SCADA. It doesn‘t have its
a whole as well as individually.
own database like Microsoft etc. However, its
storage depends on databases available in viii. Recipe management: Being one of the finest
features of SCADA, recipe management can
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
FIELD AUTOMATION AND CONTROL 84
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
CHAPTER - 10
10. PIPED IRRIGATION NETWORK EXAMPLE
10.1 General
10.2 Network Layout
The design example given in this chapter compares
Canal network and relative position of Arangi
both options of Canal and PIN and their relative
Minor (in inset) have been shown in the Figure
costs. For the purpose of demonstration, canal
10.1. The minor has a total area of 204 acres with a
network of Kholra distributor of Pratapur Branch
design off take discharge of 1.95 cusec.
on Left Main Canal has been taken from the DPR
of Kanhar Project, Jharkhand. In the analysis of 10.3 Chak boundaries, Outlet Location
slopes, it is found that the distributor has flat Contour map of Arangi Minor with 0.5m contour
longitudinal slope. The minors have steep slope interval (major contours are only depicted) is
favourable for gravity Piped Irrigation Network. shown in Figure 10.2. Location of five Chak
The source for canal is Lawadoni Dam on Kanhar outlets, boundary and net GCA of each chak have
River and source for present Piped Irrigation been marked out. The south boundary of command
Network is Kholra distributor. In this example the of minor is the Railway line and north boundary is
first Minor, namely Arangi Minor has been tried village OOC.
for Piped Irrigation Network vis a vis canal.
Figure 10.1 Canal Network of Kholra Distributary and Location of Arangi Minor
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPED IRRIGATION NETWORK EXAMPLE 86
Guidelines for Planning and Design of Piped Irrigation Network – Part I (2017)
PIPED IRRIGATION NETWORK EXAMPLE 87
10.4 Capacity Statement addition to the falls, the canal has two pipe
culverts, two pipe crossings, one stream siphon
The capacity statement of minor is worked out
and one box culvert. Total of 9 canal structures are
with authorised duty of 1500 ha/cumec. This may
present in the layout.
be cross checked with crop water requirement for
more scientific assessment. The off taking 10.5.1 Land Acquisition for Minor Canal
discharge at the head of the minor has been arrived
The design canal width with service road is shown
as 0.055 cumec or 1.95 cusec with a CCA of 82.53
in Figure 10.5. Average right of way required for
ha or 204 acres. Head discharge for canal option
the canal is 18 m. Total land required is 15 X
with 90% conveyance is 0.061 cumec.
2795/10000 = 4.2 ha. The L-section of the Canal is
10.5 Canal Option given in Figure 10.6.
10.6 Pipe Option
Considering pipe option, gravity head of 11.714m
is available. With a Hazen William Coefficient of
130 for HDPE pipes and a trial velocity of 1 m/s,
the head losses and residual head at outlets have
been worked as given in Table 10.2. L-Section for
pipe option is given in Figure 10.6. Above
mentioned calculations by analytical method have
been checked by a computer analysis and the
results of head loss and residual head are found to
be matching. The actual velocities with provided
diameter of pipe have also been worked out as
shown in the computer screen shots given by
Figure 10.7.
10.7 Cost Comparison - Canal Vs Pipe
Comparison of cases of canal and pipe are
illustrated in Table 10.1. It shows the cost involved
in both cases and also gives an indication of the
amount of water saved by on using the option of
pipe.
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
PIPED IRRIGATION NETWORK EXAMPLE 89
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
PIPED IRRIGATION NETWORK EXAMPLE 90
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
PIPED IRRIGATION NETWORK EXAMPLE 91
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 92
APPENDIX
DISCLAIMER:
In this Appendix, the case studies of various Irrigation projects with piped Irrigation network in
the country and international experiences presented in the workshop on Pipe Irrigation Network
held in New Delhi in March 2017 have been given. The information presented is for illustrative
purpose only. The views/recommendations/comments expressed in the presentations are solely of
the Project Authorities/Authors, and these shall not be considered as part of Guidelines.
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 93
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 94
The CCA has been increased from 1.35 lac hectare to 2.46 lac hectare i.e. 78% increased. No. Of villages benefited
for irrigation increased from 89 to 233. Drinking water facility in 1541 villages and 3 towns has been provided,
which was not proposed earlier. Increase in food production has been assessed 534 cr. to 2200 cr. i.e. 1666 cr.
(312%) based on year 2015-16.
Comparison of Cost between Piped Irrigation Network & Open Canal Networks
Analysis of rates for piped irrigation network for CCA of 100 ha
(A) Civil work Rs. In lacs
Cost of Diggie 6.18
Cost of Sump 1.70
Cost of Pump House & Boundary Wall 7.08
Total of Civil Work 14.96
(B) Mechanical work
Cost of 2 Nos. of Motor driven horizontal centrifugal pumping sets of discharge 12 3.00
LPS to 16 LPS including suction pipes, vacuum pumps, all valve, foot valve, foot
valve strainer with required pipes and fittings such as flanges, bends, tees,
reducers, enlargers, tail piece etc. and delivery pipes and its accessories, electric
control panel of 16 SWG(CRCA), Aluminum PVC insulated PVC sheathed
armoured cable including earthing two pits and providing and installaton of hydro
cyclone filter
(C) Supplying, laying, jointing, testing and commissioning of designing and planning Rs0.13538/Ha
of Buried HDPE pipe network or Rs13.538/100Ha
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 95
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 96
in Rs.
AMRP Nalgonda
Purna C.Bhaga
Balh Valley
Telangana)
(Gujarat )
Shiggaon
Location
LIMIP
KNNL
MRP
(MS)
(KS)
Area to be /
Irrigated 988 533 617 455 14,820 29600 5,817 24,453 37,050
(Ac)
Beneficiarie
600 180 200 216 5,000 10544 7,500 8,154 3,000
s
Canal
Water M.I. Canal Community Canal Canal Canal River Canal
(SSNN
Source Tank (AMRP) Tubewells (PBC) (Purna) (BBMB) (Varada) (IGNP)
L)
Cost Per
Acre 40,486 9,750 43,450 14,500 31,000 7,080 1,11,700 68,700 5,950
(In Rs.) *
Duration
6 12 9 6 4 26 36 26 12
(Mnth)
Handed
2008 2009 2010 2011 2011 2011 2012 2012 2012
Over
Maintenanc
e
1 2 1 1 3 2 5 2 2
Contract
(Yrs.)
Pres.
Pres. &
System Pressurised Pressurised Drip / Gravity Pressurised
Gvty.
Type Drip / Sprinkler Drip Sprinkl Pipe Drip / Sprinkler
Sprinkler
er
Kandi
NCP Ramthal Cane Agro Nadaun
Integrated
Location Sanchore, Hungund Sangli Hamirpur
Kandi
(Raj.) (Kar.) (MS) (HP)
(Punjab)
Area to be /
3,38,400 30,381 2,009 1,642 7,360
Irrigated (Ac)
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 97
With an area of 11,700 Ha is a mega Community Drip Irrigation Project launched by KBJNL in Northern
Karnataka.
a) The uniqueness of this first of its kind, worlds largest Community Drip Irrigation Project
b) Mega Community Drip Irrigation Project 24000 Ha
c) Total beneficiaries in package I of project = 6700 farmers
d) Total infrastructure cost is borne by Govt.
e) Project execution time is only 18 months including monsoon
f) System operation is through wireless automation
g) O&M of the system for first 5 years
h) Formation of WUA & marketing linkages
i) Irrigation is only for partial command area – 80% during kharif season & 50% during rabi season
6. PROJECTS IN MAHARASHTRA
1. Gunjawani Project : Dam Head Available 42 m, Head utilized for pressurized PDS, Storage108 Mm3 , ICA
21400 ha, Chak Size 2.5 Ha, Residual Head 20 m, Totally PDS including Main line, Distribution network upto
drip point Compatible with drip, Water will be seen either at Dam or drip point at root zone.
