Saudi Aramco Inspection Checklist: Concrete Coatings Pre-Installation Inspection SAIC-H-1003 1-Nov-09 Civil

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 3

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) Rev 3 30-Jun-08

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Concrete Coatings Pre-Installation Inspection SAIC-H-1003 1-Nov-09 CIVIL-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Surface preparation, moisture testing and environmental condition


A
inspection

The coating shall be applied after the full curing time of concrete in SAES-H-003
A1
accordance to SAES-Q-001. Sec. 8.1.4

New concrete must have a moisture content of 4% or less before the


coating applications commence.
SAES-H-003
A2
Note: Test report SATR-H-1003 " Concrete Moisture Field Test Sec. 8.1.4
(For Coating Purposes)" shall be available for review/verification of
concrete moisture condition.

Surface temperature, humidity and dew point readings shall be recorded.


SAES-H-003
A3 The substrate temperature shall be less than
Sec. 9.3.1
3°C (5°F) above the dew point prior to coating application.

Remove any protrusions and sharp edges with an abrasive


SAES-H-003
A4 carborundum brick, power grinding, or power brushing prior to coating
Sec. 7.2.1.1
concrete.

Surfaces shall be sound such that a metal object run over the concrete SAES-H-003
A5
shall not loosen any particles. Sec. 7.2.1.1

Surface contaminants such as laitance and form oils must be


removed. Form oils, grease, etc. shall be removed by steam SAES-H-003
A6
cleaning with a water emulsifying detergent added. Laitance Sec. 7.2.1.2
shall be removed by wire brushing.

Materials that cannot be removed by steam cleaning or abrasion can be


removed by Hydochloric acid etching; The adequacy of the water SAES-H-003
A7
flushing shall be checked by placing litmus paper on the wet surface to Sec. 7.2.1.3
ensure that it is fully neutralized.

New concrete shall be roughened to the texture of medium grit


SAES-H-003
A8 sandpaper by grit blasting when it has a troweled or "formed" smooth
Sec. 7.2.1.4
surface.

The tensile strength of heavy duty surface concrete by ASTM D4541


SAES-H-003
A9 shall meet or exceed 175psi for immersion service and 260 psi for
Sec. 7.2.2
industrial floors.

Remove all loose concrete, surface contaminations, sealants, and old


coatings by abrasive blasting (or other mechanical means) and/or hot SAES-H-003
A10
water high pressure washing as appropriate, prior to making concrete Sec. 7.3.1
repairs and coating application.

Neutralize acidic surfaces with an alkaline cleaner such as soda ash SAES-H-003
A11
(sodium carbonate) followed by a high pressure fresh water rinse. Sec. 7.3.2b

Page 1 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) Rev 3 30-Jun-08

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Concrete Coatings Pre-Installation Inspection SAIC-H-1003 1-Nov-09 Civil


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Concrete surfaces (such as acid waste neutralizing tanks) that have


SAES-H-003
A12 been in prolonged contact with acids require a minimum soak of 24 hours
Sec. 7.3.2b
at a pH of 7-8, agitating the solution during soaking.

After rinsing, force air dry surfaces for at least 24 hours prior to making SAES-H-003
A13
any repairs to the concrete. Sec. 7.3.2b

Neutralize alkaline surfaces by steam cleaning. ASTM D4262 ---


SAES-H-003
A14 "Standard Test Method for Determining pH of Chemically Cleaned or
Sec. 7.3.2c
Etched Concrete Surfaces" shall be performed.

A strip of pH Test Paper is dipped in the rinse water remaining on the


surface. The pH reading obtained should not be more than 1.0 pH units SAES-H-003
A15
lower or 2.0 pH units higher than readings taken on the fresh water rinse Sec. 7.3.2c
before being applied to the concrete surface.

B Primer/sealer application inspection

Cracks less than 10 mm wide and holes not exceeding 10 mm in


SAES-H-003
B1 diameter shall be filled using a qualified epoxy filler or grout before
Sec. 7.4.1
applying primer/sealer to the surface.

Expansion and construction joints shall be cleaned and masked off prior SAES-H-003
B2
to coating. Sec. 7.4.3

All voids shall be prepared, primed and filled using suitable and
SAES-H-003
B3 compatible epoxy filler prior to coating. The epoxy filler materials shall be
Sec. 7.4.4
approved by the Civil and/ or the Coating engineers of the CSD.

Surfaces with sharp corners and subject to immersion conditions shall be


SAES-H-003
B4 rounded by forming a fillet with approximately 25 mm radius using an
Sec. 7.4.5
epoxy grout.

Sealer/primer shall be use in accordance with the manufacturer's data


SAES-H-003
B5 sheet and shall be spray applied in a thin coat except for touch-up repairs
Sec. 8.1.3
of small areas [less than 0.1 m²].

SAES-H-100
B6 Paints shall not be used from a container showing a sign of leakage.
Sec. 6.3

Coatings or their components which have exceeded the Manufacturer's


recommended shelf life shall be set aside and must not be used unless SAES-H-100
B7
written authorization is given by Saudi Aramco Consulting Services Sec. 6.4
Department.

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-H-003 -- Coating Requirements for Concrete Surfaces, 12 October 2005

Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) Rev 3 30-Jun-08

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Concrete Coatings Pre-Installation Inspection SAIC-H-1003 1-Nov-09 Civil


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

2- SAES-H-100 -- Coating Materials & Application Requirements for Industrial Facilities, 31 July 2004
3- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 5 March 2008

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 3 of 3