Saic-H-2027
Saic-H-2027
Saic-H-2027
00 30-Sep-17
UPGRADE FIRE WATER SYSTEM AT RASTANURA SOUTH TERMINAL BI-10-01333 SAUDI ARCHIRODON COMPANY LTD
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
FLANGE REST SUPPORT
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
168-B-XA-864219-003-00-1 & 2
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
08/03/2022 09:30 AM 08/03/2022 09:30 AM SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SATIP-H-100-01 3.1
SAUDI ARAMCO INSPECTION LEVEL
W
CONTRACTOR INSPECTION LEVEL
H
NO
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Coating system to be applied was verified to conform with the Selection SAES-H-001 Sec.
A2 Requirements for industrial plants and equipments listed in SAES-H- 7&
001, Sec. 7 and scope of work. Scope of Work
High intensity flood or spotlights are installed in vessels, tanks, and SAES-H-001 Para
A4
other poorly illuminated locations for visibility. 6.5.3
Sufficient dust suction blowers are provided to remove dust and fine SAES-H-001 Para
A7
blasting debris during the blasting operation. 6.5.4
The substrate was solvent or detergent cleaned where presence of oil SAES-H-001 Para
B1
or grease is observed. 6.4.1
Rough welds and cut-off are ground to a minimum radius. Weld SAES-H-001 Para
B2
Spatters and
Substrate surface laminations
temperature are removed.
is at least 3°C above the Dew point. 6.4.2
SAES-H-001 Para
B3
6.4.3
UPGRADE FIRE WATER SYSTEM AT RASTANURA SOUTH TERMINAL BI-10-01333 SAUDI ARCHIRODON COMPANY LTD
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
SAES-H-001 Para
B4 Nozzle pressure is 620 kPa (90 psig) measured at the nozzle side.
8.1.4
Abrasive used for blasting are as per the APCS sheet, contain less than
50 PPM of sulfates & chlorides and calcium carbonate shall be 1.0% by SAES-H-100
weight. (Verified by certificates) and following limitations applied: Para 8.2.1
B6 a) Sand is not used as a blasting abrasive as prohibited by GI-0006.021. to
b) The use of reclaimed slag abrasives is prohibited. Para 8.2.3
c) The use of reclaimed garnet is permitted provided it meets the above & Para 6.3.4
requirements and a CSD-approved recycling system is utilized.
1. APCS-2A/2B/2C/2D/2E/2F/2G/2H/2I
SAES-H-001 Para
/11B/19C//27/28 ..............................................Sa-3 (SP 5)
8.1.1
C4
&
2. APCS-1A/1B/1C/1D/1E/1F/3/5A/5B/ 9/11A/12/17A
Para 8.1.3
/17A /19A/19B/20A/20B/22A/22B/26/26T.......Sa-21/2 (SP10)
3. APCS-4/6/10/23.............................................Sa-2 (SP 6)
4. APCS-7.....................................................St-2 (SP2)/St 3 (SP3)
5. APCS-11C...............................................C/S SP1,SP6. S/S SP1
6. Others:__APCS-3_______..... ..........._SSPC-SP16_____
UPGRADE FIRE WATER SYSTEM AT RASTANURA SOUTH TERMINAL BI-10-01333 SAUDI ARCHIRODON COMPANY LTD
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
6. APCS-1C/1F............................................25-40 Min-Max
7. APCS-7/10...............................................Not critical
8 . APCS-9..................................................25-50 Min-Max
9. APCS-11B..............................................25 Max
10. APCS-20A/20B.........................As recommended by coating Mfg
11. Others:_APCS-3_________.............19 -40 Min-Max .............
_________________
REMARKS
ATTACHMENTS:
REFERENCE DOCUMENTS:
1. SAES-H-001,Coating Selection and Application Requirements for Industrial Plants and Equipment (5 April 2016)
2. SAES-H-102: Safety requirements for Coating Applications (24 October 2012)
3. SAEP-316, Performance Qualification of Coating Personnel (31 July 2016)
4. Schedule "Q", Quality Requirements for Contractors (Project Specific)
5. G.I.-0006.021, Safety Requirements for Abrasive Blast Cleaning, (19 June 2012 )
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: HARSHAD PATIL Name, Initials and Date: