Saudi Aramco Typical Inspection Plan

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1/ 11

SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.

00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE: Civil & Mechanical

Structural Steel-Piperack, Steel Supports & Miscellaneous* Steel


SATIP-M-001-01 15-Jul-18 MECHANICAL- Structural Steel
Structures (* Incl. Piping Supports per Specification)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Procedure for Tightening of High


1.1 SAIC-M-2001 SAIC-M-2001 RH RH
Strength Bolted connections

Procedure for Localized Heating for


1.2 SAIC-M-2002 SAIC-M-2002 RH RH See Item 3.11 thru 3.14 for welding related repairs
warpage repair (CSD approval reqd)
Procedure for Steel Pile Driving (Pipe, Refer to applicable SATIPs for NDT, Welding, Coating
1.3 SAIC-M-2022 SAIC-M-2022 RH RH
Steel Shapes such as H, etc) and develop QC forms & logs for this activity
Utilize Pre-qualified WPS per AWS D1.1 (2004) or
Procedure for Structural Steel Welding
1.4 See Remarks See Remarks RH RH existing WPS from earlier editions. See Items 3.11 thru
(SA PID Approval req'd)
3.14 for welding & related repairs
Use Pre-qualified WPS per AWS D1.1 (2004) or existing
Procedure for Structural Steel
WPS from earlier editions.
Welding & *Repairs (*Splice welds,
*ALL
1.5 Common repairs, Bolthole misalignment SAIC-M-2012 SAIC-M-2012 RH RH
Repairs require authorization by Engineer and the
& relocation, Repair welding defects, &
Authorized SA Inspector. Implementation is the
AWS D1.1 Inspection Reqmts.
responsibility* of QA/QC Mgr. & Engineer.

2.0 MATERIAL RECEIVING

2.1 Structural Steel Shapes and Plates SAIC-M-2003 SAIC-M-2003 H W SA shall be notified for the first batch of deliveries.

2.2 Bolts, Nuts and Washers SAIC-M-2021 SAIC-M-2021 H W SA shall be notified for the first batch of deliveries.

2.3 Fabricated Steel Structures SAIC-M-2004 SAIC-M-2004 H W SA shall be notified for the first batch of deliveries.

2.4 Storage, Handling & Preservation SAIC-M-2005 SAIC-M-2005 H S

3.0 INSTALLATION

Inspection of Support Foundation prior to


3.1 SAIC-M-2006 SAIC-M-2006 H W
Structural or Equipment Installation
3.2 Field Weld connection inspection Refer to Items 3.11 -3.14 below

3.3 Structural Alignment prior to Grouting SAIC-M-2007 SAIC-M-2007 I S USE SATR-M-2001

3.4 Grouting Refer to SATIP-Q-010-01

Repair/Correction of Errors of See SAIC-M-2012 for welding related repairs & any
3.5 SAIC-M-2008 SAIC-M-2008 I W
Structural Alignment (No welding) Required NDE resulting (Correction of errors)
Pre-Installation Procedure Verification
Testing of Turn-of-Nut Method
3.6 SATR-M-2002 SATR-M-2002 H H
ASTM A325 or ASTM A490
Bolts

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE: Civil & Mechanical

Structural Steel-Piperack, Steel Supports & Miscellaneous* Steel


SATIP-M-001-01 15-Jul-18 MECHANICAL- Structural Steel
Structures (* Incl. Piping Supports per Specification)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Pre-Installation Procedure Verification


3.7 Testing of DIRECT TENSIONING SATR-M-2003 SATR-M-2003 H H
INDICATOR (ASTM A325/A490 Bolts)
Pre-Installation Procedure Verification
3.8 Testing of Calibration Wrench* SATR-M-2004 SATR-M-2004 H H
ASTM A325 or ASTM A490 Bolts
*SA is notified for INITIAL bolt tightening activities.
3.9 Final bolt tightening insp & testing SAIC-M-2009 SAIC-M-2009 I W Use With applicable SATRs in previous
steps.
3.10 Inspect Access Structure Installation SAIC-M-2010 SAIC-M-2010 I W
AWS D1.1 Application incl Repair
Refer to the applicable SATIP for NDE
3.11 Pre-Welding SAIC-M-2012 SAIC-M-2012 I W
Inspection
AWS D1.1 Application incl Repair
Refer to the applicable SATIP for NDE
3.12 In-process Welding SAIC-M-2012 SAIC-M-2012 I W
Inspection
AWS D1.1 Application incl Repair
3.13 Post Welding Final SAIC-M-2012 SAIC-M-2012 I W Refer to the applicable SATIP for NDE
Inspection
NDE Of Structural Steel (AWS D1.1)
Refer also to the Applicable NDE SATIP for NDE.
NDE* Follows NDE Process Control
3.14 Selection & Performance of NDE SAIC-M-2012 SAIC-M-2012 I W
Procedure.
including any repairs.

3.15 Painting/Coating and touch up See Remarks See Remarks Refer to applicable SATIP-H series

4.0 PRE-COMMISSIONING

Structural Re-Instatement/Final List Final MCC Exception Items, Use SATR-A-2011 or


4.1 SAIC-M-2011 SAIC-M-2011 H W
Punchlisting SATR-A-6133 (FEIL) or other document agreed on.
Clear any MCC Exception Items, SATR-A-6133 (FEIL) or
4.2 Mechanical Completion Punch listing SATR-A-6133 H
other document as agreed on.

GENERAL NOTES

NOTICE (SAEP-1160- July 10,2011 , Section 9.2): Use of Welding and NDT SAICS 9.2.1 One SAIC per day per activity is required for production welding on a daily or continual basis, e.g., fit-up, in-
process, and final inspection. Applicable weld numbers must be entered in Remarks Box on the appropriate SAIC. 9.2.2 Special welding activities such as branch connections, tie-ins, sleeve installation, hot-
tap welding, and temperature tie-ins will require a separate IR per weld per activity in accordance with the applicable SATIP. Structural steel Repairs (by Welding) are a special activity. 9.2.3 NDT
subcontractors must complete NDT Checklists on a daily basis per above but not as an IR with the exception of the start of NDT activities. Follow NDE Process Control procedure.

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, inspection or test shall be performed as scheduled if QA/QC org rep is not present.
4 Hold: QA/QC org shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE: Civil & Mechanical

Structural Steel-Piperack, Steel Supports & Miscellaneous* Steel


SATIP-M-001-01 15-Jul-18 MECHANICAL- Structural Steel
Structures (* Incl. Piping Supports per Specification)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.05.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


15-Jul-18 15-Jul-18

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.05.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


15-Jul-18 15-Jul-18

Saudi Aramco: Company General Use