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 98
Salient Features
Water Source Khanerajuri M.I. Tank (Dongarwadi L.I.Scheme)
Type Of Pipe : P.S.C. Pipes
Pipe Dia.: 1700 To 350 Mm
Pressure: 4 TO 8 Kg/Cm2
Design Disch. : 2.165 Cumec
Cost Of Work: 117 Crore
Work Period: 30 Months
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 99
Cost Analysis :
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 100
Sr. Main Canal Discharge Pipe Type Length Gradient Velocity Total Total Cost
No /Branch Canal cum/sec Dia of in km of m/sec. ICA Cost / Ha
in Pipe Pipeline Ha Rs
mm Lakh
Bhose Gravity Main
A Main Canal /Branch Canal
1 Bhose Gravity 2.17 1700 P.S.C. 19.80 1 in 1328 1.07 4581 5651.57 1.23
Main to to to
0.05 350 0.52
B Distributary & Minors
a Malgaon Main 0.72 1000 P.S.C. 5.17 1 in 250 1.001 765 616.14 0.81
to to to
0.03 350 0.312
Sub Mains on 0.135 450 P.S.C. 6.18 1 in 141 0.936 396 534.88 1.35
Malgaon Main to to to to
0.055 350 1 in 75 0.312
b Kalambi Main 0.52 900 P.S.C. 5.26 1 in 133 0.916 518 548.62 1.06
to to to
0.03 350 0.312
Sub Mains on 0.08 350 P.S.C. 3.93 1 in 169 0.832 179 282.97 1.58
Kalambi Main to to to
0.03 1 in 115 0.312
c Sub Main-7 0.865 1100 P.S.C. 7.05 1 in 181 0.962 978 999.08 1.02
to to to
0.03 350 0.312
Sub Mains on 0.270 600 P.S.C. 8.45 1 in 339 0.955 430 634.29 1.48
Sub Main-7 to to to to
0.03 350 1 in 47 0.312
C Minors
Direct Sub 0.240 600 P.S.C. 27.08 1 in 130 1.196 1892 2448.37 1.29
Mains (Total - to to to to
14 No.) 0.03 350 1 in 35 0.312
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 101
7. MEGA LIFT IRRIGATION PROJECTS, CLUSTER NOS. - XII, SUNDERGARD AND JHARSUGUDA, ODISHA
Execution of 16 nos. of Lift Irrigation Schemes with intake points in Ibb, Sapei and Basundhara river having
Command area between 500Ha. to 2000 Ha. in Cluster No. XII in the district of Sundergarh and Jharsuguda
including its distribution network, up to 4 Ha Chak having total planned Culturable Command Area of 21,300 Ha.
on ―EPC –Turn Key‖ basis including power system connectivity and Operation & Maintenance of complete
commissioned schemes for five years
Details of works covered in the Scope of Work for each LI Scheme under the cluster is as below:
1. Intake works in the river with RCC pipe up to the Pump house including all river protection works.
2. Constructing Pump House with Panel Room & Operating rooms.
3. Approach roads to Pump House.
4. Ductile Iron Pipeline for Transmission of Water up to delivery chamber (optional), Surge Control Devices /
Water Hammer Control Devices, other appurtenances.
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 102
5. Delivery chamber (optional) and the Irrigation Distribution Network through Ductile Iron (from 300 mm
diameter to 1200 mm diameter) and HDPE pipes (below 300 mm diameter).
6. O & M for Civil, Mechanical & Electrical Works for 5 years
Supplying of water from Left bank Rising main system and delivering at farmer‘s field through the various
junctions/off takes from left bank rising mains by pressurized pipeline system for micro irrigation and in the
Culturable command area of 87000 hectare out of gross command area 135250 hectare (the entire compact and
contiguous possible arable area should be fully covered and any arable area found in excess should be dropped at
the tail end) indicated in the index map for Left Bank Micro Irrigation system under Mohanpura Project. It includes
all activities starting from survey, investigation, designing, procurement, construction, laying, installing, energizing,
etc of pumping system ,rising and gravity mains , main line, branch lines, distribution network ,controlling and
regulation system etc for supply of water for irrigation under pressure.
Note : All pipes of 300 mm dia and above – Ductile Iron / Mild Steel
Pipes less than 300 mm dia - Ductile Iron / Mild Steel / HDPE
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 103
Failure due to :
Micro level Land fragmentation
Drainage issues
Obstruction in Transportation path
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 104
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 105
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 106
Input
a) Sub chak name and its chainage.
b) CCA of chak.
c) Available FSL of Parent Canal.
d) Ground Level at Turnout of Sub chak command.
Output
a) Design Discharge of the Sub minor.
b) Head loss due to friction in pipeline (Using Modified Hazen-William formula).
c) Available FSL and Required FSL at Turnout point.
d) Flow Condition of subminor i.e.Gravity Flow or Lift flow.
e) Height of Well
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 107
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 108
xiv. No power bill for the farmers, project to be operated and maintained by Department of Soil and Water
Conservation, Punjab in association with the executing entity i.e. Jain Irrigation Systems Limited for seven
years.
xv. The beneficiaries farmers have been organized into a Water User Association (WUA) which can even have
an arrangement with the PSPCL to purchase power during low demand periods.
11. TIKTOLI DISTRIBUTARY PIPE IRRIGATION PROJECT BY GRAVITY FLOW, GWALIOR, MADHYA PRADESH
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
APPENDIX 109
CHINA
China Could save 30 % of water delivered, 2-4% land, 25% labour input as compared to open canal system.8.91
Mha under Piped irrigation ( 22% of total saved irrigation area), amounting to 15% of total irrigation area.
Design standards:
a) First Stage: Working pressure maintained at <0.2 MPa, Applicable for low pressure pipe irrigation schemes
with ground water as source.
b) Second Stage: Working pressure maintained at <0.4 MPa, Applicable for low pressure pipe irrigation
schemes.(Applied to well irrigation schemes, pumping irrigation schemes & gravity irrigation schemes in
mountainous regions for command area < 80 Ha).
c) Third Stage: Working pressure maintained at <1.0 MPa & Outlet pressure at most unfavorable pt. not to exceed
0.02 MPa. Applicable for new expanded and rebuilded pipe irrigation projects.
Choice of pipe material:
a) If pipe internal dia < 400 MM (PE(Polyethylene pipes) to be used.
b) If pipe internal dia> 400 MM (Concrete Pipes, PRC, GRP (Glass fibre reinforced plastic), DIP (Ductile Iron
Pipes) to be used.
c) Nominal pressure of chosen pipe material should not be less than the sum of design working pressure and water
hammer pressure.
d) When the sulphate concentration in soil exceeds 1%, concrete pipes and metal pipes should not be used.
Technical Parameters Followed:
a) Probability of irrigation water requirement should not be lower than 75%.
b) Design value of pipe network water efficiency should not be lower than 0.95.
c) Design value of water efficiency at farm level should not be lower than 0.90, for rice irrigation, not lower than
0.95.
AUSTRALIA
Guidelines for Planning and Design of Piped Irrigation Network (Part-I) (2017)
PART-II
OUTLET TO FIELD
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
CHAPTER-11
11. OUTLET TO FIELD
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
OUTLET TO FIELD 113
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
OUTLET TO FIELD 114
10.67𝑄1.85 𝐿
𝐻𝑓 =
𝐶 1.85 𝑑 4.87
Where,
𝑓 = Head loss in metre (water) over the
Figure 11.5 Piped line distribution network length of pipe
𝐿 =Length of pipe in metre
𝑄 = Volumetric flow rate in m3/s
𝐶 = Pipe roughness coefficient
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
OUTLET TO FIELD 115
16680 x 39
75 x 0.5
= 17347 say 17350 HP
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
APPENDIX 117
APPENDIX
Annex-I
Crop Water requirements for Rabi season (Drip Irrigation)
Wheat Pulses Vegetables Barley Mustard Total
Month days Area Water Area Water Area Water need Area Water Area Water Area Water
(In ha) need (In ha) need (In ha) (cumec) (In ha) need (In ha) need (In need
(cumec) (cumec) (cumec) (cumec) ha) (cumec)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Oct-I 1 to 10 0 0 0 0 0 0 0 0 0
11 to
Oct-II 0 0 0 0 0 0 0 0 0
20
21 to
Oct-III 0 0 0 0 0 0 0 0 0
31
Nov-I 1 to 10 2500 0.12 0 500 0 500 0 500 0 4000 0.12
11 to
Nov-II 2500 0.57 1000 0 500 0 500 0 500 0 5000 0.57
20
21 to
Nov-III 2500 0.85 1000 0 500 0 500 0 500 0 5000 0.85
30
Dec-I 1 to 10 2500 1.05 1000 0 500 0 500 0 500 0 5000 1.05
11 to
Dec-II 2500 1.10 1000 0 500 0.17 500 0 500 0.11 5000 1.37
20
21 to
Dec-III 2500 1.19 1000 0 500 0.21 500 0 500 0.17 5000 1.56
31
Jan-I 1 to 10 2500 1.05 1000 0.12 500 0.19 500 0 500 0.19 5000 1.54
Jan-II 11 to 2500 1.02 1000 0.14 500 0.19 500 0 500 0.21 5000 1.55
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
APPENDIX 118
20
21 to
Jan-III 2500 0.96 1000 0.00 500 0.22 500 0 500 0.25 5000 1.42
31
Feb-I 1 to 10 2500 0.56 1000 0.20 500 0.20 500 0.13 500 0.24 5000 1.32
11 to
Feb-II 2500 0.15 1000 0.33 500 0.05 500 0.22 500 0.25 5000 0.99
20
21 to
Feb-III 2500 0 1000 0.38 500 0 500 0.22 500 0.21 5000 0.80
28
Mar-I 1 to 10 2500 0 1000 0.63 500 0 500 0.31 500 0.21 5000 1.15
11 to
Mar-II 2500 0 1000 0.69 500 0 500 0.35 500 0.13 5000 1.16
20
21 to
Mar-III 2500 0 1000 0.83 500 0 500 0.41 500 0 5000 1.24
31
Apr-I 1 to 10 2500 0 1000 0.82 500 0 500 0.41 500 0 5000 1.22
11 to
Apr-II 2500 0 1000 0.70 500 0 500 0.37 500 0 5000 1.06
20
21 to
Apr-III 2500 0 1000 0.29 500 0 500 0.21 500 0 5000 0.49
30
May-I 1 to 10 2500 0 1000 0 500 0 500 0.05 0 4500 0.05
Max 1.56
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
APPENDIX 119
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
APPENDIX 120
Annex-III
The various BIS codes for different components of the system are tabulated as under-
S.No Component description BIS code
1 Polyethylene pipe for irrigation-Laterals with amendments number 5 IS 127886:1989(reaffirmed 1998)
5 Irrigation equipment rotating sprinkler Part II, Test IS 12232 (Part IS 12232 (Part II) 1995
II) Method for uniformity of distribution (1 st revision)(amendment
1)(including rain gun)
6 Polyethylene micro tubes for drip system IS 14482:1997
12 Irrigation equipment sprinkler pipes specifications IS 14151 (Part IS 14151 (Part I) 1999
I)1999 Part I Polyethylene pipes
13 Irrigation equipment sprinkler pipes specifications IS 14151 (Part II) 1999
Part II quick couples Polyethylene pipes
14 Quality of Irrigation water IS 11624 : 1986
15 HDPE Pipes IS 4984 : 1995
16 Moulded PVC Fittings IS 7834 : 1987
17 GI and MS Fittings IS 1879 : 1987
18 GM Valves IS 778 : 1984
19 CI Non Return Valves IS 778 : 1984
20 Fabricated PVC Fittings IS 10124 : 1988
21 GI Pipes IS 1879 : 1987
22 Sluice Valves IS 780: 1984
23 PE Fabricated Fittings IS 8360: 1977
24 PE Moulded Fittings IS 808: 2003
25 PVC Foot Valves and NRV IS 10805: 1986
26 Irrigation equipment rotating sprinkler Part I, IS 12232 (Part I) 1996
Design and Operational requirements (1st revision)
27 Design, Installation and Field evaluation of MIS IS 10799: 1999
28 Prevention and treatment of blockages problems IS 14791: 2000
in drip irrigation systems
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
APPENDIX 121
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
APPENDIX 122
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
COMPOSITION OF THE COMMITEE 123
CHAIRMAN
1. Sh. S.Masood Husain, Member (WP&P), Central Water Commission.
MEMBERS
SPECIAL INVITEES:
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
REFERENCES 124
REFERENCES
ii) IS 5822 :1994 - Code of Practice for Laying of Electrically Welded Steel Pipes for
Water Supply
vii) Manual on water supply and treatment by central public health and environmental
xii) FAO Irrigation and Drainage Paper 44 “Design and Optimization of Irrigation
Distribution Networks”,1988
Guidelines for Planning and Design of Piped Irrigation Network (part-II) (2017)
Guidelines for Planning and Design of Piped Irrigation Network (2017)
CONTACT INFORMATION